Attachment G - ILSM Checklist Permit.pdf

PDF 371 KB Posted

Attached to
Y1DZ--600-17-108 Site Prep for SPS Sterilizers and Equipment, B126, 7th Floor
Solicitation number
36C26222B0009_1
Issued by

About this file

This document is an interim life safety measure checklist for a construction project at the VA Long Beach Healthcare System located at 5901 E 7th St, Long Beach, CA 90822. The project, numbered 600-17-108, is for site preparation work related to sterilizers and equipment in Building 126, 7th floor and exterior areas in front of the building. The checklist identifies life safety deficiencies that may result from the construction and rehabilitation work, and the corresponding interim measures that must be implemented to compensate for deficiencies that cannot immediately be corrected. Responsible parties must sign off on completion of inspections and tests of any temporary systems implemented.

View the file

Other files

File Type Posted
36C26222B0009_1 0006.pdf PDF
36C26222B0009_1 0005.pdf PDF
36C26222B0009_1 0004 V2.pdf PDF
S05 RFI Question Answer-Amendment 0004.pdf PDF
36C26222B0009_1 0003.pdf PDF
Amendment 3 RFIs_SOW_Specifications.pdf PDF
SPS Phasing-DRAFT.pdf PDF
Barrier-SalesBrochure.pdf PDF
barrier-STARC-Full-Product-Catalog-web.pdf PDF
8-24-2022 RFI Question Answer.pdf PDF
36C26222B0009_1 0002.pdf PDF
36C26222B0009_1 0001.pdf PDF
8-12-2022 Pre-bid conference sign in.pdf PDF
Attachment I - Contractor Laydown Areas.pdf PDF
Attachment R - Excavation Permit.pdf PDF
Attachment D - Drawings - Design Set Combined - June 8 2021.pdf PDF
Attachment M - VA Long Beach ACM Survey Report B126.pdf PDF
Attachment E - IMS SOP 07-013 Cable Installation Labeling and Testing.pdf PDF
Attachment H - Laydown Areas Request Form.docx DOCX document
Attachment L - VALBHS Utility and Service Impact Process.pdf PDF
Attachment C - Specifications - Final.pdf PDF
Attachment P - Safety Lockout Tagout of Equipment Electric Shop.pdf PDF
36C26222B0009_1.pdf PDF
Attachment A - Wage Determination Apr 28 2022.pdf PDF
Attachment O - Utility and Service Impact Permit.pdf PDF
Attachment N - VA Electric Shop Electrical Work Permit.pdf PDF
Attachment K - VALBMC Above The Ceiling and Penetration Permit.pdf PDF
Attachment J - AHA Activity hazard analysis.pdf PDF
Attachment F - ILSM Map of Construction Areas.pdf PDF
Attachment B - SOW CONSTRUCTION June 8 2021.pdf PDF
Attachment S - Electric Work Permit.pdf PDF
Attachment Q - ILSM and Hot Work Permit.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HSP 003S-04

Attachment A

VA LONG BEACH HEALTHCARE SYSTEM

INTERIM LIFE SAFETY MEASURE (ILSM) ASSESSMENT CHECKLIST

WHAT (brief description of deficiency): __ WHERE (areas affected):

Building(s) #: Floor(s): Room(s)#:

FIX (corrective action planned):

WORK (description to be performed): _ _ PERMITS (in conjunction with): Hot work Above the Ceiling & Penetration Energized Work Permit N/A TIMELINE Implementation Date/Time: Completion Date/Time:

Deficient Life Safety Conditions (as a result of any construction / rehabilitation) YES NO N/A If YES, implement ILSM & applicable PROVISIONS

A Existing EXITS are obstructed. 3, 5, 9, 10, 12, 13, 14

B Emergency responders’ access is limited or impaired. 3,4, 5, 9, 12, 14

C Disruption of FIRE ALARM SYSTEM is greater than 4 hours in a 24-hour period. 2, 4, 5, 6, 7, 9, 13, 14, 15

D Disruption of FIRE SUPPRESSION SYSTEM is greater than 10 hours in a 24-hour period. 1, 2, 6, 7, 9, 10, 12, 13, 14,15

E Temporary construction partitions are erected. 8, 9, 10, 12, 13, 14

F Fire and smoke compartments will not remain intact. 9, 10, 12

G Demolition in construction area that generates major amounts of debris 7, 8, 9, 10, 12

H Doors locked against egress. 3, 4, 8, 9, 11, 12

I Fire exit stairs discharge improperly. 3, 7, 8, 10, 13

J Greater than 150 feet travel distance to an approved exit. 8, 9, 13

K Lack of two remote exits. 7, 8, 9, 10, 12

L Nonconforming building construction material. 6, 8, 9, 10, 11, 13,15

M Improperly protected vertical openings 8, 9, 12

N Penetrations in fire/smoke barriers. 7, 8, 9, 10, 11

O Corridor walls do not extend to the structure 8, 9, 11, 12

P Major renovation of an occupied floor. 3, 4, 5, 6, 8, 9, 11, 12,15

Q Replacing or repairing fire alarm system (out-of-service). 3, 4, 7, 8, 9, 11

R Replacing or repairing sprinkler system (out-of-service) 2, 5, 6, 7, 9, 10, 13,15

S Significantly modifying smoke or barrier walls. 5, 8, 9, 11, 12

T Blocking off an approved exit 3, 4, 5, 9, 12, 13

U Disconnecting alarm devices 4, 5, 7, 8

V Other (specify):

PROVISIONS: To put in place, to effectively COMPENSATE Life Safety Deficiency that cannot be immediately corrected.

1. Ensure the Chief of OSEMS provides notification to LB Fire Department (or other emergency response group, e.g., VA Police), when a fire alarm (FA) or fire suppression (FS) system is out of service more than 4 hours (FA) or 10 hours (FS), in a 24-hour period: in an occupied building (notification is documented).

2. Initiate a fire watch when: a fire alarm system is out of service for more than 4 hours, w/in a 24-hour period, or a fire suppression system is out of service more than 10 hours in a 24-hour period in an occupied building. Utilize Attachment – B (VALBMC Fire Watch Action Log), to document Fire watch / times.

3. Ensure access and post signage identifying the location of alternative exits to everyone affected.

4. Ensure alternate access for emergency services.

5. Inspect exits in affected areas on a daily basis.

6. A temporary but equivalent fire alarm and detection systems shall be provided when a fire system is impaired. Ensure fire alarm and detection systems are in good working order.

7. Provide additional firefighting equipment. Write type and location of firefighting equipment:

8. Ensure temporary construction partitions are smoke tight or made of noncombustible or limited-combustible materials that will not contribute to the development and spread of fire.

9. Smoking is NOT allowed at VALBMC. Increase surveillance of: buildings, grounds, & equipment storage; w/ extra attention to construction areas, excavations, & temp field offices.

10. Enforce storage, housekeeping, and debris-removal practices that reduce the building’s flammable and combustible fire load to the lowest feasible level.

11. Provide additional training to those who work in the hospital on the use of firefighting equipment.

12. Conduct one additional fire drill (tour of duty) per quarter.

13. Conduct education to promote awareness of building deficiencies, construction hazards, and temporary measures implemented to maintain fire safety.

14. Train those who work in the affected areas and construction personnel to compensate for impaired structural or compartmental fire safety features.

15. Inspects and tests temporary systems monthly. Document completion dates of tests.

Signatures of Persons Implementing (sign/date):

1.Initiator/COR: 2. General Contractor Competent Person:

3. Project Section/Unit Supervisor: 4. Chief/M&O

5. APPROVED by (Chief of ENGINEERING): Date:

6. FINAL APPROVAL (Chief of OSEMS): Date:

HSP 003S-04

Revised January 2020

Text1: 600-17-108 AJP Site Prep for SPS Sterilizers and Equipment, Bldg 126, 7th Floor
Text2: SPS Areas and Exterior Areas in Front of Building 126
Text3: 126 & Exterior
Text4: 7th Floor
Text5:
Text6:
Text7:
Check Box8: Yes
Check Box9: Yes
Check Box10: Yes
Text11: TBD
Text12: TBD
Check Box13: Yes
Check Box14: Yes
Check Box15: No
Check Box16: No
Check Box17: Yes
Check Box18: No
Check Box19: Yes
Check Box20: No
Check Box21: No
Check Box22: Yes
Check Box23: Yes
Check Box24: No
Check Box25: No
Check Box26: Yes
Check Box27: Yes
Check Box28: Yes
Check Box29: Yes
Check Box30: Yes
Check Box31: No
Check Box32: No
Check Box33: No
Check Box34: No
Text14: Fire Extinguisher at the lay-down area
Text22:
Text23:
Text21:
2020-10-21T14:42:26-0700
Rodrigo Basler

File details come from the government source that posted it. Updated .