This is a solicitation for a construction project to rehabilitate the Little Round Top Visitor Use Area and various routes at Gettysburg National Military Park. The solicitation includes 38 contract line items for work such as site improvements and restoration at Little Round Top, retaining wall construction, tree removal, signage installation, and pavement preservation on multiple park roads. Bids are due by a specified date in 2022. The award will be a firm-fixed-price contract performed over multiple seasons. The National Park Service is the contracting agency.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REHABILITATE LITTLE ROUND TOP VISITOR
USE AREA
GETTYSBURG NATIONAL MILITARY PARK
GETT PMIS NO. 250272
DIVISION 1 & TECHNICAL
SPECIFICATIONS
FOR CLINS 1-17
NATIONAL PARK SERVICE
DENVER SERVICE CENTER
OCTOBER 1, 2021
CONSTRUCTION DOCUMENTS
GETT - 250727 TOC-1
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 26 01 Contract Modification Procedures 01 27 00 Definition of Contract Line Items 01 31 00 Project Management & Coordination 01 32 16 Construction Schedule 01 32 33 Photographic Documentation 01 33 23 Submittal Procedures 01 35 13.22 Archeological Protection 01 35 23 Safety Requirements 01 35 91 Historic Preservation Treatment Procedures 01 40 00 Quality Requirements 01 42 00 Reference Standards 01 50 00 Temporary Facilities and Controls 01 56 39 Tree Retention and Protection 01 57 19.12 Noise & Acoustics Management 01 57 23 Temporary Storm Water Pollution Prevention 01 67 00 Product Requirements 01 73 40 Execution 01 74 19 Construction Waste Management and Disposal 01 77 00 Closeout Procedures 01 78 23 Operation and Maintenance Data 01 81 13 Sustainable Design Requirements
DIVISION 02: EXISTING CONDITIONS
02 41 00 Site Demolition
DIVISION 03: CONCRETE
03 30 00 Cast-In-Place Concrete
DIVISION 05: METALS
05 50 00 Metal Fabrications
DIVISION 10: SPECIALTIES
10 14 26 Post and Panel Signage
DIVISION 26: ELECTRICAL
26 05 43 Underground Ducts and Raceways for Electrical Systems
DIVISION 31: EARTHWORK
31 10 00 Invasive Species Removal – Not in Contract 31 20 00 Earth Moving 31 25 00 Erosion and Sediment Control 31 32 50 Watering 31 37 19 Stonework 31 50 00 Excavation Support and Protection
GETT - 250727 TOC-2
DIVISION 32: EXTERIOR IMPROVEMENTS
32 12 16 Asphalt Paving 32 13 13 Concrete Paving 32 13 73 Concrete Paving Joint Sealants 32 15 40 Stabilized Aggregate and Stabilized Soil 32 16 13.43 Stone Curb 32 17 26 Tactile Warning Surfacing 32 32 23.01 Mechanically Stabilized Earth Wall 32 33 00 Site Furnishings 32 91 13 Soil Preparation 32 92 19 Seeding and Mulching 32 93 00 Planting
DIVISION 33: UTILITY CONSTRUCTION
33 41 00 Storm Utility Drainage Piping 33 46 00 Subdrainage
GETT - 250272 01 11 00 - 1
091015 SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Work phases.
3. Work under other contracts.
4. Government Furnished Materials.
5. Contractor use of premises.
6. Public use of site.
7. Occupancy requirements for buildings.
8. Work Restrictions.
9. Special Construction Requirements.
10. Soils Investigation Report.
11. Additional Reports.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. This specification book references Contract Line Item Nos 1 – 17.
B. Project Location: The project site is Little Round Top at Gettysburg National Military Park, located in Gettysburg, Adams County, Pennsylvania. The scope of these CLINS includes work on Little Round Top.
C. The Work consists of the following:
1. The Work consists of all work associated with the stabilization, restoration and rehabilitation of Little Round Top. The cultural landscape of Gettysburg National Military Park is listed on the National Register of Historic Places. Little Round Top is a contributing resource to the national significance of the park. There are contributing built and natural resources located throughout the project area. All work must adhere to the Secretary of Interior’s Standards, as per Section 01 35 91 “Historic Preservation Treatment Procedures”. Work includes but is not limited to; temporary monument protection measures, soil erosion and sediment controls, temporary chain link construction fencing & flagging, tree protection fencing, traffic detour devices, permitting, BMPs, demolition of asphalt road and parking, Telford Base protection measures, select areas of asphalt mill and overlay, removal of gravel shoulder, removal and stockpile of topsoil aggregate shoulder, removal of wheel stops, removal of detectable warning strips, salvage select landscape boulders, select removal of boulders and rock outcroppings, demolition of culverts and headwalls, demolition of retaining walls, demolition of signage, demolition of fencing, salvaging and reinstalling stone stairs, and stripping of topsoil, removal of trees, various height stumps to remain, shrubs and groundcover. Improvements include but are not limited to; import of fill material, rough grading, asphalt road, asphalt parking and drop-off areas, asphalt overlay, full depth asphalt patch, granite curbs, paving striping, GETT - 250272 01 11 00 - 2
Modified MSE retaining wall with guardrail, concrete retaining wall with stone veneer & guardrail, cut stone retaining walls, cut stone seat walls, cut stone headwalls, exposed aggregate concrete, stabilized aggregate, stabilized soil, cut stone stairs, cut stone bollards, 34” height guide rails, turndown edge, cut stone edging, pavers culverts, area inlets, riprap, signs, signage foundation and posts, installation of signage panels provided by NPS, empty electrical conduit and restacking historic breastworks. Reference the contract documents for the full project scope.
2. This project is not seeking a Certification Level according to the U.S. Green Building Council's Leadership in Energy & Environmental Design (LEED) Rating System. See as Division 01 Section "Sustainable Design Requirements for Non LEED Projects” for additional information.
D. Project will be constructed under a single prime contract.
1.3 CONTRACTOR USE OF SITE
A. General: Contractor shall have full use of the approved designated project areas for specific construction operations during the construction period. Contractor's use of the site is limited to minimizing site disturbance to the extent possible and by the Government's right to perform work or to retain other contractors on portions of Project. There will be no visitor access within the designated fenced in approved project areas.
B. Limit use of premises to approved project areas. Do NOT disturb the site beyond areas in which the Work is indicated. Reference G5.0, Site Construction Fencing Plan, for project boundaries.
1. Boundaries are defined by a combination of chain link fence, construction fencing and flagging as per the drawings. The boundaries encompass a larger area for the full build out of Little Round Top (LRT). The Contractor does not have full use of the demarcated areas.
Access is limited to improvements and equipment and foot traffic access per the Contractor submitted and Contracting Officer approved construction access plans listed within the Division 01 and Technical specification requirements. The boundaries will be field verified by the Contractor for Contracting Officer approval.
2. NOT THIS CONTRACT: The concurrent Little Round Top Vegetation Restoration (LRT Vegetation) project, under separate contract, will have full access to the project area, including the staging area.
3. Duplicative fencing and flagging, parallel to each other, is not intended. Contractor to consolidate fencing where feasible, as approved by Contracting Officer.
C. Work must be completed without damage to irreplaceable commemorative signs, monuments, stone walls or earthworks, trees not to be removed, trails, survey monuments or signs, roads, or other property. The Contractor will be financially liable to the park for any costs incurred as a result of repairing and/or replacing any of the aforementioned items or for the value of the item as assessed by an archeologist or biologist. Any artifacts recovered are property of Gettysburg National Military Park and should be immediately submitted to the Contracting Officer.
D. Although attempts have been made to locate and evaluate archaeological sites and/or components prior to construction activities, there is a potential that previously unidentified archeological sites, components, and/or human remains will be identified during construction activities. In the event that construction activities inadvertently discover a previously unidentified archeological site, component, and/or human remains the contractor will work cease in the immediate area and notify the contracting officer. Any willful destruction of the archeological site, component, and/or human
GETT - 250272 01 11 00 - 3
remains can result in the prosecution of individuals under the Archeological Resource Protection Act of 1979 (16 U.S.C. 470), and other statutes that protect the Park’s cultural resources.
1. Reference Section 01 35 13.22 “Archeological Protection” for protection and discovery of resources procedures.
2. Any uncovered archeological resources must be protected. If archaeological resources are encountered during work, contractor shall stop work at that location immediately and notify the Contracting Officer. Any artifacts recovered are property of Gettysburg National Military Park.
E. Unexploded Ordinance: Reference Section 01 35 13.22 “Archeological Protection” for additional requirements.
F. Archeological Sensitive Areas: equipment or foot traffic within this area is to be approved by the Contracting Officer. Contractor to provide composite matting per equipment weight for access within the designated archeological sensitive area. Methods to be approved by the Contracting Officer.
G. Do not perform work when climate and existing site conditions will not provide satisfactory results (e.g. wet, freezing). The Contracting Officer reserves the right to deny construction procedures on days that are deemed to be unfavorable for installation. Proceed with construction only when existing and forecasted weather conditions permit construction to be performed when beneficial and optimum results may be obtained.
H. Contractor’s operations shall be conducted reasonably to prevent rutting or other soil damage.
Skidding of logs will not be permitted. No work shall be allowed for at least a 24-hour period following a rain accumulation of one (1) inch or more during the proceeding 24-hour period. After any work stoppage, it will be the responsibility of the Contracting Officer to determine when work may re-commence. Any lost time due to prolonged periods of rain will automatically be credited and added to the length of the contract.
I. All vehicles and other heavy equipment involved in the completion of this contract will be restricted to roads, parking areas, and road shoulders no more than 10’ from the edge of the road surface unless given case-specific permission by the Contracting Officer. Off road equipment use is solely at the discretion of the Contracting Officer and subject to change based on current or anticipated conditions.
Rutting or other resource damage will not be tolerated. All work from trails will be considered off road and must adhere to the same guidelines and restrictions.
J. All vehicles should be equipped with absorptive pads while on park property in order to quickly contain any spills of oil or hydraulic fluid. Any such spills must be reported to the Contracting Officer as soon as is safely possible.
K. Damage to natural areas, existing grades, vegetation, pavements, underground utilities, and other improvements and areas of protection, caused during work under this Contract, shall be repaired to original condition or better at no additional cost to the National Park Service
L. Vehicular accessibility on site shall be as directed by Contracting Officer. Repair damage to existing surfaces, caused by vehicular access and movement during work under this Contract, to original condition at no additional cost to the National Park Service.
M. Western Slope Access Restrictions: all types of construction vehicles are prohibited to traverse the western slope face. Small equipment, for example; wheelbarrows, hand compactors or vibratory plate
GETT - 250272 01 11 00 - 4
compactors, needed for earthwork activities are to utilize the existing asphalt walk for access.
Reference plans for limits of construction.
N. Sykes Avenue Modified MSE Retaining Wall Access Restrictions: large construction vehicles, with more than 2 axles, are prohibited from traversing down the eastern slope face. Medium size vehicles, 2 axles maximum, for example; dump trucks for hauling excess and importing material, bulldozer or backhoe, needed for foundation activities are permitted within the construction limits only. Large construction vehicles 2 axles or greater, for example; flatbed trailers and cranes are to utilize the parking lot area for construction. Reference plans for limits of construction.
O. Stabilized Soil Trail: to the extent possible, eliminate the use of medium size vehicles, 2 axles maximum. Contractor to utilize small equipment, for example; bobcats, wheelbarrows, hand compactors or vibratory plate compactors, needed for trail activities to minimize the area of disturbance to the extent possible. Reference plans for limits of construction.
P. Tree and understory removals outside of the limits of earthwork are to be accessed for removal or felling with the least amount of ground disturbance as possible. Only equipment absolutely needed for tree and understory removals or felling of trees is permitted.
1. Reference Section 02 41 00 Site Demolition and 01 56 39 Tree Retention and Protection for additional information and submittals.
Q. Archeological Monitoring provided by NPS: An Archeological Monitor will observe all ground-disturbing site work, including but not limited to, construction of temporary facilities and all areas of cut and hardscape surface removals, at all archeologically sensitive areas, from a safe location mutually agreed on by Contractor and Monitor. As new ground is broken, Monitor will examine excavated materials, using construction layout centerline and perimeter staking as a reference point to record locations of findings.
1. Reference Section 01 35 13.22 Archeological Protection for additional information and submittals.
R. Storage of Materials: Confine storage of materials to the staging areas identified on the drawings.
Contractor is to coordinate the final staging area boundaries with the Contracting Officer.
Modifications to the approved staging area boundaries are to be approved by the Contracting Officer.
1. Staging area erosion control and stormwater management per NPDES permit requirements and Civil plans and specifications.
2. Existing monuments, breastworks, roads, walls, curbs and gutters, landscape, structures, and improvements destroyed, damaged or removed due to construction of this project shall be replaced or restored in like kind at no additional expense to the Government.
S. Concurrent Projects: Several concurrent projects will be underway during this project’s construction season.
1. Contractor to coordinate limits of construction, temporary fencing and barriers, temporary utilities, staging area, placement of temporary facilities and access needs to not interfere with concurrent projects. Maintain a clear path for emergency access and deliveries at all times. Adjust limits of construction, staging areas limits and temporary utilities throughout the construction season as per the direction of the Contracting Officer.
2. Contractor to coordinate with the concurrent Rehabilitate Little Round Top Visitor Use Area – Vegetation Restoration project (LRT Vegetation) to complete the full build out of the LRT improvements within the specified seasonal and inclement weather restrictions and approved schedule.
3. Contractor to coordinate with the selected concurrent Pavement Preservation Projects.
GETT - 250272 01 11 00 - 5
T. Preservation of Natural and Existing Built Features:
1. The cultural landscape of Gettysburg National Military Park is listed on the National
Register of Historic Places. Little Round Top is a contributing resource to the national significance of the park. There are contributing built and natural resources located throughout the project area. All work must adhere to the Secretary of Interior’s Standards, as per Section 01 35 91 “Historic Preservation Treatment Procedures”.
2. Identification and protection of natural and built features are to be field verified with the Contracting Officer prior to issuing the Historic Preservation Features Preservation Plan.
a. Reference Section 01 35 91 “Historic Preservation Treatment” for additional requirements.
U. Preservation of Natural Features:
1. Ground disturbance is to be approved and monitored by a Government provided
Archeologist, reference 01 35 13.22 “Archeological Protection” for additional information.
2. Sensitive roosting and pupping seasons of the Indiana bat and the Northern long-eared bat is from March 1st through November 1st. Tree clearing is not permitted between March 1st through November 1st. NPS to complete surveys for active nests of migratory birds prior to construction as needed.
3. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
4. Maintain the temporary chain link fence, construction fencing and flagging throughout the duration of construction. Chain link fence to have no ground penetrating posts. Remove fencing and flagging when construction is complete as directed by the Contracting Officer.
5. Provide temporary barriers to protect existing trees and plants and root zones.
6. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with
Contracting Officer and remove agreed-on roots and branches that interfere with construction.
7. Do not fasten ropes, cables, or guys to existing trees.
8. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
9. Reference Section 01 56 39 “Tree Retention and Protection” for retention and protection of trees during the construction of the project.
V. Preservation of Existing Built Features:
1. Prevent damage to existing features not included in the scope of Work. Restore damage to pre-existing conditions, repairing or replacing damage as directed by Contracting Officer, at no additional expense to the Government.
2. Provide temporary barriers to protect existing features and portions thereof.
3. Carefully supervise excavating, grading, filling, and other construction operations near existing features to prevent unintended damage.
W. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
X. Construction Camp: Establishment of a camp within the park will not be permitted.
GETT - 250272 01 11 00 - 6
Y. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent and found the park webpage: Superintendent's Compendium - Gettysburg National Military Park (U.S. National Park Service) (nps.gov) A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
1. Reference Sheet G1.0, Vicinity and Traffic Detour Plan for additional hauling restrictions.
2. Per Superintendent’s compendium: 36 CFR §4.11 – Vehicle Load, Weight and Size Limits;
The following load, weight and size limits, which are more restrictive than State law, apply to the roads indicated under the terms and conditions, and/or under permit as noted:
a. Vehicle load, weight and size limits are addressed in sections 4921 through 4925 of
The Pennsylvania Consolidated Statutes, Title 75.
b. Vehicles exceeding 35 foot in length are prohibited on the following park avenues:
i. South Sickles Avenue between the intersection with Warren Avenue and Ayres Avenue.
ii. Hunt Avenue, Wright Avenue and Howe Avenue along their entire length.
c. No vehicles exceeding eight (8) feet in width are permitted to be operated on park avenues or roadways without a permit and escort.
d. Per Memorandum to Files dated February 12, 1992, the park and Cumberland
Township authorities resolved to restrict commercial truck traffic on Wheatfield Road To vehicles weighing less than 13 tons (26,000 pounds).
3. Visiting hours, public use limits, closures, and area designations for specific use or activities;
a. All park roads are closed to commercial vehicle traffic unless connected with the operations of the park, with the following exceptions;
i. Per memorandum to files dates February 12, 1992, the park and Cumberland
Township Authorities resolved to restrict commercial truck traffic on Wheatfield Road to vehicles weighing less than 13 tons (26,000 pounds).
Commercial vehicles weighing less than 13 tons are permitted on Wheatfield Road.
ii. Commercial vehicles are permitted on Millerstown Road.
4. Activities that require a permit;
a. See the Park’s permit webpage for more information. The following is a compilation of those activities for which a permit from the Superintendent is required;
i. Exceeding of established vehicle load, weight and size limits. Contact the Contracting Officer for permit.
5. Load restrictions when hauling on NPS roads, do not exceed the load restrictions shown in the following table;
Single Units Gross Vehicle Weight, LBS 2 Axles 40,000 3 Axles 48,000
4 or more axles 52,000
6. When the ground is saturated with water or during periods of freezing and thawing, the
Contracting Officer may impose further load restrictions or suspend hauling.
Z. Bridge Load Restrictions:
1. Warren Avenue and Crawford Avenue Historic Bridge Restrictions: Contractor is to limit construction vehicle access over both Warren Avenue and Crawford Avenue historic bridges. Access routes and types of vehicles to be approved by the Contracting Officer.
https://www.nps.gov/gett/learn/management/superintendents-compendium.htm https://www.nps.gov/gett/learn/management/superintendents-compendium.htm
GETT - 250272 01 11 00 - 7
2. Below per four (4) bridge inspection reports, by the Federal Highway Administration in December 2014. Design load for the report(s) was assumed to be a A H15 equivalent (15 tons). Trucks over a H15 equivalent shall not use the bridges.
a. (002P) South Confederate Avenue Bridge (reconstructed 1935): open, no restriction
i. Curb to curb width 30.5’
b. (003P) Crawford Avenue Bridge (built 1902): open, no restriction
i. Curb to curb width 20.3”
c. (004P) Warren Avenue Bridge (reconstructed 1935): open, no restriction
i. Curb to curb width 20.0’
d. (006P) Wheatfield Road Bridge (reconstructed 1935): open, no restriction
ii. Curb to curb width 19.2’
3. The Contractor shall use extreme caution and protective measures shall be in place prior to use of bridges. If there is damage to an existing bridge, it is the Contractors responsibility to repair it to pre-existing conditions per Contracting Officers direction at no additional cost to the Government.
1.4 PUBLIC USE OF SITE
A. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public.
The site will be closed to the public during construction
B. The approved designated fenced and flagged project areas will be closed to the public during construction. Contractor will be solely responsible for maintaining traffic control measures, fencing and flagging throughout the duration of construction, per requirements of all authorities having jurisdiction.
1. Contractor is responsible for tree protection, chain link fence, construction fence and flagging.
2. NOT IN CONTRACT – Vegetation Flagging as labeled and shown on G5.0 Site Construction Fencing Plan
C. Public visitation will continue throughout Gettysburg National Military Park and around the perimeter of Little Round Top.
D. Reference Sheet G1.0, Vicinity and Traffic Detour Plan for traffic detours, road closures and construction traffic route.
1. Tour Route Detour continues into the town of Gettysburg.
E. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public.
Contractor shall make any and all necessary measures to protect the general public from the construction sites. Temporary walk closures will be permitted, when required, upon specific approval of Contracting Officer for a maximum amount of time as approved by NPS.
1. Contractor to identify and provide all means necessary for maintaining ABAAS access routes, egress routes, emergency access and service access within NPS property.
Contractor to sequence construction as necessary and relocate temporary ramps, fencing and gates, signage, barriers and other identified means necessary for access as needed throughout the construction period.
2. Contractor to coordinate vehicular and pedestrian detour plan with Contracting Officer.
Temporary closers to be approved by the Contracting Officer.
GETT - 250272 01 11 00 - 8
1.5 CONDUCT OF OPERATIONS
A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
B. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.6 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 5:00 p.m., Monday through Friday, except when otherwise indicated.
1. Weekend Hours: 7:00 a.m. to 5:00 p.m., are permitted upon request and approval by the Contracting Officer.
2. Early Morning Hours: are permitted upon request and approval by the Contracting Officer.
3. Work on Saturdays, Sundays, Federal holidays, Federal Government Closures (Weather, etc.) or at night may not be performed without prior consent from the Contracting Officer.
Submit requests 24 hours in advance of the work to the Contracting Officer for approval.
4. Hours for noisy activity: are permitted prior to visitors arriving to the park, upon request and approval by the Contracting Officer.
5. Dust: Contractor to adhere to all NPS, Stormwater Pollution Prevention Plan (SWPPP), Best Management Practices (BMPs) and NPDES requirements. Correction measures to take place immediately upon the Contracting Officers request.
6. Work is not permitted 3-4 days prior to and after July 4th, exact duration to be requested and approved by the Contracting Officer.
7. Work is not permitted on November 19th, unless requested and approved by the Contracting Officer.
8. Sensitive roosting and pupping seasons of the Indiana bat and the Northern long-eared bat is from March 1st through November 1st. Tree clearing is not permitted between March 1st through November 1st. NPS to complete surveys for active nests of migratory birds prior to construction as needed.
B. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for contacting Pennsylvania One Call Systems, Inc to locate all utilities prior to construction, 811 or 1-800-242-1776.
3. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
4. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Do not proceed with utility interruptions without Contracting Officer’s written permission.
2. Do not proceed with utility interruptions without contacting the utility company.
GETT - 250272 01 11 00 - 9
3. Notify Contracting Officer not less than two days in advance of proposed utility interruptions.
4. Hours for Utility Shutdowns: are per approval by the Contracting Officer for no longer than 2 hours’ maximum in duration.
D. Smoking: Contractor to establish designated Contractor smoking areas as approved by the Contracting Officer.
E. Existing Historic Resources: Historic structures and features once existed on or near the Project areas. All remnants of existing historic structures and features are to remain undisturbed and archeologically monitored under all circumstances associated with the scope of this Contract.
F. Concurrent Projects: Several concurrent projects will be underway during this project’s construction season. Contractor to coordinate all project schedules.
1.7 SPECIAL CONSTRUCTION REQUIREMENTS
A. Project Website: A project website provided by the CMR and administered by the CMR, will be used by relevant parties, including the Contractor, Government, Designer of Record, Construction Management Representative, and others, for purposes of managing communication and documents during the construction stage.
1. See Section 01 31 00 “Project Management and Coordination” for requirements on using the Project Website.
B. The cultural landscape of Gettysburg National Military Park is listed on the National Register of Historic Places. Little Round Top is a contributing resource to the national significance of the park.
There are contributing built and natural resources located throughout the project area. All work must adhere to the Secretary of Interior’s Standards, as per Section 01 35 91 “Historic Preservation Treatment Procedures”.
C. Sensitive roosting and pupping seasons of the Indiana bat and the Northern long-eared bat is from March 1st through November 1st. Tree clearing is not permitted between March 1st through November 1st. NPS to complete surveys for active nests of migratory birds prior to construction as needed.
D. Any uncovered archeological resources will take a minimum of one day to clear. Durations to be assessed on a case-by-case basis.
E. Unexploded Ordinance: Although the discovery of unexploded ordinance is unlikely, should any unexploded ordinance be encountered during project activities, all necessary steps must be taken to protect such ordinance, as well as Contract staff employees, Park staff and visitors. In the event unexploded ordinances are discovered during the excavation, construction work at that location will stop immediately and the area secured.
1. Contact the Park Archeologist and Supervisory Protection Ranger immediately.
2. If the Park Archeologist and Supervisory Protection Ranger determine the ordinance is an immediate safety hazard, they will contact the Pennsylvania State Police, Gettysburg Barracks 717.334.8111 (who will then contact the Explosive Ordnance Disposal unit).
3. The ordnance must be safely identified, photo documented from as many sides as possible with the exact location identified with GPS coordinate points prior to destruction.
GETT - 250272 01 11 00 - 10
4. Reference Section 01 35 13.22 “Archeological Protection” for additional requirements.
F. Human Remains: The discovery of human remains, funerary objects and objects of cultural patrimony, will be treated in accordance with the Native American Graves and Repatriation Act (NAGPRA); 25 U.S.C. 3001. In the event that human remains, likely funerary objects, or objects of cultural patrimony are discovered during the excavations, construction work at that location will stop immediately, the area will be secured, and the construction foreman or project director (the responsible official on site) will notify the Park Archaeologist immediately.
1. Contact the Park Archeologist and Supervisory Protection Ranger immediately.
2. Reference Section 01 35 13.22 “Archeological Protection” for additional requirements.
G. Contractor to provide all third-party inspections. Contractor to submit inspection reports to the Contracting Officer.
H. Winter Work is permitted. Contractor to submit winter operation plan to the Contracting Officer.
I. Unforeseen circumstances or closures mandated by the Federal Government: the park is closed.
J. Excavation and paving work may be affected seasonally. Paving subbase preparations to take place per Geotechnical report and Civil specifications during the months of April through October.
K. Telford base: use as temporary access road to be approved by the Contracting Officer.
L. No specific phasing required beyond typical construction sequencing.
M. Site consists of shallow bedrock. Reference geotechnical report and Civil specifications for additional removal and construction information.
N. Modified MSE Wall delegated design. Reference Civil drawings and specifications.
O. Tree Felling: will conform to currently approved horticultural practices and the United States Department of Labor Occupational Safety & Health Administration (OSHA) standards. Reference Section 02 41 00 “Site Demolition” for additional information.
1.8 SOILS INVESTIGATION REPORT
A. A soils investigation report entitled Geotechnical Engineering Report, NPS Gettysburg – Little Round Top, October 15, 2020 has been prepared by Schnabel Engineering.
B. A copy of the report is available to all plan holders with this package.
C. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.
1.9 ADDITIONAL DOCUMENTS
A. A report entitled Sykes Avenue Mechanically Stabilized Earth (MSE) Wall Design, November 2020 has been prepared by WSP.
GETT - 250272 01 11 00 - 11
B. Gettysburg National Military Park, Little Round Top, Cultural Landscape Report, Treatment & Management Plan, dated March 2, 2021.
C. GETT-250272-Rehabilitation of Little Round Top Visitor Use Area - Restoration Vegetation Package (not in contract) contract drawings.
D. A copy of the documents are available to all plan holders with this package.
E. If conflicts occur between the additional documents and drawings or specifications, the drawings and specifications govern.
1.10 SUMMARY OF CONTRACT PACKAGES
A. GETT-250272-Rehabilitation of Little Round Top Visitor Use Area includes
1. Contract Drawings (3 PDFs)
2. Division 1 & Technical Specifications (refers to CLINs 1-17) (1 PDF)
3. Soils Investigation Report
4. Sykes Avenue Mechanically Stabilized Earth Wall Design Calculations
B. GETT-318024-Wright Avenue Paving Preservation includes
1. Contract Drawings (1 PDF)
2. Division 1 & Technical Specifications (refers to CLIN 18) (1 PDF)
C. GETT-318022-Warren Avenue Paving Preservation includes
1. Contract Drawings (1 PDF)
2. Division 1 & Technical Specifications (refers to CLIN 19) (1 PDF)
D. GETT 221207-Rehabiltation of Various Routes Package 2 includes
1. Contract Drawings (1 PDF)
2. Division 1 & Technical Specifications (refers to CLINs 20-38) (1 PDF)
3. Geotechnical Report (1 PDF)
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
GETT - 250272 01 26 01 - 1
031414 CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. The work of this section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager, Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
GETT - 250272 01 26 01 - 2
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: This is the hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:
1) Social Security
2) Medicare
3) Workers Compensation– Policy and company calculation to be made available.
4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.
5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.
GETT - 250272 01 26 01 - 3
6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement.
Contractor may utilize the government provided Contractor Estimate Form, or their http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank http://www.nps.gov/dscw/publicforms.htm#ct
GETT - 250272 01 26 01 - 4
own form, provided that it contains the same information and level of detail as the Gov’t provided form.
3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.
Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.
5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.
Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. The labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by the NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for the work being performed.
2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.
3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)
b. Construction Blue Book
GETT - 250272 01 26 01 - 5
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals.
Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.
6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.
8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead………………10% Profits…………….……8%
2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
GETT - 250272 01 26 01 - 6
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 012601
GETT - 250272 01 27 00 - 1
082714 DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
General Note: There are 38 total CLINs associated with this project. Items in dark, black text are referenced in this specification book. Please refer to other specification books for additional CLINs.
A. Contract Line Item No. 1 Gettysburg Little Round Top Improvements (PMIS 250272)
1. This item consists of all work associated with the stabilization, restoration and rehabilitation of Little Round Top. The cultural landscape of Little Round Top is classified as a Historic Site. There are contributing built and natural resources located throughout the project area. All work must adhere to the Secretary of Interior’s Standards. Work includes but is not limited to; temporary monument protection measures, soil erosion and sediment controls, temporary chain link construction fencing, flagging, temporary construction fencing, tree protection fencing, traffic detour devices, permitting, topsoil stripping and stockpiling, demolition of asphalt road and parking, select areas of asphalt mill and overlay, removal of gravel shoulder, removal and stockpile of topsoil aggregate shoulder, removal of wheel stops, removal of detectable warning strips, salvage select landscape boulders, select removal of boulders, demolition of inlets, culverts and headwalls, demolition of retaining walls, demolition of signage, salvaging of fencing, salvaging and reinstalling stone stairs, and removal of trees, shrubs and groundcover.