01_33_00_-_Submittals_AMD0003_0003.pdf

PDF 333 KB Posted

Attached to
Arkansas Valley Conduit (AVC) Injection Site
Solicitation number
140R6023R0013
Issued by

About this file

This document outlines submittal requirements for a federal construction contract solicitation. The solicitation is for the Arkansas Valley Conduit Injection Site and Backflow Preventer Site project with the Bureau of Reclamation. It specifies over 100 required submittals across various construction phases, including quality control plans, schedules, safety documentation, shop drawings, test reports, as-built drawings and more. Submittals are due based on the project schedule and must follow naming and formatting conventions. The government allows 28 days for review and requires electronic submission through a shared Microsoft Teams site.

View the file

Other files

Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Arkansas Valley Conduit Injection Site Phase 1 and Backflow Preventer Site Amendment No. 0003 Fryingpan-Arkansas Project, Colorado Solicitation No. 140R6023R0013

Submittals

Revised - 01 33 00 - 1

SECTION 01 33 00

SUBMITTALS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost: Include in prices offered in the Price Schedule for other items of work.

1.02 DEFINITIONS

A. Days: Calendar days.

B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.

C. Submittals: Considered “shop drawings” within the terms of the clause at FAR 52.236- 21, Specifications and Drawings for Construction.

1.03 REFERENCE STANDARDS

A. American Society of Mechanical Engineers (ASME)

1. ASME Y14.1-20 Decimal Inch Drawing Sheet Size and Format

B. National Institute of Building Sciences (NIBS)

1. NIBS NCS-14 United States National CAD Standards, Version 6

1.04 SUBMITTAL REQUIREMENTS

A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included in this section take precedence.

B. General:

1. Prepare in English.

2. Label with contract number and title, and RSN.

3. Measurement Units: US Customary Units.

C. Drawings:

1. Minimum Identification in Title Block:

a. Contract number and title.

b. Contractor's or supplier's title and drawing number.

Revised - 01 33 00 - 2

c. Date.

2. Reserve 3- by 3-inch space next to title block for review stamps.

3. Size: D size (22 inches by 34 inches) in accordance with ASME Y14.1.

4. Draw to scale using computer drafting.

a. In accordance with NIBS NCS.

b. Electronic file format: Compatible with AutoCAD Version 2021 or later.

c. Compile using “eTransmit” utility in AutoCAD.

d. Government will provide electronic AutoCAD format template.

e. Title block and sheet format:

1) As shown on Standard Drawing 40-D-7102.

2) Government will supply template.

3) Government will supply specific title block information to be used.

f. Show as-built changes, including revision dates, made during installation.

Indicate changes by clouding.

D. Manuals:

1. Copies:

a. Printed copies: Bound and indexed.

b. Electronic copies: Adobe pdf submitted to Microsoft Teams. Bookmark longer files to assist in navigating file.

2. Contents:

a. Parts identification lists, lists of special tools, and accessories.

b. Schematics and wiring diagrams.

c. Detailed instructions for installing, operating, lubricating, and maintaining equipment.

d. As-built drawings, photographs, and test records or reports if required by the specifications.

E. Product Data:

1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.

a. Identify manufacturer's name, type, model, size, and characteristics.

b. Illustrate that product or equipment meets requirements of specifications.

c. Mark items to be furnished in a manner that will photocopy (no highlighter).

d. Strike through items that do not apply.

Revised - 01 33 00 - 3

F. Certifications:

1. Certifications by a registered professional: Signed and sealed by registered professional.

2. Manufacturer's certifications: Signed by authorized representative of manufacturer.

G. Photographs:

1. Professional quality:

a. Include contract number, name of equipment, and view title.

b. Digital files in .jpeg.

H. Videos:

1. Digital file in MP4 format.

2. Upload to Microsoft Teams.

I. Samples and Color Selection Submittals:

1. Ship samples except color samples to Technical Service Center, Bureau of Reclamation, Attn: 86-68160, P.O. Box 25007, Denver CO 80225-0007; Express Mail: Sixth and Kipling, Building 67, Room 152.

2. Ship color samples to Government field office, refer to Section 01 52 10 - Field Office and Laboratory.

3. Label with complete manufacturer’s product and color identification.

4. Include type and quantity of materials specified in the referenced section in each “set” of samples.

5. Samples: Representative of product to be installed. Xerographic sheets for color selection are not acceptable.

6. Color Chips: Sample paint chips. Ink color reproductions are not acceptable.

7. Label each sample, sample kit, set of color chips, of color chart with contract number and title.

8. Government will select architectural color and pattern after product approval.

1.05 SUBMITTALS PROCEDURES

A. Submit only checked submittals. Submittals without evidence of Contractor's approval will not be reviewed.

B. Submit complete sets of required materials for each RSN as specified in “Submittals Required” column in Table 01 33 00A - List of Submittals. A complete set includes all listed items for RSNs with multiple parts.

Revised - 01 33 00 - 4

C. Submit in accordance with “No. of sets to be sent:” columns in Table 01 33 00A - List of Submittals:

1. Electronic submittals:

a. In Portable Document Format (PDF).

1) Optical Character Recognition (OCR).

2) 508 compliant.

3) RSNs having more than one requirement shall be bookmarked.

4) RSNs with requirements for files other than PDF (.XER, .PLF, .DWGs, etc.) shall be combined using WINZip.

5) Include RSN transmittal letter.

6) Each submittal shall be submitted as one PDF or WINZip (only when multiple file types are required).

b. Personally Identifiable Information (PII) shall be encrypted using WINZip or Adobe Acrobat before transmitting electronically.

2. Submit electronic submittals via Microsoft Teams:

a. Access to Microsoft Teams will be made available for transmission of submittals, correspondence, and information sharing following Notice to Proceed.

b. Submittals received after 5:00 p.m. Mountain Time shall be documented as received the next business day.

D. Include the following information in transmittal letters:

1. Cover Letter:

a. Contract number and title.

b. RSN for attached submittal.

c. Responsible code.

d. Identify submittal as initial or resubmittal.

2. Submittal contents following cover letter. Shall include all listed items for RSNs with multiple parts.

E. Resubmittal of submittals not approved:

1. Mark changes such that they are readily identifiable and show revision date.

Resubmitted drawings shall include a revision block with date.

2. Describe reasons for significant changes in transmittal letter.

3. Resubmit returned submittals within 14 calendar days after receiving comments.

4. Requirements for initial submittals apply to resubmittals.

Revised - 01 33 00 - 5

5. Resubmittals shall be complete submittals without reference to the original submittal.

F. Submit each RSN under a separate transmittal letter. Multiple RSNs submitted under a single letter will not be reviewed.

1.06 REVIEW OF SUBMITTALS

A. Time Required:

1. Submittal review will require 28 calendar days for review of each submittal or resubmittal, unless otherwise specified.

2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through the date the response is uploaded to Microsoft Teams.

3. Provide Submittal Register as required within Section 01 32 10 – Construction Program. Submittal Register shall be complete and include anticipated submittal dates for each RSN:

a. Division 1 submittals shall be provided per due date or delivery time provided within Table 01 33 00A – List of Submittals.

b. Sequence Division 2 through 46 submittals to maintain Contractor’s construction schedule, with submittals intentionally staggered. Submit no more than 5 submittals, counting original and resubmittals, per Division(s) listed below within one 7-day period.

1) Division 2 through 23.

2) Division 25 through 28.

3) Division 31 through 32.

4) Division 33 through 46.

c. Contractor and Government shall mutually agree to a revised review time for submittals received in excess of 5 submittals per 7-calendar day period for the Division(s) listed above.

d. Approval drawings and data submittals shall be approved by the Government prior to purchase of applicable materials.

B. Time in Excess of Specified:

1. The CO may extend contract completion date to allow additional time for completing work affected by excess review time.

a. Time extension will be to extent that excess review time caused delay to contract completion date.

b. Time extension will not exceed time used in excess of specified number of days for review of submittals or resubmittals.

Revised - 01 33 00 - 6

c. Concurrent days of excess review time resulting from review of 2 or more separate submittals or resubmittals will be counted only once in extending contract completion date.

2. No time extension will be allowed if Contractor fails to make complete action submittals in sequence and within time periods specified.

3. Adjustment for delay will be made only to extent that:

a. Approval was required under contract, and

b. Requests for approval were submitted as required, in a timely fashion, and were approved.

4. Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at FAR 52.242-14, Suspension of Work; however, no such delay shall be deemed to be a “suspension order” as the term is used in that clause.

C. Submittal Response:

1. Response letter will indicate whether submittal is approved, not approved, acceptable, not acceptable, or acknowledged receipt.

a. Revise and resubmit submittals not approved or not acceptable.

b. Do not change designs without approval of CO after drawings, documentation, and technical data have been approved.

2. Request For Information (RFI). A response will be provided within 28 calendar days.

3. General Correspondence to the COR. A response will be provided within 28 calendar days.

1.07 TRANSMITTAL

A. Microsoft Teams access will be established for uploading all correspondence and transmittals listed in Table 01 33 00A - List of Submittals.

B. Submittals required by specifications, but not listed in Table 01 33 00A - List of Submittals:

1. Submit in accordance with this section.

2. Submit to COR unless otherwise specified.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

Revised - 01 33 00 - 7

Table 01 33 00A - List of Submittals

* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.

RSN Clause or Section Title

Submittals required

Due date or delivery time

Respon-sible code

No. of sets to be sent to:

CO COR

1 Performance and

Payment Bonds - Construction

FAR 52.228-15

Performance and Payment Bonds

No later than 10 days after award

CO 1

electronic

2 Additional Bond Security

FAR 52.228-2

Additional Bond Security

No later than 10 days after award

CO 1

electronic

3 Insurance-Work on a Government Installation

FAR 52.228-5

1) Written certification that the required insurance has been obtained

2) Current certification of insurance for each subcontractor

Before commencing onsite work

CO 1

electronic electronic

4 Liability Insurance

DIAR

1452.228-70

Acceptable Certificate of Liability Insurance

Prior to commencement of work under the contract

CO 1

electronic

5 Release of Claims

DIAR

1452.204-70

Release of Claims (DI-137) against the Government

After completion of the work and prior to final payment

CO 1

electronic

6 Personal Identity Verification of Contractor Personnel

FAR 52.204-9

SF-85 and OF-306 for each employee and subcontractor employee working on site

No later than 10 days after receipt of Notice to Proceed or 10 days before commenting work (for new hire)

CO 1

electronic

7 Subcontracts (Labor Standards)

FAR 52.222-11

1) List of subcontractors

No later than 14 days after award of contract

COR 1

electronic

1 electronic

8 Subcontracts (Labor Standards)

FAR 52.222-11

2) Statement and Acknowledgement Form (SF-1413) for each subcontract

No later than 14 days after award of subcontract

COR 1

electronic

1 electronic

9 Payrolls and Basic Records

FAR 52.222-8

Copies of all payrolls

Weekly for each week of contract performance

COR 1

electronic encrypted

1 electronic encrypted

10 Site Security

GP-7

List of contractor and subcontractor employees

Submitted and approved prior to arriving at worksite

COR 0 1 electronic encrypted

11 Site Security

GP-7

List of vehicles and equipment to be brought on site

Submitted and approved prior to arriving at worksite

COR 0 1 electronic encrypted

Revised - 01 33 00 - 8

Table 01 33 00A - List of Submittals

* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.

RSN Clause or Section Title

Submittals required

Due date or delivery time

Respon-sible code

No. of sets to be sent to:

CO COR

12 Superintendence by the Contractor

FAR 52.236-6

Site Superintendent

Submitted and approved at least 28 days before mobilization

COR 0 1 electronic

01 14 10-1 Use of Site Land Use and Landscape Rehabilitation Plan

Submitted and approved at least 28 days before mobilization

COR 0 1 electronic

01 14 12-1 Work Restrictions and Limitations

Request for Pueblo Water Connection

At least 28 days before work onsite

COR 0 1 electronic

01 31 19-1 Project Management and Coordination

Weekly Coordination Meeting Documentation

Weekly, 3 days prior to meeting

COR 0 1 electronic

01 31 19-2 Project Management and Coordination

Weekly Coordination Meeting Minutes

Weekly, within 3 days after meeting

COR 0 1 electronic

01 31 19-3 Project Management and Coordination

Expanded Right-of-Way Land Use Coordination

At least 6 months prior to use of land

COR 0 1 electronic

01 32 10-1 Construction Program

Representative Information

Submitted within 21 days after NTP

COR 0 1 electronic

01 32 10-2 Construction Program

Baseline Schedule Submitted within 21 days after NTP

COR 0 1 electronic

01 32 10-3 Construction Program

Submittal Register Submitted and approved within 28 days of NTP and monthly after approval

COR 0 1 electronic

01 32 10-4 Construction Program

Updated Schedule Reports

Monthly after Baseline Schedule is approved

COR 0 1 electronic

01 32 10-5 Construction Program

Time Impact Analysis

No later than 28 days after the CO directs a contract change, with any proposal for a future modification, with any value engineering proposal, or with any request or claim for an equitable adjustment to the contract

COR 0 1 electronic

01 32 10-6 Construction Program

Schedule of Values Submitted and approved before any payment other than bonds and insurance

COR 0 1 electronic

01 35 10-1 Safety Data Sheets

Complete LHM and SDS

Submitted and approved at least 28 days before jobsite delivery of hazardous material

COR 0 1 electronic

01 35 10-2 Safety Data Sheets

Updated LHM and

SDS

Submitted and approved at least 28 days before jobsite delivery of hazardous material not previously listed

Revised - 01 33 00 - 9

Table 01 33 00A - List of Submittals

* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.

RSN Clause or Section Title

Submittals required

Due date or delivery time

Respon-sible code

No. of sets to be sent to:

CO COR

01 35 20-1 Safety and

Health Safety Program Submitted and accepted at least 28 days before mobilization

COR 0 1 electronic

01 35 20-2 Safety and Health

Monthly Accident Summary Reports

Monthly COR 0 1 electronic

01 35 20-3 Safety and Health

Respirator User Documentation

Submitted and accepted at least 28 days before onsite work begins

COR 0 1 electronic encrypted

01 35 20-4 Safety and Health

Crane Operation Certificates

Submitted and accepted at least 28 days before onsite work begins

COR 0 1 electronic

01 35 20-5 Safety and Health

Exposure Assessment Form

Submitted and accepted at least 28 days before onsite work begins

COR 0 1 electronic

01 35 20-6 Safety and Health

Other Training Certificates

Submitted and accepted at least 28 days before onsite work begins

COR 0 1 electronic

01 35 20-7 Safety and Health

Pandemic Notification

No later than 24 hours after positive test

COR 0 1 electronic

01 35 20-8 Safety and Health

Employee Return to Work Documentation

7 days prior to returning to work

COR 0 1 electronic

01 35 30-1 Contractor's Onsite Safety Personnel

Qualifications Submitted and accepted at least 28 days before mobilization

COR 0 1 electronic encrypted

01 35 30-2 Contractor's Onsite Safety Personnel

Safety Inspection Reports

Weekly COR 0 1 electronic

01 46 00-1 Quality Procedures

Contractor Quality Control Program

Submitted and approved at least 28 days before mobilization

COR 0 1 electronic

01 46 00-2 Quality Procedures

Contractor's Daily Reports

Weekly COR 0 1 electronic

01 46 00-3 Quality Procedures

Quality Control Supervisor Resume

Submitted and approved at least 28 days before mobilization

COR 0 1 electronic encrypted

01 46 00-4 Quality Procedures

Contractor’s Quality Testing Plan

Submitted and approved at least 28 days before mobilization

COR 0 1 electronic

01 46 00-5 Quality Procedures

Summary of Test Results

Monthly COR 0 1 electronic

01 46 20-1 Testing Agency Services

Testing Agency Services Plan

Submitted and approved at least 28 days before mobilization

COR 0 1 electronic

01 46 20-2 Testing Agency Services

Certifications Submitted and approved at least 28 days before mobilization

Revised - 01 33 00 - 10

Table 01 33 00A - List of Submittals

* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.

RSN Clause or Section Title

Submittals required

Due date or delivery time

Respon-sible code

No. of sets to be sent to:

CO COR

01 46 25-1 Special

Inspections Preconstruction Submittals

Submitted and approved at least 28 days before mobilization

COR 0 1 electronic

01 46 25-2 Special Inspections

Test Reports Submitted and approved at least 28 days before mobilization

COR 0 1 electronic

01 46 25-3 Special Inspections

Certificates At time of preconstruction conference

COR 0 1 electronic

01 46 25-4 Special Inspections

Closeout Submittals

Submitted and accepted at least 28 days after completion of construction

COR 0 1 electronic

01 52 10-1 Field Office and Laboratory

Delivery Schedule and Site Layout

Submitted and approved at least 28 days before delivery and setup

COR 0 1 electronic

01 52 10-2 Field Office and Laboratory

Approved Pueblo Regional Building Department Permits

Submitted and approved at least 28 days before mobilization

COR 0 1 electronic

01 55 00-1 Vehicular Access and Parking

Temporary Access Roadway Plan

Submitted and approved at least 28 days before mobilization

COR 0 1 electronic

01 55 00-2 Vehicular Access and Parking

Pre-Construction Video

Submitted and approved at least 28 days before mobilization

COR 0 1 electronic

01 55 00-3 Vehicular Access and Parking

Post-Construction Video

No later than 7 days after completing construction

COR 0 1 electronic

01 55 00-4 Vehicular Access and Parking

Post-Repair Video No later than 7 days after completing repair

COR 0 1 electronic

01 55 20-1 Traffic Control Approved CDOT Permit(s)

Submitted and approved at least 28 days before mobilization

COR 0 1 electronic

01 56 15-1 Protection of Existing Utilities

Utility Owner Acknowledgment

Submitted and approved at least 28 days before mobilization

COR 0 1 electronic

01 57 15-1 Utility Line Investigations

Utility Crossing Investigations

Submitted and approved at least 28 days before preparation of pipelaying diagrams required by Section 33 11 10

COR 0 1 electronic

01 57 15-2 Utility Line Investigations

Permits Submitted and approved at least 28 days before beginning work in area of each utility line

Revised - 01 33 00 - 11

Table 01 33 00A - List of Submittals

* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.

RSN Clause or Section Title

Submittals required

Due date or delivery time

Respon-sible code

No. of sets to be sent to:

CO COR

01 57 20-1 Environmental

Controls Dust Control Plan Submitted and approved at least 28 days before mobilization

COR 0 1 electronic

01 57 20-2 Environmental Controls

Copy of Applicable Air Pollution Emissions Notice (APEN) and Air Quality Permits

Submitted and approved at least 28 days before mobilization

COR 0 1 electronic

01 57 30-1 Water Pollution Control

Stormwater Management Plan

(SWMP)

Submitted and approved at least 28 days before mobilization

COR 0 1 electronic

01 57 30-2 Water Pollution Control

Spill Prevention, Control, and Countermeasure Plan (SPCC)

Submitted and approved at least 28 days before mobilization

COR 0 1 electronic

01 71 20-1 Surveying Surveying Plan Submitted and approved at least 28 days before mobilization

COR 0 1 electronic

01 71 20-2 Surveying Resumes At least 28 days before beginning survey work; At least 28 days before personnel change

COR 0 1 electronic

01 71 20-3 Surveying Accuracy Check Results

Submitted and approved at least 28 days before beginning survey work

COR 0 1 electronic

01 71 20-4 Surveying Topographic Survey of Existing Conditions at the Drainage Outfall and Existing Culvert

45 days prior to starting earthwork

COR 0 1 electronic

01 71 20-5 Surveying Topographic Survey of Detention Basin

Prior to seeding COR 0 1 electronic

01 71 20-6 Surveying Topographic Survey of Backflow Preventer Site Frontage Road

45 days prior to starting Frontage Road construction

COR 0 1 electronic

01 71 20-7 Surveying Topographic Survey of Frontage Road after Paving

Prior to seeding COR 0 1 electronic

01 71 20-8 Surveying Completed and Reduced Survey Notes

No later than 7 days after completing and reducing notes

Revised - 01 33 00 - 12

Table 01 33 00A - List of Submittals

* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.

RSN Clause or Section Title

Submittals required

Due date or delivery time

Respon-sible code

No. of sets to be sent to:

CO COR

01 71 20-9 Surveying Quantity Survey

Notes and Computations

Submitted and approved for monthly progress payments

COR 0 1 electronic

01 74 00-1 Cleaning and Waste Management

Waste Production and Disposal Plan

Submitted and approved at least 28 days before mobilization

COR 0 1 electronic

01 74 00-2 Cleaning and Waste Management

Waste Production and Disposal Records

No later than 7 days after waste disposal

COR 0 1 electronic

01 74 00-3 Cleaning and Waste Management

Environmental Consultant Resume

At least 28 days before beginning environmental assessment

COR 0 1 electronic

01 74 00-4 Cleaning and Waste Management

Environmental Site Assessment

No later than 14 days after completion of work

COR 0 1 electronic

01 78 30-1 Project Record Documents

As-built Drawings No later than 28 days after completion of work

COR 0 1 electronic

01 78 30-2 Project Record Documents

Final Drawings No later than 28 days after completion of work

COR 0 1 electronic

01 78 30-3 Project Record Documents

As-built Record of Materials

No later than 28 days after completion of work

COR 0 1 electronic

01 78 30-4 Project Record Documents

Extra Materials No later than 28 days after completion of work

COR 0 1 electronic

01 78 30-5 Project Record Documents

Warranties No later than 28 days after completion of work

COR 0 1 electronic

01 79 20-1 Training Instructor Qualifications

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

01 79 20-2 Training Training Materials In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

01 79 20-3 Training Training Video In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

01 91 13-1 Testing, Disinfection, and Commissioning

Qualifications Submitted and approved no later than 150 days after Notice to Proceed and at least 45 days prior to commissioning

COR 0 1 electronic

01 91 13-2 Testing, Disinfection, and Commissioning

Testing and Commissioning Plan

Submitted and approved 60 days prior to commissioning

COR 0 1 electronic

01 91 13-3 Testing, Disinfection, and Commissioning

Disinfection Plan Submitted and approved 60 days prior to commissioning

Revised - 01 33 00 - 13

Table 01 33 00A - List of Submittals

* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.

RSN Clause or Section Title

Submittals required

Due date or delivery time

Respon-sible code

No. of sets to be sent to:

CO COR

01 91 13-4 Testing, Disinfection, and Commissioning

Testing, Disinfection, and Commissioning Report

Submitted and accepted no later than 7 days after completing each test

COR 0 1 electronic

01 91 13-5 Testing, Disinfection, and Commissioning

Post Testing and Commissioning Documentation

No later than 28 days after completing commissioning

COR 0 1 electronic

03 15 17-1 Hydrophilic Strip Waterstop

Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

03 20 00-1 Concrete Reinforcing

Reinforcement Diagrams and Lists

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

03 20 60-1 Concrete Anchors

Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

03 20 60-2 Concrete Anchors

Mill Test Reports In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

03 20 60-3 Concrete Anchors

Instructions In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

03 30 00-1 Cast-In-Place Concrete

Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

03 30 00-2 Cast-In-Place Concrete

Concrete Placement Schedule

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

03 30 00-3 Cast-In-Place Concrete

Certifications In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

03 30 00-4 Cast-In-Place Concrete

Test Reports In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

03 35 10-1 Concrete Floor Hardener

Manufacturer’s Instructions

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

03 48 00-1 Precast Concrete Structures

Certificates In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

03 48 00-2 Precast Concrete Structures

Shop Drawings In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

03 48 00-3 Precast Concrete Structures

Approval Data and Test Reports

In accordance with approved RSN 01 32 10-3 Submittal Register

Revised - 01 33 00 - 14

Table 01 33 00A - List of Submittals

* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.

RSN Clause or Section Title

Submittals required

Due date or delivery time

Respon-sible code

No. of sets to be sent to:

CO COR

03 48 00-4 Precast Concrete

Structures Notification of Factory Production

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

03 62 20-1 Nonshrink Grout for Equipment and Metalwork

Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

03 63 00-1 Epoxy Grout Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

04 22 10-1 Reinforced Concrete Unit Masonry Assemblies

Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

04 22 10-2 Reinforced Concrete Unit Masonry Assemblies

Color Samples In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 set of physical samples

04 22 10-3 Reinforced Concrete Unit Masonry Assemblies

Instructions In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

05 12 10-1 Structural Steel Qualifications In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

05 12 10-2 Structural Steel Dimensional Drawings

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

05 12 10-3 Structural Steel Approval Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

05 12 10-4 Structural Steel Test Reports In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

05 12 10-5 Structural Steel Weld Inspection Reports

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

05 12 10-6 Structural Steel Final Drawings In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

05 12 10-7 Structural Steel AISC “Quality Certified Fabricator” Certificate

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

05 40 00-1 Cold-Formed Metal Framing

Approval Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal

Revised - 01 33 00 - 15

Table 01 33 00A - List of Submittals

* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.

RSN Clause or Section Title

Submittals required

Due date or delivery time

Respon-sible code

No. of sets to be sent to:

CO COR

05 40 00-2 Cold-Formed

Metal Framing Certifications In accordance with approved

RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

05 40 00-3 Cold-Formed Metal Framing

Erection Plans and Manual

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

05 50 00-1 Metal Fabrications

Approval Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

05 50 00-2 Metal Fabrications

Final Drawings In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

05 51 30-1 Metal Ladders Approval Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

05 52 20-1 Fall Protection Rail System

Approval Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

05 52 20-2 Fall Protection Rail System

Operation and Maintenance Manual

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

06 82 10-1 Fiberglass Reinforced Plastic (FRP) Fabrications

Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

06 82 10-2 Fiberglass Reinforced Plastic (FRP) Fabrications

Approval Drawings and Calculations

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

07 19 20-1 Silane Water Repellent

Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

07 19 20-2 Silane Water Repellent

Instructions In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

07 19 20-3 Silane Water Repellent

Qualifications and Attestation

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

07 21 20-1 Extruded Polystyrene Foam Insulation

Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

07 21 60-1 Insulation Jacket Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

07 21 60-2 Insulation Jacket Instructions In accordance with approved RSN 01 32 10-3 Submittal

Revised - 01 33 00 - 16

Table 01 33 00A - List of Submittals

* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.

RSN Clause or Section Title

Submittals required

Due date or delivery time

Respon-sible code

No. of sets to be sent to:

CO COR

07 41 13-1 Insulated Metal

Roof Panels Sample and Color Sample Kit

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 set of physical samples

07 41 13-2 Insulated Metal Roof Panels

Qualifications In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

07 41 13-3 Insulated Metal Roof Panels

Approval Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

07 42 13-1 Insulated Metal Wall Panels

Sample and Color Sample Kit

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 set of physical samples

07 42 13-2 Insulated Metal Wall Panels

Qualifications In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

07 42 13-3 Insulated Metal Wall Panels

Approval Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

07 72 30-1 Roof Hatches Sample and Color Sample Kit

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 set of physical samples

07 72 30-2 Roof Hatches Approval Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

07 84 00-1 Firestopping Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

07 92 00-1 Joint Sealants and Masonry Joints

Approval Data and Color Samples

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 set of physical samples

07 92 00-2 Joint Sealants and Masonry Joints

Certification In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

07 92 00-3 Joint Sealants and Masonry Joints

Field Quality Control Verification Report

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

08 11 10-1 Steel Doors and Frames

Approval Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

08 11 10-2 Steel Doors and Frames

Instructions In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

08 31 25-1 Access Hatches Approval Data In accordance with approved RSN 01 32 10-3 Submittal

Revised - 01 33 00 - 17

Table 01 33 00A - List of Submittals

* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.

RSN Clause or Section Title

Submittals required

Due date or delivery time

Respon-sible code

No. of sets to be sent to:

CO COR

08 33 20-1 Roll-Up Doors Approval

Drawings and Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

08 33 20-2 Roll-Up Doors Sample and Color Sample Kit

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 set of physical samples

08 45 13-1 Structured- Polycarbonate Panel Assemblies

Approval Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

08 71 00-1 Door Hardware Approval Data and Hardware Schedule

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

08 71 00-2 Door Hardware Operation and Maintenance Manuals

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

09 29 00-1 Gypsum Board Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

09 65 10-1 Resilient Wall Base

Approval Data and Color Sample Kit

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

09 96 20-1 Coatings Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

09 96 20-2 Coatings Final Approval Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

09 96 20-3 Coatings Paint Chip Samples

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 set of physical samples

09 96 20-4 Coatings Qualifications In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

09 96 20-5 Coatings Quality Control Plan

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

09 96 20-6 Coatings Contractor Quality Testing Final Report

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

10 14 00-1 Signage Approval Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

10 14 01-1 Entry Sign Approval Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal

Revised - 01 33 00 - 18

Table 01 33 00A - List of Submittals

* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.

RSN Clause or Section Title

Submittals required

Due date or delivery time

Respon-sible code

No. of sets to be sent to:

CO COR

10 14 26-1 Utility Markers Utility Marker

Plan In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

10 44 20-1 Fire Extinguishers

Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

11 53 00-1 Laboratory Equipment

Approval Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

11 53 00-2 Laboratory Equipment

Operation and Maintenance Manuals

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

12 30 00-1 Casework and Countertops

Approval Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

12 30 00-2 Casework and Countertops

Color Samples In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 set of physical samples

13 34 21-1 Metal Building System

Approval Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

13 34 21-2 Metal Building System

Fabricator Qualifications

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

13 34 21-3 Metal Building System

Certification In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

13 34 21-4 Metal Building System

Design Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

13 34 21-5 Metal Building System

Anchorage Design Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

13 34 21-6 Metal Building System

Erection Plans, Manual, and Documentation

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

13 34 21-7 Metal Building System

Final Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

21 11 16-1 Fire Hydrants Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

21 11 16-2 Fire Hydrants Shop Testing Certifications and Reports

In accordance with approved RSN 01 32 10-3 Submittal

Revised - 01 33 00 - 19

Table 01 33 00A - List of Submittals

* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.

RSN Clause or Section Title

Submittals required

Due date or delivery time

Respon-sible code

No. of sets to be sent to:

CO COR

21 11 16-3 Fire Hydrants Operation and

Maintenance Manual

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

21 13 13-1 Automatic Fire Sprinkler Systems

Approval Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

21 13 13-2 Automatic Fire Sprinkler Systems

Test Plan In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

21 13 13-3 Automatic Fire Sprinkler Systems

Final Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

21 13 13-4 Automatic Fire Sprinkler Systems

Instructions In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 paper copy

21 25 00-1 Hybrid Water Mist Fire Suppression System

Qualifications In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

21 25 00-2 Hybrid Water Mist Fire Suppression System

Approval Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

21 25 00-3 Hybrid Water Mist Fire Suppression System

Test Plan In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

21 25 00-4 Hybrid Water Mist Fire Suppression System

Contractor Field Test Notification

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

21 25 00-5 Hybrid Water Mist Fire Suppression System

Test Reports In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

21 25 00-6 Hybrid Water Mist Fire Suppression System

Final Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

22 05 00-1 Common Work Results for Plumbing

Approval Drawings

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

22 05 00-2 Common Work Results for Plumbing

Final Drawings In accordance with approved RSN 01 32 10-3 Submittal

Revised - 01 33 00 - 20

Table 01 33 00A - List of Submittals

* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.

RSN Clause or Section Title

Submittals required

Due date or delivery time

Respon-sible code

No. of sets to be sent to:

CO COR

22 05 17-1 Sleeves and

Sleeve Seals for Plumbing Piping

Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

22 05 19-1 Meters and Gauges for Plumbing Piping

Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

22 05 23-1 General-Duty Valves for Plumbing Piping

Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

22 05 29-1 Hangers and Supports for Plumbing Piping and Equipment

Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

22 05 53-1 Identification for Plumbing Piping and Equipment

Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

22 07 19-1 Plumbing Piping Insulation

Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

22 11 16-1 Domestic Water Piping

Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

22 11 16-2 Domestic Water Piping

Test Reports In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

22 11 16-3 Domestic Water Piping

Operation and Maintenance Manuals

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

22 11 19-1 Domestic Water Piping Specialties

Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

22 11 23-1 Domestic Water Packaged Booster Pumps

Approval Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

22 11 23-2 Domestic Water Packaged Booster Pumps

Final Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

22 11 25-1 Domestic Water In-Line Recirculation Pump

Approval Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

22 11 25-2 Domestic Water In-Line Recirculation Pump

Final Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal

Revised - 01 33 00 - 21

Table 01 33 00A - List of Submittals

* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.

RSN Clause or Section Title

Submittals required

Due date or delivery time

Respon-sible code

No. of sets to be sent to:

CO COR

22 12 23-1 Facility Indoor

Potable-Water Storage Tanks

Approval Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

22 12 23-2 Facility Indoor Potable-Water Storage Tanks

Factory Test Report

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

22 12 23-3 Facility Indoor Potable-Water Storage Tanks

Operation and Maintenance Manual

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

22 13 10-1 Facility Gravity Drainage Piping System

Approval Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

22 13 10-2 Facility Gravity Drainage Piping System

Operation and Maintenance Manuals

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

22 13 63-1 Facility Gray Water Tanks

Approval Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

22 13 63-2 Facility Gray Water Tanks

Factory Test Report

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

22 33 00-1 Electric Domestic Water Heaters

Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

22 33 00-2 Electric Domestic Water Heaters

Final Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

22 45 00-1 Emergency Plumbing Fixtures

Approval Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

22 45 00-2 Emergency Plumbing Fixtures

Field Test Plan In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

22 45 00-3 Emergency Plumbing Fixtures

Final Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 05 00-1 Common Work Results for

HVAC

Approval Drawings

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 05 00-2 Common Work Results for

HVAC

Final Drawings In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 05 29-1 Hangers and Supports for HVAC Piping and Equipment

Approval Data In accordance with approved RSN 01 32 10-3 Submittal

Revised - 01 33 00 - 22

Table 01 33 00A - List of Submittals

* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.

RSN Clause or Section Title

Submittals required

Due date or delivery time

Respon-sible code

No. of sets to be sent to:

CO COR

23 05 53-1 Identification for

HVAC Piping and Equipment

Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 05 93-1 Testing, Adjusting, and Balancing for

HVAC

Qualification Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 05 93-2 Testing, Adjusting, and Balancing for

HVAC

Test Plan In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 05 93-3 Testing, Adjusting, and Balancing for

HVAC

Final Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 07 13-1 Duct Insulation Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 07 13-2 Duct Insulation Qualification Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 08 00-1 Commissioning of HVAC

Commissioning Authority Statement of Qualifications

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 08 00-2 Commissioning of HVAC

Commissioning Plan

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 08 00-3 Commissioning of HVAC

Test Procedures In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 08 00-4 Commissioning of HVAC

Draft Commissioning Report

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 08 00-5 Commissioning of HVAC

Deficiency Report and Test Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 08 00-6 Commissioning of HVAC

Final Commissioning Report

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 31 00-1 HVAC Ducts and Casings

Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 33 00-1 Air Duct Accessories

Approval Data In accordance with approved RSN 01 32 10-3 Submittal

Revised - 01 33 00 - 23

Table 01 33 00A - List of Submittals

* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.

RSN Clause or Section Title

Submittals required

Due date or delivery time

Respon-sible code

No. of sets to be sent to:

CO COR

23 34 00-1 HVAC Fans Approval

Drawings and Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 34 00-2 HVAC Fans Operation and Maintenance Manuals

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 37 00-1 Air Outlets and Inlets

Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 74 15-1 Packaged Outdoor Air- Conditioning Units

Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 74 15-2 Packaged Outdoor Air- Conditioning Units

Vibration Isolation Design

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 74 15-3 Packaged Outdoor Air- Conditioning Units

Final Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 74 33-1 Dedicated Outdoor-Air Units

Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 74 33-2 Dedicated Outdoor-Air Units

Vibration Isolation Design

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 74 33-3 Dedicated Outdoor-Air Units

Final Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 81 26-1 Split-System Air-Conditioners

Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 81 26-2 Split-System Air-Conditioners

Operation and Maintenance Manual

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 82 39-1 Unit Heaters Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

23 82 39-2 Unit Heaters Operation and Maintenance Manuals

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

25 00 01-1 Control and Monitoring

Approval Data In accordance with approved RSN 01 32 10-3 Submittal

Revised - 01 33 00 - 24

Table 01 33 00A - List of Submittals

* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.

RSN Clause or Section Title

Submittals required

Due date or delivery time

Respon-sible code

No. of sets to be sent to:

CO COR

25 00 01-2 Control and

Monitoring Factory Acceptance Test Procedures

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

25 00 01-3 Control and Monitoring

Factory Acceptance Test Notification

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

25 00 01-4 Control and Monitoring

Factory Acceptance Test Reports

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

25 00 01-5 Control and Monitoring

Final Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

25 12 10-1 Programmable Logic Controller

Approval Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

25 12 10-2 Programmable Logic Controller

System Description Documentation

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

25 12 10-3 Programmable Logic Controller

Final Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

25 15 11-1 HMI and Basic Control Functions

Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

25 15 11-2 HMI and Basic Control Functions

Factory Acceptance Test Procedures

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

25 15 11-3 HMI and Basic Control Functions

Factory Acceptance Test Notification

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

25 15 11-4 HMI and Basic Control Functions

Factory Acceptance Test Reports

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

25 15 11-5 HMI and Basic Control Functions

Field Quality Test Report

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

25 15 11-6 HMI and Basic Control Functions

Final Drawings and Data

In accordance with approved RSN 01 32 10-3 Submittal Register

COR 0 1 electronic

26 05 10-1 Conductors and Cables

Approval Data In accordance with approved RSN 01 32 10-3 Submittal Register

CO…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .