About this file
This document is a Position/Task Risk Designation Levels Matrix that establishes security clearance requirements for labor categories across eight defined tasks related to facility management and acquisition services.
All eight tasks—including Comprehensive Project Management Services (16.1), Comprehensive Interior Design/FF&E and Space Planning Services (16.2), Concept of Operations and Transition Planning (16.3), Acquisition Planning Services (16.4), Acquisition Packages Development (16.5), Activation Services and Post Occupancy Support (16.6), Staff Training and Orientation (16.7), and Warehousing and Warehousing Management Services (17.1)—are designated at the LOW sensitivity level, requiring only NACI (No Agency Check Investigation) clearance or equivalent. The document provides a sample list of 23 labor categories spanning project management, design, acquisition, warehousing, installation, and construction roles. All listed positions—including Project Director, Project Manager, Designer, Acquisition Project Manager, Warehouse Supervisor, Construction Manager, Engineer, and Trainer—are classified as LOW sensitivity positions with no positions requiring MODERATE (MBI) or HIGH (BI) clearance designations. This matrix serves as a staffing guidance document establishing minimum security clearance prerequisites for personnel assigned to the specified tasks.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
POSITION/TASK RISK DESIGNATION LEVELS MATIX
TASK TASK DESCRIPTION POSITION SENSITIVITY LEVEL
(LOW/NACI),
(MODERATE/MBI),
(HIGH/BI)
16.1 Comprehensive Project Management Services LOW
16.2 Comprehensive Interior Design, FF&E and Space
Planning Services
LOW
16.3 Concept of Operations (CONOPS), Transition Planning and
Project Staffing Planning
LOW
16.4 Acquisition Planning Services LOW
16.5 Acquisition Packages Development LOW
16.6 Activation Services and Post Occupancy Support LOW
16.7 Staff Training and Orientation LOW
17.1 Warehousing and Warehousing Management Services LOW
***Sample Labor Categories under the specific Tasks listed above
LABOR CATEGORY LOW
(NACI)
MODERATE
(MBI)
HIGH
(BI)
Administrative Assistant X
Database Developer X
Project Director X
Project Manager X
Quality Assurance Manager X
SharePoint Manager X
IT Specialist X
Scheduler X
StratCom Manager X
Transition Planner X
Designer X
Equipment Planner X
Acquisition Project Manager X
Acquisition Specialist X
Warehouse Laborer X
Warehouse Supervisor X
BMET X
Installer – FF&E X
Relocation Supervisor X
Trainer X
Truck Driver X
Construction Laborer X
Construction Manager X
Engineer X