Attachment R- Robins BFS 2024.pdf

PDF 5 MB Posted

Attached to
Robins AFB Paving Multi-Award IDIQ
Solicitation number
FA850126R0004
Issued by

About this file

This is the Robins Air Force Base 2024 Base Facility Standards document, which serves as a comprehensive design and construction guideline for all new construction and renovation projects conducted at Robins AFB by mission partners. The document establishes mandatory standards across multiple engineering disciplines and requires compliance with federal, state, and local regulations, including coordination with the 78th Civil Engineering Group. Key requirements include: adherence to the GeoBase Program for utility and planimetric data with submissions in electronic format; implementation of detailed Industrial Safety and Health Plans reviewed by the 78 ABW Safety Office; Pre-Engineered Metal Building (PEMB) specifications requiring IAS AC472 accreditation, tapered columns for non-finished spaces, 3-inch minimum height roof panels with 360-degree seams, and 20-year no-dollar-limit warranties on weather-tightness and finishes; mandatory Green Procurement Plan compliance for environmentally preferable products; and comprehensive environmental compliance including historical resource preservation, natural resource conservation, and stormwater management per EISA Section 438 standards.

Structural and civil engineering requirements mandate compliance with latest UFC standards, Risk Category III design analysis, Class F fly ash only for concrete, minimum 1.50 safety factors for foundations, and engagement of registered professional engineers for geotechnical work. Contractors must obtain Dig Permits 21 days prior to land disturbance, conduct hand-digging within three feet of utilities, and assume responsibility for damage to identified underground structures. Wastewater systems require duplex pump configurations with Grundfos or Flygt pumps, SCADA integration, nine-gauge chain link fencing with barbed wire outriggers around lift stations, and Operation and Maintenance Manuals. Mechanical systems must include HVAC commissioning, backflow prevention devices compliant with ASSE 1015, whole-facility metering for electrical, natural gas, water, steam, and chilled water connections, and compressed air systems with specific dryer and receiver tank requirements. Electrical standards specify medium to low voltage duct banks, lightning protection systems, fire alarm and mass notification systems, intrusion detection systems, and corrosion control services. Additional standards cover landscaping, lawn sprinkler irrigation systems with Hunter and Irritrol equipment specifications, contractor trailer policies limiting trailers to 10 by 50 feet with required signage, and termite pre-treatment for all exposed soil locations around slabs and footings.

View the file

Other files

File Type Posted
RobinsAFB_PavingIDIQ_FA850126R0004_UpdatedPage1.pdf PDF
WD_GA20260322.txt TXT text file
Attachment I - Blank Sample Form 911 xx Design Discipline Review.docx DOCX document
A - PROCEDURAL GUIDE FOR DESIGNERS INCLUDING AE FIRMS 2023.pdf PDF
Attachment T- UHHZ250030 SSR Document.pdf PDF
DEMO Project UHHZ260007 SOW.pdf PDF
Attachment U- UHHZ250030 _ DOT SSR Document_.pdf PDF
Attachment O- Bid Schedule.docx DOCX document
Attachment K - Master Utility Outage.pdf PDF
Attachment F BLANK SAMPLE AF Form 3064.xlsx XLSX spreadsheet
Attachment E - Blank Sample AF Form 3052.xls XLS spreadsheet
Attachment D AF Form 3000.pdf PDF
Attachment B AFMAN 31-116 Motor Vehicle Traffic Supervision (1).pdf PDF
DEMO PROJECT UHHZ260007 SUBMITTAL REGISTER.xls XLS spreadsheet
DEMO PROJECT UHHZ260007 Bid Schedule.pdf PDF
Attachment P- BLANK SAMPLE Schedule of Values Template_UNLOCKED.pdf PDF
Attachment M - App C UHHZ 250030.pdf PDF
Attachment L - Robins AFB Asbestos Management Plan - January 2015.pdf PDF
Attachment H - BLANK SAMPLE DD Form 1354 Transfer and Acceptance of DoD Real Property.pdf PDF
Attachment G - BLANK SAMPLE AF Form 3065.xlsx XLSX spreadsheet
Attachment C AFMAN 32-1084 Civil Engineering Facility Requirements.pdf PDF
Basewide Paving IDIQ SOW.pdf PDF
RobinsAFB_PavingIDIQ_FA850126R0004.pdf PDF
Attachment J - Blank Sample SUBMITTAL REGISTER.xls XLS spreadsheet
Attachment A - af2586_new.pdf PDF
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RAFB BFS 2024

ROBINS AIR FORCE BASE

APPROVED FOR PUBLIC RELEASE; DISTRIBUTION UNLIMITED

2024 BASE FACILITY STANDARDS

Any copyrighted material included in this document is identified at its point of use.

Use of the copyrighted material apart from this document must have the permission of the copyright holder.

BASE FACILITY STANDARD

AIR FORCE MATERIAL COMMAND/ 78 AIR BASE WING/ 78 CIVIL ENGINEERING

GROUP

This update of the Base Facility Standards is a major update of the document. As such it should be reviewed in its entirety as some sections, figures, and tables have been completely renumbered.

Record of Changes (changes are indicated by \1\ ... /1/)

Change No. Date Location

This Base Facility Standard supersedes all previous versions.

FOREWORD

The Robins AFB Base Facility Standards (BFS) is both a resource and a guidebook to facilitate the design and construction of successful, high-performance buildings and infrastructure projects. The guidance provided in this document applies to all new construction and renovations carried out by all Mission Partners at Robins AFB.

The 2024 Edition of the Base Facility Standards is a significant update and includes major changes for clarity and technical content. Note that the Criteria Reference Documents are combined into Appendix A at the end of the document, and Forms are consolidated into Appendix B. Thanks go to the many subject matter experts that provided their time and expertise to make this happen.

Please contact the Chief, Project Execution Section with all recommendations for updates, corrections, or changes.

AUTHORIZED BY:

R. ERIC YATES, NH-04, DAF MARSHALL S. WALL, JR., P.E.

Director Chief, Engineering Division

78th Civil Engineer Group 78th Civil Engineer Group

Terry “Ross” Stinson Chief, Project Execution Support Section

78th CEG/CENME

Derek A. Grimsley, P.E.

Chief, Project Management Element

78th CEG/CENMP

TABLE OF CONTENTS RAFB BFS 2024

i

TABLE OF CONTENTS

CHAPTER 1 SPECIAL STANDARDS

SECTION 1A GEOBASE PROGRAM

1A-1 GENERAL REQUIREMENTS

SECTION 1B SAFETY PROVISIONS

1B-1 SAFETY PLAN REQUIREMENTS

1B-2 SITE PROTECTION

1B-3 OPERATIONS SAFETY

1B-4 OVERHEAD DOOR OPERATIONS

1B-5 GUIDANCE FOR CLEAN WORK AREAS

SECTION 1C PRE-ENGINEERED METAL BUILDINGS (PEMB)

1C-1 SYSTEM COMPONENTS AND DESIGN REQUIREMENTS

1C-2 WARRANTIES

SECTION 1D GREEN PROCUREMENT PLAN

1D-1 GENERAL

SECTION 1E FLIGHTLINE PHOTOGRAPHY

1E-1 GENERAL GUIDANCE

1E-2 PROHIBITED PHOTOGRAPHY

1E-3 PHOTOGRAPHIC DEVICES

SECTION 1F CONTRACTOR TRAILER POLICY

1F-1 GENERAL GUIDANCE

CHAPTER 2 ENVIRONMENTAL REQUIREMENTS

SECTION 2A GENERAL GUIDANCE

2A-1 REGULATORY COMPLIANCE MANDATE

SECTION 2B PRESERVING HISTORICAL AND ARCHAELOGICAL RESOURCES 14

2B-1 PROGRAMMATIC AGREEMENT

2B-2 COORDINATION

2B-3 DISCOVERIES

2B-4 ARCHAELOGICAL FINDS

SECTION 2C CONSERVATION OF NATURAL RESOURCES

2C-1 GENERAL

2C-2 GREEN INFRASTRUCTURE PLAN (GIP)

SECTION 2D PROTECTION OF WATER AND LAND RESOURCES

ii

2D-1 GENERAL

CHAPTER 3 STRUCTURAL AND CIVIL ENGINEERING ELEMENTS

SECTION 3A STRUCTURAL REQUIREMENTS

3A-1 GENERAL STRUCTURAL REQUIREMENTS

3A-2 SPECIAL STRUCTURAL REQUIREMENTS

3A-3 FOUNDATIONS

SECTION 3B CIVIL ENGINEERING AND SITE PLANNING

3B-1 PLAN REQUIREMENTS

3B-2 SITE VISIT

3B-3 SITE INVESTIGATIONS

SECTION 3C WASTE WATER TREATMENT

3C-1 GENERAL INFORMATION

3C-2 WASTEWATER TREAMENT SYSTEM

3C-3 WASTEWATER SYSTEM CONSTRUCTION

SECTION 3D SUBSURFACE INVESTIGATIONS

3D-1 GENERAL REQUIREMENTS

3D-2 DIGGING AND EXCAVATION REQUIREMENTS

SECTION 3E TERMITE PRE-TREATMENT

3E-1 GENERAL REQUIREMENTS

3E-2 SAFETY REQUIRMENTS FOR USE AND HANDLING

SECTION 3F LAWN SPRINKLER SYSTEMS

3F-1 GENERAL REQUIREMENTS

3F-2 DESIGN REQUIREMENTS

3F-3 INSTALLATION

3F-4 POST CONSTRUCTION REQUIREMENTS

SECTION 3G CIVIL STORMWATER

3G-1 STORMWATER MANAGEMENT FOR FEDERAL FACILITIES -

SECTION 438 OF THE ENERGY INDEPENDENCE AND SECURITY

ACT (EISA)

3G-2 STORMWATER MANAGEMENT DURING CONSTRUCTION

3G-3 POST CONSTRUCTION STORMWATER MANAGEMENT

CHAPTER 4 ARCHITECTURAL ELEMENTS

SECTION 4A SPECIFICATION, REGULATIONS, & STANDARDS

4A-1 INSTALLATION DEVELOPMENT PLAN

iii

4A-2 HIERARCHY OF REQUIREMENTS

4A-3 SUSTAINABILITY

4A-4 ACCESSIBILITY

4A-5 ANTITERRORISM/FORCE PROTECTION (AT/FP)

SECTION 4B EXTERIOR FACILITY STANDARDS

4B-1 ARCHITECTURAL CHARACTER

4B-2 EXTERIOR COLOR PLAN

4B-3 OUTSIDE WALLS AND FINISHES

4B-4 METAL

4B-5 WOOD FRAMING, SHEATHING AND DECKING

4B-6 ROOFING

4B-7 DOORS AND WINDOW

SECTION 4C VEHICULAR CIRCULATION & PARKING

4C-1 PARKING DESIGN GUIDELINES

4C-2 PEDESTRIAN CIRCULATION

SECTION 4D LANDSCAPING

4D-1 GENERAL GUIDANCE

SECTION 4E SITE ELEMENTS

4E-1 WALLS AND FENCES

4E-2 DUMPSTERS

4E-3 SITE FURNISHINGS

4E-4 OUTDOOR LIGHTING

4E-5 OUTDOOR SIGNAGE

SECTION 4F INTERIOR FACILITY GUIDELINES

4F-1 INTERIOR FINISHES AND COLORS

4F-2 INTERIOR WALL INSULATION

4F-3 CEILING TILES

4F-4 RESTROOMS

4F-5 BREAKROOMS

4F-6 CARPETS AND VINYL COVEBASE COLORS

4F-7 LUXURY VINYL TILE FLOORING (COMMERCIAL GLUE DOWN

ONLY)

4F-8 INTERIOR PAINT COLOR OPTIONS

CHAPTER 5 MECHANICAL ENGINEERING ELEMENTS

iv

SECTION 5A MECHANICAL STANDARDS

5A-1 GENERAL REQUIREMENTS

5A-2 SYSTEM REQUIREMENTS

5A-3 MAINTENANCE REQUIREMENTS

SECTION 5B HEATING, VENTILATION, AND AIR CONDITIONING STANDARDS 77

5B-1 DESIGN REQUIREMENTS

5B-2 HVAC WATER TREATMENT

5B-3 SYSTEM COMMISSIONING OF HVAC

5B-4 SYSTEM MAINTAINABILITY

SECTION 5C WATER DISTRIBUTION SYSTEMS

5C-1 SYSTEM WATER SUPPLY

5C-2 BUILDING WATER SUPPLY

5C-3 BACKFLOW PREVENTION DEVICES (BPDS)

SECTION 5D COMPRESSED AIR

5D-1 GENERAL REQUIREMENTS

5D-2 ENERGY CONSERVATION

5D-3 AIR COMPRESSORS

5D-4 AIR DRYERS

5D-5 RECEIVER TANKS

5D-6 PIPING SYSTEMS

5D-7 AIR DROPS AND CONNECTORS

5D-8 AUTOMATIC DRAIN VALVES

SECTION 5E FIRE SUPPRESSION

5E-1 GENERAL GUIDANCE

5E-2 SUPPRESSION SYSTEM DESIGN

SECTION 5F WHOLE FACILITY METERING

5F-1 GENERAL REQUIREMENTS

5F-2 INTERFACE WITH VIRTUAL CE LAN

5F-3 ELECTRICAL CONNECTION

5F-4 NATURAL GAS CONNECTION

5F-5 WATER CONNECTION

5F-6 STEAM CONNECTION

5F-7 CHILLED WATER CONNECTION

v

5F-8 RENOVATION AND DEMOLITION

CHAPTER 6 ELECTRICAL ENGINEERING ELEMENTS

SECTION 6A ELECTRICAL GUIDELINES

6A-1 GOVERNANCE

6A-2 EQUIPMENT PADS

6A-3 UTILITY BOLLARDS

6A-4 UNDERGROUND UTILITY PLACEMENT

6A-5 ELECTRICAL CLOSETS

6A-6 STANDARD PLAN AND OPERATIONS REQUIREMENTS

SECTION 6B MEDIUM TO LOW VOLTAGE

6B-1 GENERAL GUIDANCE

6B-2 DUCT BANK

6B-3 MANHOLES

6B-4 HANDHOLES

6B-5 CABLE

6B-6 AIR SWITCHES

6B-7 TRANSFORMERS

6B-8 WALK-IN ENCLOSURES

SECTION 6C LOW VOLTAGE

6C-1 METERING

6C-2 SURGE PROTECTION DEVICES (SPDs)

6C-3 STEP-DOWN (DRY-TYPE) TRANSFORMERS

6C-4 SWITCHBOARDS

6C-5 MOTOR CONTROL CENTERS (MCC)

6C-6 DISTRIBUTION PANELBOARDS 600 AND 800 Amps

6C-7 PANELBOARDS 200 TO 400 Amps

6C-8 FIRE ALARM and MASS NOTIFICATION SYSTEM (MNS)

6C-9 FIRE ALARM CONTROL SYSTEM

6C-10 COMBINED FIRE ALARM AND MASS NOTIFICATION SYSTEM ... 134

SECTION 6D GROUNDING

6D-1 GENERAL GUIDANCE

SECTION 6E LIGHTNING PROTECTION SYSTEMS (LPS)

6E-1 LPS REQUIREMENTS

vi

6E-2 SPECIFIC APPLICATIONS

6E-3 SIMPLE RISK ANALYSIS

SECTION 6F COMMUNICATIONS

6F-1 GENERAL

6F-2 COMMUNICATIONS (COMM) ROOMS / SPACES

6F-3 ELECTRICAL POWER REQUIREMENTS FOR COMMUNICATIONS

ROOMS

6F-4 COMMUNICATIONS FOR MINOR PROJECTS

6F-5 FAMILY HOUSING

SECTION 6G INTRUSION DETECTION SYSTEMS

6G-1 DESIGN AND ACQUISTION

6G-2 SYSTEM REQUIRMENTS

SECTION 6H AUXILIARY POWER

6H-1 GENERATOR PLACEMENT AND SIZE

6H-2 ENVIRONMENTAL REQUIREMENTS

6H-3 COMPONENTS

6H-4 ABOVE GROUND FUEL TANKS

SECTION 6I CORROSION CONTROL

6I-1 SERVICES OF CORROSION ENGINEER

6I-2 PROTECTIVE COATINGS

6I-3 CATHODIC PROTECTION SYSTEMS

6I-4 SYSTEMS REQUIRING PROTECTION

SECTION 6J LIGHTING

6J-1 GENERAL

6J-2 DESIGN REQUIREMENTS

6J-3 MOUNTING LUMINAIRES

6J-4 RENOVATION AND DEMOLITION

SECTION 6K AIRFIELD NAVAIDS

6K-1 ROBINS AFB INVENTORY

6K-2 POWER SERVICE

SECTION 6L TRAFFIC SIGNAL CONTROL SYSTEMS

6L-1 TRAFFIC SIGNAL COMPONENTS

6L-2 SEQUENCE OF OPERATIONS

vii

APPENDIX A criteria reference DOCUMENTS

APPENDIX B forms

B-1 ROBINS AFB BASE FACILITY STANDARD FORMS

B-1.1 WAIVER REQUEST

B-2 ENVIRONMENTAL FORMS

B-2.1 SPECIAL WASTE ACCEPTANCE APPLICATION (SWAA)

B-2.2 WASTE MANAGEMENT REPORT (MONTHLY)

B-2.3 WASTE SHIPMENT TRACKING DOCUMENT

B-2.4 DD Form 1348-1A ISSUE RELEASE/ RECIEPT DOCUMENT

B-3 RESERVED FOR FUTURE USE

B-4 RESERVED FOR FUTURE USE

B-5 RESERVED FOR FUTURE USE

B-6 ELECTRICAL FORMS

B-6.1 ELECTRICAL SAFETY DOCUMENTATION

B-6.2 LIGHTNING PROTECTION SYSTEM (LPS) DATA

SPECIAL STANDARDS RAFB BFS 2024

CHAPTER 1 SPECIAL STANDARDS

SECTION 1A GEOBASE PROGRAM

1A-1 GENERAL REQUIREMENTS

1A-1.1 The Robins AFB GeoBase Program is the primary repository of utility, planimetric and environmental data on Robins AFB. The goal of the program is to ensure that all design and construction projects make use of the most up-to-date utility and planimetric data, and that post construction updates are properly submitted and integrated to keep the base utility and planimetric data current.

1A-1.2 All project files prepared and modified throughout the construction process, shall be in electronic format red-lines, as-builts and delivered record drawings as specified in the contract documents.

1A-1.2.1 Planimetric and utility features are the responsibility of the 78 CEG/CENME.

• Planimetric Data: Airfield, Roads, Sidewalks, Buildings, Geodetic, Hydrography, Landform, Pedestrian and Land Status.

• Utility Data: Air, Electrical, Fuel, Gas, Heating/Cooling, Industrial, Storm, Wastewater and Water.

1A-1.2.2 The Environmental features are the responsibility of the 78 CEG/CEIE office.

• Environmental Data: Air Quality, Groundwater Quality, Pollution Control, Regulated Tanks, Solid Waste, Hazardous Materials (Hazmat), Hazardous Waste (Hazwaste), Remediation, Cultural, Fauna, Flora and Wetlands.

1A-1.2.3 The location and orientation of all elements shall be based on the following:

Table 1A-1

GEOGRAPHIC COORDINATES

Location Station ID Latitude Longitude Country

ROBINS

AFB

KWRB 32.64 -83.59 UNITED STATES -

GA

1A-1.3 All project files prepared and modified throughout the construction process, shall be in electronic format red-lines, as-builts and delivered record drawings as specified in the contract documents.

COORDINATES

COORDINATE SYSTEM

DATUM North American Datum (NAD) of 1983

FORMAT State Plane Coordinates for Georgia West FIPS 1002

SECTION 1B SAFETY PROVISIONS

1B-1 SAFETY PLAN REQUIREMENTS

The Contractor shall prepare a detailed project-specific Industrial Safety and Health Requirements Plan (Safety Plan) IAW OSHA guidance and DAFI 91-202, “The Air Force Mishap Prevention Program,” dated April 2024; AF Policy Directive 91-2, “Safety Programs,” dated September 2019; and as outlined in each Construction Contract or Task Order at Robins AFB.

The Safety Plan shall be submitted for review by the 78 ABW Safety Office and used to coordinate and perform work in a manner that does not impact the safety of Government or non- Contractor personnel, or cause damage to government property. The Contractor shall not start any construction activities until the Safety Plan has been deemed acceptable and all aspects of the Plan are in place.

1B-2 SITE PROTECTION

1B-2.1 Temporary Structures

1B-2.1.1 Plans for the layout of temporary structures such as buildings, facilities, fencing, access routes and anchoring systems for temporary structures shall be submitted for review and approval prior to implementation. The plans shall consider the following loading IAW American Society of Civil Engineers (ASCE) 7 current edition, Minimum Design Loads for Buildings and Other Structures:

• Dead and live loads

• Soil and hydrostatic pressures

• Wind loads

• Rain and snow loads

• Flood and ice loads

• Seismic forces

1B-2.1.2 Trailers and other temporary structures used as field offices, personnel housing or for storage shall be anchored with rods and cables or by steel straps to ground anchors. The anchor system shall be designed to withstand winds and meet applicable state or local standards for anchoring mobile trailer homes.

1B-2.2 Temporary Fencing

1B-2.2.1 Temporary project fencing (or an acceptable substitute) shall be provided on all projects located in areas of active use by members of the public, including those areas near family housing areas and/or daycare facilities.

1B-2.3 Signage for Construction Sites

Warning signs shall be posted at each construction site to identify the presence of construction hazards and require that unauthorized persons keep out of the designated construction area.

Signs shall be posted along each side of the project and spaced no more than 150 feet apart.

Provide safety signs as required at job sites, such as MEN WORKING ABOVE, DO NOT WATCH WELDER, and NO SMOKING.

1B-2.4 Protective Barriers

Contractor is responsible to provide barricades when it is necessary to protect an area due to operations including excavation, open manholes, overhead work, hazardous operations, or moving equipment. Erect barricades before the work begins. If the barricades are in a roadway or walkway, blinking lights must be used during the hours of darkness. Barricades and associated equipment shall be always kept neat and orderly. Immediately remove barricades from the job site when the work is complete. Kerosene lamps and open flame pots shall not be used for or with warning signs or devices.

1B-3 OPERATIONS SAFETY

1B-3.1 Foreign Object Damage (FOD) Prevention for Flightline Projects

1B-3.1.1 To prevent damage to aircraft from construction-generated debris, the Contractor shall establish and maintain an effective FOD prevention program as an overall component of project execution.

1B-3.1.2 All vehicles must stop at FOD checkpoints on the Flightline. The vehicle operator will visually inspect all tires treads for rocks and other debris to ensure all trapped items are removed and disposed of properly to prevent the loose objects from being carried onto the Flightline.

1B-3.2 Fire Reporting

Report all fires as soon as discovered. The fire reporting number on or off Base is 911 (RAFB 911: 478-222-2900). The caller should give his or her name and location of the fire and any other information that may be requested by the Fire Department dispatcher. Stay on the telephone until the dispatcher has obtained all necessary information.

1B-3.3 Welding, Cutting, Brazing and Open Flames

1B-3.3.1 Do not start operations involving welding, cutting, brazing and open flames until the Technical Representative of the Contracting Officer has been notified, the site has been inspected and approved by the authorized Fire Inspector.

1B-3.3.2 Complete AF Form 592 (Welding, Cutting, and Brazing Permit).

1B-3.3.3 Perform a fire watch for at least one-half hour after the operations are finished.

Sign and return the AF Form 592 to the Fire Department at Building 377 within one hour.

1B-3.4 Utilities

The Contractor shall coordinate with the respective shop prior to performing any activity that will affect utilities, systems, or operations at Robins AFB.

1B-4 OVERHEAD DOOR OPERATIONS

All overhead doors shall be wired for momentary operation i.e., constant pressure must be applied to the manual controls to operation in either direction. The only exception will be for Fire Department and DLA infrastructure requiring remote control doors. Any door with remote control operation capability will require a safety edge at the bottom of the door. Door controls shall be mounted on opposite side of door from motor and gear. Any exception shall require written approval from 78 CES.

1B-5 GUIDANCE FOR CLEAN WORK AREAS

Wipe samples are routinely collected in industrial areas at Robins AFB by the Bioenvironmental Office. The Contractor shall review posted Bio Survey Assessments at individual work areas to determine special procedures or requirements associated with doing construction activities in that facility.

SECTION 1C PRE-ENGINEERED METAL BUILDINGS (PEMB)

1C-1 SYSTEM COMPONENTS AND DESIGN REQUIREMENTS

1C-1.1 Metal Building Manufacturer Accreditation

Manufacturer shall be accredited by the International Accreditation Service Inspection (IAS) Programs for the Manufacturers of Metal Building Systems, AC472. Provide copy of the current accreditation.

1C-1.2 Structural Frame Configuration

• Buildings not containing finished spaces: Tapered Columns

• Buildings containing finished spaces: Straight Columns

1C-1.2.1 All new PEMB shall be expandable unless otherwise noted in the statement of work.

1C-1.2.2 For pre-engineered metal buildings on design-build and design-bid-build projects, the structural drawings shall include, but not be limited to, the following:

• Column reactions for each frame line

• Foundation plan and details

• Base plate and anchor location and details

• Elevations showing primary and secondary member locations and sizes, including all framing for architectural and mechanical openings.

• All bracing, wind post, and portal frame locations.

1C-1.3 Roof Panel Configuration

Roof panel configuration shall meet the requirements of Table 1C-1 below for new industrial and simple commercial roofs with no valleys; or new commercial Architectural roofs, which may contain valleys. Roof selection shall be consistent with adjacent facilities.

Table 1C-1

ROOF PANEL CONFIGURATION

New Industrial & Simple Commercial Roofs (No Valleys)

New Commercial Architectural Roofs (May Contain Valleys)

3” min. height trapezoidal mechanically seamed standing seam roof panels

2” min. height vertical leg mechanically seamed standing seam roof panels

360° seam (90°/180° seams not allowed) 360° seam (90°/180° seams not allowed)

24” max. width panels shall have intermediate low profile ribs (flat pans not allowed)

18” max. width panels shall have intermediate low profile ribs (flat pans not allowed)

1C-1.4 Insulation

1C-1.4.1 Minimum Thickness for Walls, Fascia (if applicable) and Roof

3.5 inches (R = 13) in unconditioned buildings.

1C-1.4.2 Scrim or Facing on Insulation (also referred to as Vapor Retarder)

• Factory applied white polypropylene film, fiberglass, and polyester scrim, 30# natural kraft and metalized polyester (PSKP) or Polypropylene-Scrim-Kraft Polyester

• Tensile strength MD - 65 pounds per inch (lbs/in) / XD - 60 lbs/inch minimum

• Water Vapor Transmission Rate (WVTR) - 0.02 perm (unit of permeance) or less

• Basis of Design – Lamtec® WMP-50

1C-1.4.3 Configuration

Insulation/scrim system shall be installed as a 100% vapor barrier with a six (6) inch single side tab. Tabs shall be sealed as required to maintain the barrier. Designer shall provide sufficient detailing to adequately describe installation so that no condensation is trapped inside the wall section.

1C-1.5 Finishes

Structural Steel Frames and Columns/Posts - Preferred Finish: Factory applied primer and painted for exposed conditions; shop primed only for concealed locations.

1C-1.6 Girts and Purlins

Primed and painted for exposed conditions, primed only for concealed locations.

1C-1.7 Panels

Coated with Kynar 500® Polyvinylidene Fluoride (PVDF) or Hylar® 5000 PVDF meets the required finish warranty requirements.

1C-2 WARRANTIES

All warranties shall be from a single source manufacturer. Manufacturer used as a design basis shall be capable of meeting warranty requirements. Contractor shall provide sample warranty to 78 CEG/CEN for review prior to proceeding with design or submitting any other PEMB submittals for review.

1C-2.1 Weather-Tightness System – Labor and Materials

20-Year No Dollar Limit (NDL) Warranty Required - The warranty shall cover roof weather tightness up to the required design wind speed. Repairs that become necessary because of defective materials and workmanship while roof panel system is under warranty are to be performed within 48 hours after notification. Failure to perform repairs within 48 hours of notification will constitute grounds for having emergency repairs performed by others and will not void the warranty. Follow-up and completion of repairs must be performed within 14 calendar days from date of notification.

1C-2.2 Roof and Wall Panel Finish System – Labor and Materials

20-Year No Dollar Limit (NDL) Warranty Required - The warranty shall cover repairs that become necessary because of defective materials and workmanship while the roof and wall panel system is under warranty are to be performed within 48 hours after notification unless additional time is approved by the Contracting Officer. Failure to perform repairs within 48 hours of notification will constitute grounds for having emergency repairs performed by others and will not void the warranty. Follow-up and completion of repairs must be performed within 14 calendar days from date of notification.

SECTION 1D GREEN PROCUREMENT PLAN

1D-1 GENERAL

The Green Procurement Plan (GPP) is a mandatory federal acquisition program that focuses on the purchase and use of environmentally preferable and bio-based products and services. Air Force GPP Policy includes the purchasing of Energy and Water Efficient Products; Alternative Fuels and Fuel Efficiency; Bio-based Products; Non-Ozone Depleting Substances; Priority Chemicals; and Environmentally Preferable Products.

GPP requirements apply to all acquisitions including services and new requirements. Federal Acquisition Requirement 23.404(b) applies and requires 100% of US EPA designated product purchases to contain recovered materials unless the item cannot be acquired competitively within a reasonable timeframe; meeting reasonable performance standards; or at a reasonable price.

SECTION 1E FLIGHTLINE PHOTOGRAPHY

1E-1 GENERAL GUIDANCE

Photographs of facilities or assets within the industrial flightline area of Robins AFB may be taken only with prior authorization. Any such photographs shall be taken FOR OFFICIAL USE ONLY and may include but not be limited to the following:

• Recording of existing conditions associated with specific building construction and repair projects; or

• Providing documentation of progress, details or issues associated with specific building construction and repair projects.

1E-2 PROHIBITED PHOTOGRAPHY

Photography of classified assets or activities is strictly prohibited.

1E-3 PHOTOGRAPHIC DEVICES

Official photographs shall be taken with a government owned camera or other approved devices with photo-taking capabilities. Use of personal cameras, cell phones or other devices is prohibited.

SECTION 1F CONTRACTOR TRAILER POLICY

1F-1 GENERAL GUIDANCE

Only the prime contractor is allowed office trailer space at Robins AFB. Office Trailer locations authorized for use outside of construction laydown sites are not authorized for storage.

1F-1.1 Office Trailer/Conex Policy

1F-1.1.1 Authorized use of Contractor Office Trailers, Conex/Storage containers and laydown yards are discretionary. Before any area is assigned, the prime contractor shall formally request in writing a siting approval for a trailer with full justification to the 78 Civil Engineer Group (78 CEG/CEN) Community Planning section. The assigned 78 CEG Construction/Project Manager will facilitate this request at the contract level.

1F-1.1.2 If water, sewage, or electrical power is required and available within the work areas, the contractor must request connection through the 78 CEG Construction/Project Manager.

1F-1.1.3 Digging or trenching for utilities requires a Digging Permit approval through the 78 Civil Engineer Squadron Digging Permit process. Consult the 78 CEG Construction/ Project Manager about instruction for the process.

1F-1.1.4 The Contractor is responsible for the utilities not available on site, by alternative means (portable containers/ tanks for water and sewage collection).

• Portable Generators shall not violate EPA Clean Air permitted levels.

• The contractor shall shield generators to control excessive noise levels.

1F-1.1.5 The contractor shall maintain the area assigned, keeping grass cut, shrubs trimmed, and debris properly disposed of.

1F-1.1.6 Once the contract, project, or task order is completed, the contractor shall have ten (10) calendar days to remove the Office Trailer, Conex/Storage Containers, laydown yard and all debris materials from the Base. The contractor shall restore impacted area to original condition.

1F-1.1.7 Existing trailer already located on the installation are not grandfathered in or exempt from this policy. This policy shall take effect at the publication of this document.

1F-1.2 Office Trailer/Conex Size and Marking Requirements

1F-1.2.1 Office Trailer shall not be larger than 10 feet by 50 feet. Job site Conex and/or Office Trailer shall not be any larger than 8 feet by 20 feet.

1F-1.2.2 Office Trailer shall display 3 feet by 5 feet sign at least 4 feet from the bottom of the structure on the most visible exterior side of the trailer. The sign shall include:

• Company name with logo.

• Contract associated with the office trailer.

• Company representative and telephone number with 24-hour contact.

1F-1.2.2.2 Location of sign on the trailer or conex and the proposed sign shall be approved by 78 CEG/CEN prior to trailer coming on the installation.

ENVIRONMENTAL REQUIREMENTS RAFB BFS 2024

CHAPTER 2 ENVIRONMENTAL REQUIREMENTS

SECTION 1560

Protected Wetland Area

ENVIRONMENTAL REQUIREMENTSRAFB BFS 2024

SECTION 2A GENERAL GUIDANCE

2A-1 REGULATORY COMPLIANCE MANDATE

All contracts performed on Robins AFB are bound by requirements established by the Federal Government, State of Georgia, Houston County and Department of Defense (DoD); as well as Air Force laws, regulations and policies specific to Robins AFB. Work is coordinated through regulatory permits and management plans to ensure that hazardous work conditions are minimized, personnel are protected, accidental damage to Base assets is prevented, and disturbed sites are fully restored when excavation has been completed. Environmental compliance is required for the following programs: solid and hazardous wastes, toxics, water quality, air quality, natural resources, storage tanks, cultural resources, pollution prevention, hazardous materials, and fuels. Environmental Management, 78 CEG/CEIE, is the organization responsible for management of base environmental concerns. Contact program managers in 78 CEG/CEIE at (478) 926-9645, or via email: 78ceg.cev.FrontOfc@us.af.mil.

Contractors shall comply with all requirements of Robins Division 1 specifications Section 01560 Environmental Requirements for Robins Air Force Base. Section 01560 is updated regularly, request for copies of the updated document may be requested through the 78 CEG Construction/Project Manager.

SECTION 2B PRESERVING HISTORICAL AND

ARCHAELOGICAL RESOURCES

2B-1 PROGRAMMATIC AGREEMENT

On 10 September 2014 a Programmatic Agreement was finalized between Robins AFB, the Georgia State Historic Preservation Office and the Advisory Council on Historic Preservation regarding maintenance, rehabilitation and minor development activities that may impact historic properties at Robins AFB that are eligible for inclusion in the National Register of Historic Places. When a building or archaeological site determined eligible for the National Register of Historic Places is within a project area, the Contractor shall take measures to prevent adverse impact to the cultural resource. This may include the development of a mitigation plan or consultation with the Georgia State Historic Preservation Office, the Advisory Council on Historic Preservation and twelve culturally affiliated Native American tribes. Specific facilities and archaeological sites were identified, including the following:

Table 2B-1

Buildings Eligible for the National Historic Register – Robins AFB

12 98 107 220 410 415 2067

94 105 110 400 411 450 2081

97 106 125 405 412 1400

Reference Division 1 Section 01560 for additional information.

2B-2 COORDINATION

The contractor shall provide 78 CEG/CEIE with project information about the building or archaeological site. The Contractor shall contact 78 CEG/CEIEC Cultural Resources Program Manager at the beginning of the project prior to beginning any work.

2B-3 DISCOVERIES

When cultural resources are inadvertently discovered during construction, maintenance, or repairs, project personnel are directed to avoid the site of discovery and immediately contact the 78 CEG/CEIEC Cultural Resources Program Manager. All work around discovery must stop until it can be investigated. 78 CEG/CEIE will send a qualified representative to the site and the resource will need to be recorded and evaluated and the effects mitigated as necessary.

2B-4 ARCHAELOGICAL FINDS

Archaeological finds are artifacts, eco-facts, or modifications to the landscape that are associated with past human activity and are a minimum of 50 years old. All archaeological finds are the property of Robins AFB. Do not remove or disturb finds without the CO’s written authorization.

SECTION 2C CONSERVATION OF NATURAL RESOURCES

2C-1 GENERAL

The Ocmulgee skullcap (Scutellaria Ocmulgee) is one plant that is proposed federally threatened on Robins AFB and eight other plant species are considered rare. There are two proposed federally endangered animals, the Tricolored bat (Perimyotis subflavus) and the Monarch butterfly (Danaus Plexippus) that occur on Robins AFB. Bald Eagles (Haliaeetus leucocephalus) and Wood Storks (Mycteria americana) are occasionally seen on base.

Additionally, most wildlife species including birds, bats, turtles, non-venomous snakes, and game species are protected by law.

2C-1.1 Coordination

The contractor shall not clear vegetation on project sites without prior approval from 78 CEG/CEIEC. The contractor shall not harm wildlife of any kind or injure any rare species or their habitats. If the Contractor encounters problems with wildlife, notify the Project Manager/ Construction Manager. The Project Manager/ Construction Manager shall contact the 78 CEG/CEIEC Natural Resources Program Manager to determine the best solution for each problem.

2C-2 GREEN INFRASTRUCTURE PLAN (GIP)

Green infrastructure planning is used to identify deficiencies and enhance natural functions and values of the interconnected network of waterways, wetlands, woodlands, grasslands, and other natural areas of significance throughout the Installation, collectively known as green infrastructure. The implementation strategy of the Green Infrastructure Plan (GIP) will be delivered through four major focus areas, including urban forestry, pollinator habitats, stormwater drainage vegetative buffers, and invasive species management. The GIP will provide sustainable practices, and promote societal and ecological benefits, giving the RAFB community more comfortable, attractive working and living conditions. The GIP will also support mission effectiveness and readiness by enhancing, maintaining, and preserving natural resources in both the built and natural environments on the Installation. Managers of the construction process and contractors shall consider the principles and implementation strategy of the GIP, consult with 78 CEG/CEIEC during construction planning, and incorporate these concepts into project execution when conducive to mission objectives.

The GIP can be found at https://usaf.dps.mil/teams/10623/Robins/Shared%20Documents/Natural%20Resources/Robins %20AFB-GIP-Facility%20Standards.pdf or requested from the Environmental Management front office at 78ceg.cev.FrontOfc@us.af.mil.

SECTION 2D PROTECTION OF WATER AND LAND

RESOURCES

2D-1 GENERAL

The Contractor shall not take any action that will adversely affect the existing Water Quality Standards classification of any streams, rivers, lakes, wetlands, or reservoirs within or adjacent to the project site or otherwise contribute to the pollution of these water resources. No fuel, oils, bituminous materials, calcium chloride, acids, construction waste or otherwise harmful materials shall be permitted to enter these water resources. Land resources shall be preserved in their present condition or restored to a condition that appears natural and does not detract from the appearance of the surrounding area. Restoration of water and land resources through mitigation actions may be necessary for some projects. If restoration is to be accomplished, the Contractor shall submit an appropriate restoration plan and receive base approval from 78 CEG/CEIE on the proposed mitigation procedures.

Reference Robin AFB Division 1 Specifications Section 01560 and Section 3G of this document for additional information.

STRUCTURAL AND CIVIL ENGINEERING ELEMENTS RAFB BFS 2024

CHAPTER 3 STRUCTURAL AND CIVIL

ENGINEERING ELEMENTS

SECTION 3A STRUCTURAL REQUIREMENTS

3A-1 GENERAL STRUCTURAL REQUIREMENTS

3A-1.1 All structural design work necessary to construct a new facility, to repair, modify or demolish an existing facility shall be analyzed and designed to safely support all applicable loads and load combinations and to meet all serviceability requirements of these loads and shall comply with relevant Codes and Standards.

3A-1.2 Structural design shall conform to the requirements of all applicable UFCs.

3A-1.3 The structural designer of record may not delegate responsibility of structural design at Robins AFB, and must provide a complete design package including, but not limited to, calculations, specifications, plans, details, and design of systems or component parts of the structure in compliance with UFC 3-301-01. The structural designer may utilize a manufacturer as a design basis for design development. For specifics on pre-engineered metal building design refer to Section 1C.

3A-2 SPECIAL STRUCTURAL REQUIREMENTS

3A-2.1 Stability

Wind loads shall be analyzed and designed for a minimum exposure of Category “C” IAW ASCE/SEI 7-latest edition, Chapter 26.

3A-2.2 Risk Factor

Analysis and design shall be based on Risk Category “III” as described in ASCE/SEI 7-latest edition, unless otherwise instructed by the 78 CEG/CEN.

3A-2.3 Non-Standard Floor Loads

The designer shall review the project for floor-loading conditions not normally encountered, such as safes, industrial equipment, etc.

3A-2.4 Mezzanines/ Additional Floor

The project shall be designed for any special floor loading requirements planned for mezzanine or added floor level areas.

3A-2.5 Clearances

Minimum clearances shall be allowed in design and construction of walkways, roads, and accessories.

3A-2.6 Fly Ash in Concrete

If fly ash is used as a component of concrete (typically to meet green procurement requirements), only Class F fly-ash may be used. Other classes of fly ash are not allowed at Robins AFB. Quality guidance for fly ash in Portland Cement Concrete may be found at

AASHTO M295 (ASTM C 618).

3A-3 FOUNDATIONS

3A-3.1 No foundation shall be constructed over existing or new water, sewer, steam, natural gas, chilled-water, industrial waste, communications, or foundation main lines.

Exceptions may be granted on a case-by-case basis. This does not apply to laterals or service lines. Minimum cover shall be provided between bottom of concrete and top of utilities as required by this document, UFC, or other industry standards.

3A-3.2 The safety factor used for Overturning, Sliding, and Uplift shall be a minimum of 1.50.

3A-3.3 ANTENNAS AND OTHER EXTERIOR USER EQUIPMENT

3A-3.3.1 No antennas or other user equipment shall be mounted on the roof or walls unless the mountings have been specifically analyzed and designed and approved by the Structural Engineer in 78 CEG/CEN prior to the installation.

3A-3.3.2 Exceptions may be granted only for small items approved on a case-by-case basis by the Structural Engineer in 78 CEG/CEN. Request and approval must be completed in writing.

STRUCTURAL AND CIVIL ENGINEERING ELEMENTS CIVIL ENGINEERING AND

SITE PLANNING

SECTION 3B CIVIL ENGINEERING AND SITE PLANNING

3B-1 PLAN REQUIREMENTS

All civil design or site work necessary to construct or modify any existing or new facility, infrastructure, roadway of other element or appurtenance, including all applicable calculations, shall be provided at each design submittal level.

3B-1.1 Location Plan (Scale 1”=400’)

1) Facility or Project Location at Robins AFB

2) Site Access Route entering through the Commercial Gate (Gate 7) or an alternate gate if directed

3) Designated Construction Material Storage Area, which shall be secured and maintained throughout the Construction Contract

3B-1.2 Site Plan (Scale 1”=50’ minimum)

1) Existing grades and contours using a (minimum) one foot contour interval

2) The facility location (or location of element being constructed) and orientation based on the Project Coordinate System: North American Datum (NAD) 1983; State Plane Georgia West FIPS 1002

3) Designated Construction Material Storage Area showing Construction Office Trailer (if applicable)

4) Project Construction Limits

5) Existing and Proposed Pavements, including:

a. Sidewalks and walkways

b. Parking lot striping

c. Road cuts

d. Curbs, gutters, culverts and pads sufficient to comply with stormwater and drainage requirements

e. Runways, taxiways, aprons, overruns, and shoulders

6) Bridges and fences

7) Existing natural site features, including:

a. Existing State Waters and Streams with any prescribed buffers

b. Designated Wetlands

c. Trees greater than three inches measured diameter at breast height (DBH)

8) Proposed changes to site elements, encroachment into vegetation, buffer or wetland areas or removal of specific trees or mature vegetation

9) Existing and proposed structures and utilities, including:

a. Existing industrial and sanitary wastewater piping, manholes, valves, and lift stations

b. Storm piping and structures, drainage ditches/swales, headwalls, and ponds

c. Gas distribution and service lines

d. Water lines and valves

e. Communication lines

f. Electrical lines

g. Cathodic protection cables and equipment

h. Heat service or steam lines

i. Chilled water lines

j. POL facilities, including pipelines, valves, etc.

k. Fire hydrant

l. Groundwater monitoring wells locations

10) All civil and site elements shall be analyzed and designed for safety as well as long-term maintainability and serviceability

3B-2 SITE VISIT

A site visit shall be scheduled with the Contractor and Base Officials prior to the first formal plans submittal to review on-the-ground site conditions and the potential impact of proposed site changes and improvements.

3B-3 SITE INVESTIGATIONS

All site investigations shall be done during the design phase of the project. Site investigations including topographic survey, utility locate including potholing, and geotechnical/environmental investigations shall be accomplished and incorporated prior to the 60% (preliminary) design phase.

SECTION 3C WASTE WATER TREATMENT

3C-1 GENERAL INFORMATION

3C-1.1 A Design Analysis shall be completed for the projected industrial or functional wastewater discharge of any proposed project to include the following:

• A Site Plan showing all existing and proposed sewer lines

• Calculations, sewer profiles and related hydraulic information for proposed wastewater connections

• Plan shall be stamped by registered professional engineer from the

State of Georgia

3C-1.2 An Operation and Maintenance Manual shall be provided by the Construction Contractor for all new wastewater pretreatment systems, lift stations or wastewater treatment facility systems.

3C-2 WASTEWATER TREAMENT SYSTEM

3C-2.1 The project shall be evaluated to verify the existing wastewater flow and available design capacity for treatment, including limitation of the existing systems that require wastewater pretreatment and segregation.

3C-2.2 The quantity and quality of wastewater discharged shall be evaluated to determine if it can be adequately handled by the existing Robins AFB wastewater treatment system.

3C-2.3 Adequate capacity shall be assessed for all downstream lift stations. Sewer flow characteristics shall be modeled for projects with high-volume (>50,000 gallons per day), or large-batch discharges (>5000 gallons).

3C-2.4 Proposed new process discharges of industrial wastewater that may affect the quality of the effluent shall be listed in the design narrative. An evaluation shall be prepared providing the strength and mass loading of the wastewater constituents, such as chemical oxygen demand, solids (including oil and grease), metals, nutrients and toxic pollutants, or any other chemical which could affect effluent quality.

3C-2.5 Any wastewater sludge or solids that may be accumulated as part of the project will be evaluated and methods for collection and removal of the accumulation shall be proposed.

All efforts to incorporate recycling and reuse of wastewater shall be included.

3C-2.6 Any required changes or improvements in the existing treatment plants, pre-treatment systems, trunk mains, manholes, lift stations, fuel/oil-water separators, or storage and bypass restrictions will be identified and evaluated.

3C-3 WASTEWATER SYSTEM CONSTRUCTION

3C-3.1 All new lift stations shall be constructed using a duplex pump system, level controls, visible and audible alarms, and shall be connected to the Robins AFB SCADA system and include all appropriate appurtenances. Duplex pump system shall be Grundfos (or Flygt as alternative) manufactured pumps with MPE SC -1000 pump controllers. An additional valve pit, with a lockable metal hatch, shall be constructed outside of the wet-well to house isolation valves, check valves, and air release valves. A manual transfer switch with camlock connections for emergency backup power shall be installed. Minimum 3-inch force main exiting the lift station.

3C-3.2 Any structure that is built to surround the lift station will be secured. Doors will be locked; any vents or opening will be hardened and locked and will have an area of no more than 96 square inches. Any ladder on the exterior of the building shall have a minimum vertical clearance of 20 feet between the bottom rung and any appurtenance that could assist access by climbing.

3C-3.3 A nine (9) gauge, seven (7)-foot height chain link fence with three (3) barbed wire outriggers shall be constructed around the lift station and secured with a tamper-resistant lock.

Vegetation shall be cleared from the area around the perimeter fence sufficient to avoid aid in climbing the fence or concealing an object near the fence. The area shall be illuminated to provide one (1) footcandle of light within a 50-foot radius of the lift station.

3C-3.4 The SCADA system connection shall be accomplished with a Remote Transmitting Unit (RTU) provided at each lift station that is compatible and capable of interfacing with the Robins AFB SCADA system manufactured by minsait ACS, Inc. of Norcross, Georgia.

The RTU shall have battery back-up radio controls and transmit the following points to the central base monitoring system: pump status, water levels and power status for lift station.

Contact the Electric Shop for information at 478-327-8945.

3C-3.5 Existing sewer main lines located underneath any proposed new facility shall be removed and relocated.

3C-3.6 No interruption of sewage flow shall occur during construction.

SECTION 3D SUBSURFACE INVESTIGATIONS

3D-1 GENERAL REQUIREMENTS

3D-1.1 Each project that requires design of foundations and earth structures for new or existing facility at Robins AFB shall include one or more registered professional engineer(s) with experience in the principles of engineering associated with soil mechanics. Foundations and earth structures shall be designed to meet the requirements of UFC 3-220-01 Geotechnical Engineering (latest edition).

3D-1.2 Site data provided as part of the general bidding package is based on best available record drawings and may contain inaccuracies. The contractor shall be responsible for identifying all utilities and underground structures for each project. Additional potholing and/or GPR required to identify all underground elements not captured in the proposal shall be performed at no additional cost to the Government.

3D-2 DIGGING AND EXCAVATION REQUIREMENTS

3D-2.1 A Dig Permit is required for any land disturbance or earth movement.

3D-2.1.1 Contractor shall notify the AF Project Manager/Construction Manager 21 days prior to needing a dig permit. The process takes 15 business days from the date the completed submittal request is entered.

3D-2.1.2 The Georgia 811 dig permit clearance # and date shall be provided. Provide a copy of the GA811 clearance to the AF PM/CM.

3D-2.1.3 The Contractor shall clearly mark the area outlined in white paint and flags prior to requesting utility locate. Maintenance of markings and area are the responsibility of the contractor. Contractor shall be responsible for renewing markings at least once every 30 days.

3D-2.1.4 Drawings are required that accurately show all buried structures and utility lines and the full extent of digging and excavation including the width, depth, and length of any trench or hole.

3D-2.1.5 Utility personnel from 78 CEG will meet with the Contractor at the site and locate the underground utility lines and buried structures that may be affected.

3D-2.2 The following special provisions apply to all Dig Permits:

3D-2.2.1 No digging or excavation shall be done after 1600 hours on weekdays or anytime on weekends unless prior approval is obtained.

3D-2.2.2 Excavation, trenching or backfilling within three (3) feet on either side of buried structures or utility lines must be completed by hand digging. Do not use motorized equipment within these parameters. Only open these trenches when replacement work is ready to proceed.

3D-2.2.3 Trenches should be backfilled and stabilized as required by the drawings or specifications as quickly as possible after approval by the technical representative.

3D-2.2.4 The Contractor is responsible for any damage to underground structures and utility lines identified on the drawings and as identified and marked in the field as a result of obtaining a Dig Permit. If any underground utility is damaged, notify the technical representative immediately.

SECTION 3E TERMITE PRE-TREATMENT

3E-1 GENERAL REQUIREMENTS

Provide termite pre-treatment for all exposed soil locations around the interior and exterior sides of slabs and footings, excluding sidewalks.

3E-2 SAFETY REQUIRMENTS FOR USE AND HANDLING

3E-2.1 Deliver termiticide material to the site in the original unopened containers bearing legible labels indicating the EPA registration number and manufacturer's registered uses. All other materials, to be used on site for the purpose of termite control, shall be delivered in new or otherwise good condition as supplied by the manufacturer or formulator.

3E-2.2 Inspect termiticides upon arrival at the job site for conformity to type and quality.

Each label shall bear evidence of registration under the Federal Insecticide, Fungicide, and Rodenticide Act (FIFRA), as amended or under appropriate regulations of the host county.

Other materials shall be inspected for conformance with specified requirements. Any unacceptable materials shall be removed from the job site.

3E-2.3 Handle termiticides in accordance with manufacturer's warnings and precautions and prevent contamination by dirt, water, and organic material.

3E-2.4 Formulate, treat, and dispose of termiticides and their containers in accordance with label directions.

3E-2.5 Ensure that proper protective clothing and equipment are worn and used during all phases of termiticide application.

3E-2.6 Secure termiticides, other pesticides and related materials under lock and key when unattended.

3E-2.7 Dispose of used pesticide containers off Government property.

SECTION 3F LAWN SPRINKLER SYSTEMS

3F-1 GENERAL REQUIREMENTS

The following guidelines apply when a permanent underground sprinkler irrigation system is required to irrigate turf and planted areas associated with new facilities or projects.

Note that irrigation systems are no longer maintained by CES. The organization occupying the facility and requesting irrigation will be responsible for contracting maintenance services for the system.

3F-1.1 The water supply for the sprinkler system shall be the Base potable water system.

3F-1.2 The design shall concentrate on ease of maintenance, economy of water usage and durability of the working parts.

3F-1.3 Adequate pressure shall be provided to all sprinkler heads but water pressure required by the facility shall not be adversely affected.

3F-2 DESIGN REQUIREMENTS

3F-2.1 Minimum Water Pressure

The minimum design water pressure shall be 50 psi at connection to main backflow prevention device. All systems shall be automatic and shall be installed with a rain sensor and rain shut off valve.

3F-2.2 Component Design Basis

3F-2.2.1 Sprinkler Systems

Utilize Hunter I-20 Stainless Steel, Hunter I-25 Stainless Steel, Hunter Pop-Up Mist Heads 10A nozzle, 12A nozzle, 15A nozzle, and 17A nozzle spraying capabilities; and Hunter Spray Heads in the following specifications: PS0410A, PS0412A, PS0415A, or PS0417A, Hunter SS nozzle, Hunter PS045SS Spray Head, Hunter SRS 12 spray head spraying capabilities, whichever is applicable, and Irritrol Drip Irrigation Products or equivalent.

3F-2.2.2 Emitter Heads

3F-2.2.2.1 Use self-cleaning emitter heads with pressure compensating diaphragms and one or six self-piercing barbed outlets.

3F-2.2.2.2 Each shall be capable of emitting from ¼ to 2 gallons per hour flow.

3F-2.2.2.3 Emitter bodies shall be ultraviolet stabilized, algae and heat resistant plastic construction.

3F-2.2.3 Remote Control Valves

These shall be Hunter HPV series, Hunter ICV with filter sentry in the applicable size; Rain Bird PGA and PEB series in the applicable size; or Weathermatic in the applicable size

3F-2.2.4 Automatic Controllers

Use Hunter ICC Commercial Controller 8 or equivalent.

3F-2.2.5 Control Wire

3F-2.2.5.1 Use 12-gauge single or multi-strand, whichever is applicable, and UF type designed for direct burial.

3F-2.2.5.2 Wires shall be buried beside pipe in same trench and shall be attached to the piping in increments of every 15-20 feet.

3F-2.2.5.3 Rigid conduit shall be provided where wires run under paving.

3F-2.2.5.4 Each zone shall use different color wire to facilitate zone identification; zone wire color shall be continuous for the entire length of the circuit.

3F-2.2.5.5 One control circuit shall be provided for each zone and a circuit to control sprinkler system.

3F-2.2.5.6 A minimum loop of 24 inches shall be left at each valve, at each splice, at each change in direction, at every 500 feet of straight run and at each controller for expansion and servicing.

3F-2.2.5.7 Splices and connections shall be watertight and leak-proof and shall be indicated on the “as built” plan.

3F-2.2.5.8 Wire shall be within a protective sleeve for bridge or…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .