This document outlines the scope of work for a federal construction contract opportunity involving rehabilitation projects at Gettysburg National Military Park. The solicitation seeks a contractor to perform work such as stabilization, restoration, and rehabilitation of the Little Round Top Visitor Use Area, as well as road and parking area repairs on various routes throughout the park. Relevant projects include milling and overlay of asphalt surfaces, patching, sealing cracks and resurfacing, as well as drainage improvements, signage, and landscaping. The selected contractor will be required to adhere to safety and environmental compliance standards, and ensure protection of archaeological resources during ground-disturbing activities.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GETTYSBURG NATIONAL MILITARY PARK
Gettysburg, Pennsylvania
Rehabilitation of Various Routes
PMIS NO. 221207
Package 2
PROJECT DOCUMENTS & SPECIFICATIONS
FOR CLINS 20-38
NATIONAL PARK SERVICE
DENVER SERVICE CENTER
July 31, 2020
GETT - 221207 TOC-1
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 27 00 Definition of Contract Line Items 01 31 00 Project Management & Coordination 01 32 16 Construction Schedule 01 33 23 Submittal Procedures 01 35 13.22 Archeological Protection 01 35 23 Safety Requirements 01 40 00 Quality Requirements 01 42 00 References 01 50 00 Temporary Facilities 01 57 19.12 Noise & Acoustics Management 01 57 23 Temporary Storm Water Pollution Prevention 01 67 00 Product Requirements 01 73 40 Execution 01 74 19 Construction Waste Management and Disposal 01 77 00 Closeout Procedures
DIVISION 03 – CONCRETE
03 30 53 Miscellaneous Cast-In-Place Concrete
DIVISION 04 – MASONRY
04 43 00 Stone Masonry
DIVISION 31 – EARTHWORK
31 00 00 Earthwork 31 25 00 Erosion and Sedimentation Controls 31 37 00 Riprap
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 01 16.71 Cold Milling Asphalt Paving 32 01 17.61 Sealing Cracks in Asphalt Paving 32 01 17.71 Partial Depth Patch Repair 32 01 17.72 Full Depth Patch Repair 32 11 23 Aggregate Base Course 32 11 41 Antietam Base Course 32 12 13.13 Asphalt Tack Coat 32 12 16.04 Ultra-Thin Asphalt Pavement 32 17 13.19 Precast Concrete Parking Curbstops 32 17 23 Pavement Markings 32 91 19.14 Aggregate Topsoil Course
GETT - 221207 TOC-2
DIVISION 33 – UTILITIES
33 42 11 Stormwater Gravity Piping 33 42 31 Stormwater Area Drains and Inlets
GETT - 221207 01 11 00 - 1
SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Contractor use of premises.
3. Public use of site.
4. Work Restrictions.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. This specification book references Contract Line Items Nos. 20-38.
B. Project Location: This project is located at Gettysburg National Military Park. Gettysburg National Military Park is located in Gettysburg city limits in the south-central part of Pennsylvania. The scope of these CLINS includes work on Ayers Avenue, Berdan Avenue, Birney Avenue, Crawford Avenue, Cross-Brooke-DeTrobriand Avenue, Hancock Avenue, Howe Avenue, Humphreys Avenue, North Sickles Avenue, Sedwick Avenue, South Confederate-Sykes Avenue, Big Round Top Parking Area, South Sickles Avenue, Devils Den Parking Area, United States Avenue, West Confederate Avenue, Virginia Memorial Loop Parking Area, Longstreet Tower Parking Area, and Wheatfield Avenue.
C. The Work consists of the following:
1. This project will consist of pavement management of the roads, parking areas and pullouts within Gettysburg National Military Park. This work includes, but is not limited to, asphalt planing, ultra-thin overlay, partial depth patching, full depth pavement patches, spot repairs and pavement markings.
D. Project will be constructed under a single prime contract.
1.3 CONTRACTOR USE OF SITE
A. General: Contractor shall have full use of the site for construction operations during the construction period. Contractor's use of the site is limited only by the Government's right to perform work or to retain other contractors on portions of Project.
B. Storage of Materials: Confine storage of materials to staging area locations mutually acceptable to the Contractor and the Contracting Officer.
C. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
GETT - 221207 01 11 00 - 2
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with
Contracting Officer and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
D. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
E. Construction Camp: Establishment of a camp within the park will not be permitted.
Limits are essential in order to protect the motor road and appurtenances, to protect resources, and for reasons of visitor safety.
F. Hauling Restrictions: State and Federal Hauling Restrictions shall be followed at all times for the classification of roads within this project. Contractor is responsible for coordinating and obtaining Park Hauling Restrictions from the CO prior to the start of the project.
G. Water: Water sources shall be determined during the pre-construction meeting.
A serviceable backflow prevention device or physical separation between the parks water source and receiving equipment must be used. If the contractor is found not to be using such a device or providing a physical separation, access to all park water will be terminated immediately.
1.4 PUBLIC USE OF SITE
A. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public.
Road closures will be permitted, when required, upon specific approval of Contracting Officer. Two lanes of traffic shall be maintained at the end of each workday.
1.5 CONDUCT OF OPERATIONS
A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
GETT - 221207 01 11 00 - 3
1.6 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7 a.m. to 7 p.m., Monday through Friday, except when otherwise indicated.
1. Weekend and Federal Holiday Hours: No work shall be performed on the weekends and federal holidays without prior approval including the Fridays before Easter, Memorial Day, Labor Day, June 30 through July 4, and on the Gettysburg Address, November 19th.
Contractor shall coordinate with CO for additional restrictions associated with the Gettysburg Address.
2. Early Morning Hours: No work shall be performed before 7 a.m. unless approved by the Contracting Officer.
B. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than 2 days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
3. Disruptions to facilities outside the project limits shall be prevented by investigation of existing utilities and protection during construction. Contractor shall be responsible for all costs associated with remedy of accidental disruptions to facilities outside the project limits.
1.7 NOT USED
1.8 NOT USED
1.9 ADDITIONAL REPORTS
A. A report entitled Geotechnical Data Report, March 2020 has been prepared by Terracon Consultants, Inc.
B. A copy of the report is available to all plan holders with this package.
C. If conflicts occur between the report and the drawings or specifications, the drawings and specifications govern.
GETT - 221207 01 11 00 - 4
1.10 SUMMARY OF CONTRACT PACKAGES
A. GETT-250272-Rehabilitation of Little Round Top Visitor Use Area includes
1. Contract Drawings (3 PDFs)
2. Division 1 & Technical Specifications (refers to CLINs 1-17) (1 PDF)
3. Soils Investigation Report
4. Sykes Avenue Mechanically Stabilized Earth Wall Design Calculations
B. GETT-318024-Wright Avenue Paving Preservation includes
1. Contract Drawings (1 PDF)
2. Division 1 & Technical Specifications (refers to CLIN 18) (1 PDF)
C. GETT-318022-Warren Avenue Paving Preservation includes
1. Contract Drawings (1 PDF)
2. Division 1 & Technical Specifications (refers to CLIN 19) (1 PDF)
D. GETT 221207-Rehabiltation of Various Routes Package 2 includes
1. Contract Drawings (1 PDF)
2. Division 1 & Technical Specifications (refers to CLINs 20-38) (1 PDF)
3. Geotechnical Report (1 PDF)
1.11
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
GETT - 286031 01 27 00 - 1
DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No. 1 Gettysburg Little Round Top Improvements (PMIS 250272)
1. This item consists of all work associated with the stabilization, restoration and rehabilitation of Little Round Top. The cultural landscape of Little Round Top is classified as a Historic Site. There are contributing built and natural resources located throughout the project area. All work must adhere to the Secretary of Interior’s Standards. Work includes but is not limited to; temporary monument protection measures, soil erosion and sediment controls, temporary chain link construction fencing, flagging, temporary construction fencing, tree protection fencing, traffic detour devices, permitting, topsoil stripping and stockpiling, demolition of asphalt road and parking, select areas of asphalt mill and overlay, removal of gravel shoulder, removal and stockpile of topsoil aggregate shoulder, removal of wheel stops, removal of detectable warning strips, salvage select landscape boulders, select removal of boulders, demolition of inlets, culverts and headwalls, demolition of retaining walls, demolition of signage, salvaging of fencing, salvaging and reinstalling stone stairs, and removal of trees, shrubs and groundcover. Improvements include but are not limited to; import of fill material, rough grading of the entire project area, fine grading for all non-vegetated surface materials, asphalt road, asphalt parking areas, asphalt mill and overlay, full depth patch, cut granite curbs, paving striping, modified MSE retaining wall with guardrail, concrete retaining wall with guardrail, cut stone retaining walls, cut stone seat walls, cut stone stacked seating, cut stone headwalls, steel gates and foundation, exposed aggregate concrete, stabilized soil, stabilized aggregate, aggregate topsoil, granite pavers, rock water bar, stone spillway, stone culvert, cut stone steps, cut stone bollards, 34” height rails, turndown edge, cut stone edging, culverts, area inlets, riprap, vehicular signage signs with post and foundation, upright signage and foundation, low profile/cantilevered signage and foundation, trailside marker, installation of Contractor and Government furnished signage panels, bike rack, empty electrical conduit and restacking historic breastworks. Reference the contract documents for the full project scope.
2. Measurement for payment will be percentage of the work completed in the previous month.
GETT - 286031 01 27 00 - 2
3. Payment will be made at the contract lump sum price prorated each month for work completed.
B. Contract Line Item No. 2 Modified MSE Retaining Wall (PMIS 250272)
1. This item consists of all work associated with excavation / trenching within shallow bedrock.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed. Payment will be compensation in full for all costs of design and construction including facing panels, soil reinforcement, connection devices, bearing pads, joint materials, leveling pad, impervious layer, technical representatives, and other items which do not have separate pay items but are necessary to complete the MSE Wall.
C. Contract Line Item No. 3 Demolition of Rock Outcroppings (PMIS 250272)
1. This item consists of all work associated with the demolition of rock outcroppings. For bidding purposes, include 30 cubic yards (CY) of demolition of rock outcroppings and 390 SF of delicate removal by hand to shape of existing features to remain.
2. Measurement for payment will be percentage of the work completed in the previous month.
Include issued truck load receipts of the CY of work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed.
D. Contract Line Item No. 4 Excavation / Trenching Shallow Bedrock (PMIS 250272)
1. This item consists of all work associated with excavation / trenching within shallow bedrock. For bidding purposes, include 50 cubic yards (CY) of excavation / trenching within shallow bedrock.
2. Measurement for payment will be percentage of the work completed in the previous month.
Include issued truck load receipts of the CY of work completed in the previous month.
Payment will be made at the contract lump sum price prorated each month for work completed.
E. Contract Line Item No. 5 Tree Removal within Designated Areas of Grading Disturbance (PMIS 250272)
1. This item consists of all work associated with tree removals, full stump removal, partial stump removal, and felling and preparing tree trunks to remain in place.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed.
F. Contract Line Item No. 6 Restacking Historic Breastworks with Collected On-site Stone (PMIS 250272)
1. This item consists of all work associated with restacking historic breastworks for both 44th
New York and Chamberlain Avenue, including but not limited to; contractor to provide a written means and methods proposal, mockups, Contractor to collect stone from immediate adjacent locations, soil work, stabilization as required, dismantling breastworks, reconstruction with mortar and breastworks demarcation. For bidding purposes, include 550 square feet of area for stone collection.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed.
GETT - 286031 01 27 00 - 3
G. Contract Line Item No. 7 Winter Work (PMIS 250272)
1. This item consists of facilitating construction activities during cold weather, as specified.
This item only includes additional labor and materials required to meet the cold weather requirements of the specifications.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed.
H. Contract Line Item No. 8, OPTION A, Restacking Historic Breastworks to 42” Height at All Locations with Imported Material (PMIS 250272)
1. This item consists of all work associated with restacking historic breastworks for both 44th
New York and Chamberlain Avenue, including but not limited to; contractor to provide a written means and methods proposal, mockups, Contractor to collect stone from immediate adjacent locations and import stone as needed to achieve height, imported stone type to match existing breastworks stone, imported source as selected by the Contracting Officer, soil work, stabilization as required, dismantling breastworks, reconstruction with mortar, breastworks demarcation and importing stone.
2. Option A is in lieu of CLIN 6.
3. Measurement for payment will be percentage of the work completed in the previous month.
4. Payment will be made at the contract lump sum price prorated each month for work completed.
I. Contract Line Item No. 9, OPTION B, Stone Edging at Grade – Future Rail (PMIS 250272)
1. This item consists of all work associated with cut granite edging, including but not limited to excavation, custom cut granite blocks and placement.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed.
J. Contract Line Item No. 10, OPTION C, Temporary Seeding (PMIS 250272)
1. This item consists of temporary seeding and then removal, if the revegetation contractor cannot start immediately behind the General Contractor.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed.
K. Contract Line Item No. 11, OPTION D, Tree Removal Selective Clearing (PMIS 250272)
1. This item consists of all work associated with tree removals, including but not limited to;
full stump removal, partial stump removal, and felling and preparing tree trunks to remain in place.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed.
L. Contract Line Item No. 12, OPTION E, 20th Maine Area Improvements (PMIS 250272)
1. This item consists of all related construction activities, including but not limited to;
flagging, erosion control, demolition and improvements within the area identified as 20th Main Area Improvements.
2. Option E is paired with Option F.
3. Measurement for payment will be percentage of the work completed in the previous month.
GETT - 286031 01 27 00 - 4
4. Payment will be made at the contract lump sum price prorated each month for work completed.
M. Contract Line Item No. 13, OPTION F, 20th Maine Area Improvements Tree Removal within Designated Areas of Grading Disturbance (PMIS 250272)
1. This item consists of all work associated with tree removals, full stump removal, partial stump removal, and felling and preparing tree trunks to remain in place.
2. Option F is paired with Option E
3. Measurement for payment will be percentage of the work completed in the previous month.
4. Payment will be made at the contract lump sum price prorated each month for work completed.
N. Contract Line Item No. 14, OPTION G, 20th Maine Area Improvements Tree Removal Selective Clearing (PMIS 250272)
1. This item consists of all work associated with tree removals, full stump removal, partial stump removal, and felling and preparing tree trunks to remain in place.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed.
O. Contract Line Item No. 15, OPTION H, Trail, Northern Segment near Wheatfield Road (PMIS 250272)
1. This item consists of all related construction activities, including but not limited to;
flagging, erosion control, demolition and improvements within the area identified as Trail, Northern Segment near Wheatfield Road Improvements.
2. Option H is paired with Option I
3. Measurement for payment will be percentage of the work completed in the previous month.
4. Payment will be made at the contract lump sum price prorated each month for work completed.
P. Contraction Line Item No. 16, OPTION I, Northern Segment near Wheatfield Road Tree Removal Selective Clearing (PMIS 250272)
1. This item consists of all work associated with tree removals, full stump removal, partial stump removal, and felling and preparing tree trunks to remain in place.
2. Option I is paired with Option H.
3. Measurement for payment will be percentage of the work completed in the previous month.
4. Payment will be made at the contract lump sum price prorated each month for work completed.
Q. Contract Line Item No. 17 OPTION J, Replace existing Stone Retaining Wall at Sykes Avenue Main Parking Lot with Stacked Block Granite Retaining Wall (PMIS 250272)
1. This item consists of all work associated with replacing the existing stone retaining wall at
Sykes Avenue main parking lot with a stacked block granite retaining wall.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed.
R. Contract Line Item No. 18 OPTION PA, Warren Avenue Paving Preservation (PMIS 318022)
1. This item consists of all work associated with the Warren Avenue paving preservation project. The cultural landscape of Gettysburg National Military Park is classified as a Historic Site. There are contributing built and natural resources located throughout the
GETT - 286031 01 27 00 - 5
project area. All work must adhere to the Secretary of Interior’s Standards. Work includes but is not limited to; temporary chain link construction fencing, monument protection measures, soil erosion and sediment control, construction staging, maintenance and protection of traffic control devices, cleaning out of all culverts, removal of topsoil aggregate shoulder, road paving surface rehabilitation, mill and overlay of failing pavement, asphalt gutter resurfacing, aggregate shoulder work, shoulder grading, full or partial depth patching as necessary, removal of inlets, removal of culverts, disassembly and reassembly of stone headwall, new inlets, custom metal grates, new culverts, new stone headwalls, new precast concrete headwalls and revegetation. Reference the contract documents for the full project scope.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed.
S. Contract Line Item No. 19 OPTION PB, Wright Avenue Paving Preservation (PMIS 318024)
1. This item consists of all work associated with the Wright Avenue paving preservation project. The cultural landscape of Gettysburg National Military Park is classified as a Historic Site. There are contributing built and natural resources located throughout the project area. All work must adhere to the Secretary of Interior’s Standards. Work includes but is not limited to; temporary chain link construction fencing, monument protection measures, soil erosion and sediment control, construction staging, maintenance and protection of traffic control devices, cleaning out of all culverts, removal of topsoil aggregate shoulder, road paving surface rehabilitation, mill and overlay of failing pavement, asphalt gutter resurfacing, aggregate shoulder work, shoulder grading, full or partial depth patching as necessary, removal of inlets, removal of culverts, disassembly and reassembly of stone headwall, new inlets, custom metal grates, new culverts, new stone headwalls, new precast concrete headwalls and revegetation. Reference the contract documents for the full project scope.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed.
T. Contract Line Item No.20 OPTION PC, Ayers Avenue (Rt. 044) Construction (PMIS 222018)
1. This item consists of all work for pavement repairs and surface treatments detailed in the specifications and exhibits. This item also consists of supplemental verification cores as described in the contract drawings and specifications.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed.
U. Contract Line Item No.21 OPTION PD, Berdan Avenue (Rt. 020) Construction (PMIS 221219)
1. This item consists of all work for pavement repairs and surface treatments detailed in the specifications and exhibits.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work
V. Contract Line Item No.22 OPTION PE, Birney Avenue (Rt. 202) Construction (PMIS 268471)
GETT - 286031 01 27 00 - 6
1. This item consists of all work for pavement repairs and surface treatments detailed in the specifications and exhibits.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed.
W. Contract Line Item No.23 OPTION PF, Crawford Avenue (Rt. 017) Construction (PMIS 222017)
1. This item consists of all work for pavement repairs and surface treatments detailed in the specifications and exhibits.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed.
X. Contract Line Item No.24 OPTION PG, Cross-Brooke-DeTrobriand Avenue (Rt. 043) Construction (PMIS 268632)
1. This item consists of all work for pavement repairs and surface treatments detailed in the specifications and exhibits.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed.
Y. Contract Line Item No.25 OPTION PH, Hancock Avenue (Rt. 010) Construction (PMIS 221224)
1. This item consists of all work for pavement repairs and surface treatments detailed in the specifications and exhibits.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed.
Z. Contract Line Item No.26 OPTION PI, Howe Avenue (Rt. 054) Construction (PMIS 222016)
1. This item consists of all work for pavement repairs and surface treatments detailed in the specifications and exhibits.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed.
AA. Contract Line Item No.27 OPTION PJ, Humphreys Avenue (Rt. 022) Construction (PMIS 221218)
1. This item consists of all work for pavement repairs and surface treatments detailed in the specifications and exhibits.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed.
BB. Contract Line Item No.28 OPTION PK, North Sickles Avenue (Rt. 015) Construction (PMIS 221208)
GETT - 286031 01 27 00 - 7
1. This item consists of all work for pavement repairs and surface treatments detailed in the specifications and exhibits.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed.
CC. Contract Line Item No.29 OPTION PL, Sedgwick Avenue (Rt. 011) Construction (PMIS 221223)
1. This item consists of all work for pavement repairs and surface treatments detailed in the specifications and exhibits.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed.
DD. Contract Line Item No.30 OPTION PM, South Confederate-Sykes Avenue (Rt. 012) Construction
(PMIS 221222)
1. This item consists of all work for pavement repairs and surface treatments detailed in the specifications and exhibits for South Confederate Ave portion of route only.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed.
EE. Contract Line Item No.31 OPTION PN, Big Round top Parking Area (Rt. 916) Construction
(PMIS 311453)
1. This item consists of all work for pavement repairs and surface treatments detailed in the specifications and exhibits.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed.
FF. Contract Line Item No.32 OPTION PO, South Sickles Avenue (Rt. 042) Construction (PMIS 222019)
1. This item consists of all work for pavement repairs and surface treatments detailed in the specifications and exhibits.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed.
GG. Contract Line Item No.33 OPTION PP, Devils Den Parking Area (Rt. 914) Construction (PMIS 311454)
1. This item consists of all work for pavement repairs and surface treatments detailed in the specifications and exhibits.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work
GETT - 286031 01 27 00 - 8
HH. Contract Line Item No.34 OPTION PQ, United States Avenue (Rt. 014) Construction (PMIS 221220)
1. This item consists of all work for pavement repairs and surface treatments detailed in the specifications and exhibits.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed.
II. Contract Line Item No.35 OPTION PR, West Confederate Avenue (Rt. 018) Construction (PMIS 221207)
1. This item consists of all work for pavement repairs and surface treatments detailed in the specifications and exhibits.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed.
JJ. Contract Line Item No.36 OPTION PS, Virginia Memorial Loop Parking Area (Rt. 908) Construction (PMIS 311455)
1. This item consists of all work for pavement repairs and surface treatments detailed in the specifications and exhibits.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed.
KK. Contract Line Item No.37 OPTION PT, Longstreet Tower Parking Area (Rt. 912) Construction
(PMIS 311456)
1. This item consists of all work for pavement repairs and surface treatments detailed in the specifications and exhibits.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work completed.
LL. Contract Line Item No.38 OPTION PU, Wheatfield Avenue (Rt. 013) Construction (PMIS 221221)
1. This item consists of all work for pavement repairs and surface treatments detailed in the specifications and exhibits.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract lump sum price prorated each month for work
END OF SECTION 01 27 00
GETT - 221207 01 31 00 - 1
PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Construction Coordination.
2. Submittals
3. Coordination Drawings.
4. Requests for Information (RFIs).
5. Project meetings.
6. Environmental Coordination.
B. Related Requirements:
1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.
1.2 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
GETT - 221207 01 31 00 - 2
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Pre-installation conferences.
7. Project closeout activities.
1.3 SUBMITTALS
A. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.
1. Letter designating Project Superintendent.
2. Construction Schedule.
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention Plan.
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the
Contactor and all subcontractors.
8. Waste Management Plan.
9. Quality Control Plan.
10. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP).
B. All items listed must be provided to the Contracting Officer before the Pre-Construction Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
1.4 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form created on the NPS/DSC SharePoint Project website.
1. CO will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
GETT - 221207 01 31 00 - 3
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially.
2. Date.
3. RFI subject.
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
8. Contractor's signature.
9. Requested date for response.
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Form: Complete the RFI Form on the NPS/DSC SharePoint website as follows:
1. Enter the general information at the top of the form.
2. Under the “Action” section at the bottom of the form, select “Question” then select “CMR” in the drop-down of the “Send to” box.
3. Enter the details of the question and attach related documents.
4. Select “Submit Form” at the bottom of the page.
D. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond.
CO will determine the critical nature of each RFI and issue a response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Incomplete RFIs or inaccurately prepared RFIs.
2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.
3. CO's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.
GETT - 221207 01 31 00 - 4
1.5 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:
1. Roles & Responsibilities/ Lines of Authority.
2. Park rules and regulations.
3. Jobsite Safety.
4. Resolution of comments on required Division 01 documents.
5. Coordination of Subcontractors.
6. Labor law application.
7. Modifications.
8. Payments to Contractor.
9. Payroll reports.
10. Contract time.
11. Liquidated damages.
12. Contractor Performance Evaluation.
13. Display of Hotline posters.
14. Notice to proceed.
15. Correspondence procedures.
16. NPS/DSC SharePoint Project website.
17. Acceptance/rejection of work.
18. Progress meetings.
19. Submittal procedures.
20. NPS Final Accessibility Inspection.
21. Environmental requirements.
22. As-constructed drawings/operation and maintenance (O&M) manuals.
23. Saturday, Sunday, holiday and night work.
24. Reference materials.
25. Value engineering.
B. Progress Meetings: The Contracting Officer will schedule weekly meetings with the Contractor.
1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:
a. Approval of minutes of previous meetings.
b. Submittal status.
c. Requests for information (RFI) and other issues.
d. Modifications.
e. Work in progress and projected.
1) Status of required inspections (Special Inspections, Accessibility, etc.)
f. Inspections of work in progress and projected (Special inspections, GETT - 221207 01 31 00 - 5
g. Construction Schedule update (provide updated CPM).
h. Status of Project Record Drawings and O&M manuals.
i. Other business relating to work.
j. Permit requirements.
1.6 ENVIRONMENTAL COORDINATION
A. Contractor’s Environmental Manager: Designate an on-site party responsible for overseeing the Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.
1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to those of this project; must be familiar with environmental regulations applicable to construction operations.
2. Responsibilities: Responsibilities shall include:
a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.
b. Implementation of the Storm Water Pollution Prevention Plan(SWPPP).
c. Monitoring and documentation of environmental procedures.
B. Perform project quality control in accordance with requirements specified in Related Sections, including:
1. Quality Requirements.
2. Regulatory Requirements.
3. Temporary Storm Water Pollution Prevention Environmental Management.
4. Construction Waste Management.
C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on the project site. Training shall include the following:
1. Overview of environmental issues related to the Project.
2. Review of site specific procedures and management plans:
a. Construction Waste Management.
b. Temporary Storm Water Pollution Prevention.
3. Pollution Prevention (P2) practices: Submit evidence of familiarity with P2 practices.
4. Compliance with environmental regulations: As specified in Regulatory Requirements.
Submit Contractor 40 CFR employee training records upon request of Contracting Officer.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 31 00
GETT - 221207 01 32 16 - 1
CONSTRUCTION SCHEDULE
SECTION 01 32 16 – CONSTRUCTION SCHEDULE
PART 1 - GENERAL
1.1 SUMMARY
A. This Section consists of Construction Schedule requirements including but not limited to the following:
1. Schedule of Values
2. Construction Schedule Requirements.
3. Construction Schedule Updates.
4. Time Impact Analysis.
B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The Construction Schedule will assist the Contractor and Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment.
1.2 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. Cost Loading: The allocation of the Schedule of Values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.
C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.
D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.
E. Float: The measure of leeway in starting and completing an activity.
1. Float: Float is not for the exclusive use or benefit of either the Government or the Contractor but is jointly owned.
2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.
GETT - 221207 01 32 16 - 2
3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.
F. Resource Loading: The allocation of manpower and equipment necessary for the completion of an activity as scheduled.
G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.
1.3 SUBMITTALS
A. Electronic Copies: All schedules and reports submitted shall be posted on the NPS DSC SharePoint project website, provided in the native electronic file format. It is the intent of the Government to limit the number of printed reports to only those reports determined by the project team to be essential.
B. Schedule of Values: After contract award and before the Pre-Construction conference submit a schedule of dollar values based on the Contract Price Schedule.
C. Construction Baseline Schedule: After contract award and before the Pre-Construction conference, submit two paper copies of baseline schedule, large enough to show entire schedule for entire construction period.
D. Construction Schedule Updates: On or before the 7th day preceding the progress payment request date, submit estimates of the percent completion of each schedule activity and necessary supporting data. Provide two paper copies.
E. Construction Schedule Revisions and Time Impact Analysis: For each Construction Schedule revision submit two paper copies of a Time Impact Analysis. Each Time Impact Analysis shall include a Fragmentary Network (Fragnet), incorporated into the currently accepted Construction Schedule, demonstrating how the Contractor proposes to incorporate a modification, change, delay, or Contractor request.
1.4 QUALITY ASSURANCE
A. The Contractor shall meet with the Contracting Officer on the day of the preconstruction conference to go over the following:
1. Review software limitations, content and format for reports.
2. Verify availability of qualified personnel needed to develop and update schedule.
3. Discuss constraints, including phasing, work stages, area separations, interim milestones.
4. Review delivery dates for Government-furnished products.
5. Review schedule for work of separate Government contracts.
6. Review time required for review of submittals and re-submittals.
7. Review requirements for tests and inspections by independent testing and inspecting agencies.
8. Review time required for completion and startup procedures.
9. Review time required for obtaining and activating permits.
10. Review and finalize list of construction activities to be included in schedule.
GETT - 221207 01 32 16 - 3
11. Review baseline schedule comments, resolve issues and progress on incorporating them
12. Review procedures for updating schedule.
13. Discuss reporting requirements and establish a protocol for naming and transmitting electronic schedules.
B. Contractor's Schedule Representative: Before or at the preconstruction conference, designate an authorized representative to be responsible for the preparation and maintenance of the Construction Schedule. A resume outlining the qualifications of the Scheduler shall be submitted to the Contracting Officer for acceptance. The Scheduler shall have prepared and maintained at least 5 previous schedules of similar size and complexity similar to this Contract, demonstrating proficiency in the use of scheduling software. The authorized representative will be responsible for preparing the Baseline Schedule, all required updates, revisions, Time Impact Analyses, and preparation of reports.
1.5 COORDINATION
A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate Contractors.
B. Coordinate Construction Baseline Schedule with the Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.
1. In developing the Construction Baseline Schedule, ensure that the Subcontractor’s work at all tiers, as well as the prime Contractor’s work, is included and coordinated.
2. Secure time commitments for performing critical elements of the Work from parties involved.
3. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
PART 2 - PRODUCTS
2.1 SCHEDULE OF VALUES
A. Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component work activities for each lump-sum item. Do not include mobilization, general condition costs, overhead or profit as a separate item.
B. Do not break down unit price items. Use only the contract price for unit price items.
C. The total cost of all items shall equal the contract price.