Attachment_R_-_Technical_Specifications_-Chiller_-__067196-12_Bid-Permit_Specs_Combined.pdf

PDF 1 MB Posted

Attached to
Chiller Replacement, Glen Burnie, MVA
Solicitation number
BPM047469
Issued by
Anne Arundel County, Maryland

About this file

This is a technical specifications document for a chiller replacement project at the Glen Burnie Branch of the Maryland Department of Transportation (MDOT) Motor Vehicle Administration (MVA). The project consists of removing and replacing chillers and associated equipment located in Building A at Glen Burnie, Maryland, with Gannett Fleming serving as the Design Professional. The specifications outline detailed requirements across multiple divisions including General Requirements, HVAC, and Electrical work, with comprehensive sections covering administrative procedures, quality control, temporary facilities, product requirements, and execution standards.

The document primarily focuses on technical requirements rather than pricing or funding details. It specifies that the contract will be based on a Stipulated Price with a single prime contractor. The specifications require contractors to submit detailed schedules, maintain daily construction reports, coordinate with owner's security protocols, and establish proper temporary facilities. The project requires work to be performed while maintaining building occupancy, with contractors needing to minimize disruption to MVA operations and coordinate access with facility management.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIFICATIONS

Glen Burnie Branch Chiller Replacement

Maryland Department of Transportation (MDOT) Motor Vehicle Administration (MVA)

Bid / Permit Submission August 11, 2023

Submitted By:

MVA GB Chiller Replacement Table of Contents

067196-12 08/11/2023 TOC-1

MARYLAND DEPARTMENT OF TRANSPORTATION (MDOT)

MOTOR VEHICLE ADMINISTRATION (MVA)

GLEN BURNIE BRANCH

CHILLER REPLACEMENT

TABLE OF CONTENTS

DIVISION 01 GENERAL REQUIREMENTS

01 10 00 Summary 01 20 00 Price and Payment Procedures 01 21 00 Allowances 01 22 00 Unit Prices 01 23 00 Alternates 01 25 00 Substitution Procedures 01 30 00 Administrative Requirements 01 32 16 Construction Progress Schedule 01 35 53 Security Procedures 01 40 00 Quality Requirements 01 50 00 Temporary Facilities and Controls 01 51 00 Temporary Utilities 01 52 13 Field Offices and Sheds 01 55 00 Vehicular Access and Parking 01 60 00 Product Requirements 01 61 16 Volatile Organic Compound (VOC) Content Restrictions 01 70 00 Execution and Closeout Requirements 01 74 19 Construction Waste Management and Disposal 01 78 00 Closeout Submittals 01 91 13 General Commissioning Requirements 01 91 14 Commissioning Authority Responsibilities

DIVISION 23 HVAC

23 05 13 Common Motor Requirements or HVAC Equipment 23 05 19 Meters and Gauges for HVAC Piping 23 05 23 General Duty Valves for HVAC Piping 23 05 29 Hangers and Supports for HVAC Piping and Equipment 23 05 48 Vibration and Seismic Controls for HVAC 23 05 53 Identification for HVAC Piping and Equipment 23 05 93 Testing, Adjusting and Balancing for HVAC 23 07 19 HVAC Piping Insulation 23 09 13 Instrumentation and Control Devices for HVAC 23 21 13 Hydronic Piping 23 21 14 Hydronic Specialties 23 25 00 HVAC Water Treatment 23 64 26 Rotary Screw Water Chillers

DIVISION 26 ELECTRICAL

26 00 10 Electrical General Provisions 26 00 51 Common Work Results for Electrical 26 05 19 Conductors and Cables 26 05 26 Grounding and Bounding 26 05 29 Hangers and Supports for Electrical Systems

MVA GB Chiller Replacement Table of Contents

067196-12 08/11/2023 TOC-2

26 05 33 Raceways and Boxes 26 05 53 Electrical Identification 26 51 19 Led Interior Lighting

MVA GB Chiller Replacement 01 10 00 - 1 Summary 067196-12 08/11/2023

SECTION 01 10 00

SUMMARY

PART 1 GENERAL

1.01 PROJECT

A. Project Name: 067196.12 MVA GB Chiller Replacement

B. Owner's Name: Maryland Motor Vehicle Administration (MVA) .

C. Design Professional's Name: Gannett Fleming.

D. The Project consists of the removal and replacement of chillers and all associated equipment located in Building A at Glen Burnie, Maryland.

1.02 CONTRACT DESCRIPTION

A. Contract Type: A single prime contract based on a Stipulated Price.

1.03 DESCRIPTION OF ALTERATIONS WORK

A. Scope of alterations work is indicated on drawings.

1.04 OWNER OCCUPANCY

A. Owner intends to occupy the Project upon Substantial Completion.

B. Cooperate with Owner to minimize conflict and to facilitate Owner's operations.

C. Schedule the Work to accommodate Owner occupancy.

1.05 CONTRACTOR USE OF SITE AND PREMISES

A. Provide access to and from site as required by law and by Owner:

1. Emergency Building Exits During Construction: Keep all exits required by code open during construction period; provide temporary exit signs if exit routes are temporarily altered.

2. Do not obstruct roadways, sidewalks, or other public ways without permit.

1.06 WORK SEQUENCE

1.07 SPECIFICATION SECTIONS APPLICABLE TO EVERY CONTRACT

A. Unless otherwise noted, provisions of the sections listed below apply to every contract.

Specific items of work listed under individual contract descriptions constitute exceptions.

B. Section 01 20 00 - Price and Payment Procedures.

C. Section 01 21 00 - Allowances.

D. Section 01 22 00 - Unit Prices.

E. Section 01 23 00 - Alternates.

F. Section 01 25 00 - Substitution Procedures.

G. Section 01 30 00 - Administrative Requirements.

H. Section 01 31 14 - Facility Services Coordination.

I. Section 01 32 16 - Construction Progress Schedule.

J. Section 01 35 53 - Security Procedures.

K. Section 01 40 00 - Quality Requirements.

L. Section 01 42 16 - Definitions.

M. Section 01 42 19 - Reference Standards.

N. Section 01 50 00 - Temporary Facilities and Controls.

O. Section 01 51 00 - Temporary Utilities.

P. Section 01 52 13 - Field Offices and Sheds.

Q. Section 01 55 00 - Vehicular Access and Parking.

MVA GB Chiller Replacement 01 10 00 - 2 Summary

R. Section 01 58 13 - Temporary Project Signage.

S. Section 01 60 00 - Product Requirements.

T. Section 01 61 16 - Volatile Organic Compound (VOC) Content Restrictions.

U. Section 01 70 00 - Execution and Closeout Requirements.

V. Section 01 78 00 - Closeout Submittals.

END OF SECTION

MVA GB Chiller Replacement 01 20 00 - 1 Price and Payment Procedures

SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Procedures for preparation and submittal of applications for progress payments.

B. Change procedures.

C. Procedures for preparation and submittal of application for final payment.

1.02 SCHEDULE OF VALUES

A. Electronic media printout including equivalent information will be considered in lieu of standard form specified; submit draft to Design Professional for approval.

B. Forms filled out by hand will not be accepted.

C. Submit Schedule of Values in duplicate within 15 days after date of Owner-Contractor Agreement.

1.03 APPLICATIONS FOR PROGRESS PAYMENTS

A. Payment Period: Submit at intervals stipulated in the Agreement.

B. Electronic media printout including equivalent information will be considered in lieu of standard form specified; submit sample to Design Professional for approval.

C. Forms filled out by hand will not be accepted.

D. For each item, provide a column for listing each of the following:

1. Item Number.

2. Description of work.

3. Scheduled Values.

4. Previous Applications.

5. Work in Place and Stored Materials under this Application.

6. Authorized Change Orders.

7. Total Completed and Stored to Date of Application.

8. Percentage of Completion.

9. Balance to Finish.

10. Retainage.

E. Execute certification by signature of authorized officer.

F. List each authorized Change Order as a separate line item, listing Change Order number and dollar amount as for an original item of work.

G. Submit one electronic and three hard-copies of each Application for Payment.

H. Include the following with the application:

1. Transmittal letter as specified for submittals in Section 01 30 00.

2. Construction progress schedule, revised and current as specified in Section 01 30 00.

1.04 MODIFICATION PROCEDURES

A. For minor changes not involving an adjustment to the Contract Sum or Contract Time, Design Professional will issue instructions directly to Contractor.

B. For other required changes, Design Professional will issue a document signed by Owner instructing Contractor to proceed with the change, for subsequent inclusion in a Change Order.

1. The document will describe the required changes and will designate method of determining any change in Contract Sum or Contract Time.

2. Promptly execute the change.

C. For changes for which advance pricing is desired, Design Professional will issue a document that includes a detailed description of a proposed change with supplementary or revised drawings and specifications, a change in Contract Time for executing the change with a stipulation of any overtime work required and the period of time during which the requested

MVA GB Chiller Replacement 01 20 00 - 2 Price and Payment Procedures price will be considered valid . Contractor shall prepare and submit a fixed price quotation within 7 days.

D. Computation of Change in Contract Amount: As specified in the Agreement and Conditions of the Contract.

E. Execution of Change Orders: Design Professional will issue Change Orders for signatures of parties as provided in the Conditions of the Contract.

1.05 APPLICATION FOR FINAL PAYMENT

A. Prepare Application for Final Payment as specified for progress payments, identifying total adjusted Contract Sum, previous payments, and sum remaining due.

B. Application for Final Payment will not be considered until the following have been accomplished:

1. All closeout procedures specified in Section 01 70 00.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

MVA GB Chiller Replacement 01 21 00 - 1 Allowances

SECTION 01 21 00

ALLOWANCES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Inspecting and testing allowances.

B. Payment and modification procedures relating to allowances.

1.02 RELATED REQUIREMENTS

A. Section 01 20 00 - Price and Payment Procedures: Additional payment and modification procedures.

1.03 INSPECTING AND TESTING ALLOWANCES

A. Costs Not Included in the Inspecting and Testing Allowances:

1. Costs of incidental labor and facilities required to assist inspecting or testing agency.

2. Costs of testing services used by Contractor separate from Contract Document requirements.

3. Costs of retesting upon failure of previous tests as determined by Design Professional.

B. Payment Procedures:

1. Submit one copy of the inspecting or testing firm's invoice with next application for payment.

PART 2 PRODUCTS - NOT USED

MVA GB Chiller Replacement 01 22 00 - 1 Unit Prices

SECTION 01 22 00

UNIT PRICES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. List of unit prices, for use in preparing Bids.

B. Measurement and payment criteria applicable to Work performed under a unit price payment method.

1.02 RELATED REQUIREMENTS

A. Section 01 20 00 - Price and Payment Procedures: Additional payment and modification procedures.

1.03 COSTS INCLUDED

A. Unit Prices included on the Bid Form shall include full compensation for all required labor, products, tools, equipment, plant, transportation, services and incidentals; erection, application or installation of an item of the Work; overhead and profit.

1.04 UNIT QUANTITIES SPECIFIED

A. Quantities indicated in the Bid Form are for bidding and contract purposes only. Quantities and measurements of actual Work will determine the payment amount.

1.05 MEASUREMENT OF QUANTITIES

A. Measurement methods delineated in the individual specification sections complement the criteria of this section. In the event of conflict, the requirements of the individual specification section govern.

B. Take all measurements and compute quantities. Measurements and quantities will be verified by Design Professional.

C. Assist by providing necessary equipment, workers, and survey personnel as required.

D. Measurement by Weight: Concrete reinforcing steel, rolled or formed steel or other metal shapes will be measured by handbook weights. Welded assemblies will be measured by handbook or scale weight.

E. Measurement by Volume: Measured by cubic dimension using mean length, width and height or thickness.

F. Measurement by Area: Measured by square dimension using mean length and width or radius.

G. Linear Measurement: Measured by linear dimension, at the item centerline or mean chord.

H. Stipulated Price Measurement: Items measured by weight, volume, area, or linear means or combination, as appropriate, as a completed item or unit of the Work.

1.06 PAYMENT

A. Payment for Work governed by unit prices will be made on the basis of the actual measurements and quantities of Work that is incorporated in or made necessary by the Work and accepted by the Design Professional, multiplied by the unit price.

B. Payment will not be made for any of the following:

1. Products wasted or disposed of in a manner that is not acceptable.

2. Products determined as unacceptable before or after placement.

3. Products not completely unloaded from the transporting vehicle.

4. Products placed beyond the lines and levels of the required Work.

5. Products remaining on hand after completion of the Work.

6. Loading, hauling, and disposing of rejected Products.

1.07 DEFECT ASSESSMENT

A. Replace Work, or portions of the Work, not complying with specified requirements.

MVA GB Chiller Replacement 01 22 00 - 2 Unit Prices

B. If, in the opinion of Design Professional, it is not practical to remove and replace the Work, Design Professional will direct one of the following remedies:

1. The defective Work will be partially repaired to the instructions of the Design Professional, and the unit price will be adjusted to a new unit price at the discretion of Design Professional.

C. If, in the opinion of Owner, it is not practical to remove and replace the Work, Owner will direct one of the following remedies:

1. The defective Work will be partially repaired to the instructions of the Owner, and the unit price will be adjusted to a new unit price at the discretion of Owner.

D. The individual specification sections may modify these options or may identify a specific formula or percentage price reduction.

E. The authority of Owner to assess the defect and identify payment adjustment is final.

PART 2 PRODUCTS - NOT USED

MVA GB Chiller Replacement 01 23 00 - 1 Alternates

SECTION 01 23 00

ALTERNATES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Description of Alternates.

B. Procedures for pricing Alternates.

C. Documentation of changes to Contract Price and Contract Time.

1.02 ACCEPTANCE OF ALTERNATES

A. Alternates quoted on Bid Forms will be reviewed and accepted or rejected at Owner's option.

Accepted Alternates will be identified in the Owner-Contractor Agreement.

B. Coordinate related work and modify surrounding work to integrate the Work of each Alternate.

PART 2 PRODUCTS - NOT USED

MVA GB Chiller Replacement 01 25 00 - 1 Substitution Procedures

SECTION 01 25 00

SUBSTITUTION PROCEDURES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Procedural requirements for proposed substitutions.

1.02 RELATED REQUIREMENTS

A. Section 01 22 00 - Unit Prices, for additional unit price requirements.

B. Section 01 23 00 - Alternates, for product alternatives affecting this section.

C. Section 01 30 00 - Administrative Requirements: Submittal procedures, coordination.

D. Section 01 60 00 - Product Requirements: Fundamental product requirements, product options, delivery, storage, and handling.

1.03 DEFINITIONS

A. Substitutions: Changes from Contract Documents requirements proposed by Contractor to materials, products, assemblies, and equipment.

1. Substitutions for Cause: Proposed due to changed Project circumstances beyond

Contractor's control.

a. Unavailability.

b. Regulatory changes.

2. Substitutions for Convenience: Proposed due to possibility of offering substantial advantage to the Project.

1.04 REFERENCE STANDARDS

A. CSI/CSC Form 1.5C - Substitution Request (During the Bidding/Negotiating Stage).

B. CSI/CSC Form 13.1A - Substitution Request (After the Bidding/Negotiating Phase).

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 GENERAL REQUIREMENTS

A. A Substitution Request for products, assemblies, materials, and equipment constitutes a representation that the submitter:

1. Has investigated proposed product and determined that it meets or exceeds the quality level of the specified product, equipment, assembly, or system.

2. Agrees to provide the same warranty for the substitution as for the specified product.

3. Agrees to coordinate installation and make changes to other work that may be required for the work to be complete, with no additional cost to Owner.

4. Waives claims for additional costs or time extension that may subsequently become apparent.

B. Document each request with complete data substantiating compliance of proposed substitution with Contract Documents. Burden of proof is on proposer.

C. Content: Include information necessary for tracking the status of each Substitution Request, and information necessary to provide an actionable response.

1. No specific form is required. Contractor's Substitution Request documentation must include the following:

a. Project Information:

1) Official project name and number, and any additional required identifiers established in Contract Documents.

b. Substitution Request Information:

1) Discrete and consecutive Substitution Request number, and descriptive subject/title.

2) Issue date.

MVA GB Chiller Replacement 01 25 00 - 2 Substitution Procedures

3) Reference to particular Contract Document(s) specification section number, title, and article/paragraph(s).

4) Description of Substitution.

5) Reason why the specified item cannot be provided.

6) Differences between proposed substitution and specified item.

7) Description of how proposed substitution affects other parts of work.

c. Attached Comparative Data: Provide point-by-point, side-by-side comparison addressing essential attributes specified, as appropriate and relevant for the item:

1) Physical characteristics.

2) In-service performance.

3) Expected durability.

4) Warranties.

5) Other salient features and requirements.

6) Include, as appropriate or requested, the following types of documentation:

(a) Product Data:

(b) Samples.

(c) Certificates, test, reports or similar qualification data.

(d) Drawings, when required to show impact on adjacent construction elements.

d. Impact of Substitution:

1) Savings to Owner for accepting substitution.

2) Change to Contract Time due to accepting substitution.

D. Limit each request to a single proposed substitution item.

1. Submit an electronic document, combining the request form with supporting data into single document.

3.02 SUBSTITUTION PROCEDURES DURING PROCUREMENT

A. Submittal Time Restrictions:

1. Instructions to Bidders specifies time restrictions and the documents required for submitting substitution requests during the bidding period.

2. Owner will consider requests for substitutions only if submitted at least 10 days prior to the date for receipt of bids.

B. Submittal Form (before award of contract):

1. Submit substitution requests by completing CSI/CSC Form 1.5C - Substitution Request.

See this form for additional information and instructions. Use only this form; other forms of submission are unacceptable.

3.03 SUBSTITUTION PROCEDURES DURING CONSTRUCTION

A. Submittal Form (after award of contract):

1. Submit substitution requests by completing CSI/CSC Form 13.1A - Substitution Request

(After Bidding/Negotiating). See this form for additional information and instructions. Use only this form; other forms of submission are unacceptable.

B. Submit request for Substitution for Cause within 14 days of discovery of need for substitution, but not later than 14 days prior to time required for review and approval by Design Professional, in order to stay on approved project schedule.

C. Submit request for Substitution for Convenience within 14 days of discovery of its potential advantage to the project, but not later than 14 days prior to time required for review and approval by Design Professional, in order to stay on approved project schedule.

1. In addition to meeting general documentation requirements, document how the requested substitution benefits the Owner through cost savings, time savings, greater energy conservation, or in other specific ways.

2. Document means of coordinating of substitution item with other portions of the work, including work by affected subcontractors.

3. Bear the costs engendered by proposed substitution of:

MVA GB Chiller Replacement 01 25 00 - 3 Substitution Procedures

a. Owner's compensation to the Design Professional for any required redesign, time spent processing and evaluating the request.

D. Substitutions will not be considered under one or more of the following circumstances:

1. When they are indicated or implied on shop drawing or product data submittals, without having received prior approval.

2. Without a separate written request.

3.04 RESOLUTION

A. Design Professional may request additional information and documentation prior to rendering a decision. Provide this data in an expeditious manner.

B. Design Professional will notify Contractor in writing of decision to accept or reject request.

1. Design Professional's decision following review of proposed substitution will be noted on the submitted form.

3.05 ACCEPTANCE

A. Accepted substitutions change the work of the Project. They will be documented and incorporated into work of the project by Change Order, Construction Change Directive, Architectural Supplementary Instructions, or similar instruments provided for in the Conditions of the Contract.

3.06 CLOSEOUT ACTIVITIES

A. See Section 01 78 00 - Closeout Submittals, for closeout submittals.

B. Include completed Substitution Request Forms as part of the Project record. Include both approved and rejected Requests.

MVA GB Chiller Replacement 01 30 00 - 1 Administrative Requirements

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. General administrative requirements.

B. Electronic document submittal service.

C. Preconstruction meeting.

D. Site mobilization meeting.

E. Progress meetings.

F. Construction progress schedule.

G. Contractor's daily reports.

H. Progress photographs.

I. Coordination drawings.

J. Submittals for review, information, and project closeout.

K. Number of copies of submittals.

L. Requests for Interpretation (RFI) procedures.

M. Submittal procedures.

1.02 RELATED REQUIREMENTS

A. Section 01 60 00 - Product Requirements: General product requirements.

B. Section 01 70 00 - Execution and Closeout Requirements: Additional coordination requirements.

C. Section 01 78 00 - Closeout Submittals: Project record documents; operation and maintenance data; warranties and bonds.

D. Section 01 91 13 - General Commissioning Requirements: Additional procedures for submittals relating to commissioning.

1. Where submittals are indicated for review by both Design Professional and the

Commissioning Authority, submit one extra and route to Design Professional first, for forwarding to the Commissioning Authority.

2. Where submittals are not indicated to be reviewed by Design Professional, submit directly to the Commissioning Authority; otherwise, the procedures specified in this section apply to commissioning submittals.

1.03 REFERENCE STANDARDS

A. AIA G716 - Request for Information.

B. AIA G810 - Transmittal Letter.

1.04 GENERAL ADMINISTRATIVE REQUIREMENTS

A. Comply with requirements of Section 01 70 00 - Execution and Closeout Requirements for coordination of execution of administrative tasks with timing of construction activities.

B. Make the following types of submittals to Design Professional:

1. Requests for Interpretation (RFI).

2. Requests for substitution.

3. Shop drawings, product data, and samples.

4. Test and inspection reports.

5. Design data.

6. Manufacturer's instructions and field reports.

7. Applications for payment and change order requests.

8. Progress schedules.

MVA GB Chiller Replacement 01 30 00 - 2 Administrative Requirements

9. Coordination drawings.

10. Correction Punch List and Final Correction Punch List for Substantial Completion.

11. Closeout submittals.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 ELECTRONIC DOCUMENT SUBMITTAL SERVICE

A. All documents transmitted for purposes of administration of the contract are to be in electronic (PDF, MS Word, or MS Excel) format, as appropriate to the document, and transmitted via an Internet-based submittal service that receives, logs and stores documents, provides electronic stamping and signatures, and notifies addressees via email.

1. Besides submittals for review, information, and closeout, this procedure applies to

Requests for Interpretation (RFIs), progress documentation, contract modification documents (e.g. supplementary instructions, change proposals, change orders), applications for payment, field reports and meeting minutes, Contractor's correction punchlist, and any other document any participant wishes to make part of the project record.

2. Contractor and Design Professional are required to use this service.

3. It is Contractor's responsibility to submit documents in allowable format.

4. Subcontractors, suppliers, and Design Professional's consultants are to be permitted to use the service at no extra charge.

5. Users of the service need an email address, internet access, and PDF review software that includes ability to mark up and apply electronic stamps (such as Adobe Acrobat, www.adobe.com, or Bluebeam PDF Revu, www.bluebeam.com), unless such software capability is provided by the service provider.

6. Paper document transmittals will not be reviewed; emailed electronic documents will not be reviewed.

7. All other specified submittal and document transmission procedures apply, except that electronic document requirements do not apply to samples or color selection charts.

B. Submittal Service: The selected service is:

C. Training: One, one-hour, web-based training session will be arranged for all participants, with representatives of Design Professional and Contractor participating; further training is the responsibility of the user of the service.

D. Project Closeout: Design Professional will determine when to terminate the service for the project and is responsible for obtaining archive copies of files for Owner.

3.02 PRECONSTRUCTION MEETING

A. Design Professional will schedule a meeting after Notice of Award.

B. Attendance Required:

1. Owner.

2. Design Professional.

3. Contractor.

C. Agenda:

1. Execution of Owner-Contractor Agreement.

2. Submission of executed bonds and insurance certificates.

3. Distribution of Contract Documents.

4. Submission of list of subcontractors, list of products, schedule of values, and progress schedule.

5. Submission of initial Submittal schedule.

6. Designation of personnel representing the parties to Contract and Design Professional .

7. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.

8. Scheduling.

MVA GB Chiller Replacement 01 30 00 - 3 Administrative Requirements

D. Record minutes and distribute copies within two days after meeting to participants, with two copies to Design Professional, Owner, participants, and those affected by decisions made.

3.03 SITE MOBILIZATION MEETING

A. Owner will schedule meeting at the Project site prior to Contractor occupancy.

B. Attendance Required:

1. Contractor.

2. Owner.

3. Design Professional.

4. Contractor's superintendent.

5. Major subcontractors.

C. Agenda:

1. Use of premises by Owner and Contractor.

2. Owner's requirements.

3. Construction facilities and controls provided by Owner.

4. Temporary utilities provided by Owner.

5. Survey and building layout.

6. Security and housekeeping procedures.

7. Schedules.

8. Application for payment procedures.

9. Procedures for testing.

10. Procedures for maintaining record documents.

11. Requirements for start-up of equipment.

12. Inspection and acceptance of equipment put into service during construction period.

D. Record minutes and distribute copies within two days after meeting to participants, with two copies to Design Professional, Owner, participants, and those affected by decisions made.

3.04 PROGRESS MEETINGS

A. Design Professional will make arrangements for meetings, prepare agenda with copies for participants, preside at meetings.

B. Attendance Required:

1. Contractor.

2. Owner.

3. Design Professional.

4. Contractor's superintendent.

5. Major subcontractors.

C. Agenda:

1. Review minutes of previous meetings.

2. Review of work progress.

3. Field observations, problems, and decisions.

4. Identification of problems that impede, or will impede, planned progress.

5. Review of submittals schedule and status of submittals.

6. Maintenance of progress schedule.

7. Corrective measures to regain projected schedules.

8. Planned progress during succeeding work period.

9. Maintenance of quality and work standards.

10. Effect of proposed changes on progress schedule and coordination.

11. Other business relating to work.

D. Record minutes and distribute copies within two days after meeting to participants, with two copies to Design Professional, Owner, participants, and those affected by decisions made.

MVA GB Chiller Replacement 01 30 00 - 4 Administrative Requirements

3.05 CONSTRUCTION PROGRESS SCHEDULE - SEE SECTION 01 32 16

A. Within 10 days after date of the Agreement, submit preliminary schedule defining planned operations for the first 60 days of work, with a general outline for remainder of work.

B. If preliminary schedule requires revision after review, submit revised schedule within 10 days.

C. Within 20 days after review of preliminary schedule, submit draft of proposed complete schedule for review.

1. Include written certification that major contractors have reviewed and accepted proposed schedule.

D. Within 10 days after joint review, submit complete schedule.

E. Submit updated schedule with each Application for Payment.

3.06 DAILY CONSTRUCTION REPORTS

A. Include only factual information. Do not include personal remarks or opinions regarding operations and/or personnel.

B. In addition to transmitting electronically a copy to Owner and Design Professional, submit two printed copies at weekly intervals.

1. Submit in format acceptable to Owner.

C. Prepare a daily construction report recording the following information concerning events at Project site and project progress:

1. Date.

2. High and low temperatures, and general weather conditions.

3. List of subcontractors at Project site.

4. List of separate contractors at Project site.

5. Approximate count of personnel at Project site.

a. Include a breakdown for supervisors, laborers, journeymen, equipment operators, and helpers.

6. Major equipment at Project site.

7. Material deliveries.

8. Safety, environmental, or industrial relations incidents.

9. Meetings and significant decisions.

10. Unusual events (submit a separate special report).

11. Stoppages, delays, shortages, and losses. Include comparison between scheduled work activities (in Contractor's most recently updated and published schedule) and actual activities. Explain differences, if any. Note days or periods when no work was in progress and explain the reasons why.

12. Testing and/or inspections performed.

13. Signature of Contractor's authorized representative.

3.07 PROGRESS PHOTOGRAPHS

A. Submit new photographs at least once a month, within 3 days after being taken.

B. Maintain one set of all photographs at project site for reference; same copies as submitted, identified as such.

C. Photography Type: Digital; electronic files.

D. Provide photographs of site and construction throughout progress of work produced by an experienced photographer, acceptable to Design Professional.

E. In addition to periodic, recurring views, take photographs of each of the following events:

1. Final completion, minimum of ten (10) photos.

F. Views:

1. Provide non-aerial photographs from four cardinal views at each specified time, until date of Substantial Completion.

2. Consult with Design Professional for instructions on views required.

3. Provide factual presentation.

MVA GB Chiller Replacement 01 30 00 - 5 Administrative Requirements

4. Provide correct exposure and focus, high resolution and sharpness, maximum depth of field, and minimum distortion.

G. Digital Photographs: 24 bit color, minimum resolution of 1024 by 768, in JPG format; provide files unaltered by photo editing software.

1. Delivery Medium: Via email.

2. File Naming: Include project identification, date and time of view, and view identification.

3. PDF File: Assemble all photos into printable pages in PDF format, with 2 to 3 photos per page, each photo labeled with file name; one PDF file per submittal.

3.08 COORDINATION DRAWINGS

A. Review drawings prior to submission to Design Professional.

3.09 REQUESTS FOR INTERPRETATION (RFI)

A. Definition: A request seeking one of the following:

1. An interpretation, amplification, or clarification of some requirement of Contract

Documents arising from inability to determine from them the exact material, process, or system to be installed; or when the elements of construction are required to occupy the same space (interference); or when an item of work is described differently at more than one place in Contract Documents.

2. A resolution to an issue which has arisen due to field conditions and affects design intent.

B. Preparation: Prepare an RFI immediately upon discovery of a need for interpretation of Contract Documents. Failure to submit a RFI in a timely manner is not a legitimate cause for claiming additional costs or delays in execution of the work.

1. Prepare a separate RFI for each specific item.

a. Review, coordinate, and comment on requests originating with subcontractors and/or materials suppliers.

b. Do not forward requests which solely require internal coordination between subcontractors.

2. Prepare in a format and with content acceptable to Owner.

a. Use AIA G716 - Request for Information .

3. Prepare using software provided by the Electronic Document Submittal Service.

C. Reason for the RFI: Prior to initiation of an RFI, carefully study all Contract Documents to confirm that information sufficient for their interpretation is definitely not included.

1. Unacceptable Uses for RFIs: Do not use RFIs to request the following::

a. Approval of submittals (use procedures specified elsewhere in this section).

b. Approval of substitutions (see Section - 01 60 00 - Product Requirements)

c. Changes that entail change in Contract Time and Contract Sum (comply with provisions of the Conditions of the Contract).

d. Different methods of performing work than those indicated in the Contract Drawings and Specifications (comply with provisions of the Conditions of the Contract).

2. Improper RFIs: Requests not prepared in compliance with requirements of this section, and/or missing key information required to render an actionable response. They will be returned without a response, with an explanatory notation.

3. Frivolous RFIs: Requests regarding information that is clearly indicated on, or reasonably inferable from, Contract Documents, with no additional input required to clarify the question. They will be returned without a response, with an explanatory notation.

D. Content: Include identifiers necessary for tracking the status of each RFI, and information necessary to provide an actionable response.

1. Official Project name and number, and any additional required identifiers established in

Contract Documents.

2. Issue date, and requested reply date.

3. Reference to particular Contract Document(s) requiring additional information/interpretation. Identify pertinent drawing and detail number and/or specification section number, title, and paragraph(s).

MVA GB Chiller Replacement 01 30 00 - 6 Administrative Requirements

4. Annotations: Field dimensions and/or description of conditions which have engendered the request.

5. Contractor's suggested resolution: A written and/or a graphic solution, to scale, is required in cases where clarification of coordination issues is involved, for example;

routing, clearances, and/or specific locations of work shown diagrammatically in Contract Documents. If applicable, state the likely impact of the suggested resolution on Contract Time or the Contract Sum.

E. RFI Log: Prepare and maintain a tabular log of RFIs for the duration of the project.

1. Indicate current status of every RFI. Update log promptly and on a regular basis.

2. Note dates of when each request is made, and when a response is received.

3. Highlight items requiring priority or expedited response.

4. Highlight items for which a timely response has not been received to date.

F. Review Time: Design Professional will respond and return RFIs to Contractor within seven calendar days of receipt. For the purpose of establishing the start of the mandated response period, RFIs received after 12:00 noon will be considered as having been received on the following regular working day.

1. Response period may be shortened or lengthened for specific items, subject to mutual agreement, and recorded in a timely manner in progress meeting minutes.

G. Responses: Content of answered RFIs will not constitute in any manner a directive or authorization to perform extra work or delay the project. If in Contractor's belief it is likely to lead to a change to Contract Sum or Contract Time, promptly issue a notice to this effect, and follow up with an appropriate Change Order request to Owner.

1. Response may include a request for additional information, in which case the original RFI will be deemed as having been answered, and an amended one is to be issued forthwith.

Identify the amended RFI with an R suffix to the original number.

2. Do not extend applicability of a response to specific item to encompass other similar conditions, unless specifically so noted in the response.

3. Upon receipt of a response, promptly review and distribute it to all affected parties, and update the RFI Log.

4. Notify Design Professional within seven calendar days if an additional or corrected response is required by submitting an amended version of the original RFI, identified as specified above.

3.10 SUBMITTAL SCHEDULE

A. Submit to Design Professional for review a schedule for submittals in tabular format.

1. Submit at the same time as the preliminary schedule specified in Section - 01 32 16 -

Construction Progress Schedule.

2. Coordinate with Contractor's construction schedule and schedule of values.

3. Format schedule to allow tracking of status of submittals throughout duration of construction.

4. Arrange information to include scheduled date for initial submittal, specification number and title, submittal category (for review or for information), description of item of work covered, and role and name of subcontractor.

5. Account for time required for preparation, review, manufacturing, fabrication and delivery when establishing submittal delivery and review deadline dates.

a. For assemblies, equipment, systems comprised of multiple components and/or requiring detailed coordination with other work, allow for additional time to make corrections or revisions to initial submittals, and time for their review.

3.11 SUBMITTALS FOR REVIEW

A. When the following are specified in individual sections, submit them for review:

1. Product data.

2. Shop drawings.

3. Samples for selection.

4. Samples for verification.

MVA GB Chiller Replacement 01 30 00 - 7 Administrative Requirements

B. Submit to Design Professional for review for the limited purpose of checking for compliance with information given and the design concept expressed in Contract Documents.

C. Samples will be reviewed for aesthetic, color, or finish selection.

D. After review, provide copies and distribute in accordance with SUBMITTAL PROCEDURES article below and for record documents purposes described in Section 01 78 00 - Closeout Submittals.

3.12 SUBMITTALS FOR INFORMATION

A. When the following are specified in individual sections, submit them for information:

1. Design data.

2. Certificates.

3. Test reports.

4. Inspection reports.

5. Manufacturer's instructions.

6. Manufacturer's field reports.

7. Other types indicated.

B. Submit for Design Professional's knowledge as contract administrator or for Owner.

3.13 SUBMITTALS FOR PROJECT CLOSEOUT

A. Submit Correction Punch List for Substantial Completion.

B. Submit Final Correction Punch List for Substantial Completion.

C. When the following are specified in individual sections, submit them at project closeout in compliance with requirements of Section 01 78 00 - Closeout Submittals:

1. Project record documents.

2. Operation and maintenance data.

3. Warranties.

4. Bonds.

5. Other types as indicated.

D. Submit for Owner's benefit during and after project completion.

3.14 NUMBER OF COPIES OF SUBMITTALS

A. Electronic Documents: Submit one electronic copy in PDF format; an electronically-marked up file will be returned. Create PDFs at native size and right-side up; illegible files will be rejected.

B. Samples: Submit the number specified in individual specification sections; one of which will be retained by Design Professional.

1. After review, produce duplicates.

2. Retained samples will not be returned to Contractor unless specifically so stated.

3.15 SUBMITTAL PROCEDURES

A. General Requirements:

1. Submit separate packages of submittals for review and submittals for information, when included in the same specification section.

2. Schedule submittals to expedite the Project, and coordinate submission of related items.

a. For sequential reviews involving Design Professional's consultants, Owner, or another affected party, allow an additional 7 days.

b. For sequential reviews involving approval from authorities having jurisdiction (AHJ), in addition to Design Professional's approval, allow an additional 30 days.

3. Identify variations from Contract Documents and product or system limitations that may be detrimental to successful performance of the completed work.

4. Provide space for Contractor and Design Professional review stamps.

5. When revised for resubmission, identify all changes made since previous submission.

B. Product Data Procedures:

1. Submit only information required by individual specification sections.

MVA GB Chiller Replacement 01 30 00 - 8 Administrative Requirements

2. Collect required information into a single submittal.

3. Do not submit (Material) Safety Data Sheets for materials or products.

C. Shop Drawing Procedures:

1. Prepare accurate, drawn-to-scale, original shop drawing documentation by interpreting

Contract Documents and coordinating related work.

2. Do not reproduce Contract Documents to create shop drawings.

3. Generic, non-project-specific information submitted as shop drawings do not meet the requirements for shop drawings.

D. Samples Procedures:

1. Transmit related items together as single package.

2. Identify each item to allow review for applicability in relation to shop drawings showing installation locations.

3.16 SUBMITTAL REVIEW

A. Submittals for Review: Design Professional will review each submittal, and approve, or take other appropriate action.

B. Submittals for Information: Design Professional will acknowledge receipt and review. See below for actions to be taken.

C. Design Professional's actions will be reflected by marking each returned submittal using virtual stamp on electronic submittals.

D. Design Professional's and consultants' actions on items submitted for review:

1. Authorizing purchasing, fabrication, delivery, and installation:

a. "Approved", or language with same legal meaning.

b. "Approved as Noted, Resubmission not required", or language with same legal meaning.

1) At Contractor's option, submit corrected item, with review notations acknowledged and incorporated.

c. "Approved as Noted, Resubmit for Record", or language with same legal meaning.

2. Not Authorizing fabrication, delivery, and installation:

E. Design Professional's and consultants' actions on items submitted for information:

1. Items for which no action was taken:

a. "Received" - to notify the Contractor that the submittal has been received for record only.

2. Items for which action was taken:

a. "Reviewed" - no further action is required from Contractor.

MVA GB Chiller Replacement 01 32 16 - 1 Construction Progress Schedule

SECTION 01 32 16

CONSTRUCTION PROGRESS SCHEDULE

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Preliminary schedule.

B. Construction progress schedule, bar chart type.

1.02 RELATED SECTIONS

A. Section 01 10 00 - Summary: Work sequence.

1.03 SUBMITTALS

A. Within 10 days after date of Agreement, submit preliminary schedule.

B. If preliminary schedule requires revision after review, submit revised schedule within 10 days.

C. Within 20 days after review of preliminary schedule, submit draft of proposed complete schedule for review.

1. Include written certification that major contractors have reviewed and accepted proposed schedule.

D. Within 10 days after joint review, submit complete schedule.

E. Submit updated schedule with each Application for Payment.

F. Submit in PDF format.

1.04 SCHEDULE FORMAT

A. Listings: In chronological order according to the start date for each activity. Identify each activity with the applicable specification section number.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 PRELIMINARY SCHEDULE

A. Prepare preliminary schedule in the form of a horizontal bar chart.

3.02 CONTENT

A. Show complete sequence of construction by activity, with dates for beginning and completion of each element of construction.

B. Identify each item by specification section number.

C. Identify work of separate stages and other logically grouped activities.

D. Provide sub-schedules for each stage of Work identified in Section 01 10 00 - Summary.

E. Provide sub-schedules to define critical portions of the entire schedule.

F. Show accumulated percentage of completion of each item, and total percentage of Work completed, as of the first day of each month.

G. Coordinate content with schedule of values specified in Section 01 20 00 - Price and Payment Procedures.

H. Provide legend for symbols and abbreviations used.

3.03 BAR CHARTS

A. Include a separate bar for each major portion of Work or operation.

B. Identify the first work day of each week.

3.04 REVIEW AND EVALUATION OF SCHEDULE

A. Participate in joint review and evaluation of schedule with Design Professional at each submittal.

B. Evaluate project status to determine work behind schedule and work ahead of schedule.

MVA GB Chiller Replacement 01 32 16 - 2 Construction Progress Schedule

C. After review, revise as necessary as result of review, and resubmit within 10 days.

3.05 UPDATING SCHEDULE

A. Maintain schedules to record actual start and finish dates of completed activities.

B. Indicate progress of each activity to date of revision, with projected completion date of each activity.

C. Annotate diagrams to graphically depict current status of Work.

D. Identify activities modified since previous submittal, major changes in Work, and other identifiable changes.

E. Indicate changes required to maintain Date of Substantial Completion.

F. Submit reports required to support recommended changes.

3.06 DISTRIBUTION OF SCHEDULE

A. Distribute copies of updated schedules to Contractor's project site file, to subcontractors, suppliers, Design Professional, Owner, and other concerned parties.

B. Instruct recipients to promptly report, in writing, problems anticipated by projections indicated in schedules.

MVA GB Chiller Replacement 01 35 53 - 1 Security Procedures

SECTION 01 35 53

SECURITY PROCEDURES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Security measures including entry control, personnel identification, and miscellaneous restrictions .

1.02 RELATED REQUIREMENTS

A. Section 01 10 00 - Summary: use of premises and occupancy.

1.03 SECURITY PROGRAM

A. Protect Work , existing premises and Owner's operations from theft, vandalism, and unauthorized entry.

B. Initiate program in coordination with Owner's existing security system at project mobilization.

C. Maintain program throughout construction period until Owner occupancy.

1.04 ENTRY CONTROL

A. Restrict entrance of persons and vehicles into Project site and existing facilities.

B. Allow entrance only to authorized persons with proper identification.

1.05 PERSONNEL IDENTIFICATION

A. Provide identification badge to each person authorized to enter premises.

B. Badge To Include: Personal photograph, name, assigned number , expiration date and employer.

C. Require return of badges at expiration of their employment on the Work.

1.06 RESTRICTIONS

PART 2 PRODUCTS - NOT USED

MVA GB Chiller Replacement 01 40 00 - 1 Quality Requirements

SECTION 01 40 00

QUALITY REQUIREMENTS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Submittals.

B. Quality assurance.

C. References and standards.

D. Testing and inspection agencies and services.

E. Control of installation.

F. Tolerances.

G. Defect Assessment.

1.02 RELATED REQUIREMENTS

A. Section 01 21 00 - Allowances: Allowance for payment of testing services.

B. Section 01 30 00 - Administrative Requirements: Submittal procedures.

C. Section 01 42 16 - Definitions.

D. Section 01 42 19 - Reference Standards.

E. Section 01 60 00 - Product Requirements: Requirements for material and product quality.

1.03 REFERENCE STANDARDS

A. IAS AC89 - Accreditation Criteria for Testing Laboratories.

1.04 DEFINITIONS

A. Contractor's Quality Control Plan: Contractor's management plan for executing the Contract for Construction.

1.05 SUBMITTALS

A. See Section 01 30 00 - Administrative Requirements, for submittal procedures.

B. Test Reports: After each test/inspection, promptly submit two copies of report to Design Professional and to Contractor.

1. Include:

a. Date issued.

b. Project title and number.

c. Name of inspector.

d. Date and time of sampling or inspection.

e. Identification of product and specifications section.

f. Location in the Project.

g. Type of test/inspection.

h. Date of test/inspection.

i. Results of test/inspection.

j. Compliance with Contract Documents.

k. When requested by Design Professional, provide interpretation of results.

2. Test report submittals are for Design Professional's knowledge as contract administrator for the limited purpose of assessing compliance with information given and the design concept expressed in the Contract Documents, or for Owner's information.

C. Manufacturer's Instructions: When specified in individual specification sections, submit printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing, for the Owner's information. Indicate special procedures, perimeter conditions requiring special attention, and special environmental criteria required for application or installation.

1.06 QUALITY ASSURANCE

A. Testing Agency Qualifications:

MVA GB Chiller Replacement 01 40 00 - 2 Quality Requirements

1. Prior to start of work, submit agency name, address, and telephone number, and names of full time registered Engineer and responsible officer.

2. Submit copy of report of laboratory facilities inspection made by NIST Construction Materials Reference Laboratory during most recent inspection, with memorandum of remedies of any deficiencies reported by the inspection.

3. Qualification Statement: Provide documentation showing testing laboratory is accredited under IAS AC89.

B. Contractor's Quality Control (CQC) Plan:

1. Prior to start of work, submit a comprehensive plan describing how contract deliverables will be produced. Tailor CQC plan to specific requirements of the project. Include the following information:

a. Management Structure: Identify personnel responsible for quality. Include a chart showing lines of authority.

1) Include qualifications (in resume form), duties, responsibilities of each person assigned to CQC function.