Attachment O - Utility and Service Impact Permit.pdf

PDF 661 KB Posted

Attached to
Y1DZ--600-17-108 Site Prep for SPS Sterilizers and Equipment, B126, 7th Floor
Solicitation number
36C26222B0009_1
Issued by

About this file

This document consists of a solicitation and related federal contract opportunity. The solicitation is for construction project 600-17-108 SPS Sterilizers and Equipment Site Prep at the VA Long Beach Healthcare System located in Long Beach, California. The work includes general construction, alterations, mechanical and electrical work, utility systems, necessary demolition and removal of existing structures, and other items required for completion. All work must be performed according to the solicitation terms, conditions, specifications, drawings, and applicable local and VA building codes. The related federal contract opportunity is solicitation number 36C26222B0009_1 for the same project. The description notes the requirement is for construction to perform site prep in a functioning hospital environment, with the contractor providing all labor, materials, tools, equipment, transportation, supervision, and training to accomplish the work.

View the file

Other files

File Type Posted
36C26222B0009_1 0006.pdf PDF
36C26222B0009_1 0005.pdf PDF
36C26222B0009_1 0004 V2.pdf PDF
S05 RFI Question Answer-Amendment 0004.pdf PDF
36C26222B0009_1 0003.pdf PDF
Amendment 3 RFIs_SOW_Specifications.pdf PDF
SPS Phasing-DRAFT.pdf PDF
Barrier-SalesBrochure.pdf PDF
barrier-STARC-Full-Product-Catalog-web.pdf PDF
8-24-2022 RFI Question Answer.pdf PDF
36C26222B0009_1 0002.pdf PDF
36C26222B0009_1 0001.pdf PDF
8-12-2022 Pre-bid conference sign in.pdf PDF
Attachment I - Contractor Laydown Areas.pdf PDF
Attachment R - Excavation Permit.pdf PDF
Attachment D - Drawings - Design Set Combined - June 8 2021.pdf PDF
Attachment M - VA Long Beach ACM Survey Report B126.pdf PDF
Attachment E - IMS SOP 07-013 Cable Installation Labeling and Testing.pdf PDF
Attachment H - Laydown Areas Request Form.docx DOCX document
Attachment L - VALBHS Utility and Service Impact Process.pdf PDF
Attachment C - Specifications - Final.pdf PDF
Attachment P - Safety Lockout Tagout of Equipment Electric Shop.pdf PDF
36C26222B0009_1.pdf PDF
Attachment A - Wage Determination Apr 28 2022.pdf PDF
Attachment N - VA Electric Shop Electrical Work Permit.pdf PDF
Attachment K - VALBMC Above The Ceiling and Penetration Permit.pdf PDF
Attachment G - ILSM Checklist Permit.pdf PDF
Attachment J - AHA Activity hazard analysis.pdf PDF
Attachment F - ILSM Map of Construction Areas.pdf PDF
Attachment B - SOW CONSTRUCTION June 8 2021.pdf PDF
Attachment S - Electric Work Permit.pdf PDF
Attachment Q - ILSM and Hot Work Permit.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA Long Beach Healthcare System Tibor Rubin Medical Center

ES Form 600-138G-1 USIP Revised - 09.17.20

Date:

GC Safety Manager:

Phone:

Start Date: Start Time:

End Date: End Time:

Oxygen Nitrous Oxide Air Vacuum

Feeder Panel (#_____) Riser Circuit (#_____)

Air Handler Exhaust Fan

Water Steam Natural Gas

Hot Water Cold Water Heating Sewer

Device Type: Device Identifier:

Sprinkler Fire Pump Jockey Pump

Smoke Heat Pull AV

Date:

Phone:

Map of impacted areas and control shutoff points included with this form

Narrative to include sequence to make utility safe and then bring back on line; SOP may be attached in lieu of a description.

Section C - Shutdown Process

Section B - Areas Effected by Shutdown

List the rooms effected by the shutdown (Highlight rooms that contain Critical Mission equipment or functions)

Section B - Date and Time of Impact - 21 day notice required (form submission to VA)

Describe the purpose of the utility and/or system impact.

VA COR/PM:

When impacting fire alarm system utilize Worksheet A if shutdown effects only an individual device or system reset to restore to normal. Complete Parts II and III of this form if multiple devices or entire fire zone is effected.

Project #

Plant:

Section A - Requestor Information

Section A - COR/PM Information

Medical Gas:

Electrical:

Section C - Systems (This section may be revised during Part II coordination)

Plumbing:

Fire Alarm:

Section D - Purpose of Shutdown

PART II (Filled out by COR, Supervisor, or PM in coordination with Integrated Project Team - GC, Engineering M&O, Safety, etc)

Work order(s) placed. WO #'s_______________________________________________________

UTILITY AND SERVICE IMPACT PERMIT

Fire Suppression:

Initiating Device:

Other:

Prime Contractor:

Contractor POC:

HVAC:

PART I (Filled out by Contractor or Requestor)

Utility and Service Impact Permit 1 of 2

ES Form 600-138G-1 USIP Revised - 09.17.20

UTILITY AND SERVICE IMPACT PERMIT

Lockout: Simple Complex Form Attached (Complex Only) _____N/A

Electric "Live Work": Yes No Form Attached

Hot Taps:

Hot Work Permit: Yes No Form Attached

Hazard Assessment: Yes No Form Attached

ILSM: Yes No Form Attached

VISN Notification: Yes No Form Attached

ICRA: Yes No Form Attached

Yes No Form Attached

Service POC :__________________________ Title: ________________ Signature:____________________________

Service POC :__________________________ Title: ________________ Signature:____________________________

Service POC :__________________________ Title: ________________ Signature:____________________________

Service POC :__________________________ Title: ________________ Signature:____________________________

Service POC :__________________________ Title: ________________ Signature:____________________________

Service POC :__________________________ Title: ________________ Signature:____________________________

Service POC :__________________________ Title: ________________ Signature:____________________________

Service POC :__________________________ Title: ________________ Signature:____________________________

Service POC :__________________________ Title: ________________ Signature:____________________________

Service POC :__________________________ Title: ________________ Signature:____________________________

Service POC :__________________________ Title: ________________ Signature:____________________________

Service POC :__________________________ Title: ________________ Signature:____________________________

Service POC :__________________________ Title: ________________ Signature:____________________________

COR/Supervisor/PM : Signature: Date:

Shop Requiring Shutdown: __________________. Supervisor approval below:

Print name: Signature: Date:

Shop Requiring Shutdown: __________________. Supervisor approval below:

Print name: Signature: Date:

Shop Requiring Shutdown: __________________. Supervisor approval below:

Print name: Signature: Date:

OSEMS Safety Manager: Signature: Date:

General Foreman: Signature: Date:

Owning Section Chief: Recommendation: Approval Disapproval

Signature: Date:

Chief, Engineering Service: Date:

Excavation & Trenching:

PART II Cont'd (Filled out by COR, Supervisor, or PM in coordination w/ Integrated Project Team - GC, Engineering M&O, Safety, etc)

Affected employees shall be notified both before the onset of and after completion of the outage.

Section D - Special Issues Required (Forms highlighted below need to be posted in the jobsite)

NOT AUTHORIZED

Section A - Approvals

PART III (Routed to Signatures per Section A)

Date: ______________

Date: ______________

Date: ______________

Date: ______________

Date: ______________

Construction Safety Committee Notified - Email: VHALONCSCNotifications@va.gov

General Notification (3 Days Out) - On schedule -Email: VHALONENGINEERINGACTIONITEM@va.gov

Section E - Service representative concurrence (Service POC will print name, job title, sign, and date)

Date: ______________

Date: ______________

Date: ______________

Date: ______________

Date: ______________

Date: ______________

Date: ______________

Date: ______________

Section B - Notification of Employees

Utility and Service Impact Permit 2 of 2

ES Form 600-138G-1 USIP Revised - 09.17.20

General Notes:

2. VA Facilitates all programing.

What type of device Fire Alarm: Device Type: Device Identifier:

Fire Suppression: Sprinkler Fire Pump Jockey Pump

Initiating Device: Smoke Heat Pull/AV

Electronics Contractor

Safety Office Other: .

Has Safety Service been informed? YES NO N/A

Describe the work that is being conducted:

Describe how this work will impact the fire alarm system:

Describe how long the fire alarm system will be affected- Time/date(s):

Additional Comments:

List the areas that will be affected - Building(s), Area(s), Floor(s)+1, etc.:

FIRE ALARM EQUIPMENT STATUS

REPORT OF ACTIONS

Who is putting the fire system into a trouble condition? (Name and Department/Section)

1. Fill out form to ensure an accurate account of the fire system is kept.

3. If fire alarm system is affected for more than 4 hours, ILSM and Fire Watch forms are needed. Final copies must be sent to the VA Electric Shop.

Worksheet A 1 of 1

Prime Contractor:
Contractor POC:
Start Date:
End Date:
Circuit:
Panel:
Device Identifier:
Smoke:
undefined:
Work orders placed WO s:
Text2:
Text3:
Text4:
Text5:
Text6:
Text7:
Text8:
Check Box9: Off
Check Box10: Off
Text11:
Check Box12: Off
Check Box13: Off
Check Box14: Off
Check Box15: Off
Check Box16: Off
Check Box17: Off
Check Box18: Off
Check Box19: Off
Check Box20: Off
Check Box21: Off
Check Box22: Off
Check Box23: Off
Check Box24: Off
Check Box25: Off
Check Box26: Off
Check Box27: Off
Check Box28: Off
Check Box29: Off
Check Box30: Off
Check Box31: Off
Check Box32: Off
Check Box33: Off
Check Box34: Off
Check Box35: Off
Service POC:
Service POC_2:
Service POC_3:
Service POC_4:
Service POC_5:
Service POC_6:
Service POC_7:
Service POC_8:
Service POC_9:
Service POC_10:
Service POC_11:
Service POC_12:
Service POC_13:
Title:
Title_2:
Title_3:
Title_4:
Title_5:
Title_6:
Title_7:
Title_8:
Title_9:
Title_10:
Title_11:
Title_12:
Title_13:
Shop Requiring Shutdown:
Shop Requiring Shutdown_2:
Shop Requiring Shutdown_3:
name1:
name2:
name3:
name4:
name5:
name:
Check Box2: Off
Check Box3: Off
Check Box4: Off
Check BoxFA: Off
Check BoxFA1: Off
Check BoxFA2: Off
Check BoxFA3: Off
Check BoxFA4: Off
Check BoxFA5: Off
Check Box5: Off
Check Box6: Off
Check Box7: Off
Check Box8: Off
Check Box11: Off
Check Box1: Off
Text14:
Text15:
Text16:
Text17:
Text18:
Text19:
Text20:
Text21:
Text22:
Text23:
Text24:
Text25:
Text26:
Text27:
Text28:
Text29:
Text30:
Text31:
Text32:
Text33:
Text34:
Check Box46: Off
Check Box48: Off
Check Box49: Off
Text1:
Text9:
Check Box36: Off
Check Box37: Off
Check Box38: Off
Check Box39: Off
Check Box40: Off
Check Box41: Off
Check Box42: Off
Check Box43: Off
Check Box44: Off
Check Box45: Off
Text46:
Check Box47: Off
Text50:
Text51:
Text52:
Text53:
Text54:
Text56:
Text191:
Text201:
Text211:

File details come from the government source that posted it. Updated .