This is a blank sample Schedule of Values for a federal construction contract (Contract No. FA8501-XX-X-XXXX) under the United States Air Force (UHHZ project). The document provides a comprehensive cost breakdown template organized by 33 divisions of construction work, with a total bid value of $43.72 million and a close-out documents section valued at $0.00.

The schedule itemizes costs across all major construction disciplines including general requirements ($3.13M, 7.16%), existing conditions/demolition ($6.50M, 14.87%), concrete ($3.15M, 7.20%), masonry ($4.01M, 9.17%), metals ($0.90M, 2.06%), wood and composites ($0.68M, 1.56%), thermal and moisture protection ($0.72M, 1.65%), openings ($0.77M, 1.76%), finishes ($1.78M, 4.07%), specialties ($1.01M, 2.31%), special construction ($4.14M, 9.47%), fire suppression ($0.94M, 2.15%), plumbing ($0.82M, 1.88%), HVAC ($4.42M, 10.11%), electrical ($3.68M, 8.42%), communications ($2.18M, 4.99%), electronic safety and security ($2.34M, 5.35%), earthwork ($0.27M, 0.62%), exterior improvements ($1.60M, 3.66%), and utilities ($0.68M, 1.56%). Each line item includes specific descriptions and percentage allocations. Close-out documents for as-built drawings, warranties, operations and maintenance manuals, and roof inspection reports are included with zero assigned value, indicating these may be required but not priced separately in this template.

View the file

Other files

File Type Posted
RobinsAFB_PavingIDIQ_FA850126R0004_UpdatedPage1.pdf PDF
WD_GA20260322.txt TXT text file
Attachment I - Blank Sample Form 911 xx Design Discipline Review.docx DOCX document
A - PROCEDURAL GUIDE FOR DESIGNERS INCLUDING AE FIRMS 2023.pdf PDF
Attachment T- UHHZ250030 SSR Document.pdf PDF
DEMO Project UHHZ260007 SOW.pdf PDF
Attachment U- UHHZ250030 _ DOT SSR Document_.pdf PDF
Attachment O- Bid Schedule.docx DOCX document
Attachment K - Master Utility Outage.pdf PDF
Attachment F BLANK SAMPLE AF Form 3064.xlsx XLSX spreadsheet
Attachment E - Blank Sample AF Form 3052.xls XLS spreadsheet
Attachment D AF Form 3000.pdf PDF
Attachment B AFMAN 31-116 Motor Vehicle Traffic Supervision (1).pdf PDF
DEMO PROJECT UHHZ260007 SUBMITTAL REGISTER.xls XLS spreadsheet
DEMO PROJECT UHHZ260007 Bid Schedule.pdf PDF
Attachment M - App C UHHZ 250030.pdf PDF
Attachment L - Robins AFB Asbestos Management Plan - January 2015.pdf PDF
Attachment H - BLANK SAMPLE DD Form 1354 Transfer and Acceptance of DoD Real Property.pdf PDF
Attachment G - BLANK SAMPLE AF Form 3065.xlsx XLSX spreadsheet
Attachment C AFMAN 32-1084 Civil Engineering Facility Requirements.pdf PDF
Basewide Paving IDIQ SOW.pdf PDF
RobinsAFB_PavingIDIQ_FA850126R0004.pdf PDF
Attachment R- Robins BFS 2024.pdf PDF
Attachment J - Blank Sample SUBMITTAL REGISTER.xls XLS spreadsheet
Attachment A - af2586_new.pdf PDF
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DIVISION 01 - GENERAL REQUIREMENTS

LINE NO. DESCRIPTION VALUE PERCENTAGE

1.1 Project Management $0.73 1.67%

1.2 Supervision $0.97 2.22%

1.3 Project Trailer (including deliver & return) $0.05 0.11%

1.4 Roll-Off Dumpster $0.53 1.21%

1.5 Temporary Fence $0.53 1.21%

1.6 Bond $0.13 0.30%

1.7 Rental Equipment (Lull, Manlift, Boom Truck) $0.19 0.43%

1.8 Tools $0.19 0.43%

Division 01 Total $3.13 7.16%

DIVISION 02 - EXISTING CONDITIONS

LINE NO. DESCRIPTION VALUE PERCENTAGE

2.1 Demolition Interior (Electrical) $0.88 2.01%

2.2 Demolition Interior (Mechanical) $0.32 0.73%

2.3 Demolition (Plumbing) $0.15 0.34%

2.4 Demolition (Flooring) $0.15 0.34%

2.5 Demolition (Openings) $0.88 2.01%

2.6 Demolition (Concrete) $0.88 2.01%

2.7 Demolition (Ceilings) $0.88 2.01%

2.8 Demolition (Walls) $0.55 1.26%

2.9 Demolition (Fire Suppression) $0.88 2.01%

2.10 Demolition (Fire Alarm System) $0.68 1.56%

2.11 Demolition (Communications) $0.25 0.57%

Division 02 Total $6.50 14.87%

DIVISION 03 - CONCRETE

LINE NO. DESCRIPTION VALUE PERCENTAGE

3.1 Concrete Pad (Generator) $0.32 0.73%

3.2 Concrete Ceiling {Vault) $0.68 1.56%

3.3 Concrete Pad (Mechanical Yard} $0.87 1.99%

3.4 Concrete Pad (HVAC Units) $0.96 2.20%

3.5 Concrete Reinforcements $0.14 0.32%

3.6 Expansion Joints, Contraction Joinls $0.18 0.41%

3.7 Concrete Design Mix/Rebar Shop Drawings $0.10 0.23%

3.8 Concrete Testing and Reports $0.08 0.18%

Division 03 Total $3.15 7.20%

BLANK SAMPLE SCHEDULE OF VALUES

Contract No: FA8501-XX-X-XXXX Project No & Title: UHHZ XXXXXX Construct XXXXXXXXXXXXXXXXXXXXXXX

DIVISION 04 - MASONRY

LINE NO. DESCRIPTION VALUE PERCENTAGE

4.1 Mechanical Yard Masonrv Wall $0.31 0.71%

4.2 Generator Pad Masonry Wall $0.65 1.49%

4.3 Infill (Front Entry Area) $0.96 2.20%

4.4 Masonry Patch Work (Roll-up Door) $0.96 2.20%

4.5 Infill (Mechanical Louver Area) $0.20 0.46%

4.6 Vault $0.93 2.13%

Division 04 Total $4.01 9.17%

DIVISION 05 - METALS

LINE NO. DESCRIPTION VALUE PERCENTAGE

5.1 Metal Stud Framing (Interior) $0.78 1.78%

5.2 Metal Stud Framing Accessories $0.12 0.27%

5.3 0.00%

Division 05 Total $0.90 2.06%

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

LINE NO. DESCRIPTION VALUE PERCENTAGE

6.1 Casework (Women's Restroom) $0.34 0.78%

6.2 Casework (Men's Restroom) $0.34 0.78%

6.3 Casework (Break Room) 0.00%

Division 06 Total $0.68 1.56%

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

LINE NO. DESCRIPTION VALUE PERCENTAGE

7.1 Mineral Fiber Blanket lnsulation (Interior) $0.54 1.24%

7.2 Sound Attenuation Fire Blanket in rated walls $0.14 0.32%

7.3 Rigid (Polyisocyanurate) Insulation $0.04 0.09%

Division 07 Total $0.72 1.65%

DIVISION 08 - OPENINGS

LINE NO. DESCRIPTION VALUE PERCENTAGE

8.1 Steel Doors and Frames $0.03 0.07%

8.2 Prefinished Electric Insulated Overhead Coiling D $0.35 0.80%

8.3 Windows $0.39 0.89%

8.4 Door Hsrdware including door cylinders $0.21 0.48%

Division 08 Total $0.77 1.76%

DIVISION 09 - FINISHES

LINE NO. DESCRIPTION VALUE PERCENTAGE

9.1 Gypsum Board and mud, tape, corner beads $0.30 0.69%

9.2 Paints and Coatings $0.11 0.25%

9.3 Epoxy Flooring $0.06 0.14%

9.4 Acoustlcal Ceiling Tile and Grid $0.16 0.37%

9.5 Porcelain Tile $0.42 0.96%

9.6 Carpet Tiles $0.73 1.67%

9.7 Vinyl Composition Tile $0.24 0.55%

9.8 Rubber Base $0.11 0.25%

Division 09 Total $1.78 4.07%

DIVISION 10 - SPECIALTIES

LINE NO. DESCRIPTION VALUE PERCENTAGE

10.1 Toilet Accessories $0.15 0.34%

10.2 Interior Signage $0.86 1.97%

10.3 0.00%

Division 10 Total $1.01 2.31%

DIVISION 13 - SPECIAL CONSTRUCTION

LINE NO. DESCRIPTION VALUE PERCENTAGE

13.1 Steel Deck Vault $0.55 1.26%

13.2 Steel I-beam (Openings) $0.90 2.06%

13.3 Steel louvers (Mech Yard) $0.78 1.78%

13.4 Steel Gate (Generator) $0.58 1.33%

13.5 Steel Gate (Generator) $0.58 1.33%

13.6 Pre-engineered Metal Building $0.75 1.72%

13.7 Pre-engineered Metal Building Wall Roof panels $0.12 0.27%

13.8 Pre-engineered Metal Building Accessories $0.07 0.16%

Division 13 Total $4.14 9.47%

DIVISION 21 - FIRE SUPPRESSION

LINE NO. DESCRIPTION VALUE PERCENTAGE

21.1 Riser, Dbl Check Valves, Tamper & Flow Switches $0.02 0.05%

21.2 Wet Pipe Fire Sprinkler Piping $0.14 0.32%

21.3 Testing $0.78 1.78%

Division 21 Total $0.94 2.15%

DIVISION 22 - PLUMBING

LINE NO. DESCRIPTION VALUE PERCENTAGE

22.1 Plumbing (Fixtures) $0.09 0.21%

22.2 Plumbing Piping& Materials $0.73 1.67%

22.3 0.00%

Division 22 Total $0.82 1.88%

DIVISION 23 - HEATING, VENTILATION AND AIR CONDITIONING

LINE NO. DESCRIPTION VALUE PERCENTAGE

23.1 HVAC Air Handlers $0.11 0.25%

23.2 Acoustics Duct Silencers $0.18 0.41%

23.3 Exhaust & Supply Fans $0.35 0.80%

23.4 Boiler & Computer Room Units (CRAC) $0.58 1.33%

23.5 Variable Air Volume 0JAV) Boxes $0.74 1.69%

23.6 Fire Smoke Dampers & Louvers $0.35 0.80%

23.7 Testing, Adjusting & Balancing of HVAC Sys $0.11 0.25%

23.8 Thermal lnsulation for Mechanical Sys $0.35 0.80%

23.9 Duct Insulation $0.23 0.53%

23.10 Duct Work & Duct Work Accessories $0.50 1.14%

23.11 Diffusers, Registers & Grills $0.22 0.50%

23.12 HVAC Controls $0.70 1.60%

Division 23 Total $4.42 10.11%

DIVISION 26 - ELECTRICAL

LINE NO. DESCRIPTION VALUE PERCENTAGE

26.1 Electrical Conduit, Fillings, Boxes $0.24 0.55%

26.2 Electrical Wire & Cable $0.93 2.13%

26.3 Interior Distribution Systems $0.91 2.08%

26.4 Low Voltage SwitchQear $0.23 0.53%

26.5 Switchboards & Panel Boards $0.51 1.17%

26.6 Interior lighting $0.11 0.25%

26.7 Electrical Exterior Underground $0.75 1.72%

26.8 Electric Meter $0.07 0.16%

Division 26 Total $3.68 8.42%

DIVISION 27 - COMMUNICATIONS (IF REQUIRED AS A PART OF CONTRACT)

LINE NO. DESCRIPTION VALUE PERCENTAGE

27.1 Comm Piping, Fittings and Boxes $0.88 2.01%

27.2 Communications Wire $0.44 1.01%

27.3 Communications Cable Tray $0.80 1.83%

27.4 Testing $0.06 0.14%

Division 27 Total $2.18 4.99%

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

LINE NO. DESCRIPTION VALUE PERCENTAGE

28.1 Fire Alarm System Conduit & Fittings $0.17 0.39%

28.2 Fire Alarm Panel and Power Boosters $0.96 2.20%

28.3 Fire Alarm Programming & Testing $0.05 0.11%

28.4 MNS Conduit and Fittings $0.47 1.08%

28.5 MNS Panels $0.40 0.91%

28.6 FA/MNS Programming & Testing $0.29 0.66%

Division 28 Total $2.34 5.35%

DIVISION 31 - EARTHWORK

LINE NO. DESCRIPTION VALUE PERCENTAGE

31.1 Landscaping (Demo) $0.06 0.14%

31.2 Landscaping (Sod and Watering) $0.06 0.14%

31.3 Soii Compaction Test $0.15 0.34%

Division 31 Total $0.27 0.62%

DIVISION 32 - EXTERIOR IMPROVEMENTS

LINE NO. DESCRIPTION VALUE PERCENTAGE

32.1 Bollards $0.58 1.33%

32.2 Concrete Sidewalks $0.05 0.11%

32.3 Fog Seal (Parking Lot) $0.63 1.44%

32.4 Curb Stops (Parking Lot) $0.05 0.11%

32.5 Restnping (Parking Lot) $0.29 0.66%

Division 32 Total $1.60 3.66%

DIVISION 33 - UTILITIES

LINE NO. DESCRIPTION VALUE PERCENTAGE

33.1 Natural Gas $0.63 1.44%

33.2 Gas Meter $0.05 0.11%

33.3 0.00%

Division 33 Total $0.68 1.56%

CLOSE-OUT DOCUMENTS

LINE NO. DESCRIPTION VALUE PERCENTAGE

A As-Built Drawings 0.00% B Warranties C O&M Manuals (Paper Copy and CD/DVD's) 0.00% D Roof Inspection Reports 0.00%

Close-out Total $0.00 0.00%

BID TOTAL $43.72 100.00%