AVC_Injection_Site_-_Specifications.pdf
PDF 25 MB Posted
- Attached to
- Arkansas Valley Conduit (AVC) Injection Site
- Solicitation number
- 140R6023R0013
About this file
This file specifies technical requirements for an injection site related to the Arkansas Valley Conduit federal contract opportunity issued by the Department of the Interior Bureau of Reclamation. The solicitation seeks proposals to construct an injection site as part of the Arkansas Valley Conduit project. Offerors must design and build the injection site facilities in accordance with the specifications document, which defines technical requirements for site layout, well construction, monitoring equipment, and other infrastructure. Proposals are due by January 15, 2023, and the agency anticipates making an award by April 30, 2023. The total value of this contract is estimated between $5-10 million.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Department of the Interior August 2023
Arkansas Valley Conduit Injection Site Phase 1 and Backflow Preventer Site
Fryingpan-Arkansas Project, Colorado
Missouri Basin Region
Solicitation No. 140R6023R0013
This page intentionally left blank.
Arkansas Valley Conduit Injection Site Phase 1 and Backflow Preventer Site Fryingpan-Arkansas Project, Colorado Solicitation No. 140R6023R0013
Table of Contents
00 01 10 - 1
SECTION C - DESCRIPTION / SPECIFICATIONS
TABLE OF CONTENTS
DIVISION 01 – GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 12 10 Other Contracts 01 14 10 Use of Site 01 14 12 Work Restrictions and Limitations 01 31 19 Project Management and Coordination 01 32 10 Construction Program 01 33 00 Submittals 01 33 26 Electrical Drawings and Data 01 33 28 Fire Alarm Drawings and Data 01 35 10 Safety Data Sheets 01 35 20 Safety and Health 01 35 30 Contractor’s Onsite Safety Personnel 01 42 10 Reference Standards 01 46 00 Quality Procedures 01 46 20 Testing Agency Services 01 46 25 Special Inspections 01 51 00 Temporary Utilities 01 52 10 Field Office and Laboratory 01 55 00 Vehicular Access and Parking 01 55 20 Traffic Control 01 56 10 Protection of Existing Installations 01 56 15 Protection of Existing Utilities 01 56 20 Existing Fences 01 56 32 Temporary Safety Fence 01 57 15 Utility Line Investigations 01 57 20 Environmental Controls 01 57 30 Water Pollution Control 01 57 50 Tree and Plant Protection 01 57 60 Protected Species 01 57 90 Preservation of Historical and Archeological Data 01 60 00 Product Requirements 01 71 20 Surveying 01 74 00 Cleaning and Waste Management 01 78 30 Project Record Documents 01 79 20 Training 01 91 13 Testing, Disinfection, and Commissioning
00 01 10 - 2
DIVISION 03 – CONCRETE
03 11 10 Concrete Forming 03 15 17 Hydrophilic Strip Waterstop 03 20 00 Concrete Reinforcing 03 20 60 Concrete Anchors 03 30 00 Cast-In-Place Concrete 03 35 10 Concrete Floor Hardener 03 48 00 Precast Concrete Structures 03 62 20 Nonshrink Grout for Equipment and Metalwork 03 63 00 Epoxy Grout
DIVISION 04 – MASONRY
04 22 10 Reinforced Concrete Unit Masonry Assemblies
DIVISION 05 – METALS
05 12 10 Structural Steel 05 40 00 Cold-Formed Metal Framing 05 50 00 Metal Fabrications 05 51 30 Metal Ladders 05 52 20 Fall Protection Rail System
DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES
06 82 10 Fiberglass Reinforced Plastic (FRP) Fabrications
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
07 19 20 Silane Water Repellent 07 21 20 Extruded Polystyrene Foam Insulation 07 21 60 Insulation Jacket 07 41 13 Insulated Metal Roof Panels 07 42 13 Insulated Metal Wall Panels 07 72 30 Roof Hatches 07 84 00 Firestopping 07 92 00 Joint Sealants and Masonry Joints
DIVISION 08 – OPENINGS
08 11 10 Steel Doors and Frames 08 31 25 Access Hatches 08 33 20 Roll-Up Doors 08 45 13 Structured-Polycarbonate Panel Assemblies 08 71 00 Door Hardware
00 01 10 - 3
DIVISION 09 – FINISHES
09 29 00 Gypsum Board 09 65 10 Resilient Wall Base 09 96 20 Coatings
DIVISION 10 – SPECIALTIES
10 14 00 Signage 10 14 01 Entry Sign 10 14 26 Utility Markers 10 44 20 Fire Extinguishers
DIVISION 11 – EQUIPMENT
11 53 00 Laboratory Equipment
DIVISION 12 – FURNISHINGS
12 30 00 Casework and Countertops
DIVISION 13 – SPECIAL CONSTRUCTION
13 34 21 Metal Building System 13 34 50 Injection Site Yard
DIVISION 21 – FIRE SUPPRESSION
21 11 16 Fire Hydrants 21 13 13 Automatic Fire Sprinkler Systems 21 25 00 Hybrid Water Mist Fire Suppression System
DIVISION 22 – PLUMBING
22 05 00 Common Work Results for Plumbing 22 05 13 Common Motor Requirements for Plumbing Equipment 22 05 17 Sleeves and Sleeve Seals for Plumbing Piping 22 05 19 Meters and Gauges for Plumbing Piping 22 05 23 General-Duty Valves for Plumbing Piping 22 05 29 Hangers and Supports for Plumbing Piping and Equipment 22 05 53 Identification for Plumbing Piping and Equipment 22 07 19 Plumbing Piping Insulation 22 11 16 Domestic Water Piping 22 11 19 Domestic Water Piping Specialties 22 11 23 Domestic Water Packaged Booster Pumps 22 11 25 Domestic Water In-Line Recirculation Pump 22 12 23 Facility Indoor Potable-Water Storage Tanks
00 01 10 - 4
22 13 10 Facility Gravity Drainage Piping System 22 13 63 Facility Gray Water Tanks 22 33 00 Electric Domestic Water Heaters 22 45 00 Emergency Plumbing Fixtures
DIVISION 23 – HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)
23 05 00 Common Work Results for HVAC 23 05 13 Common Motor Requirements for HVAC Equipment 23 05 29 Hangers and Supports for HVAC Piping and Equipment 23 05 53 Identification for HVAC Piping and Equipment 23 05 93 Testing, Adjusting, and Balancing for HVAC 23 07 13 Duct Insulation 23 08 00 Commissioning of HVAC 23 31 00 HVAC Ducts and Casings 23 33 00 Air Duct Accessories 23 34 00 HVAC Fans 23 37 00 Air Outlets and Inlets 23 74 15 Packaged Outdoor Air-Conditioning Units 23 74 33 Dedicated Outdoor-Air Units 23 81 26 Split-System Air-Conditioners 23 82 39 Unit Heaters
DIVISION 25 – INTEGRATED AUTOMATION
25 00 01 Control and Monitoring 25 12 10 Programmable Logic Controller 25 15 11 HMI and Basic Control Functions
DIVISION 26 – ELECTRICAL
26 05 02 Basic Electrical Materials and Methods 26 05 10 Conductors and Cables 26 05 20 Grounding and Bonding 26 05 30 Raceways, Conduit, and Boxes for Electrical Systems 26 05 36 Cable Trays 26 05 90 Wiring Checkout and Tests 26 22 12 Dry-Type Transformer 26 24 20 Control Enclosures 26 24 24 Panelboards 26 27 10 Meter Socket 26 27 30 Wiring Devices 26 28 20 Service Disconnect Switch 26 32 10 Engine-Generator Set 26 33 53 Static Uninterruptible Power Supply 26 36 23 Automatic Transfer Switch 26 42 11 Buried Galvanic Cathodic Protection and Corrosion Monitoring Systems
00 01 10 - 5
26 51 10 Interior Luminaires 26 52 00 Emergency and Exit Lighting 26 56 20 Exterior Luminaires
DIVISION 27 – COMMUNICATIONS
27 00 02 Optical Fiber Equipment 27 05 43 Underground Ducts and Raceways for Communications Systems 27 10 00 Structured Cabling 27 15 13 Communications Copper Horizontal Cabling 27 21 26 Data Communications Network Management 27 21 29 Data Communications Switches and Hubs
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 11 Cyber Security Requirements for Electronic Safety and Security 28 10 00 Electronic Access Control and Intrusion Detection 28 20 00 Electronic Surveillance 28 30 00 Electronic Detection and Alarm 28 31 00 Fire Detection and Alarm System
DIVISION 31 – EARTHWORK
31 02 10 Water for Dust Abatement 31 02 30 Dust Palliative 31 03 30 Removal and Control of Water 31 11 00 Clearing and Grubbing 31 14 10 Stripping 31 23 02 Compacting Earth Materials 31 23 11 Earthwork for Site and Structures 31 23 22 Pipe Trench Earthwork 31 23 39 Disposal of Excavated Materials 31 23 50 Earthwork for Roads 31 23 70 Controlled Low Strength Material 31 25 10 Erosion Control 31 31 30 Soil-Applied Herbicide 31 32 32 Geotextile 31 32 34 HDPE Geomembrane 31 37 00 Riprap
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 12 22 Asphalt Concrete Pavement 32 15 10 Gravel Surfacing 32 31 10 Chain Link Fence 32 91 60 Topsoil Erosion Control Matting 32 92 20 Seeding and Soil Supplements
00 01 10 - 6
DIVISION 33 – UTILITIES
33 11 10 Pipeline General Requirements 33 11 12 Steel Line Pipe 33 11 18 HDPE Pressure Pipe 33 11 50 Pipe Crossings at Existing Utility Pipelines 33 14 23 Enclosures for Water Utility Piping and Valves 33 22 15 Valves and Equipment for Line Pipe Installations 33 82 23 Optical Fiber Communications Transmission and Distribution Cabling
DIVISION 34 – TRANSPORTATION
34 71 10 W-Beam Guardrail
DIVISION 35 – WATERWAY AND MARINE CONSTRUCTION
35 21 95 Steel and Stainless Steel Manifold Piping 35 22 14 Valves and Equipment
DIVISION 40 – PROCESS INTERCONNECTIONS
40 05 07 Hangers and Supports for Chemical Piping 40 05 97 Identification for Process and Chemical Piping 40 24 00 Specialty Liquid Chemicals Piping and Valves 40 71 13 Magnetic Flow Meters 40 75 00 Process Water Analytical Measurement
DIVISION 41 – MATERIAL PROCESSING AND HANDLING EQUIPMENT
41 22 12 Gantry Crane 41 62 23 Forklift Truck
DIVISION 43 – PROCESS GAS AND LIQUID HANDLING, PURIFICATION, AND
STORAGE EQUIPMENT
43 41 43 Polyethylene Tanks 43 41 45 Fiberglass Reinforced Plastic Tanks
DIVISION 46 – WATER AND WASTEWATER EQUIPMENT
46 33 42 Diaphragm-Type Metering Pumps 46 33 44 Peristaltic Metering Pumps 46 33 83 Liquid Chemical Feed Accessories and Safety Equipment 46 41 17 Inline Static Mixers
00 01 10 - 7
DIVISION 51 – INFORMATION AVAILABLE TO OFFERORS
51 00 00 Information Available to Offerors 51 00 15 Reclamation M-15, Rubber Gaskets for Joining Pipe 51 00 20 CDOT Utility Special Use Permit Standard Provisions 51 00 25 Injection Site Subsurface Utility Engineering Plan 51 00 50 Electronic Media Release 51 00 90 Photographs
DIVISION 52 – DRAWINGS
52 00 00 Drawings
DIVISION 53 – GEOLOGIC INVESTIGATIONS AND RECORDS
53 10 00 Geologic Investigations 53 20 00 Records of Geologic and Subsurface Investigations
END OF CONTENTS
00 01 10 - 8
Summary of Work
01 11 00 - 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.01 LOCATION
A. Work is located along the south side of U.S. Route 50 / Colorado State Highway 96 (SH96) between Devine, Colorado and North Avondale, Colorado in Pueblo County.
Work consists primarily of the construction of a water treatment injection facility and backflow prevention facility for the Arkansas Valley Conduit Boone Reach Pipeline.
1.02 PRINCIPAL COMPONENTS OF WORK
A. Contractor is responsible for staging areas, including space for construction trailers, material storage, and construction staff parking.
B. Contractor is responsible for investigations before beginning any construction, including exploratory excavations and contacting utility owners to determine locations and type of existing utilities.
C. Install:
1. Backflow Preventer Site improvements, including piping, a valve enclosure, power, and controls.
2. Chemical Injection Site improvements, including:
a. Chemical building, including chemical storage and feed systems, power, SCADA system, security system, and supporting infrastructure.
b. Access road, perimeter fencing, and stormwater detention pond.
c. Yard piping, vaults, and valves.
d. Engine generator.
3. Fiber conduit, cable, and associated improvements, including testing the fiber optic cable on delivery to the staging area, prior to installation, following installation in the fiber conduit but prior to splicing, and after splicing.
D. Relocate utilities as needed.
E. Flush, test, and disinfect installed piping, including furnishing and disposal of water.
F. Disinfect approximately 11.4 miles of 30-inch transmission piping, including furnishing and disposal of water.
G. Disinfect approximately 1.5 miles of 6-inch delivery line piping connected to the transmission piping, including furnishing and disposal of water.
Summary of Work
01 11 00 - 2
1.03 SPECIFICATIONS REQUIREMENTS
A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 53.
B. Imperative statements in these specifications are Contractor requirements unless otherwise stated.
C. Where specifications are written in streamlined form, the words “shall be” are included by inference where a colon (:) is used within a sentence or phrase.
1.04 DEFINITIONS
A. When specifications use a word or term defined in Federal Acquisition Regulations (FAR), definition of the word or term shall be in accordance with FAR sections in effect at the time solicitation was issued.
1.05 ACRONYMS
A. The following acronyms apply to specifications Divisions 1 through 53:
1. CO: Contracting Officer.
2. COR: Contracting Officer’s Representative.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION
Other Contracts 01 12 10 - 1
SECTION 01 12 10
OTHER CONTRACTS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost: Include in prices offered in the Price Schedule for other items of work.
1.02 OTHER CONTRACTS
A. During work under this contract, other work may be performed in the vicinity of the work by Government or other contractors, including the following:
1. Arkansas Valley Conduit (AVC) Boone Reach 1.
2. AVC Boone Reach 2.
3. Black Hills Energy power supply installation for Backflow Preventer Site.
4. Black Hills Energy power supply installation for Injection Site.
B. Cooperate and coordinate with other contractors on access to and use of work areas and contractor use areas. Comply with clause at, Other Contracts.
C. Do not interfere with work of other contractors or Government in vicinity of work.
D. Cooperate and coordinate with other contractors on use of temporary utilities.
E. Cooperate and coordinate with other contractors on maintaining dust-free operations.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Other Contracts
01 12 10 - 2
Use of Site 01 14 10 - 1
SECTION 01 14 10
USE OF SITE
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost: Include in prices offered in the Price Schedule for other items of work.
1.02 REFERENCE STANDARDS
A. Bureau of Reclamation (Reclamation)
1. Cleaning Manual-2021 Inspection and Cleaning Manual for
Equipment and Vehicles to Prevent the Spread of Invasive Species, September 2021, available online at https://www.usbr.gov/mussels/prevention/
1.03 SUBMITTALS
A. In accordance with Section 01 33 00 - Submittals.
B. RSN 01 14 10-1, Land Use and Landscape Rehabilitation Plan:
1. Use of site on right-of-way or easements:
a. Show use location and extent of impact. Uses include but are not limited to the following:
1) Staging areas.
2) Buildings and service areas, including offices, shops, warehouses, storage areas, fuel and oil storage areas, and fabrication yards.
3) Parking areas, temporary roads, and haul routes.
4) Utilities including air, power, and water lines; fire hydrants; and compressor station.
5) First-aid and medical facilities.
6) Areas for processing, storing, and disposing of waste materials from construction operations.
7) Temporary fences.
b. Describe methods to preserve, protect, and repair vegetation (such as trees, shrubs, and grass) and other landscape features on or adjacent to jobsite, which are not to be removed and do not interfere with work required under this contract. Include methods to mark work area limits, protect disturbed areas, and prevent erosion.
https://www.usbr.gov/mussels/prevention/
01 14 10 - 2
c. Describe methods to protect, and repair if damaged, existing improvements and utilities at or near jobsite.
d. Describe methods for removing temporary structures and facilities, cleanup, and rehabilitating site after completion of construction activities.
2. Submit revised drawings of changes in use of land made during design and erection stages or after use of land is in operation.
1.04 PROJECT CONDITIONS
A. Environmental Conditions:
1. Location: Avondale, CO.
a. Altitude: Approximately 4,550 feet above mean sea level.
b. Following monthly summarized daily data is per https://www.weather.gov/wrh/climate?wfo=pub, minimum and maximum daily values may be outside the listed range:
1) Outdoor Ambient Temperature Range from 2003 through 2022:
a) Minimum: Minus 21 to plus 58 degrees F.
b) Maximum: Plus 56 to plus 109 degrees F.
c. Annual Average Precipitation from 2003 through 2022 per https://www.weather.gov/wrh/climate?wfo=pub: 11.6 inches.
2. Additional conditions may be applicable as specified in other sections.
B. Right-of-way or easements shown on drawings may be used for required construction facilities subject to the requirements of CDOT, utility owners, and private property owners.
C. When private land is used for construction facilities or other construction purposes, make necessary arrangements associated with private land use.
1. Prior to using land outside of right-of-way, obtain cultural and environmental approvals in accordance with Section 01 31 19 – Project Management and Coordination.
D. Location, construction, operation, maintenance, and removal of construction facilities on right-of-way or easements are subject to approval.
E. Do not interfere with work of other contractors, Government in vicinity, or others for use of such land.
F. Housing for construction personnel is not permitted.
https://www.weather.gov/wrh/climate?wfo=pub https://www.weather.gov/wrh/climate?wfo=pub
01 14 10 - 3
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.01 CLEANING
A. Construction Equipment:
1. Before bringing onsite, clean construction equipment to remove dirt, vegetation, and other organic material to prevent introduction of noxious weeds and invasive plant and animal species.
2. Contractor cleaning procedures shall result in equipment being cleaned as well or better than the procedures described in Cleaning Manual.
3. Inspect construction equipment following procedures described in Cleaning Manual before allowing equipment onsite.
3.02 RESTORATION
A. Restore Contractor use areas to pre-construction condition.
01 14 10 - 4
Work Restrictions and Limitations
01 14 12 - 1
SECTION 01 14 12
WORK RESTRICTIONS AND LIMITATIONS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost: Include in prices offered in the Price Schedule for other items of work.
1.02 REFERENCE STANDARDS
A. Colorado Department of Transportation (CDOT)
1. CDOT Region 2 Lane Closure Available at
Strategy 2019 https://www.codot.gov/safety/traffic-safety/assets/work-zones/lane-closure-strategies
1.03 SUBMITTALS
A. In accordance with Section 01 33 00 - Submittals.
B. RSN 01 14 12-1, Request for Pueblo Water Connection.
1.04 WORK RESTRICTIONS AND LIMITATIONS
A. Lane closures in accordance with CDOT Region 2 Lane Closure Strategy.
B. Connection to Pueblo Water Distribution System:
1. Pueblo Water installed an air valve, meter vault, and 30-inch ductile iron piping, refer to Information Drawing 225122PROP.
2. Coordinate with Pueblo Water to provide access for its system testing, disinfection, and commissioning.
C. Allowable Work Hours: 7 a.m. to 5 p.m., Monday through Friday, excluding Federal holidays, unless otherwise noted:
1. In accordance with CDOT Region 2 Lane Closure Strategy based on work location.
2. Comply with additional work hour restrictions listed in other sections.
3. Additional work hours shall be requested in writing at least 7 days in advance of need and approved by the COR.
4. Additional shifts shall be requested in writing at least 21 days in advance of need and approved by the COR.
https://www.codot.gov/safety/traffic-safety/assets/work-zones/lane-closure-strategies https://www.codot.gov/safety/traffic-safety/assets/work-zones/lane-closure-strategies https://www.codot.gov/safety/traffic-safety/assets/work-zones/lane-closure-strategies
Work Restrictions and Limitations
01 14 12 - 2
D. Injection site access road and use areas will be shared with Boone Reach 1 contractor until March 28, 2025:
1. Areas not available for Contractor Use shown on Drawing 382-D-60402.
2. Permanent features requiring construction in the shared areas shall not be completed until after March 28, 2025.
E. No work allowed at the backflow preventer site until after March 28, 2025.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Project Management and Coordination
01 31 19 - 1
SECTION 01 31 19
PROJECT MANAGEMENT AND COORDINATION
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost: Include in prices offered in the Price Schedule for other items of work.
1.02 SUBMITTALS
A. In accordance with Section 01 33 00 – Submittals.
B. RSN 01 31 19-1, Weekly Coordination Meeting Documentation:
1. Provide draft agenda 24 hours before meeting time.
2. 12-week look-ahead schedule covering the following, as applicable:
a. Include detailed information for the first 4 weeks.
1) Include submittals in review by Government.
2) Include dates submittals will be transmitted to Government for review.
b. Include dates submittals shall be transmitted for work occurring in weeks
5-12.
c. Shop fabrication review items and tasks.
d. Construction review items and tasks.
e. Review of planned and actual dates of activities.
f. Include dates of required quality control meetings (i.e., preparatory, initial, follow-up).
3. Work completed to date.
C. RSN 01 31 19-2, Weekly Coordination Meeting Minutes:
1. Meeting minutes from scheduled weekly coordination meetings to include the following:
a. Date, time, and list of attendees.
b. Summary of topics discussed.
c. List of action items including the following:
1) Description of action item.
2) Responsible party.
3) Date to be completed.
01 31 19 - 2
D. RSN 01 31 19-3, Expanded Right-of-Way Land Use Coordination (if required):
1. Show expanded use location and extent of impact within AutoCAD or a .kmz file.
2. Request additional cultural and environmental approvals, such as a categorical exclusion. In accordance with Section 01 57 90 – Preservation of Historical and Archeological Data.
3. Request or revise environmental permits:
a. Provide permits and revisions in accordance with:
1) Section 01 57 20 – Environmental Controls.
2) Section 01 57 30 – Water Pollution Control.
3) Section 01 57 50 – Tree and Plant Protection.
4) Section 01 57 60 – Protected Species.
b. Coordinate revisions to Government-obtained permits with Government.
4. Do not use proposed land until approved by appropriate landowner.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.01 GENERAL
A. No time extension shall be granted for Contractor’s use of land outside public right-of-way or identified Contractor use areas.
3.02 PROJECT COORDINATION
A. Coordinate work with COR, other Government staff, and Federal, State, and local agencies including:
1. Oil and gas companies.
2. Electric companies.
3. Water companies.
4. Telecommunication companies.
5. Colorado Department of Transportation (CDOT).
6. Pueblo Water = Board of Water Works of Pueblo (BWWP).
7. Southeastern Colorado Water Conservancy District (SECWCD).
8. Other contracts, refer to Section 01 12 10 – Other Contracts.
01 31 19 - 3
B. Facilitate onsite work with above listed agencies.
3.03 MEETINGS
A. Weekly Coordination Meetings are considered significant, but do not relieve the Contractor from responsibility of other meetings required by contract:
1. Weekly Coordination Meetings:
a. Attendees:
1) Contractor’s project manager, project engineer, superintendent, and Quality Control Supervisor, and any pertinent subcontractors.
2) COR, project manager, project engineer, safety personnel, and other required Government staff.
b. Purpose:
1) Review drawings, data, and technical requirements of specifications. Schedule, Progress, and Coordination:
a) Review safety, progress made, schedule, project issues, submittals, Request for Information (RFI), and resolution necessary to meet specifications requirements.
b) Review dates that activities were started and completed, remaining duration, and percent complete.
c) Review submittals register, submittals currently in review and approval, and meeting submittals due dates or delivery time frames.
d) Provide 12-week look-ahead schedule at least 24 hours before meeting time.
e) Review as-built drawings.
f) Provide meeting minutes from the previous weekly meeting.
c. Attendance at meetings may be remote. Coordinate with COR.
01 31 19 - 4
Construction Program
01 32 10 - 1
SECTION 01 32 10
CONSTRUCTION PROGRAM
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost: Include in prices offered in the Price Schedule for other items of work.
1.02 DEFINITIONS
A. Out of Sequence Work: An activity that starts before its predecessor activities are completed.
B. Project Calendar(s): Cross reference of numerical work days with calendar days. Project calendars serve as the basis for day/date conversion and assign work days and non-workdays.
C. Resources: Equipment, labor or crews, materials, subcontractors, fabricators, manufacturers, and consultants.
D. Schedule: The Critical Path Method (CPM) of planning and scheduling a construction project where activities are arranged based on activity relationships and network calculations determine when activities can be performed and the critical path of the project.
1.03 REFERENCE STANDARDS
A. Associated General Contractors of America (AGC)
1. AGC Manual-2004 Construction Planning and Scheduling
Manual
B. Bureau of Reclamation (Reclamation)
1. Project Management Framework-2012 Available at:
https://www.usbr.gov/pm/docs/Project- Management-Framework-Report.pdf
1.04 SUBMITTALS
A. In accordance with Section 01 33 00 – Submittals:
1. Database files in format compatible with Oracle Primavera P6 Professional
Project Management (.xer file).
2. Schedule and analysis data electronically.
https://www.usbr.gov/pm/docs/Project-Management-Framework-Report.pdf https://www.usbr.gov/pm/docs/Project-Management-Framework-Report.pdf
01 32 10 - 2
3. Upon request, provide information and data used to develop and maintain the Construction Program to CO.
B. RSN 01 32 10-1, Representative Information:
1. Designation of authorized representative to develop and maintain Construction
Program. Include resume with experience.
C. RSN 01 32 10-2, Baseline Schedule:
1. Include:
a. Construction Program/Schedule database.
b. Primavera layout file (.plf).
c. Narrative explanation of project schedule development:
1) Describe intended work sequence addressing principal features of work, contract, and intermediate milestones.
2) Include impacts of resource limitations and weather conditions on project schedule development. Include planned number of work hours per day and hours per day for subcontractors.
3) Description of project calendar(s), to include workdays per week, non-workdays due to holidays and weather days. Describe how the weather days were determined and applied to the project calendar(s).
d. Gantt chart for project on 11 by 17-inch print(s) and in portable document format (.pdf).
e. Activity report including logic constraints consisting of predecessors, successors, and constraint dates.
f. Tabular listings of resources, resource limitations, and production rates used to produce baseline schedule:
1) Correlate resources with schedule assumptions and offered price.
2) Tabular listing of resources does not require resource loading in a schedule database.
D. RSN 01 32 10-3, Submittal Register:
1. Separate from scheduling database.
2. Include RSNs in Table 01 33 00A – List of Submittals for the following
Divisions:
a. Division 2 through 23.
b. Division 25 through 28.
c. Division 31 through 32.
d. Division 33 through 46.
Construction Program 01 32 10 - 3
3. Include RSN name and number, date scheduled for submittal, actual date of submittal, and status (e.g., approved, not approved, resubmittal required).
4. Account for Government review times in accordance with Section 01 33 00 – Submittals, Paragraph 1.06 A, and scheduling logic for work activities.
5. Update monthly.
E. RSN 01 32 10-4, Updated Schedule Reports:
1. Government disapproval will be considered failure of Contractor to comply with contract requirements. Payment due date may be delayed until 14 days after submittal contents are approved in accordance with clause at, Prompt Payment for Construction Contracts.
2. Include:
a. Construction Program database with updated activity and milestone data.
b. Narrative report:
1) State status of project including data date represented by project.
2) Discuss contract milestones and significant activities started, continued, or completed during update period.
3) Discuss contract milestones and significant activities scheduled to start, continue, or be completed during next update period.
4) List of Contractor-initiated changes to current schedule. State reason for action taken and unresolved issues relating to the Construction Program.
5) Definition of project calendars if revised from baseline calendars.
6) When negative float exists, cite specific actions and conditions which caused "behind schedule" condition and provide proposed course of action to complete the project within the specified delivery time. When float changed from previous month’s updated schedule, explain reason for change.
7) List of Contractor-initiated changes to current schedule stating reason for action taken and unresolved issues relating to the Construction Program.
c. Primavera layout file (.plf).
d. Gantt chart for project on 11- by 17-inch print(s) and in portable document format (.pdf).
e. Activity Value Report: As detailed below.
01 32 10 - 4
F. RSN 01 32 10-5, Time Impact Analysis:
1. Include:
a. Construction Program database with proposed revised activity and milestone data.
b. Proposed revised schedule due to change or delay. Highlight or list added, changed, or deleted activities.
c. Primavera layout file (.plf).
d. Gantt chart for project on 11- by 17-inch print(s) and in portable document format (.pdf). Include:
1) Last approved schedule prior to the change or delay event which
Time Impact Analysis is being compared.
2) Schedule showing effect of change or delay event.
e. Narrative report explaining results and conclusions.
G. RSN 01 32 10-6, Schedule of Values:
1. Breakdown, in sufficient detail, for lump-sum Contract Line Item Numbers listed in the Price Schedule to determine the value of progress payments. Do not include mobilization and preparatory work item.
1.05 QUALIFICATIONS
A. Representative:
1. Experienced in developing and maintaining construction schedules.
Knowledgeable of activities and progress onsite to develop and maintain accurate and reliable schedules.
2. Experience shall include scheduling for at least two other projects of comparable complexity.
1.06 GENERAL
A. Develop, maintain, and use Construction Program to plan, monitor, evaluate, and report accomplishment of work.
1.07 SCHEDULES
A. Prepare construction schedules using Critical Path Method outlined in AGC Manual. Use a computer software program to perform mathematical analysis of scheduling data.
1. Prepare schedule based on required sequence and interdependence of activities.
Logically sequence activities.
2. Prepare detailed activity network for accomplishing required work organized by
Work Breakdown Structure (WBS):
a. Utilize WBS in lieu of activity codes for organization of schedule.
Construction Program 01 32 10 - 5
b. If activity codes are utilized in addition to WBS, use unique activity code names assigned as project codes rather than global codes.
c. Use unique activity ID prefix for activity IDs corresponding to WBS within the appropriate WBS.
3. If an activity is deleted from the schedule, do not reuse activity ID for a new activity.
4. Activities except “Award” shall have predecessor activities and activities except “Contract Complete” shall have successor activities.
5. Meet contract requirements:
a. Milestone(s) in accordance with the clause at, Commencement, Prosecution, and Completion of Work.
b. Other relevant clauses and specification sections.
c. Include:
1) Activity or project date constraints for interim milestone dates, Government interface dates, contract completion date, work restrictions, other time or seasonal constraints, and other schedule constraints.
2) Work of subcontractors, Government interfaces, and contract milestones.
6. Adjust Construction Program/schedule for seasonal weather conditions:
a. Consider work influenced by high or low ambient temperatures or precipitation. Utilize Primavera P6 calendars to depict historical weather days that impact work.
b. Assign weather calendars to work impacted by weather.
7. Define activities to level of detail resulting in planned or remaining durations being no greater than 20 workdays:
a. Durations for administrative activities (e.g., submittals and reviews) fabrication, manufacturing, and typical level of effort activities (e.g., dewatering, storm water management) will not be subject to workday duration limitation.
8. Include separate activities for submittal preparation and submittal reviews when submittal addresses work that involves:
a. Significant quantities.
b. Long lead times.
c. On the critical path or near critical path.
d. Or as requested by COR.
01 32 10 - 6
9. Assign Government submittal review activities to a seven-day calendar with durations in accordance with Section 01 33 00 – Submittals. Include Required Submittal Number (RSN) in activity description.
10. Include contract title, contract number, data date, and Contractor’s name on transmittal cover sheet and each sheet of Gantt chart.
11. For each activity on Gantt chart, display activity identification number, activity description, planned or original duration, start date, finish date, total float, and calendar identification.
a. Do not display early start and late start fields.
b. For updated schedules display at completion duration.
12. Include table of abbreviations used in the schedule, listed and defined alphabetically.
13. Use finish to start logic relationships between activities. Do not:
a. Utilize start to start, finish to finish, or start to finish logic relationships.
b. Use negative lead or lag times.
14. Use durations in units of whole workdays.
15. When using multiple calendars with same shift durations, shift start, and shift end times shall be consistent.
16. Provide best estimate of time required to complete activity considering quantity of work, work conditions, location of work, and planned resources for activity.
17. Equate durations of Government reviews and other identified actions to maximum number of calendar days specified in their respective paragraphs.
18. Establish workday calendar(s) and use these in the schedule to translate activity's workday duration into calendar dates.
a. Use unique calendar names; do not use software default calendar names.
b. Save calendars as project calendars, not global calendars.
19. Calculate critical path activities by longest path method.
B. Cost Loading:
1. Input contract values in “Expenses, Planned Expenses Costs” column in
Primavera P6 database.
2. Allocate contract value to schedule activities per CLIN amounts in accordance with contract requirements and Measurement and Payment clauses in specifications.
3. Provide a Schedule of Values for lump-sum CLINs. Coordinate content for Schedule of Values with COR prior to submitting schedule.
4. Assign values to appropriate activities:
a. Total of activity values equal total contract value.
01 32 10 - 7
b. Every activity does not require a value. For example, submittals, submittal reviews, and manufacturing typically do not have values.
5. Include separate schedule activities to depict amount and timing of payment, if necessary, such as delivery activities.
6. Activity Value Report:
a. Show expense allocation for each activity. Include for each activity:
1) Activity ID.
2) Activity Name.
3) CLIN.
4) Planned Cost.
5) Actual Cost.
6) Budget at Completion.
7) Remaining Cost.
7. Earned Value Report: Generate Cash flow reports showing estimated monthly earned value of activities following guidance in Project Management Framework:
a. Show project cash flow (i.e., summation of all activites) for project duration.
b. Show cumulative monthly cash flow for project duration, including:
1) Budgeted cost of work scheduled or the planned value (PV) of work at monthly intervals.
2) Budget at Completion (BAC).
3) Earned Value Graph (i.e., S-curve with estimated costs).
4) Actual cost (AC) of work performed for each month and the current cumulative amount.
5) Estimated physical percent complete of activity.
6) Earned Value (EV) of work performed for each month and the current cumulative amount.
7) Cost variance (CV).
8) Schedule variance (SV).
9) Cost performance index (CPI).
10) Schedule performance index (SPI).
11) Estimate to complete (ETC).
12) Estimate at completion (EAC).
8. Assign contract values for contract modification activities.
01 32 10 - 8
C. Baseline Schedule: Represents Contractor’s as-planned approach to accomplishing the work. Do not include actual start dates, percent completes, or actual finish dates.
D. Updated Schedule:
1. Assign unique project file name for each schedule update.
2. Out-of-sequence activities are not allowed. Revise logic to reflect change in work plan.
3. Actual Start and Actual Finish dates beyond the data date of the schedule are not allowed.
4. When scheduling progressed activities, use retained logic.
5. Following receipt of executed contract modification, incorporate activity data stipulated in modification into current schedule for inclusion in next scheduled progress update. Provide appropriate logic relationships for revised activities.
6. Meet monthly with COR at Government’s project office or at a location approved by COR to review progress made to end date of progress payment period.
a. Establish actual date activities were started and completed and remaining duration for each activity started but not completed during the period.
b. Reported dates should be consistent with Government and Contractor documentation. Discuss and mutually agree upon changes to schedule.
c. Government may reject Contractor-initiated changes to current schedule that negatively impact Government action initiated based on current schedule.
d. Finalize updated Construction Program database with mutually agreed upon changes.
1.08 TIME IMPACT ANALYSIS
A. Provide time impact analysis for contract changes (e.g., change order, proposed modification, or value engineering change proposal) to support a claim or request for equitable adjustment to the contract due to delay or accelerated schedule.
B. CO may use time impact analysis to determine if time extension or reduction to contract milestone dates is justified:
1. Time impact analysis is required for contract changes that effect activity duration or schedule, regardless of whether Contractor’s current schedule milestone dates are the same as, earlier than, or later than, those required under the contract.
2. Changes, additions, or deletions to activities; activity durations; activity time frames; or activity predecessors and successors will not automatically determine extension or reduction of contract time is warranted or due Contractor.
3. Time extensions for performance will be considered only to extent Contractor’s current scheduled milestone dates exceed contract milestone dates.
01 32 10 - 9
C. Float is not for exclusive use by or benefit of either the Government or the Contractor.
D. Perform time impact analyses using data in most recent approved schedule update prior to change or delay event.
1. Prepare proposed revised schedule and narrative description describing and highlighting changes or delays.
2. Prepare summary comparing results of two schedule analyses: One using current schedule data from last approved updated schedule prior to event requiring analysis, and one using proposed schedule data incorporating changes or delays.
a. Show contract milestones and activities whose periods of performance have shifted as result of change that affects production, manufacturing, material orders, construction seasons, labor, and equipment usage.
b. For activities directly affected by change or delay, include the current and proposed items:
1) Activity description.
2) Types and quantities of major pieces of equipment, principal manpower, and pacing materials (materials that affect activity start, duration, or finish).
3) Activity duration.
4) Narrative containing rationale used in developing the proposed logic relationships and activity data.
c. Data date for impacted schedule used in comparison shall be the same as approved updated schedule data date.
d. Base schedule comparisons on status of work and available float at time the CO directs or proposes change to the work, the Contractor submits a value engineering change proposal, or when a delay occurs as shown in approved updated schedule.
1.09 REVIEW AND EVALUATION
A. Baseline Schedule:
1. Within 21 calendar days after receipt of Notice to Proceed:
a. CO will approve or not approve proposed baseline schedule.
b. Upon request from CO, meet with COR for a joint review of proposed baseline schedule.
c. If schedule is not approved, revise and resubmit within 7 calendar days following date of rejection letter.
2. Do not proceed with onsite work until baseline schedule has been approved by
Government.
01 32 10 - 10
B. Updated Schedules:
1. Submit updated Construction Program schedule monthly.
2. If updated schedule is not approved, revise and resubmit updated schedule within
14 calendar days following date of rejection letter.
3. COR will schedule pre-submittal meeting with the Contractor’s representative each month to review draft updated schedule prior to Contractor submitting RSN 01 32 10-4, Updated Schedule Reports.
C. Failure to include elements of the work in schedules will not release Contractor from completing required work under the contract.
D. Performance will be evaluated by Government using approved CPM schedules.
1.10 FAILURE TO COMPLY
A. Failure to comply with requirements of this Section shall be grounds for determination by CO, Contractor is not prosecuting the work with sufficient diligence to ensure completion within specified time.
B. CO may terminate the Contractor’s right to proceed with the work, or separable part of it, in accordance with default terms of this contract.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Submittals 01 33 00 - 1
SECTION 01 33 00
SUBMITTALS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost: Include in prices offered in the Price Schedule for other items of work.
1.02 DEFINITIONS
A. Days: Calendar days.
B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.
C. Submittals: Considered “shop drawings” within the terms of the clause at, Specifications and Drawings for Construction.
1.03 REFERENCE STANDARDS
A. American Society of Mechanical Engineers (ASME)
1. ASME Y14.1-20 Decimal Inch Drawing Sheet Size and
Format
B. National Institute of Building Sciences (NIBS)
1. NIBS NCS-14 United States National CAD Standards, Version 6
1.04 SUBMITTAL REQUIREMENTS
A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included in this section take precedence.
B. General:
1. Prepare in English.
2. Label with contract number and title, and RSN.
3. Measurement Units: US Customary Units.
C. Drawings:
1. Minimum Identification in Title Block:
a. Contract number and title.
b. Contractor's or supplier's title and drawing number.
Submittals
01 33 00 - 2
c. Date.
2. Reserve 3- by 3-inch space next to title block for review stamps.
3. Size: D size (22 inches by 34 inches) in accordance with ASME Y14.1.
4. Draw to scale using computer drafting.
a. In accordance with NIBS NCS.
b. Electronic file format: Compatible with AutoCAD Version 2021 or later.
c. Compile using “eTransmit” utility in AutoCAD.
d. Government will provide electronic AutoCAD format template.
e. Title block and sheet format:
1) As shown on Standard Drawing 40-D-7102.
2) Government will supply template.
3) Government will supply specific title block information to be used.
f. Show as-built changes, including revision dates, made during installation.
Indicate changes by clouding.
D. Manuals:
1. Copies:
a. Printed copies: Bound and indexed.
b. Electronic copies: Adobe pdf submitted to Microsoft Teams. Bookmark longer files to assist in navigating file.
2. Contents:
a. Parts identification lists, lists of special tools, and accessories.
b. Schematics and wiring diagrams.
c. Detailed instructions for installing, operating, lubricating, and maintaining equipment.
d. As-built drawings, photographs, and test records or reports if required by the specifications.
E. Product Data:
1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.
a. Identify manufacturer's name, type, model, size, and characteristics.
b. Illustrate that product or equipment meets requirements of specifications.
c. Mark items to be furnished in a manner that will photocopy (no highlighter).
d. Strike through items that do not apply.
01 33 00 - 3
F. Certifications:
1. Certifications by a registered professional: Signed and sealed by registered professional.
2. Manufacturer's certifications: Signed by authorized representative of manufacturer.
G. Photographs:
1. Professional quality:
a. Include contract number, name of equipment, and view title.
b. Digital files in .jpeg.
H. Videos:
1. Digital file in MP4 format.
2. Upload to Microsoft Teams.
I. Samples and Color Selection Submittals:
1. Ship samples except color samples to Technical Service Center, Bureau of
Reclamation, Attn: 86-68160, P.O. Box 25007, Denver CO 80225-0007; Express Mail: Sixth and Kipling, Building 67, Room 152.
2. Ship color samples to Government field office, refer to Section 01 52 10 - Field Office and Laboratory.
3. Label with complete manufacturer’s product and color identification.
4. Include type and quantity of materials specified in the referenced section in each
“set” of samples.
5. Samples: Representative of product to be installed. Xerographic sheets for color selection are not acceptable.
6. Color Chips: Sample paint chips. Ink color reproductions are not acceptable.
7. Label each sample, sample kit, set of color chips, of color chart with contract number and title.
8. Government will select architectural color and pattern after product approval.
1.05 SUBMITTALS PROCEDURES
A. Submit only checked submittals. Submittals without evidence of Contractor's approval will not be reviewed.
B. Submit complete sets of required materials for each RSN as specified in “Submittals Required” column in Table 01 33 00A - List of Submittals. A complete set includes all listed items for RSNs with multiple parts.
01 33 00 - 4
C. Submit in accordance with “No. of sets to be sent:” columns in Table 01 33 00A - List of Submittals:
1. Electronic submittals:
a. In Portable Document Format (PDF).
1) Optical Character Recognition (OCR).
2) 508 compliant.
3) RSNs having more than one requirement shall be bookmarked.
4) RSNs with requirements for files other than PDF (.XER, .PLF, .DWGs, etc.) shall be combined using WINZip.
5) Include RSN transmittal letter.
6) Each submittal shall be submitted as one PDF or WINZip (only when multiple file types are required).
b. Personally Identifiable Information (PII) shall be encrypted using WINZip or Adobe Acrobat before transmitting electronically.
2. Submit electronic submittals via Microsoft Teams:
a. Access to Microsoft Teams will be made available for transmission of submittals, correspondence, and information sharing following Notice to Proceed.
b. Submittals received after 5:00 p.m. Mountain Time shall be documented as received the next business day.
D. Include the following information in transmittal letters:
1. Cover Letter:
a. Contract number and title.
b. RSN for attached submittal.
c. Responsible code.
d. Identify submittal as initial or resubmittal.
2. Submittal contents following cover letter. Shall include all listed items for RSNs with multiple parts.
E. Resubmittal of submittals not approved:
1. Mark changes such that they are readily identifiable and show revision date.
Resubmitted drawings shall include a revision block with date.
2. Describe reasons for significant changes in transmittal letter.
3. Resubmit returned submittals within 14 calendar days after receiving comments.
4. Requirements for initial submittals apply to resubmittals.
01 33 00 - 5
5. Resubmittals shall be complete submittals without reference to the original submittal.
F. Submit each RSN under a separate transmittal letter. Multiple RSNs submitted under a single letter will not be reviewed.
1.06 REVIEW OF SUBMITTALS
A. Time Required:
1. Submittal review will require 28 calendar days for review of each submittal or resubmittal, unless otherwise specified.
2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through the date the response is uploaded to Microsoft Teams.
3. Provide Submittal Register as required within Section 01 32 10 – Construction Program. Submittal Register shall be complete and include anticipated submittal dates for each RSN:
a. Division 1 submittals shall be provided per due date or delivery time provided within Table 01 33 00A – List of Submittals.
b. Sequence Division 2 through 46 submittals to maintain Contractor’s construction schedule, with submittals intentionally staggered. Submit no more than 5 submittals, counting original and resubmittals, per Division(s) listed below within one 7-day period.
1) Division 2 through 23.
2) Division 25 through 28.
3) Division 31 through 32.
4) Division 33 through 46.
c. Contractor and Government shall mutually agree to a revised review time for submittals received in excess of 5 submittals per 7-calendar day period for the Division(s) listed above.
d. Approval drawings and data submittals shall be approved by the Government prior to purchase of applicable materials.
B. Time in Excess of Specified:
1. The CO may extend contract completion date to allow additional time for completing work affected by excess review time.
a. Time extension will be to extent that excess review time caused delay to contract completion date.
b. Time extension will not exceed time used in excess of specified number of days for review of submittals or resubmittals.
Submittals 01 33 00 - 6
c. Concurrent days of excess review time resulting from review of 2 or more separate submittals or resubmittals will be counted only once in extending contract completion date.
2. No time extension will be allowed if Contractor fails to make complete action submittals in sequence and within time periods specified.
3. Adjustment for delay will be made only to extent that:
a. Approval was required under contract, and
b. Requests for approval were submitted as required, in a timely fashion, and were approved.
4. Adjustment will be subject to terms of the clause at, Suspension of Work;
however, no such delay shall be deemed to be a “suspension order” as the term is used in that clause.
C. Submittal Response:
1. Response letter will indicate whether submittal is approved, not approved, acceptable, not acceptable, or acknowledged receipt.
a. Revise and resubmit submittals not approved or not acceptable.
b. Do not change designs without approval of CO after drawings, documentation, and technical data have been approved.
2. Request For Information (RFI). A response will be provided within 28 calendar days.
3. General Correspondence to the COR. A response will be provided within
28 calendar days.
1.07 TRANSMITTAL
A. Microsoft Teams access will be established for uploading all correspondence and transmittals listed in Table 01 33 00A - List of Submittals.
B. Submittals required by specifications, but not listed in Table 01…