This is a Performance Based Payment Schedule for the Landsat 10 Spacecraft contract. The document defines 28 milestone payment events tied to specific completion criteria that the contractor must satisfy before invoicing NASA for reimbursement. Payment percentages, amounts, and timing for each milestone are designated as "To Be Priced" (TBP), indicating these terms will be negotiated and finalized during contract execution.
The payment milestones span the entire spacecraft development lifecycle, beginning with the Kick-off Meeting and Major Subcontracts Awarded, progressing through design reviews (SRR, PDR, CDR), subsystem and simulator deliveries (CTSS, OOpS, SoftSim, LVIS), critical testing phases (Comprehensive Performance Test, RF Compatibility Testing, System Operational Readiness Test), observatory environmental testing (Vibration, EMI/EMC, Thermal Vacuum, Acoustics), and culminating in pre-flight activities (Mission Readiness Test, Pre-Ship Review, Launch Site CPT), successful launch and on-orbit checkout, and final acceptance via On-Orbit Acceptance Review. A fixed Completion Incentive Payment of $1 million is included as Event 14. Each milestone includes detailed completion criteria requiring Contracting Officer Representative notification that specified technical, programmatic, and deliverable requirements have been met, with particular emphasis on design compliance, test performance, data deliverable acceptance, and resolution of critical action items before payment authorization.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment No. S
Landsat 10 Spacecraft
Major Payment Events, Performance Based Schedule, and Completion Criteria
June 30, 2026
National Aeronautics and Space Administration
Goddard Space Flight Center Greenbelt, Maryland
L10 Major Payments Events and Acceptance Criteria L10-SC-DESC-0058 Rev -
(This page intentionally left blank)
L10 Major Payments Events and Acceptance Criteria L10-SC-DESC-0058 Rev -
1. Performance Based Payment Schedule The contractor shall complete all activities required for each Milestone Payment Event prior to submitting the respective invoice. The payment schedules are defined in Table 1.1 and the completion criteria are defined in Table 1.2.
Table 1.1 – Landsat 10 Major Payment Events Payment
Event No.
Payment Event Payment Percent
Payment Amount
Months
ARO
1 Kick-off Meeting TBP $TBP TBP 2 Major Subcontracts Awarded TBP $TBP TBP
3 Spacecraft System Requirements Review (SRR) Completion
TBP $TBP TBP
4 Spacecraft Preliminary Design Review (PDR) Completion
TBP $TBP TBP
5 All Subcontracts Awarded TBP $TBP TBP
6 Spacecraft Critical Design Review (CDR) Completion
TBP $TBP TBP
7 CTSS Delivery to MOC (Qty2) and to EROS (Qty3) TBP $TBP TBP 8 OOpS Delivery to MOC (Qty 2) TBP $TBP TBP 9 SC SoftSim Delivery to MOC (Qty 3) TBP $TBP TBP 10 Launch Vehicle Interface Simulator (Qty 1) Delivery TBP $TBP TBP
11 SC Baseline Comprehensive Performance Test (CPT) Completion
TBP $TBP TBP
12 RF Suitcase Simulator Delivery to EROS (Qty1) TBP $TBP TBP 13 SC EIDP Delivery and Acceptance TBP $TBP TBP 14 SC Completion Incentive Payment 100% $1M TBP 15 Operational Development Tools Delivery TBP $TBP TBP 16 Instrument Integration Completion TBP $TBP TBP 17 RF Compat Testing Completion TBP $TBP TBP 18 SORTS Completion TBP $TBP TBP
19 Observatory Pre-Environmental Review (PER) Completion
TBP $TBP TBP
20 Observatory Vibration Test Completion TBP $TBP TBP 21 Observatory EMI/EMC Test Completion TBP $TBP TBP 22 Observatory TVac Test Completion TBP $TBP TBP 23 Acoustics Test Completion TBP $TBP TBP 24 MRT Completion TBP $TBP TBP 25 Observatory Pre-Ship Review (PSR) Completion TBP $TBP TBP 26 Launch Site CPT Completion TBP $TBP TBP 27 Successful Launch and Functional SC on Orbit TBP $TBP TBP
28 Final Acceptance – On-Orbit Acceptance Review (AOR) (Clasue H.16) (10%)
TBP $TBP TBP