140R6023R0013__RFP_Amendment0003_0003.pdf

PDF 1 MB Posted

Attached to
Arkansas Valley Conduit (AVC) Injection Site
Solicitation number
140R6023R0013
Issued by

About this file

This solicitation document from the Department of the Interior Bureau of Reclamation requests proposals for the construction of a water treatment injection facility and backflow prevention facility for the Arkansas Valley Conduit Boone Reach Pipeline. Key requirements include construction of a chemical building, access road, perimeter fencing, stormwater detention pond, yard piping, vaults and valves, engine generator, fiber conduit and associated improvements. Offerors must provide pricing for various construction line items such as mobilization, field office, traffic control, utility investigations, testing, disinfection of various piping components, commissioning of facilities, and individual construction elements. Proposals are due by November 30, 2023. The performance period is 10 calendar days for mobilization and 776 calendar days from notice to proceed for completion of work.

View the file

Other files

Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Arkansas Valley Conduit (AVC) Injection Site

Solicitation No. 140R6023R0013

UNITED STATES DEPARTMENT OF THE INTERIOR

BUREAU OF RECLAMATION

MISSOURI BASIN REGION

BILLINGS, MT

Solicitation Document No.

140R6023R0013

Document Title AVC Injection Site

Contents Solicitation No. 140R6023R0013

SECTION A – SF-1442

SECTION B – ARKANSAS VALLEY CONDUIT INJECTION SITE PHASE 1 AND BACKFLOW PREVENTER SITE

FRYINGPAN-ARKANSAS PROJECT, COLORADO

SECTION C – Statement / Description / Specification of Work SECTION D – Packaging and Marking SECTION E – Inspection and Acceptance

E.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE FEBRUARY 1998

SECTION F -- Deliveries or Performance

F.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE FEBRUARY 1998

F.2 52.211-10 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK APRIL 1984

SECTION G - Contract Administration Data

G.1 1452.201-70 AUTHORITIES AND DELEGATIONS SEPTEMBER 2011

G.2 DOI-AAAP 0028 ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INVOICE PROCESSING PLATFORM (IPP)

APRIL 2013

G.3 WBR 1452.242-80 POST AWARD CONFERENCE BUREAU OF RECLAMATION JULY 1993

G.4 WBR 1452.201-80 CONTRACTING OFFICER’S REPRESENTATIVE’S AUTHORITIES AND LIMITATIONS BUREAU OF

RECLAMATION MAY 2018

SECTION H -- Special Contract Requirements H.1 DOI-AAAP-0050 CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM DECEMBER 2015

SECTION I - Contract Clauses

I.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE FEBRUARY 1998

I.2 52.203-14 DISPLAY OF HOTLINE POSTER(S) NOVEMBER 2021

I.3 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS NOVEMBER 2021

I.4 52.209-1 QUALIFICATION REQUIREMENTS FEBRUARY 1995

I.5 52.216-4 ECONOMIC PRICE ADJUSTMENT-LABOR AND MATERIAL (JAN 2017)

I.6 52.219-4 NOTICE OF PRICE PREFERENCE FOR HUBZONE SMALL BUSINESS CONCERNS SEPTEMBER 2021

I.7 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REPRESENTATION MARCH 2023

I.8 52.222-35 EQUAL OPPORTUNITY FOR VETERANS JUNE 2020

I.9 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES JUNE 2020

I.10 52.225-11 BUY AMERICAN—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS DECEMBER 2022

I.11 52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR APRIL 1984

I.12 52.236-4 PHYSICAL DATA APRIL 1984

I.13 52.236-8 OTHER CONTRACTS – RECLAMATION DEVIATION APRIL 1984

I.14 52.252-4 ALTERATIONS IN CONTRACT APRIL 1984

I.15 52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES NOVEMBER 2020

Document Title AVC Injection Site

I.16 52.228-1 BID GUARANTEE SEPTEMBER 1996

I.17 1452.203-70 RESTRICTION ON ENDORSEMENTS DEPARTMENT OF INTERIOR JULY 1996

I.18 1452.204-70 RELEASE OF CLAIMS DEPARTMENT OF THE INTERIOR JULY 1996

I.19 1452.215-70 EXAMINATION OF RECORDS BY THE DEPARTMENT OF THE INTERIOR APRIL 1984

I.20 WBR 1452.223-80 ASBESTOS FREE WARRANTY -- BUREAU OF RECLAMATION AUGUST 2021

I.21 WBR 1452.223-81 SAFETY AND HEALTH – BUREAU OF RECLAMATION OCTOBER 2022

I.22 WBR 1452.232-81 – PAYMENT FOR MOBILIZATION AND PREPARATORY WORK – BUREAU OF RECLAMATION ALT I

MARCH 2022

I.23 WBR 1452.236-84 PRESERVATION OF CULTURAL RESOURCES BUREAU OF RECLAMATION MARCH 2022

I.24 WBR 1452.243-80 MODIFICATION PROPOSALS – BUREAU OF RECLAMATION MARCH 2022

I.25 WBR 1452.237-80 SECURITY REQUIREMENTS – BUREAU OF RECLAMATION MARCH 2022 – MARCH 2022

I. 26 1452.228-70 Liability Insurance

SECTION J – List of Attachments and Exhibits SECTION K – Representations, Certifications and Other Statements of OFFERORS

K.1 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE FEBRUARY 1998

K.2 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS MARCH 2023

K.3 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR

EQUIPMENT NOVEMBER 2021

K.4 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS OCTOBER 2018

K.5 52.209-12 CERTIFICATION REGARDING TAX MATTERS OCTOBER 2020

K.6 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS – CERTIFICATION NOVEMBER 2021 K.7 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR

CONSTRUCTION FEBRUARY 1999

K.8 52.230-1 COST ACCOUNTING STANDARDS NOTICES AND CERTIFICATION JUNE 2020

K.9 52.230-7 PROPOSAL DISCLOSURE—COST ACCOUNTING PRACTICE CHANGES APRIL 2005

SECTION L – Instructions, Conditions and Notices to Bidders

L.1 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE FEBRUARY 1998

L.2 52.211-1 AVAILABILITY OF SPECIFICATIONS LISTED IN THE GSA INDEX OF FEDERAL SPECIFICATIONS, STANDARDS AND

COMMERCIAL ITEM DESCRIPTIONS, FPMR PART 101-29 AUGUST 1998

L.3 52.211-2 AVAILABILITY OF SPECIFICATIONS, STANDARDS, AND DATA ITEM DESCRIPTIONS LISTED IN THE ACQUISITION

STREAMLINING AND STANDARDIZATION INFORMATION SYSTEM (ASSIST) APRIL 2014

L.4 52.216-1 – TYPE OF CONTRACT APRIL 1984

L.5 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK May 2014 L.6 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS May

L.7 52.236-27 SITE VISIT CONSTRUCTION ALT I FEBRUARY 1995

L.8 52.252-5 AUTHORIZED DEVIATIONS IN PROVIVIONS NOVEMBER 2020

L.9 1452.215-71 USE AND DISCLOSURE OF PROPOSAL INFORMATION – DEPARTMENT OF THE INTERIOR APRIL 1984

Solicitation

Document No.

Document Title AVC Injection Site

L.10 WBR 1452.215-81 PROPOSAL INSTRUCTIONS MAR 2021

L.11 WBR 1452.215-81 PROPOSAL INSTRUCTIONS MAR 2021

SECTION M -- Evaluation Factors for Award M.1 WBR 1452.215-80 SOURCE SELECTION EVALUATION PROCEDURES – BUREAU OF RECLAMATION MAR 2021 M.2 WBR 1452.215-84 EVALUATION FACTORS FOR AWARD—QUALITY AND COST/PRICE APPROXIMATELY EQUAL –

BUREAU OF RECLAMATION MARCH 2021

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

Bureau of Reclamation

Great Plains Region

Regional Office PO Box 36900

R60

Billings MT 59107

Jessica Busman

b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

772-359-9749

5x

140R6023R0013

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

Work is located along the south side of U.S. Route 50 / Colorado State Highway 96

(SH96) between Devine, Colorado and North Avondale, Colorado in Pueblo County. Work consists primarily of the construction of a water treatment injection facility and backflow prevention facility for the Arkansas Valley Conduit Boone Reach Pipeline.

A. Contractor is responsible for staging areas, including space for construction trailers, material storage, and construction staff parking.

B. Contractor is responsible for investigations before beginning any construction, including exploratory excavations and contacting utility owners to determine locations and type of existing utilities.

C. Install:

1. Backflow Preventer Site improvements, including piping, a valve enclosure, power, and controls.

2. Chemical Injection Site improvements, including:

a. Chemical building, including chemical storage and feed systems, power, SCADA system, security system, and supporting infrastructure.

b. Access road, perimeter fencing, and stormwater detention pond.

c. Yard piping, vaults, and valves.

d. Engine generator.

3. Fiber conduit, cable, and associated improvements, including testing the fiber

Continued ...

11. The Contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 calendar days and complete it within ________________

a. Sealed offers in original and

______________________ 11/30/2023

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ______________1300 _____ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 8/2014)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

0040626558

______ 776_______ calendar days after receiving

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

PAGE 6 OF

Bureau of Reclamation Great Plains Region

Regional Office PO Box 36900

R60

Billings MT 59107

Dwane D. Esplin

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 3304(a)

STANDARD FORM 1442 (REV. 8/2014) BACK

Continued...

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

7 83

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

140R6023R0013 optic cable on delivery to the staging area, prior to installation, following installation in the fiber conduit but prior to splicing, and after splicing.

D. Relocate utilities as needed.

E. Flush, test, and disinfect installed piping, including furnishing and disposal of water.

F. Disinfect approximately 11.4 miles of 30-inch transmission piping, including furnishing and disposal of water.

G. Disinfect approximately 1.5 miles of 6-inch delivery line piping connected to the transmission piping, including furnishing and disposal of water.

00001 AVC Injection and Backflow 1 AU Product/Service Code: Y1NE

Product/Service Description: CONSTRUCTION OF

WATER SUPPLY FACILITIES

Price Schedule 1

See Following Continuation Page(s).

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Per the Reclamation Acquisition Regulation (RAR) WBR

1436.204 Disclosure of Magnitude the estimate magnitude of

construction is between $20,000,000 and $30,000,000

Continuation of Section B – Supplies or Services and Price

SECTION B – ARKANSAS VALLEY CONDUIT INJECTION SITE PHASE 1 AND BACKFLOW

PREVENTER SITE FRYINGPAN-ARKANSAS PROJECT, COLORADO

PRICE SCHEDULE

B.1 PRICE SCHEDULE

(a) Offers will be considered for award on the following Price Schedule, but no offer will be considered for award on only a part of the Price Schedule.

(b) Offers are subject to the terms and conditions of this solicitation.

(c) Quantities in the Price Schedule are estimated quantities for comparison of offers only. Except as provided in the contract clause at FAR 52.211-18, Variation in Estimated Quantity, no claim shall be made against the Government for overruns or underruns. The contract clause at FAR 52.211-18, Variation in Estimated Quantity, does not apply to lump-sum items.

(d) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN 1.

(e) Definitions:

(1) CLIN – Contract Line Item Number

Document Title AVC Injection Site

PRICE SCHEDULE

CLIN Section Supplies or Services Quantity and

Unit Unit Price

Amount

1 WBR

1452.232-81

Mobilization and Preparatory Work

For the lump sum of $

2 01 52 10 Field Office and Laboratory

For the lump sum of $

3 01 55 20 Traffic Control Management

For the lump sum of $

4 01 57 15 Utility Crossing Investigations

For the lump sum of $

5 01 91 13 Testing For the lump sum of $ 6 01 91 13 Disinfection of Backflow

Preventer Facility For the lump sum of $

7 01 91 13 Disinfection of Injection Site

For the lump sum of $

8 01 91 13 Disinfection of AVC Trunk Line

For the lump sum of $

9 01 91 13 Disinfection of Delivery Lines

For the lump sum of $

10 01 91 13 Commissioning For the lump sum of $ 11 13 34 21 Chemical Building and

Appurtenant Works For the lump sum of $

12 13 34 50 Injection Site Yard For the lump sum of $ 13 26 32 10 Engine-Generator Set For the lump sum of $ 14 31 02 10 Water for Dust Abatement For the lump sum of $ 15 31 02 30 Dust Palliative 3,000 gal $ $ 16 31 11 00 Clearing and Grubbing 7.3 acre $ $ 17 31 14 10 Stripping 5,200 yd3 $ $ 18 31 32 32 Geotextile 12,100 yd2 $ $ 19 31 37 00 Riprap 5 yd3 $ $ 20 32 12 22 Asphalt Concrete

Pavement 276 yd2 $ $

21 32 15 10 Gravel Surfacing 1,820 yd3 $ $ 22 32 92 20 Seeding and Soil

Supplements

1.62 acre $ $

23 33 11 10 Backflow Line Pipe Delivered to Site

530 lin ft $ $

24 33 11 10 Injection Site Line Pipe Delivered to Site

530 lin ft $ $

25 33 11 10 Backflow Line Pipe Installed

530 lin ft $ $

Document Title AVC Injection Site

PRICE SCHEDULE

CLIN Section Supplies or Services Quantity and

Unit Unit Price

Amount

26 33 11 10 Injection Site Line Pipe Installed

530 lin ft $ $

27 33 11 10 Filling and Testing Pipe For the lump sum of $ 28 33 14 23 Backflow Preventer

Facility For the lump sum of $

29 33 22 15 Sectionalizing Valve Assemblies

1 ea $ $

30 33 22 15 Air Valve Assemblies 1 ea $ $ 31 33 22 15 Blowoff Valve Assemblies 2 ea $ $

TOTAL FOR PRICE SCHEDULE $_________________

END OF PRICE SCHEDULE

SECTION C – Statement / Description / Specification of Work

Please See Section J Attachment(s) for specifications, drawings, and supporting data.

SECTION D – Packaging and Marking

There are no clauses included in this section.

SECTION E – Inspection and Acceptance

E.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE FEBRUARY 1998

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at the following addresses:

FAR Clauses - https://www.acquisition.gov/far/

CLAUSES INCORPORATED BY REFERENCE

Clause Title Date

52.246-12 Inspection of Construction August 1996 https://www.acquisition.gov/far/

Document Title AVC Injection Site

SECTION F -- Deliveries or Performance

F.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE FEBRUARY 1998

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at the following addresses: FAR Clauses - https://www.acquisition.gov/far/

CLAUSES INCORPORATED BY REFERENCE

Clause Title Date 52.211-13 Time Extensions September 2000 52.242-14 Suspension of Work April 1984

F.2 52.211-10 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK APRIL 1984

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 776 calendar days after notice to proceed. * The time stated for completion shall include final cleanup of the premises.

(End of clause)

SECTION G - Contract Administration Data

G.1 1452.201-70 AUTHORITIES AND DELEGATIONS SEPTEMBER 2011

(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.

(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.

(c) The COR is not authorized to perform, formally or informally, any of the following actions:

(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;

(2) Waive or agree to modification of the delivery schedule;

(3) Make any final decision on any contract matter subject to the Disputes Clause;

(4) Terminate, for any reason, the Contractor's right to proceed;

(5) Obligate in any way, the payment of money by the Government.

(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers having been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers exceeding the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.

(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.

(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR via electronic transmission. This can be through email, mail, or fax. If by fax please request the appropriate fax number. Email is the preferred method of delivery.

(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.

(End of Clause)

Document Title AVC Injection Site

G.2 DOI-AAAP 0028 ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INVOICE

PROCESSING PLATFORM (IPP) APRIL 2013

Payment requests must be submitted electronically through the U.S. Department of the Treasury's Internet Payment Platform System (IPP).

"Payment requests" means any request for contract financing payment or invoicing payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions-Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.

Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice, failure to provide the items will result in invoice rejection:

Reference requirements in FAR 52.232-5 Payments under Fixed-Price Construction Contracts

Once the invoice has been submitted into the IPP system, the Contractor shall also submit an electronic copy of the invoice to the following:

Contracting Officer: (Dwane Esplin – desplin@usbr.gov) Contract Specialist: (Jessica Busman – jbusman@usbr.gov) Procurement Technician: (Scott Becker – Tbecker@usbr.gov)

Failure to transmit invoices via electronic transmission may cause significant delay or possible rejection of your payment request.

The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in CCR) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3-5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

(End of Clause)

G.3 WBR 1452.242-80 POST AWARD CONFERENCE BUREAU OF RECLAMATION JULY 1993

(a) Prior to the Contractor starting work, a post award conference (as described in FAR Subpart 42.5), will be convened by the contracting activity or contract administration office. The Contractor's Project Manager shall attend the conference. If the contract involves subcontractors, a representative of each major subcontractor is also required to attend.

(b) The conference will be held virtual using Microsoft Teams.

(c) The Contracting Officer and the Contractor will agree to the date and time of the conference after award of the contract. In event of a conflict in schedules, the Contracting Officer shall establish the date for the conference.

(d) The Contractor shall include any associated costs for attendance at the conference in its offer.

(End of Clause) https://www.ipp.gov/ mailto:desplin@usbr.gov mailto:jbusman@usbr.gov mailto:ippgroup@bos.frb.org

G.4 WBR 1452.201-80 CONTRACTING OFFICER’S REPRESENTATIVE’S AUTHORITIES AND

LIMITATIONS BUREAU OF RECLAMATION MAY 2018

(a) Performance of the work under this contract shall be subject to the technical direction of the Reclamation Contracting Officer's Representative (COR). The term “technical direction” is defined to include, without limitation:

(1) Inspecting and accepting or rejecting work performed under the contract.

(2) Representing the Government in technical phases of the work. The COR is responsible for the technical administration of the contract and will provide instructions and interpretations to the Contractor on all technical matters relating to the contract. The COR will supervise or oversee all Government technical and administrative personnel assigned to assist the COR.

(3) Reviewing and, where required by the contract, approving submittals of technical data, shop drawings, samples, literature, plans, or other data required to be delivered by the Contractor to the Government.

(b) The Contractor will receive a copy of the written COR designation from the Contracting Officer. It will specify the extent of the COR's authority to act on behalf of the Contracting Officer.

(c) Technical direction must be within the scope of work stated in the contract. Only the Contracting Officer is authorized to determine if a change is within the scope of the contract; therefore, the COR does not have the authority to, and may not, issue any technical direction that -

(1) Constitutes a direction of additional work outside the Contract requirements;

(2) Constitutes a change as defined in the contract clause entitled “Changes;”

(3) In any manner causes an increase or decrease in the total contract cost, or the time required for contract performance;

(4) Changes any of the expressed terms, conditions or specifications of the contract; or

(5) Interferes with the Contractor's right to perform the terms and conditions of the contract.

(d) All technical direction shall be issued in writing by the COR.

(e) The Contractor must proceed promptly with the performance of technical direction duly issued by the COR in the manner prescribed by this clause and within its authority under the provisions of this clause. If, in the opinion of the Contractor, any instruction or direction by the COR falls within one of the categories defined in (c)(1) through (c)(5) of this clause, the Contractor must not proceed and must notify the Contracting Officer in writing within five (5) working days after receipt of any such instruction or direction and must request the Contracting Officer to modify the contract accordingly. Upon receiving the notification from the Contractor, the Contracting Officer must -

(1) Advise the Contractor in writing after receipt of the Contractor's letter that the technical direction is within the scope of the contract effort and does not constitute a change under the Changes clause of the contract; or

(2) Advise the Contractor that the Government will issue a written change order.

(f) A failure of the Contractor and Contracting Officer either to agree that the technical direction is within the scope of the contract or to agree upon the contract action to be taken with respect to the technical direction will be subject to the provisions of the clause entitled “Disputes.”

Document Title AVC Injection Site

SECTION H -- Special Contract Requirements

H.1 DOI-AAAP-0050 CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM

DECEMBER 2015

1) FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.

2) The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.

3) We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.

4) When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.

5) Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at: https://www.cpars.gov/.

a) Contractor Representatives may then provide comments in response to the evaluation or return the evaluation without comment.

b) Your comments should focus on objective facts in the AO's narrative and should provide your views on the causes and ramifications of the assessed performance.

c) All information provided should be reviewed for accuracy prior to submission.

d) If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.

e) Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in PPIRS-RC marked as “Pending” with or without comments and whether or not it has been closed.

f) If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."

6)The following guidelines apply concerning your use of the past performance evaluation:

a) Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions.

b) Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.

c) Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.

7) If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.

8) A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.

https://www.cpars.gov/

Document Title AVC Injection Site

H.2 Schedule of Values

(a) Definitions.

“Schedule of Values” means the clearly definable tasks, and the cost associated with each of those tasks, which comprise the total work effort required to complete a lump sum contract line item.

(B) Except for the Mobilization and Preparatory Work line item, the Contractor shall submit a Schedule of Values for review and acceptance for all lump-sum Contract Line Item Numbers listed in Section B. The Schedule of Values will be used to assess the intermediate value of work completed for the purpose of making progress payments.

H.3 Site Security - GP7

(a) At least 10 days prior to arriving at the worksite, the contractor shall submit a list to the Contracting Officer (CO) of the names of all contractor employees that will be on-site initially. Additional employee names must be provided to CO prior to additional employees arriving on-site. The list(s) must include a legible photocopy of each employee's driver's license. In the absence of a driver's license, provide an alternate source of official identification that includes: First, Middle, Last Name; date and place of birth; and place of residence. All contractor employees must be U.S. citizens or have a valid Immigrant Visa Number, Permanent Resident Card or Resident Alien Card authorizing them to work in the U.S.

(b) The contractor is hereby notified of the following:

The Government may perform background checks on any or all workers. If the Government performs background checks, workers shall be required to submit additional personal and work history information. The Government may deny access to any worker at any time, based on information discovered during the background check. Information related to criminal matters (e.g., outstanding arrest warrants) that is discovered during a background check will be reported to the appropriate authorities.

(c) At least 10 days prior to arriving at the worksite, the contractor shall submit an initial list to CO of all contractor vehicles to be brought to the worksite. A supplemental list shall be provided to CO before additional vehicles are brought on-site. For each vehicle the list shall include the year, make, model and color; and license plate numbers and state of issuance when applicable.

(d) Reclamation will provide keys and/or locks to gates and doors, etc. as necessary for contractor personnel to access points within the scope of this project. Any duplication of keys or substitution of locks is strictly prohibited. Contractor shall be accountable to secure and return all keys and/or locks provided by the Government, and shall immediately notify the CO of the loss or misplacement of any provided key and/or lock.

(e) All drawings, plans, and other sensitive documents issued to the contractor shall remain under their direct control at all times. These sensitive documents shall not be reproduced or copied or further distributed without approval from CO.

(f) All firearms and dangerous weapons are prohibited in Federal facilities for all persons not specifically authorized by Title 18, United States Code, Section 930. A license to carry a concealed firearm issued under state law is not an exception to this prohibition. This prohibition shall apply to all areas within the construction worksite and contractor use area.

(g) In case of an emergency situation, the contractor shall follow emergency instructions provided by CO.

(h) Unless exempted by CO, the contractor shall comply with all security requirements already in place at the site, i.e., those security requirements that have been adopted as standard operating procedures at the site.

(i) The contractor shall report to the CO all incidents of criminal and/or suspicious activity observed by their employees on or adjacent to the construction site.

(j) Reclamation reserves the right to change or modify security requirements as mandated by the Office of Homeland Security and/or as deemed necessary by Reclamation security staff.

(k) Any violations of Reclamation security requirements and/or restrictions may result in Reclamation denying the contractor personnel access to the worksite.

(l) Contractor shall notify the CO at least 24 hours in advance of any material delivery to worksite. Material may only be delivered to areas approved by CO.

Document Title AVC Injection Site

SECTION I - Contract Clauses

I.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE FEBRUARY 1998

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at the following addresses:

FAR Clauses - https://www.acquisition.gov/far/

CLAUSES INCORPORATED BY REFERENCE

Clause Title Date 52.202-1 Definitions June 2020 52.203-3 Gratuities April 1984 52.203-5 Covenant Against Contingent Fees May 2014 52.203-6 Restrictions on Subcontractor Sales to the Government June 2020 52.203-7 Anti-Kickback Procedures June 2020 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or

Improper Activity May 2014

52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity May 2014 52.203-12 Limitation On Payments To Influence Certain Federal

Transactions June 2020

52.203-13 Contractor Code of Business Ethics and Conduct November 2021 52.203-17 Contractor Employee Whistleblower Rights and Requirement to

Inform Employees of Whistleblower Rights June 2020

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements

January 2017

52.204-4 Printed or Copied Double-Sided on Post-Consumer Fiber Content Paper

May 2011

52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards

June 2020

52.204-13 System for Award Management Maintenance October 2018 52.204-14 Service Contract Reporting Requirements October 2016 52.204-18 Commercial and Government Entity Code Maintenance August 2020 52.204-19 Incorporation by Reference of Representations and

Certifications December 2014

52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Entities

November 2021

52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment

November 2021

52.204-27 Prohibition on a ByteDance Covered Application June 2023 52.209-6 Protecting the Government's Interest When Subcontracting With

Contractors Debarred, Suspended, or Proposed for Debarment November 2021

Document Title AVC Injection Site

52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters

October 2018

52.209-10 Prohibition on Contracting with Inverted Domestic Corporations November 2015 52.210-1 Market Research November 2021 52.211-18 Variation in Estimated Quantity April 1984 52.215-2 Audit and Records – Negotiations June 2020 52.215-8 Order of Precedence – Uniform Contract Format October 1997 52.215-11 Price Reduction for Defective Certified Cost or Pricing Data—

Modifications June 2020

52.215-13 Subcontractor Certified Cost or Pricing Data-Modifications June 2020 52.215-17 Waiver of Facilities Capital Cost or Money October 1997 52.215-21 Requirements for Certified Cost or Pricing Data and Data Other

Than Certified Cost or Pricing Data – Modifications November 2021

52.219-8 Utilization of Small Business Concerns October 2022 52.219-9 Alt II Small Business Subcontracting Plan October 2022/

Nov2016 52.219-16 Liquidated Damages-Subcontracting Plan September 2021 52.222-3 Convict Labor June 2003 52.222-4 Contract Work Hours and Safety Standards Act – Overtime

Compensation May 2018

52.222-6 Construction Wage Rate Requirements August 2018 52.222-7 Withholding of Funds May 2014 52.222-8 Payrolls and Basic Records August 2018 52.222-9 Apprentices and Trainees July 2005 52.222-10 Compliance with Copeland Act Requirements February 1988 52.222-11 Subcontracts (Labor Standards) May 2014 52.222-12 Contract Termination-Debarment May 2014 52.222-13 Compliance with Construction Wage Rate Requirements and

Related Regulations May 2014

52.222-14 Disputes Concerning Labor Standards February 1988 52.222-15 Certification of Eligibility May 2014 52.222-21 Prohibition of Segregated Facilities April 2015 52.222-26 Equal Opportunity September 2016 52.222-27 Affirmative Action Compliance Requirements for Construction April 2015 52.222-37 Employment Reports on Veterans June 2020 52.222-40 Notification of Employee Rights Under the National Labor

Relations Act December 2010

52.222-50 Combating Trafficking in Persons November 2021 52.222-54 Employment Eligibility Verification May 2022 52.222-55 Minimum Wages Under Executed Order 13658 January 2022 52.222-62 Paid Sick Leave Under Executive Order 13706 January 2022 52.223-2 Affirmative Procurement of Biobased Products Under Service

And Construction Contracts September 2013

52.223-3 Alt I Hazardous Material Identification and Material Safety Data – Alternate I

July 1995

52.223-6 Drug Free Workplace May 2001 52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts August 2018

52.223-18 Encouraging Contractor Policies to Ban text Messaging While Driving

June 2020

52.225-13 Restrictions on Certain Foreign Purchases February 2021 52.227-1 Authorization and Consent June 2020 52.227-2 Notice and Assistance Regarding Patent and Copyright

Infringement June 2020

52.227-4 Patent Indemnity – Construction Contracts December 2007 52.228-2 Additional Bond Security October 1997 52.228-5 Insurance-Work on a Government Installation January 1997 52.228-11 Pledges Of Assets February 2021 52.228-12 Prospective Subcontractor Requests for Bonds December 2022 52.228-14 Irrevocable Letter of Credit November 2014 52.228-15 Performance and Payment Bonds–Construction June 2020 52.229-3 Federal, State And Local Taxes February 2013 52.230-2 Cost Accounting Standards June 2020 52.230-6 Administration of Cost Accounting Standards June 2010 52.232-5 Payments Under Fixed-Price Construction May 2014 52.232-17 Interest May 2014 52.232-18 Availability of Funds April 1984 52.232-23 Assignment Of Claims May 2014 52.232-27 Prompt Payment for Construction Contracts January 2017 52.232-33 Payment by Electronic Funds Transfer-System for Award

Management October 2018

52.232-39 Unenforceability of Unauthorized Obligations June 2013 52.232-40 Providing Accelerated Payment to Small Business

Subcontractors March 2023

52.233-1 Disputes May 2014 52.233-3 Protest After Award August 1996 52.233-4 Applicable Law for Breach of Contract Claim October 2004 52.236-2 Differing Site Conditions April 1984 52.236-3 Site Investigation and Conditions Affecting the Work April 1984 52.236-5 Material and Workmanship April 1984 52.236-6 Superintendence by the Contractor April 1984 52.236-7 Permits and Responsibilities November 1991 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements April 1984

52.236-10 Operations and Storage Areas April 1984 52.236-11 Use and Possession Prior to Completion April 1984 52.236-12 Cleaning Up April 1984 52.236-13 Accident Prevention November 1991 52.236-15 Schedules for Construction Contracts April 1984 52.236-16 Alt I Quantity Survey April 1984 52.236-17 Layout of Work April 1984 52.236-21 Alt II Specifications and Drawings for Construction Alternate II April 1984 52.236-26 Preconstruction Conference February 1995 52.242-5 Payments to Small Business Subcontractors January 2017 52.242-13 Bankruptcy July 1995 52.243-4 Changes (CONST) June 2007 52.244- 6 Subcontracting for Commercial Items December 2022 52.246-21 Warranty of Construction March 1994 52.248-3 Value Engineering – Construction October 2020

Document Title AVC Injection Site

52.249-2 Alt I Termination for Convenience of the Government (Fixed-Price) Alternate I (September 1996) (CONST)

September 1996

52.249-10 Default (Fixed-Price Construction) April 1984 52.253-1 Computer Generated Forms January 1991

I.2 52.203-14 DISPLAY OF HOTLINE POSTER(S) NOVEMBER 2021

(a) Definition.

United States, as used in this clause, means the 50 States, the District of Columbia, and outlying areas.

(b) Display of fraud hotline poster(s). Except as provided in paragraph (c)—

(1) During contract performance in the United States, the Contractor shall prominently display in common work areas within business segments performing work under this contract and at contract work sites-

(i) Any agency fraud hotline poster or Department of Homeland Security (DHS) fraud hotline poster identified in paragraph (b)(3) of this clause; and

(ii) Any DHS fraud hotline poster subsequently identified by the Contracting Officer.

(2) Additionally, if the Contractor maintains a company website as a method of providing information to employees, the Contractor shall display an electronic version of the poster(s) at the website.

(3) Any required posters may be obtained as follows:

Poster(s) Obtain from

Hotline Posters IAW DIAR 1403.1004

Downloadable hotline posters as well as instructions for obtaining a hard copy poster are available at https://www.dol.gov/general/topics/posters & https://www.doioig.gov/complaints-requests/contractor-recipient-resources

(i) Appropriate agency name(s) and/or title of applicable Department of Homeland Security fraud hotline poster); and

(ii) The website(s) or other contact information for obtaining the poster(s).)

(c) If the Contractor has implemented a business ethics and conduct awareness program, including a reporting mechanism, such as a hotline poster, then the Contractor need not display any agency fraud hotline posters as required in paragraph (b) of this clause, other than any required DHS posters.

(d) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (d), in all subcontracts that exceed the threshold specified in Federal Acquisition Regulation 3.1004(b)(1) on the date of subcontract award, except when the subcontract — https://www.dol.gov/general/topics/posters https://www.doioig.gov/complaints-requests/contractor-recipient-resources https://www.doioig.gov/complaints-requests/contractor-recipient-resources

(1) Is for the acquisition of a commercial product or commercial service; or

(2) Is performed entirely outside the United States.

I.3 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS

NOVEMBER 2021

(a) Definitions. As used in this clause–

“Covered contractor information system” means an information system that is owned or operated by a contractor that processes, stores, or transmits Federal contract information.

“Federal contract information” means information, not intended for public release, that is provided by or generated for the Government under a contract to develop or deliver a product or service to the Government, but not including information provided by the Government to the public (such as on public Web sites) or simple transactional information, such as necessary to process payments.

“Information” means any communication or representation of knowledge such as facts, data, or opinions, in any medium or form, including textual, numerical, graphic, cartographic, narrative, or audiovisual (Committee on National Security Systems Instruction

(CNSSI) 4009).

“Information system” means a discrete set of information resources organized for the collection, processing, maintenance, use, sharing, dissemination, or disposition of information (44 U.S.C. 3502).

“Safeguarding” means measures or controls that are prescribed to protect information systems.

(b) Safeguarding requirements and procedures.

(1) The Contractor shall apply the following basic safeguarding requirements and procedures to protect covered contractor information systems. Requirements and procedures for basic safeguarding of covered contractor information systems shall include, at a minimum, the following security controls:

(i) Limit information system access to authorized users, processes acting on behalf of authorized users, or devices (including other information systems).

(ii) Limit information system access to the types of transactions and functions that authorized users are permitted to execute.

(iii) Verify and control/limit connections to and use of external information systems.

(iv) Control information posted or processed on publicly accessible information systems.

(v) Identify information system users, processes acting on behalf of users, or devices.

(vi) Authenticate (or verify) the identities of those users, processes, or devices, as a prerequisite to allowing access to organizational information systems.

Document Title AVC Injection Site

(vii) Sanitize or destroy information system media containing Federal Contract Information before disposal or release for reuse.

(viii) Limit physical access to organizational information systems, equipment, and the respective operating environments to authorized individuals.

(ix) Escort visitors and monitor visitor activity; maintain audit logs of physical access; and control and manage physical access devices.

(x) Monitor, control, and protect organizational communications (i.e., information transmitted or received by organizational information systems) at the external boundaries and key internal boundaries of the information systems.

(xi) Implement subnetworks for publicly accessible system components that are physically or logically separated from internal networks.

(xii) Identify, report, and correct information and information system flaws in a timely manner.

(xiii) Provide protection from malicious code at appropriate locations within organizational information systems.

(xiv) Update malicious code protection mechanisms when new releases are available.

(xv) Perform periodic scans of the information system and real-time scans of files from external sources as files are downloaded, opened, or executed.

(2) Other requirements. This clause does not relieve the Contractor of any other specific safeguarding requirements specified by Federal agencies and departments relating to covered contractor information systems generally or other Federal safeguarding requirements for controlled unclassified information (CUI) as established by Executive Order 13556.

(c) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph ©, in subcontracts under this contract (including subcontracts for the acquisition of commercial items, other than commercially available off-the-shelf items), in which the subcontractor may have Federal contract information residing in or transiting through its information system.

(End of Clause)

I.4 52.209-1 QUALIFICATION REQUIREMENTS FEBRUARY 1995

(a) Definition. “Qualification requirement,” as used in this clause, means a Government requirement for testing or other quality assurance demonstration that must be completed before award.

(b) One or more qualification requirements apply to the supplies or services covered by this contract. For those supplies or services requiring qualification, whether the covered product or service is an end item under this contract or simply a component of an end item, the product,…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .