01_33_00_-_Submittals_AMD0003_0003.pdf
PDF 333 KB Posted
- Attached to
- Arkansas Valley Conduit (AVC) Injection Site
- Solicitation number
- 140R6023R0013
About this file
This document outlines submittal requirements for a federal construction contract solicitation. The solicitation is for the Arkansas Valley Conduit Injection Site and Backflow Preventer Site project with the Bureau of Reclamation. It specifies over 100 required submittals across various construction phases, including quality control plans, schedules, safety documentation, shop drawings, test reports, as-built drawings and more. Submittals are due based on the project schedule and must follow naming and formatting conventions. The government allows 28 days for review and requires electronic submission through a shared Microsoft Teams site.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Arkansas Valley Conduit Injection Site Phase 1 and Backflow Preventer Site Amendment No. 0003 Fryingpan-Arkansas Project, Colorado Solicitation No. 140R6023R0013
Submittals
Revised - 01 33 00 - 1
SECTION 01 33 00
SUBMITTALS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost: Include in prices offered in the Price Schedule for other items of work.
1.02 DEFINITIONS
A. Days: Calendar days.
B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.
C. Submittals: Considered “shop drawings” within the terms of the clause at FAR 52.236- 21, Specifications and Drawings for Construction.
1.03 REFERENCE STANDARDS
A. American Society of Mechanical Engineers (ASME)
1. ASME Y14.1-20 Decimal Inch Drawing Sheet Size and Format
B. National Institute of Building Sciences (NIBS)
1. NIBS NCS-14 United States National CAD Standards, Version 6
1.04 SUBMITTAL REQUIREMENTS
A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included in this section take precedence.
B. General:
1. Prepare in English.
2. Label with contract number and title, and RSN.
3. Measurement Units: US Customary Units.
C. Drawings:
1. Minimum Identification in Title Block:
a. Contract number and title.
b. Contractor's or supplier's title and drawing number.
Revised - 01 33 00 - 2
c. Date.
2. Reserve 3- by 3-inch space next to title block for review stamps.
3. Size: D size (22 inches by 34 inches) in accordance with ASME Y14.1.
4. Draw to scale using computer drafting.
a. In accordance with NIBS NCS.
b. Electronic file format: Compatible with AutoCAD Version 2021 or later.
c. Compile using “eTransmit” utility in AutoCAD.
d. Government will provide electronic AutoCAD format template.
e. Title block and sheet format:
1) As shown on Standard Drawing 40-D-7102.
2) Government will supply template.
3) Government will supply specific title block information to be used.
f. Show as-built changes, including revision dates, made during installation.
Indicate changes by clouding.
D. Manuals:
1. Copies:
a. Printed copies: Bound and indexed.
b. Electronic copies: Adobe pdf submitted to Microsoft Teams. Bookmark longer files to assist in navigating file.
2. Contents:
a. Parts identification lists, lists of special tools, and accessories.
b. Schematics and wiring diagrams.
c. Detailed instructions for installing, operating, lubricating, and maintaining equipment.
d. As-built drawings, photographs, and test records or reports if required by the specifications.
E. Product Data:
1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.
a. Identify manufacturer's name, type, model, size, and characteristics.
b. Illustrate that product or equipment meets requirements of specifications.
c. Mark items to be furnished in a manner that will photocopy (no highlighter).
d. Strike through items that do not apply.
Revised - 01 33 00 - 3
F. Certifications:
1. Certifications by a registered professional: Signed and sealed by registered professional.
2. Manufacturer's certifications: Signed by authorized representative of manufacturer.
G. Photographs:
1. Professional quality:
a. Include contract number, name of equipment, and view title.
b. Digital files in .jpeg.
H. Videos:
1. Digital file in MP4 format.
2. Upload to Microsoft Teams.
I. Samples and Color Selection Submittals:
1. Ship samples except color samples to Technical Service Center, Bureau of Reclamation, Attn: 86-68160, P.O. Box 25007, Denver CO 80225-0007; Express Mail: Sixth and Kipling, Building 67, Room 152.
2. Ship color samples to Government field office, refer to Section 01 52 10 - Field Office and Laboratory.
3. Label with complete manufacturer’s product and color identification.
4. Include type and quantity of materials specified in the referenced section in each “set” of samples.
5. Samples: Representative of product to be installed. Xerographic sheets for color selection are not acceptable.
6. Color Chips: Sample paint chips. Ink color reproductions are not acceptable.
7. Label each sample, sample kit, set of color chips, of color chart with contract number and title.
8. Government will select architectural color and pattern after product approval.
1.05 SUBMITTALS PROCEDURES
A. Submit only checked submittals. Submittals without evidence of Contractor's approval will not be reviewed.
B. Submit complete sets of required materials for each RSN as specified in “Submittals Required” column in Table 01 33 00A - List of Submittals. A complete set includes all listed items for RSNs with multiple parts.
Revised - 01 33 00 - 4
C. Submit in accordance with “No. of sets to be sent:” columns in Table 01 33 00A - List of Submittals:
1. Electronic submittals:
a. In Portable Document Format (PDF).
1) Optical Character Recognition (OCR).
2) 508 compliant.
3) RSNs having more than one requirement shall be bookmarked.
4) RSNs with requirements for files other than PDF (.XER, .PLF, .DWGs, etc.) shall be combined using WINZip.
5) Include RSN transmittal letter.
6) Each submittal shall be submitted as one PDF or WINZip (only when multiple file types are required).
b. Personally Identifiable Information (PII) shall be encrypted using WINZip or Adobe Acrobat before transmitting electronically.
2. Submit electronic submittals via Microsoft Teams:
a. Access to Microsoft Teams will be made available for transmission of submittals, correspondence, and information sharing following Notice to Proceed.
b. Submittals received after 5:00 p.m. Mountain Time shall be documented as received the next business day.
D. Include the following information in transmittal letters:
1. Cover Letter:
a. Contract number and title.
b. RSN for attached submittal.
c. Responsible code.
d. Identify submittal as initial or resubmittal.
2. Submittal contents following cover letter. Shall include all listed items for RSNs with multiple parts.
E. Resubmittal of submittals not approved:
1. Mark changes such that they are readily identifiable and show revision date.
Resubmitted drawings shall include a revision block with date.
2. Describe reasons for significant changes in transmittal letter.
3. Resubmit returned submittals within 14 calendar days after receiving comments.
4. Requirements for initial submittals apply to resubmittals.
Revised - 01 33 00 - 5
5. Resubmittals shall be complete submittals without reference to the original submittal.
F. Submit each RSN under a separate transmittal letter. Multiple RSNs submitted under a single letter will not be reviewed.
1.06 REVIEW OF SUBMITTALS
A. Time Required:
1. Submittal review will require 28 calendar days for review of each submittal or resubmittal, unless otherwise specified.
2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through the date the response is uploaded to Microsoft Teams.
3. Provide Submittal Register as required within Section 01 32 10 – Construction Program. Submittal Register shall be complete and include anticipated submittal dates for each RSN:
a. Division 1 submittals shall be provided per due date or delivery time provided within Table 01 33 00A – List of Submittals.
b. Sequence Division 2 through 46 submittals to maintain Contractor’s construction schedule, with submittals intentionally staggered. Submit no more than 5 submittals, counting original and resubmittals, per Division(s) listed below within one 7-day period.
1) Division 2 through 23.
2) Division 25 through 28.
3) Division 31 through 32.
4) Division 33 through 46.
c. Contractor and Government shall mutually agree to a revised review time for submittals received in excess of 5 submittals per 7-calendar day period for the Division(s) listed above.
d. Approval drawings and data submittals shall be approved by the Government prior to purchase of applicable materials.
B. Time in Excess of Specified:
1. The CO may extend contract completion date to allow additional time for completing work affected by excess review time.
a. Time extension will be to extent that excess review time caused delay to contract completion date.
b. Time extension will not exceed time used in excess of specified number of days for review of submittals or resubmittals.
Revised - 01 33 00 - 6
c. Concurrent days of excess review time resulting from review of 2 or more separate submittals or resubmittals will be counted only once in extending contract completion date.
2. No time extension will be allowed if Contractor fails to make complete action submittals in sequence and within time periods specified.
3. Adjustment for delay will be made only to extent that:
a. Approval was required under contract, and
b. Requests for approval were submitted as required, in a timely fashion, and were approved.
4. Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at FAR 52.242-14, Suspension of Work; however, no such delay shall be deemed to be a “suspension order” as the term is used in that clause.
C. Submittal Response:
1. Response letter will indicate whether submittal is approved, not approved, acceptable, not acceptable, or acknowledged receipt.
a. Revise and resubmit submittals not approved or not acceptable.
b. Do not change designs without approval of CO after drawings, documentation, and technical data have been approved.
2. Request For Information (RFI). A response will be provided within 28 calendar days.
3. General Correspondence to the COR. A response will be provided within 28 calendar days.
1.07 TRANSMITTAL
A. Microsoft Teams access will be established for uploading all correspondence and transmittals listed in Table 01 33 00A - List of Submittals.
B. Submittals required by specifications, but not listed in Table 01 33 00A - List of Submittals:
1. Submit in accordance with this section.
2. Submit to COR unless otherwise specified.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
Revised - 01 33 00 - 7
Table 01 33 00A - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.
RSN Clause or Section Title
Submittals required
Due date or delivery time
Respon-sible code
No. of sets to be sent to:
CO COR
1 Performance and
Payment Bonds - Construction
FAR 52.228-15
Performance and Payment Bonds
No later than 10 days after award
CO 1
electronic
2 Additional Bond Security
FAR 52.228-2
Additional Bond Security
No later than 10 days after award
CO 1
electronic
3 Insurance-Work on a Government Installation
FAR 52.228-5
1) Written certification that the required insurance has been obtained
2) Current certification of insurance for each subcontractor
Before commencing onsite work
CO 1
electronic electronic
4 Liability Insurance
DIAR
1452.228-70
Acceptable Certificate of Liability Insurance
Prior to commencement of work under the contract
CO 1
electronic
5 Release of Claims
DIAR
1452.204-70
Release of Claims (DI-137) against the Government
After completion of the work and prior to final payment
CO 1
electronic
6 Personal Identity Verification of Contractor Personnel
FAR 52.204-9
SF-85 and OF-306 for each employee and subcontractor employee working on site
No later than 10 days after receipt of Notice to Proceed or 10 days before commenting work (for new hire)
CO 1
electronic
7 Subcontracts (Labor Standards)
FAR 52.222-11
1) List of subcontractors
No later than 14 days after award of contract
COR 1
electronic
1 electronic
8 Subcontracts (Labor Standards)
FAR 52.222-11
2) Statement and Acknowledgement Form (SF-1413) for each subcontract
No later than 14 days after award of subcontract
COR 1
electronic
1 electronic
9 Payrolls and Basic Records
FAR 52.222-8
Copies of all payrolls
Weekly for each week of contract performance
COR 1
electronic encrypted
1 electronic encrypted
10 Site Security
GP-7
List of contractor and subcontractor employees
Submitted and approved prior to arriving at worksite
COR 0 1 electronic encrypted
11 Site Security
GP-7
List of vehicles and equipment to be brought on site
Submitted and approved prior to arriving at worksite
COR 0 1 electronic encrypted
Revised - 01 33 00 - 8
Table 01 33 00A - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.
RSN Clause or Section Title
Submittals required
Due date or delivery time
Respon-sible code
No. of sets to be sent to:
CO COR
12 Superintendence by the Contractor
FAR 52.236-6
Site Superintendent
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 14 10-1 Use of Site Land Use and Landscape Rehabilitation Plan
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 14 12-1 Work Restrictions and Limitations
Request for Pueblo Water Connection
At least 28 days before work onsite
COR 0 1 electronic
01 31 19-1 Project Management and Coordination
Weekly Coordination Meeting Documentation
Weekly, 3 days prior to meeting
COR 0 1 electronic
01 31 19-2 Project Management and Coordination
Weekly Coordination Meeting Minutes
Weekly, within 3 days after meeting
COR 0 1 electronic
01 31 19-3 Project Management and Coordination
Expanded Right-of-Way Land Use Coordination
At least 6 months prior to use of land
COR 0 1 electronic
01 32 10-1 Construction Program
Representative Information
Submitted within 21 days after NTP
COR 0 1 electronic
01 32 10-2 Construction Program
Baseline Schedule Submitted within 21 days after NTP
COR 0 1 electronic
01 32 10-3 Construction Program
Submittal Register Submitted and approved within 28 days of NTP and monthly after approval
COR 0 1 electronic
01 32 10-4 Construction Program
Updated Schedule Reports
Monthly after Baseline Schedule is approved
COR 0 1 electronic
01 32 10-5 Construction Program
Time Impact Analysis
No later than 28 days after the CO directs a contract change, with any proposal for a future modification, with any value engineering proposal, or with any request or claim for an equitable adjustment to the contract
COR 0 1 electronic
01 32 10-6 Construction Program
Schedule of Values Submitted and approved before any payment other than bonds and insurance
COR 0 1 electronic
01 35 10-1 Safety Data Sheets
Complete LHM and SDS
Submitted and approved at least 28 days before jobsite delivery of hazardous material
COR 0 1 electronic
01 35 10-2 Safety Data Sheets
Updated LHM and
SDS
Submitted and approved at least 28 days before jobsite delivery of hazardous material not previously listed
Revised - 01 33 00 - 9
Table 01 33 00A - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.
RSN Clause or Section Title
Submittals required
Due date or delivery time
Respon-sible code
No. of sets to be sent to:
CO COR
01 35 20-1 Safety and
Health Safety Program Submitted and accepted at least 28 days before mobilization
COR 0 1 electronic
01 35 20-2 Safety and Health
Monthly Accident Summary Reports
Monthly COR 0 1 electronic
01 35 20-3 Safety and Health
Respirator User Documentation
Submitted and accepted at least 28 days before onsite work begins
COR 0 1 electronic encrypted
01 35 20-4 Safety and Health
Crane Operation Certificates
Submitted and accepted at least 28 days before onsite work begins
COR 0 1 electronic
01 35 20-5 Safety and Health
Exposure Assessment Form
Submitted and accepted at least 28 days before onsite work begins
COR 0 1 electronic
01 35 20-6 Safety and Health
Other Training Certificates
Submitted and accepted at least 28 days before onsite work begins
COR 0 1 electronic
01 35 20-7 Safety and Health
Pandemic Notification
No later than 24 hours after positive test
COR 0 1 electronic
01 35 20-8 Safety and Health
Employee Return to Work Documentation
7 days prior to returning to work
COR 0 1 electronic
01 35 30-1 Contractor's Onsite Safety Personnel
Qualifications Submitted and accepted at least 28 days before mobilization
COR 0 1 electronic encrypted
01 35 30-2 Contractor's Onsite Safety Personnel
Safety Inspection Reports
Weekly COR 0 1 electronic
01 46 00-1 Quality Procedures
Contractor Quality Control Program
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 46 00-2 Quality Procedures
Contractor's Daily Reports
Weekly COR 0 1 electronic
01 46 00-3 Quality Procedures
Quality Control Supervisor Resume
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic encrypted
01 46 00-4 Quality Procedures
Contractor’s Quality Testing Plan
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 46 00-5 Quality Procedures
Summary of Test Results
Monthly COR 0 1 electronic
01 46 20-1 Testing Agency Services
Testing Agency Services Plan
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 46 20-2 Testing Agency Services
Certifications Submitted and approved at least 28 days before mobilization
Revised - 01 33 00 - 10
Table 01 33 00A - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.
RSN Clause or Section Title
Submittals required
Due date or delivery time
Respon-sible code
No. of sets to be sent to:
CO COR
01 46 25-1 Special
Inspections Preconstruction Submittals
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 46 25-2 Special Inspections
Test Reports Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 46 25-3 Special Inspections
Certificates At time of preconstruction conference
COR 0 1 electronic
01 46 25-4 Special Inspections
Closeout Submittals
Submitted and accepted at least 28 days after completion of construction
COR 0 1 electronic
01 52 10-1 Field Office and Laboratory
Delivery Schedule and Site Layout
Submitted and approved at least 28 days before delivery and setup
COR 0 1 electronic
01 52 10-2 Field Office and Laboratory
Approved Pueblo Regional Building Department Permits
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 55 00-1 Vehicular Access and Parking
Temporary Access Roadway Plan
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 55 00-2 Vehicular Access and Parking
Pre-Construction Video
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 55 00-3 Vehicular Access and Parking
Post-Construction Video
No later than 7 days after completing construction
COR 0 1 electronic
01 55 00-4 Vehicular Access and Parking
Post-Repair Video No later than 7 days after completing repair
COR 0 1 electronic
01 55 20-1 Traffic Control Approved CDOT Permit(s)
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 56 15-1 Protection of Existing Utilities
Utility Owner Acknowledgment
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 57 15-1 Utility Line Investigations
Utility Crossing Investigations
Submitted and approved at least 28 days before preparation of pipelaying diagrams required by Section 33 11 10
COR 0 1 electronic
01 57 15-2 Utility Line Investigations
Permits Submitted and approved at least 28 days before beginning work in area of each utility line
Revised - 01 33 00 - 11
Table 01 33 00A - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.
RSN Clause or Section Title
Submittals required
Due date or delivery time
Respon-sible code
No. of sets to be sent to:
CO COR
01 57 20-1 Environmental
Controls Dust Control Plan Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 57 20-2 Environmental Controls
Copy of Applicable Air Pollution Emissions Notice (APEN) and Air Quality Permits
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 57 30-1 Water Pollution Control
Stormwater Management Plan
(SWMP)
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 57 30-2 Water Pollution Control
Spill Prevention, Control, and Countermeasure Plan (SPCC)
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 71 20-1 Surveying Surveying Plan Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 71 20-2 Surveying Resumes At least 28 days before beginning survey work; At least 28 days before personnel change
COR 0 1 electronic
01 71 20-3 Surveying Accuracy Check Results
Submitted and approved at least 28 days before beginning survey work
COR 0 1 electronic
01 71 20-4 Surveying Topographic Survey of Existing Conditions at the Drainage Outfall and Existing Culvert
45 days prior to starting earthwork
COR 0 1 electronic
01 71 20-5 Surveying Topographic Survey of Detention Basin
Prior to seeding COR 0 1 electronic
01 71 20-6 Surveying Topographic Survey of Backflow Preventer Site Frontage Road
45 days prior to starting Frontage Road construction
COR 0 1 electronic
01 71 20-7 Surveying Topographic Survey of Frontage Road after Paving
Prior to seeding COR 0 1 electronic
01 71 20-8 Surveying Completed and Reduced Survey Notes
No later than 7 days after completing and reducing notes
Revised - 01 33 00 - 12
Table 01 33 00A - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.
RSN Clause or Section Title
Submittals required
Due date or delivery time
Respon-sible code
No. of sets to be sent to:
CO COR
01 71 20-9 Surveying Quantity Survey
Notes and Computations
Submitted and approved for monthly progress payments
COR 0 1 electronic
01 74 00-1 Cleaning and Waste Management
Waste Production and Disposal Plan
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 74 00-2 Cleaning and Waste Management
Waste Production and Disposal Records
No later than 7 days after waste disposal
COR 0 1 electronic
01 74 00-3 Cleaning and Waste Management
Environmental Consultant Resume
At least 28 days before beginning environmental assessment
COR 0 1 electronic
01 74 00-4 Cleaning and Waste Management
Environmental Site Assessment
No later than 14 days after completion of work
COR 0 1 electronic
01 78 30-1 Project Record Documents
As-built Drawings No later than 28 days after completion of work
COR 0 1 electronic
01 78 30-2 Project Record Documents
Final Drawings No later than 28 days after completion of work
COR 0 1 electronic
01 78 30-3 Project Record Documents
As-built Record of Materials
No later than 28 days after completion of work
COR 0 1 electronic
01 78 30-4 Project Record Documents
Extra Materials No later than 28 days after completion of work
COR 0 1 electronic
01 78 30-5 Project Record Documents
Warranties No later than 28 days after completion of work
COR 0 1 electronic
01 79 20-1 Training Instructor Qualifications
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
01 79 20-2 Training Training Materials In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
01 79 20-3 Training Training Video In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
01 91 13-1 Testing, Disinfection, and Commissioning
Qualifications Submitted and approved no later than 150 days after Notice to Proceed and at least 45 days prior to commissioning
COR 0 1 electronic
01 91 13-2 Testing, Disinfection, and Commissioning
Testing and Commissioning Plan
Submitted and approved 60 days prior to commissioning
COR 0 1 electronic
01 91 13-3 Testing, Disinfection, and Commissioning
Disinfection Plan Submitted and approved 60 days prior to commissioning
Revised - 01 33 00 - 13
Table 01 33 00A - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.
RSN Clause or Section Title
Submittals required
Due date or delivery time
Respon-sible code
No. of sets to be sent to:
CO COR
01 91 13-4 Testing, Disinfection, and Commissioning
Testing, Disinfection, and Commissioning Report
Submitted and accepted no later than 7 days after completing each test
COR 0 1 electronic
01 91 13-5 Testing, Disinfection, and Commissioning
Post Testing and Commissioning Documentation
No later than 28 days after completing commissioning
COR 0 1 electronic
03 15 17-1 Hydrophilic Strip Waterstop
Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
03 20 00-1 Concrete Reinforcing
Reinforcement Diagrams and Lists
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
03 20 60-1 Concrete Anchors
Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
03 20 60-2 Concrete Anchors
Mill Test Reports In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
03 20 60-3 Concrete Anchors
Instructions In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
03 30 00-1 Cast-In-Place Concrete
Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
03 30 00-2 Cast-In-Place Concrete
Concrete Placement Schedule
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
03 30 00-3 Cast-In-Place Concrete
Certifications In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
03 30 00-4 Cast-In-Place Concrete
Test Reports In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
03 35 10-1 Concrete Floor Hardener
Manufacturer’s Instructions
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
03 48 00-1 Precast Concrete Structures
Certificates In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
03 48 00-2 Precast Concrete Structures
Shop Drawings In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
03 48 00-3 Precast Concrete Structures
Approval Data and Test Reports
In accordance with approved RSN 01 32 10-3 Submittal Register
Revised - 01 33 00 - 14
Table 01 33 00A - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.
RSN Clause or Section Title
Submittals required
Due date or delivery time
Respon-sible code
No. of sets to be sent to:
CO COR
03 48 00-4 Precast Concrete
Structures Notification of Factory Production
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
03 62 20-1 Nonshrink Grout for Equipment and Metalwork
Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
03 63 00-1 Epoxy Grout Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
04 22 10-1 Reinforced Concrete Unit Masonry Assemblies
Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
04 22 10-2 Reinforced Concrete Unit Masonry Assemblies
Color Samples In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 set of physical samples
04 22 10-3 Reinforced Concrete Unit Masonry Assemblies
Instructions In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
05 12 10-1 Structural Steel Qualifications In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
05 12 10-2 Structural Steel Dimensional Drawings
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
05 12 10-3 Structural Steel Approval Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
05 12 10-4 Structural Steel Test Reports In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
05 12 10-5 Structural Steel Weld Inspection Reports
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
05 12 10-6 Structural Steel Final Drawings In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
05 12 10-7 Structural Steel AISC “Quality Certified Fabricator” Certificate
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
05 40 00-1 Cold-Formed Metal Framing
Approval Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal
Revised - 01 33 00 - 15
Table 01 33 00A - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.
RSN Clause or Section Title
Submittals required
Due date or delivery time
Respon-sible code
No. of sets to be sent to:
CO COR
05 40 00-2 Cold-Formed
Metal Framing Certifications In accordance with approved
RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
05 40 00-3 Cold-Formed Metal Framing
Erection Plans and Manual
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
05 50 00-1 Metal Fabrications
Approval Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
05 50 00-2 Metal Fabrications
Final Drawings In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
05 51 30-1 Metal Ladders Approval Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
05 52 20-1 Fall Protection Rail System
Approval Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
05 52 20-2 Fall Protection Rail System
Operation and Maintenance Manual
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
06 82 10-1 Fiberglass Reinforced Plastic (FRP) Fabrications
Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
06 82 10-2 Fiberglass Reinforced Plastic (FRP) Fabrications
Approval Drawings and Calculations
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
07 19 20-1 Silane Water Repellent
Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
07 19 20-2 Silane Water Repellent
Instructions In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
07 19 20-3 Silane Water Repellent
Qualifications and Attestation
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
07 21 20-1 Extruded Polystyrene Foam Insulation
Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
07 21 60-1 Insulation Jacket Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
07 21 60-2 Insulation Jacket Instructions In accordance with approved RSN 01 32 10-3 Submittal
Revised - 01 33 00 - 16
Table 01 33 00A - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.
RSN Clause or Section Title
Submittals required
Due date or delivery time
Respon-sible code
No. of sets to be sent to:
CO COR
07 41 13-1 Insulated Metal
Roof Panels Sample and Color Sample Kit
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 set of physical samples
07 41 13-2 Insulated Metal Roof Panels
Qualifications In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
07 41 13-3 Insulated Metal Roof Panels
Approval Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
07 42 13-1 Insulated Metal Wall Panels
Sample and Color Sample Kit
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 set of physical samples
07 42 13-2 Insulated Metal Wall Panels
Qualifications In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
07 42 13-3 Insulated Metal Wall Panels
Approval Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
07 72 30-1 Roof Hatches Sample and Color Sample Kit
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 set of physical samples
07 72 30-2 Roof Hatches Approval Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
07 84 00-1 Firestopping Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
07 92 00-1 Joint Sealants and Masonry Joints
Approval Data and Color Samples
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 set of physical samples
07 92 00-2 Joint Sealants and Masonry Joints
Certification In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
07 92 00-3 Joint Sealants and Masonry Joints
Field Quality Control Verification Report
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
08 11 10-1 Steel Doors and Frames
Approval Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
08 11 10-2 Steel Doors and Frames
Instructions In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
08 31 25-1 Access Hatches Approval Data In accordance with approved RSN 01 32 10-3 Submittal
Revised - 01 33 00 - 17
Table 01 33 00A - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.
RSN Clause or Section Title
Submittals required
Due date or delivery time
Respon-sible code
No. of sets to be sent to:
CO COR
08 33 20-1 Roll-Up Doors Approval
Drawings and Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
08 33 20-2 Roll-Up Doors Sample and Color Sample Kit
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 set of physical samples
08 45 13-1 Structured- Polycarbonate Panel Assemblies
Approval Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
08 71 00-1 Door Hardware Approval Data and Hardware Schedule
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
08 71 00-2 Door Hardware Operation and Maintenance Manuals
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
09 29 00-1 Gypsum Board Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
09 65 10-1 Resilient Wall Base
Approval Data and Color Sample Kit
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
09 96 20-1 Coatings Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
09 96 20-2 Coatings Final Approval Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
09 96 20-3 Coatings Paint Chip Samples
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 set of physical samples
09 96 20-4 Coatings Qualifications In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
09 96 20-5 Coatings Quality Control Plan
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
09 96 20-6 Coatings Contractor Quality Testing Final Report
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
10 14 00-1 Signage Approval Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
10 14 01-1 Entry Sign Approval Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal
Revised - 01 33 00 - 18
Table 01 33 00A - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.
RSN Clause or Section Title
Submittals required
Due date or delivery time
Respon-sible code
No. of sets to be sent to:
CO COR
10 14 26-1 Utility Markers Utility Marker
Plan In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
10 44 20-1 Fire Extinguishers
Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
11 53 00-1 Laboratory Equipment
Approval Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
11 53 00-2 Laboratory Equipment
Operation and Maintenance Manuals
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
12 30 00-1 Casework and Countertops
Approval Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
12 30 00-2 Casework and Countertops
Color Samples In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 set of physical samples
13 34 21-1 Metal Building System
Approval Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
13 34 21-2 Metal Building System
Fabricator Qualifications
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
13 34 21-3 Metal Building System
Certification In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
13 34 21-4 Metal Building System
Design Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
13 34 21-5 Metal Building System
Anchorage Design Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
13 34 21-6 Metal Building System
Erection Plans, Manual, and Documentation
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
13 34 21-7 Metal Building System
Final Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
21 11 16-1 Fire Hydrants Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
21 11 16-2 Fire Hydrants Shop Testing Certifications and Reports
In accordance with approved RSN 01 32 10-3 Submittal
Revised - 01 33 00 - 19
Table 01 33 00A - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.
RSN Clause or Section Title
Submittals required
Due date or delivery time
Respon-sible code
No. of sets to be sent to:
CO COR
21 11 16-3 Fire Hydrants Operation and
Maintenance Manual
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
21 13 13-1 Automatic Fire Sprinkler Systems
Approval Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
21 13 13-2 Automatic Fire Sprinkler Systems
Test Plan In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
21 13 13-3 Automatic Fire Sprinkler Systems
Final Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
21 13 13-4 Automatic Fire Sprinkler Systems
Instructions In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 paper copy
21 25 00-1 Hybrid Water Mist Fire Suppression System
Qualifications In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
21 25 00-2 Hybrid Water Mist Fire Suppression System
Approval Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
21 25 00-3 Hybrid Water Mist Fire Suppression System
Test Plan In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
21 25 00-4 Hybrid Water Mist Fire Suppression System
Contractor Field Test Notification
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
21 25 00-5 Hybrid Water Mist Fire Suppression System
Test Reports In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
21 25 00-6 Hybrid Water Mist Fire Suppression System
Final Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
22 05 00-1 Common Work Results for Plumbing
Approval Drawings
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
22 05 00-2 Common Work Results for Plumbing
Final Drawings In accordance with approved RSN 01 32 10-3 Submittal
Revised - 01 33 00 - 20
Table 01 33 00A - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.
RSN Clause or Section Title
Submittals required
Due date or delivery time
Respon-sible code
No. of sets to be sent to:
CO COR
22 05 17-1 Sleeves and
Sleeve Seals for Plumbing Piping
Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
22 05 19-1 Meters and Gauges for Plumbing Piping
Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
22 05 23-1 General-Duty Valves for Plumbing Piping
Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
22 05 29-1 Hangers and Supports for Plumbing Piping and Equipment
Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
22 05 53-1 Identification for Plumbing Piping and Equipment
Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
22 07 19-1 Plumbing Piping Insulation
Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
22 11 16-1 Domestic Water Piping
Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
22 11 16-2 Domestic Water Piping
Test Reports In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
22 11 16-3 Domestic Water Piping
Operation and Maintenance Manuals
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
22 11 19-1 Domestic Water Piping Specialties
Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
22 11 23-1 Domestic Water Packaged Booster Pumps
Approval Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
22 11 23-2 Domestic Water Packaged Booster Pumps
Final Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
22 11 25-1 Domestic Water In-Line Recirculation Pump
Approval Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
22 11 25-2 Domestic Water In-Line Recirculation Pump
Final Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal
Revised - 01 33 00 - 21
Table 01 33 00A - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.
RSN Clause or Section Title
Submittals required
Due date or delivery time
Respon-sible code
No. of sets to be sent to:
CO COR
22 12 23-1 Facility Indoor
Potable-Water Storage Tanks
Approval Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
22 12 23-2 Facility Indoor Potable-Water Storage Tanks
Factory Test Report
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
22 12 23-3 Facility Indoor Potable-Water Storage Tanks
Operation and Maintenance Manual
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
22 13 10-1 Facility Gravity Drainage Piping System
Approval Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
22 13 10-2 Facility Gravity Drainage Piping System
Operation and Maintenance Manuals
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
22 13 63-1 Facility Gray Water Tanks
Approval Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
22 13 63-2 Facility Gray Water Tanks
Factory Test Report
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
22 33 00-1 Electric Domestic Water Heaters
Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
22 33 00-2 Electric Domestic Water Heaters
Final Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
22 45 00-1 Emergency Plumbing Fixtures
Approval Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
22 45 00-2 Emergency Plumbing Fixtures
Field Test Plan In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
22 45 00-3 Emergency Plumbing Fixtures
Final Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 05 00-1 Common Work Results for
HVAC
Approval Drawings
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 05 00-2 Common Work Results for
HVAC
Final Drawings In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 05 29-1 Hangers and Supports for HVAC Piping and Equipment
Approval Data In accordance with approved RSN 01 32 10-3 Submittal
Revised - 01 33 00 - 22
Table 01 33 00A - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.
RSN Clause or Section Title
Submittals required
Due date or delivery time
Respon-sible code
No. of sets to be sent to:
CO COR
23 05 53-1 Identification for
HVAC Piping and Equipment
Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 05 93-1 Testing, Adjusting, and Balancing for
HVAC
Qualification Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 05 93-2 Testing, Adjusting, and Balancing for
HVAC
Test Plan In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 05 93-3 Testing, Adjusting, and Balancing for
HVAC
Final Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 07 13-1 Duct Insulation Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 07 13-2 Duct Insulation Qualification Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 08 00-1 Commissioning of HVAC
Commissioning Authority Statement of Qualifications
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 08 00-2 Commissioning of HVAC
Commissioning Plan
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 08 00-3 Commissioning of HVAC
Test Procedures In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 08 00-4 Commissioning of HVAC
Draft Commissioning Report
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 08 00-5 Commissioning of HVAC
Deficiency Report and Test Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 08 00-6 Commissioning of HVAC
Final Commissioning Report
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 31 00-1 HVAC Ducts and Casings
Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 33 00-1 Air Duct Accessories
Approval Data In accordance with approved RSN 01 32 10-3 Submittal
Revised - 01 33 00 - 23
Table 01 33 00A - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.
RSN Clause or Section Title
Submittals required
Due date or delivery time
Respon-sible code
No. of sets to be sent to:
CO COR
23 34 00-1 HVAC Fans Approval
Drawings and Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 34 00-2 HVAC Fans Operation and Maintenance Manuals
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 37 00-1 Air Outlets and Inlets
Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 74 15-1 Packaged Outdoor Air- Conditioning Units
Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 74 15-2 Packaged Outdoor Air- Conditioning Units
Vibration Isolation Design
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 74 15-3 Packaged Outdoor Air- Conditioning Units
Final Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 74 33-1 Dedicated Outdoor-Air Units
Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 74 33-2 Dedicated Outdoor-Air Units
Vibration Isolation Design
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 74 33-3 Dedicated Outdoor-Air Units
Final Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 81 26-1 Split-System Air-Conditioners
Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 81 26-2 Split-System Air-Conditioners
Operation and Maintenance Manual
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 82 39-1 Unit Heaters Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
23 82 39-2 Unit Heaters Operation and Maintenance Manuals
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
25 00 01-1 Control and Monitoring
Approval Data In accordance with approved RSN 01 32 10-3 Submittal
Revised - 01 33 00 - 24
Table 01 33 00A - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.
RSN Clause or Section Title
Submittals required
Due date or delivery time
Respon-sible code
No. of sets to be sent to:
CO COR
25 00 01-2 Control and
Monitoring Factory Acceptance Test Procedures
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
25 00 01-3 Control and Monitoring
Factory Acceptance Test Notification
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
25 00 01-4 Control and Monitoring
Factory Acceptance Test Reports
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
25 00 01-5 Control and Monitoring
Final Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
25 12 10-1 Programmable Logic Controller
Approval Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
25 12 10-2 Programmable Logic Controller
System Description Documentation
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
25 12 10-3 Programmable Logic Controller
Final Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
25 15 11-1 HMI and Basic Control Functions
Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
25 15 11-2 HMI and Basic Control Functions
Factory Acceptance Test Procedures
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
25 15 11-3 HMI and Basic Control Functions
Factory Acceptance Test Notification
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
25 15 11-4 HMI and Basic Control Functions
Factory Acceptance Test Reports
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
25 15 11-5 HMI and Basic Control Functions
Field Quality Test Report
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
25 15 11-6 HMI and Basic Control Functions
Final Drawings and Data
In accordance with approved RSN 01 32 10-3 Submittal Register
COR 0 1 electronic
26 05 10-1 Conductors and Cables
Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register
CO…