This pre-solicitation notice seeks proposals for initial outfitting, transition, and activation services in support of a new outpatient clinic in Tyler, Texas. The Department of Veterans Affairs intends to solicit quotes for non-personal services including project management, interior design, furniture procurement, training, and biomedical support. The estimated period of performance is 18 months to help bring the new 53,267 square foot clinic into full operations by September 2021. This requirement is set aside only for verified service-disabled veteran-owned small businesses meeting the NAICS 541614 size standard. The anticipated solicitation will be posted on June 15th, 2020 with a closing date of July 10th, 2020 for the firm-fixed-price contract in support of the North Texas VA Health Care System's new Tyler clinic expansion.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Activity ID Activity Name Orig Dur
Rem Dur
Start Finish Total Float
VA Tyler - FVA Tyler - Field Use - 5.28.20 475 295 19-Sep-19 A 14-Jul-21 0
VA PROCESSVA PROCESSES 82 0 19-Sep-19 A 10-Jan-20 A
A1000 Inital Offer / Notice To Proceed 0 0 19-Sep-19 A A1010 VA Lease Award / Formal Notice to Proceed 12 0 19-Sep-19 A 04-Oct-19 A A1020 Project Protest Timeline 68 0 09-Oct-19 A 10-Jan-20 A
Site and ShSite and Shell Design Development 159 0 19-Sep-19 A 20-Apr-20 A
D1 Civil PackaD1 Civil Package 107 0 19-Sep-19 A 14-Feb-20 A A2100 Prepare Site Plan for P&Z Submission 7 0 19-Sep-19 A 27-Sep-19 A A2310 Submit Civil Layout to P&Z 0 0 30-Sep-19 A A2080 P&Z Meeting (To be Determined) 0 0 05-Nov-19 A A2090 City Council Meeting 0 0 14-Nov-19 A A2300 Develop D1 IFC Documents 10 0 30-Dec-19 A 10-Jan-20 A A2390 BLHI Review D1 IFC Documents 5 0 13-Jan-20 A 17-Jan-20 A A2395 Submit Civil Design for Pricing 15 0 20-Jan-20 A 07-Feb-20 A A2140 Receive Parking Lot Permit 20 0 20-Jan-20 A 14-Feb-20 A
D2 FoundationD2 Foundation, Tilt Wall / Steel Package 77 0 13-Jan-20 A 20-Apr-20 A A2110 Develop D2 90% Design Package 20 0 13-Jan-20 A 07-Feb-20 A A2350 BLHI Review D2 90% Design Package 3 0 10-Feb-20 A 12-Feb-20 A A2170 Submit D2 Design for Pricing 17 0 13-Feb-20 A 06-Mar-20 A A2360 Receive Pricing Document Comments from S 5 0 09-Mar-20 A 13-Mar-20 A A2130 Submit D2 90% Design Package for Permittin 30 0 18-Mar-20 A 20-Apr-20 A
D3 Building ShD3 Building Shell Package 77 0 13-Jan-20 A 20-Apr-20 A A2120 Develop D3 60% Shell Design Package 20 0 13-Jan-20 A 07-Feb-20 A A2320 BLHI Review D3 60% Design Package 5 0 10-Feb-20 A 14-Feb-20 A A2400 Issue D3 60% for Pricing 10 0 17-Feb-20 A 28-Feb-20 A A2330 Develop D3 90% Shell Design Package 22 0 17-Feb-20 A 17-Mar-20 A A2370 BLHI Review D3 90% Design Package 5 0 18-Mar-20 A 24-Mar-20 A A2160 Issue for Construction D2 and D3 Package 0 0 07-Apr-20 A A2180 Submit to the City for Permitting 30 0 18-Mar-20 A 20-Apr-20 A
VA Tenant BVA Tenant Build Out 218 46 01-Oct-19 A 30-Jul-20 249
A2190 Project Kick-off and Initial User Group Meeti 3 0 01-Oct-19 A 03-Oct-19 A A2200 Incorporate User Group Space Plan Comment 4 0 04-Oct-19 A 09-Oct-19 A A2203 Submit Floor Plan and Meeting Minutes to VA 2 0 13-Jan-20 A 14-Jan-20 A A2213 VA Review and Comment 5 0 15-Jan-20 A 21-Jan-20 A A2205 Incorporate User Group Space Plan Comme 8 0 22-Jan-20 A 31-Jan-20 A A2210 Submit TIA Design Package to VA 2 0 03-Feb-20 A 04-Feb-20 A A2220 VA Review and Comment on DID 1 Design P 10 0 05-Feb-20 A 18-Feb-20 A A2228 Page Review Comments 5 0 19-Feb-20 A 25-Feb-20 A A2225 DID 1 Meeting 3 0 26-Feb-20 A 28-Feb-20 A A2340 Lock Floor Plan 1 0 02-Mar-20 A 02-Mar-20 A A2295 Submit 40% TIA Package to City for Permitin 0 0 18-Mar-20 A A2230 Finalize TIA Construction Documents 30 0 03-Mar-20 A 17-Apr-20 A A2235 Submit 40% TIA Package to City for Permitin 30 0 23-Mar-20 A 20-Apr-20 A A2290 Submit TIA CD Package to VA 3 0 20-Apr-20 A 21-Apr-20 A A2250 Issue TIA Construction Documents out for B 17 0 17-Apr-20 A 11-May-20 A A2240 VA Review and Comment on Construction Do 15 0 22-Apr-20 A 12-May-20 A
0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 F March April May June July August S October N D January F March April May June July
2020 2021 e to Proceed ect Protest Timeline sion termined) elop D1 IFC Documents HI Review D1 IFC Documents
Submit Civil Design for Pricing Receive Parking Lot Permit
Develop D2 90% Design Package BLHI Review D2 90% Design Package
Submit D2 Design for Pricing Receive Pricing Document Comments from Subs
Submit D2 90% Design Package for Permitting
Develop D3 60% Shell Design Package BLHI Review D3 60% Design Package
Issue D3 60% for Pricing Develop D3 90% Shell Design Package
BLHI Review D3 90% Design Package Issue for Construction D2 and D3 Package
Submit to the City for Permitting
Group Meetings Plan Comments bmit Floor Plan and Meeting Minutes to VA A Review and Comment
Incorporate User Group Space Plan Comments Resumed Submit TIA Design Package to VA
VA Review and Comment on DID 1 Design Package Page Review Comments DID 1 Meeting Lock Floor Plan
Submit 40% TIA Package to City for Permiting with D2/D3 Package Finalize TIA Construction Documents Submit 40% TIA Package to City for Permiting with D2/D3 Package Submit TIA CD Package to VA
Issue TIA Construction Documents out for Bidding VA Review and Comment on Construction Documents
VA Tyler - Field Use - 5.28.20 Project ID: VA-T-13-02 Data Date: 28-May-20 Print Date: 01-Jun-20 07:44
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
TASK filter: All Activities
Rem Dur
Start Finish Total Float
A2245 Incorporate Comments from VA 5 0 18-May-20 A 28-May-20 6 A2260 Submit Preliminary TIA Budget to VA 7 1 12-May-20 A 28-May-20 0 A2380 Finalize TIA Pricing Based on VA Comments 15 8 27-May-20 A 08-Jun-20 31 A2410 Submit Final TIA Proposal to VA 7 7 09-Jun-20 17-Jun-20 31 A2280 Submit TI Design Package to City for Permit 40 40 28-May-20 22-Jul-20 6 A2270 Review/Negotiate TIA Bid Proposals with VA 45 45 29-May-20 30-Jul-20 0 A2420 VA Notice to Proceed 0 0 30-Jul-20 0
Major ProcuMajor Procurement Items 201 123 10-Feb-20 A 16-Nov-20 172
A1300 Buyout Sitework Package 20 0 10-Feb-20 A 06-Mar-20 A A1310 Buyout Structural Package (Steel and Tilt Up 25 0 18-Mar-20 A 06-May-20 A A1320 Buyout Shell and Core Package 25 25 09-Jun-20 13-Jul-20 38 A2050 Issue Contracts for TIA Contractors 20 20 31-Jul-20 27-Aug-20 0 A1350 Major MEP Equipment Submittals and Lead T 90 90 14-Jul-20 16-Nov-20 77
Submittal ProcSubmittal Process 73 35 06-Apr-20 A 15-Jul-20 21 A1510 Foundation Rebar Shop Drawings 10 0 06-Apr-20 A 17-Apr-20 A A1520 Tilt Panel Shop Drawings 15 0 06-Apr-20 A 23-Apr-20 A A1530 Foundation Rebar Shop Drawings Review 5 0 21-Apr-20 A 27-Apr-20 A A1500 Structural Steel Shop Drawings 25 0 06-Apr-20 A 05-May-20 A A1540 Structural Steel Submittal Review 10 0 05-May-20 A 27-May-20 A A1550 Tilt Panel Submittal Review 14 0 29-Apr-20 A 27-May-20 A A1870 Curtainwall/Punch Window Shop Drawings 25 25 28-May-20 A 01-Jul-20 21 A2850 Curtainwall/Punch Window Submittal Review 10 10 02-Jul-20 15-Jul-20 21
Material ProcuMaterial Procurement 55 60 28-May-20 A 19-Aug-20 21 A1610 Structural Steel Fabrication 25 25 28-May-20 A 01-Jul-20 11
A2860 Curtainwall/Punch Window Procurement 25 25 16-Jul-20 19-Aug-20 21
ConstructionConstruction 353 295 09-Mar-20 A 14-Jul-21 0
Major MilestonMajor Milestones 133 133 12-Aug-20 15-Feb-21 107 A2660 Structure Topped Out 0 0 12-Aug-20 240 A2670 Building Dry In 0 0 02-Sep-20 225 A2680 Permanent Power 0 0 15-Feb-21 107 A2690 Conditioned Air 0 0 15-Feb-21 107
SiteworkSitework 298 240 09-Mar-20 A 28-Apr-21 53 A1360 Site Mobilization 10 0 09-Mar-20 A 10-Mar-20 A A1370 Install Erosion Control and SWPPP 10 0 10-Mar-20 A 11-Mar-20 A A1380 Clearing and Grubbing 3 0 12-Mar-20 A 16-Mar-20 A A1385 Mass Grading 15 0 17-Mar-20 A 08-Apr-20 A A1390 Establish Building Pad 10 0 09-Apr-20 A 07-May-20 A A1400 Site Utilities, Primary Service Ductbank 20 0 22-Apr-20 A 08-May-20 A A1490 Install Utility Meter, RPZ 5 5 28-May-20 03-Jun-20 215 A1460 Fine Grade Site 5 5 30-Jul-20 05-Aug-20 175 A1450 Misc. Site Electrical and Pole Bases 5 5 06-Aug-20 12-Aug-20 175 A1410 Curb and Gutter 10 10 13-Aug-20 26-Aug-20 175 A1480 Concrete Paving 20 20 27-Aug-20 23-Sep-20 175 A1420 Hardscape/Sidewalks 13 13 12-Oct-20 28-Oct-20 163 A2040 Landscaping 15 15 29-Oct-20 18-Nov-20 163 A1430 Concrete Pavement Striping 5 5 22-Apr-21 28-Apr-21 53
0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 F March April May June July August S October N D January F March April May June July
2020 2021
Incorporate Comments from VA Submit Preliminary TIA Budget to VA
Finalize TIA Pricing Based on VA Comments Submit Final TIA Proposal to VA
Submit TI Design Package to City for Permitting Review/Negotiate TIA Bid Proposals with VA VA Notice to Proceed
Buyout Sitework Package Buyout Structural Package (Steel and Tilt Up Walls)
Buyout Shell and Core Package Issue Contracts for TIA Contractors
Major MEP Equipment Submittals and Lead Times
Foundation Rebar Shop Drawings Tilt Panel Shop Drawings Foundation Rebar Shop Drawings Review
Structural Steel Shop Drawings Structural Steel Submittal Review Tilt Panel Submittal Review
Curtainwall/Punch Window Shop Drawings Curtainwall/Punch Window Submittal Review
Structural Steel Fabrication
Curtainwall/Punch Window Procurement
Structure Topped Out Building Dry In
Permanent Power Conditioned Air
Site Mobilization Install Erosion Control and SWPPP
Clearing and Grubbing Mass Grading
Establish Building Pad Site Utilities, Primary Service Ductbank
Install Utility Meter, RPZ Fine Grade Site
Misc. Site Electrical and Pole Bases Curb and Gutter
Concrete Paving Hardscape/Sidewalks
Landscaping Concrete Pavement Str
VA Tyler - Field Use - 5.28.20 Project ID: VA-T-13-02 Data Date: 28-May-20 Print Date: 01-Jun-20 07:44
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Rem Dur
Start Finish Total Float
FoundationsFoundations 59 13 01-May-20 A 27-Jul-20 23 A1465 Mobilize Concrete Contractor 3 0 01-May-20 A 01-May-20 A A1475 Perimeter Foundations South/East 7 0 04-May-20 A 07-May-20 A A1485 Perimeter Foundations North/West 8 0 08-May-20 A 12-May-20 A A1495 Spread Footings Sequence A (approx. 24 ea) 9 0 12-May-20 A 15-May-20 A A1505 Spread Footings Sequence B (approx. 20 ea) 7 0 15-May-20 A 19-May-20 A A1595 Entry Canopy Foundations (10 ea) 5 5 09-Jul-20 15-Jul-20 11 A1605 Loading Dock Foundations/Ret. Wall 8 8 16-Jul-20 27-Jul-20 23
Tilt Panels/SOTilt Panels/SOG 93 93 19-May-20 A 05-Oct-20 0 A1515 Framing Casting Beds South/East 6 0 19-May-20 A 22-May-20 A A1525 Framing Casting Beds North/West 7 2 26-May-20 A 29-May-20 11 A1635 Frame/Pour Tilt Panels South/East 6 6 28-May-20 A 08-Jun-20 11 A1645 Frame/Pour Tilt Panels North/West 5 5 09-Jun-20 15-Jun-20 11 A1655 Panel Cure Time South/East 7 7 09-Jun-20 17-Jun-20 13 A1665 Panel Cure Time North/West 7 7 16-Jun-20 24-Jun-20 12 A1575 Erect Tilt Panels South/East 4 4 22-Jun-20 25-Jun-20 11 A1585 Erect Tilt Panels North/West 3 3 26-Jun-20 30-Jun-20 11 A1615 Demo/Haul Off Casting Beds South/East 3 3 01-Jul-20 03-Jul-20 11 A1625 Demo/Haul Off Casting Beds North/West 3 3 06-Jul-20 08-Jul-20 11 A1440 MPE Underground R/I 18 18 28-Aug-20 22-Sep-20 0 A1470 Prep and Poure SOG 9 9 23-Sep-20 05-Oct-20 0
Structural SteeStructural Steel/Deck 42 42 16-Jun-20 12-Aug-20 11 A1750 Mobilize Structural Steel Contractor 4 4 16-Jun-20 19-Jun-20 11 A2150 Erect Structural Steel Seq. A 10 10 02-Jul-20 15-Jul-20 11 A2430 Erect Structural Steel Seq. B 10 10 16-Jul-20 29-Jul-20 11 A2440 Joist and Decking Seq. A 5 5 30-Jul-20 05-Aug-20 11 A2450 Joist and Decking Seq. B 5 5 06-Aug-20 12-Aug-20 11
Building SkinBuilding Skin 197 197 30-Jul-20 30-Apr-21 53 A1580 Facade Masonry North Elevation (Sticky Ston 5 5 30-Jul-20 05-Aug-20 26 A2460 Facade Masonry East Elevation (Sticky Stone) 5 5 06-Aug-20 12-Aug-20 26 A2470 Facade Masonry South Elevations (Sticky Sto 5 5 13-Aug-20 19-Aug-20 230 A2540 Overhead Doors 5 5 13-Aug-20 19-Aug-20 58 A2480 Facade Masonry West Elevation (Sticky Stone) 5 5 20-Aug-20 26-Aug-20 230 A1590 Curtainwall/Punch Windows North Elevation 9 9 20-Aug-20 01-Sep-20 21 A1560 Roofing 15 15 13-Aug-20 02-Sep-20 48 A2490 Curtainwall/Punch Windows East Elevation 5 5 02-Sep-20 08-Sep-20 21 A1570 Prefinished Metal Coping 5 5 03-Sep-20 09-Sep-20 220 A2500 Curtainwall/Punch Windows South Elevation 5 5 09-Sep-20 15-Sep-20 21 A2510 Curtainwall/Punch Windows West Elevation 8 8 16-Sep-20 25-Sep-20 21 A2550 Sunshades 5 5 28-Sep-20 02-Oct-20 203 A1600 Dry-in 0 0 09-Oct-20 21 A2520 Clerestory Windows 10 10 28-Sep-20 09-Oct-20 21 A2530 Metal Liner Panels 5 5 12-Oct-20 16-Oct-20 193 A2560 Prefinished Aluminum Canopies 5 5 22-Apr-21 28-Apr-21 55 A2570 Composite Column Wraps and Canopy Panels 7 7 22-Apr-21 30-Apr-21 53
Build-OutBuild-Out 157 157 06-Oct-20 12-May-21 0 Area D/CArea D/C 122 122 06-Oct-20 24-Mar-21 20
0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 F March April May June July August S October N D January F March April May June July
2020 2021
Mobilize Concrete Contractor Perimeter Foundations South/East
Perimeter Foundations North/West Spread Footings Sequence A (approx. 24 ea) Spread Footings Sequence B (approx. 20 ea)
Entry Canopy Foundations (10 ea) Loading Dock Foundations/Ret. Wall
Framing Casting Beds South/East Framing Casting Beds North/West
Frame/Pour Tilt Panels South/East Frame/Pour Tilt Panels North/West Panel Cure Time South/East
Panel Cure Time North/West Erect Tilt Panels South/East
Erect Tilt Panels North/West Demo/Haul Off Casting Beds South/East
Demo/Haul Off Casting Beds North/West MPE Underground R/I
Prep and Poure SOG
Mobilize Structural Steel Contractor Erect Structural Steel Seq. A
Erect Structural Steel Seq. B Joist and Decking Seq. A
Joist and Decking Seq. B
Facade Masonry North Elevation (Sticky Stone) Facade Masonry East Elevation (Sticky Stone)
Facade Masonry South Elevations (Sticky Stone) Overhead Doors
Facade Masonry West Elevation (Sticky Stone) Curtainwall/Punch Windows North Elevation Roofing
Curtainwall/Punch Windows East Elevation Prefinished Metal Coping
Curtainwall/Punch Windows South Elevation Curtainwall/Punch Windows West Elevation
Sunshades Dry-in Clerestory Windows
Metal Liner Panels Prefinished Aluminum C Composite Column Wr
VA Tyler - Field Use - 5.28.20 Project ID: VA-T-13-02 Data Date: 28-May-20 Print Date: 01-Jun-20 07:44
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Rem Dur
Start Finish Total Float
A1630 Interior Framing 18 18 13-Oct-20 05-Nov-20 0 A1620 Mechanical Overhead R/I 30 30 06-Oct-20 16-Nov-20 0 A2580 Electrical Overhead R/I 25 25 13-Oct-20 16-Nov-20 20 A2590 Plumbing Overhead R/I 25 25 13-Oct-20 16-Nov-20 20 A2600 Fire Sprinkler Overhead R/I 25 25 13-Oct-20 16-Nov-20 20 A1650 LV Cabeling 10 10 06-Nov-20 19-Nov-20 7 A2610 In Wall MEP R/I 20 20 27-Oct-20 23-Nov-20 0 A2650 Rough Carpentry and Blocking 10 10 10-Nov-20 23-Nov-20 15 A1640 Hang and Finish Sheetrock 25 25 10-Nov-20 14-Dec-20 0 A2700 Set Mechanical and Electrical Equipment 15 15 24-Nov-20 14-Dec-20 17 A2630 Prime and First Coat 20 20 24-Nov-20 21-Dec-20 10 A1660 Acoustical Ceiling Grid 12 12 08-Dec-20 23-Dec-20 10 A1730 Floor and Wall Tile - Bathrooms, Halls etc. 20 20 01-Dec-20 28-Dec-20 35 A1670 Casework 15 15 22-Dec-20 11-Jan-21 10 A2640 MEPF Trim Out 25 25 15-Dec-20 18-Jan-21 19 A2800 Toilet Partitions and Accessories 15 15 29-Dec-20 18-Jan-21 35 A1680 Flooring - LVT, WSF etc. 20 20 29-Dec-20 25-Jan-21 20 A1690 Plumbing Fixtures 15 15 12-Jan-21 01-Feb-21 25 A1720 Drop Tile 15 15 19-Jan-21 08-Feb-21 27 A1700 Doors, Hardware, Accessories & Specialties 10 10 26-Jan-21 08-Feb-21 20 A1830 Interior Signage 5 5 11-Feb-21 17-Feb-21 20 A1710 Final Paint 8 8 09-Feb-21 18-Feb-21 20 A2750 Construction Clean 5 5 18-Feb-21 24-Feb-21 20 A2760 Internal QC Punchlist 5 5 25-Feb-21 03-Mar-21 20 A1740 Final Punch & Work-Off 15 15 04-Mar-21 24-Mar-21 20
Area A/BArea A/B 127 127 17-Nov-20 12-May-21 0 A1790 LV Cabeling 10 10 20-Nov-20 03-Dec-20 7 A1770 Interior Framing 15 15 24-Nov-20 14-Dec-20 0 A1760 Mechanical Overhead R/I 20 20 17-Nov-20 14-Dec-20 0 A2060 Electrical Overhead R/I 20 20 17-Nov-20 14-Dec-20 20 A2070 Plumbing Overhead R/I 20 20 17-Nov-20 14-Dec-20 20 A2710 Fire Sprinkler Overhead R/I 20 20 17-Nov-20 14-Dec-20 20 A2620 In Wall MEP R/I 20 20 01-Dec-20 28-Dec-20 0 A2720 Rough Carpentry and Blocking 10 10 15-Dec-20 28-Dec-20 10 A1780 Hang and Finish Sheetrock 20 20 15-Dec-20 11-Jan-21 0 A2730 Prime and First Coat 15 15 29-Dec-20 18-Jan-21 30 A1800 Acoustical Ceiling Grid 12 12 12-Jan-21 27-Jan-21 0 A2810 Floor/Wall Tile - Bathrooms, Lobby etc. 20 20 05-Jan-21 01-Feb-21 30 A2740 MEPF Trim Out 20 20 19-Jan-21 15-Feb-21 19 A2820 Toilet Partitions and Accessories 10 10 02-Feb-21 15-Feb-21 30 A1810 Casework 30 30 26-Jan-21 08-Mar-21 0 A1860 Drop Tile 18 18 16-Feb-21 11-Mar-21 19 A1820 Flooring - Terrazzo. LVT 30 30 02-Feb-21 15-Mar-21 0 A1840 Doors, Hardware, Accessories & Specialties 10 10 16-Mar-21 29-Mar-21 0 A2830 Plumbing Fixtures 15 15 09-Mar-21 29-Mar-21 7 A2840 Rubber Sheet Flooring 10 10 16-Mar-21 29-Mar-21 0 A2780 Construction Clean 5 5 30-Mar-21 05-Apr-21 2
0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 F March April May June July August S October N D January F March April May June July
2020 2021
Interior Framing Mechanical Overhead R/I Electrical Overhead R/I Plumbing Overhead R/I Fire Sprinkler Overhead R/I LV Cabeling In Wall MEP R/I Rough Carpentry and Blocking
Hang and Finish Sheetrock Set Mechanical and Electrical Equipment
Prime and First Coat Acoustical Ceiling Grid
Floor and Wall Tile - Bathrooms, Halls etc.
Casework
MEPF Trim Out Toilet Partitions and Accessories
Flooring - LVT, WSF etc.
Plumbing Fixtures
Drop Tile Doors, Hardware, Accessories & Specialties
Interior Signage Final Paint
Construction Clean Internal QC Punchlist
Final Punch & Work-Off
LV Cabeling Interior Framing Mechanical Overhead R/I Electrical Overhead R/I Plumbing Overhead R/I Fire Sprinkler Overhead R/I
In Wall MEP R/I Rough Carpentry and Blocking
Hang and Finish Sheetrock Prime and First Coat
Acoustical Ceiling Grid Floor/Wall Tile - Bathrooms, Lobby etc.
MEPF Trim Out Toilet Partitions and Accessories
Casework Drop Tile Flooring - Terrazzo. LVT
Doors, Hardware, Accessories Plumbing Fixtures Rubber Sheet Flooring
Construction Clean
VA Tyler - Field Use - 5.28.20 Project ID: VA-T-13-02 Data Date: 28-May-20 Print Date: 01-Jun-20 07:44
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Rem Dur
Start Finish Total Float
A2770 Interior Signage 5 5 01-Apr-21 07-Apr-21 0 A1850 Final Paint 8 8 30-Mar-21 08-Apr-21 0 A2790 Internal QC Punchlist 10 10 08-Apr-21 21-Apr-21 0 A1880 Final Punch & Work-Off 15 15 22-Apr-21 12-May-21 0
EquipmentEquipment 132 132 17-Nov-20 19-May-21 40 A1890 Set Rooftop Equipment 15 15 17-Nov-20 07-Dec-20 77 A1900 Install MEP Equipment 15 15 08-Dec-20 28-Dec-20 77 A1920 Permanent Power 0 0 15-Feb-21 42 A1910 Circulate Conditioned Air 0 0 15-Feb-21 42 A1940 Major Clinical Equipment (Exam Lights & Boo 20 20 16-Feb-21 15-Mar-21 87 A1970 Clinical Equipment 10 10 30-Mar-21 12-Apr-21 67 A1950 Equipment with Service Connections 20 20 16-Mar-21 12-Apr-21 67 A1960 Architecturally Insignificant Equipment 15 15 30-Mar-21 19-Apr-21 62 A1930 Radiology Equipment 20 20 22-Apr-21 19-May-21 40
InspectionsInspections 107 107 16-Feb-21 14-Jul-21 0 A1980 Test & Balance 25 25 16-Feb-21 22-Mar-21 42 A1990 Commissioning 20 20 23-Mar-21 19-Apr-21 42 A2020 VA Occupancy 0 0 16-Jun-21 20 A2010 Substantial Completion & Certifcate of Occup 0 0 16-Jun-21 0 A2000 Final Certifications & Acceptance 25 25 13-May-21 16-Jun-21 0 A2030 Final Completion 20 20 17-Jun-21 14-Jul-21 0
0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 F March April May June July August S October N D January F March April May June July
2020 2021
Interior Signage Final Paint
Internal QC Punchlist Final Punch & Work
Set Rooftop Equipment Install MEP Equipment
Permanent Power Circulate Conditioned Air
Major Clinical Equipment (Exam Lig Clinical Equipment Equipment with Service Con
Architecturally Insignifica Radiology Equipm
Test & Balance Commissioning
VA Occup Substanti Final Cert
Fi
VA Tyler - Field Use - 5.28.20 Project ID: VA-T-13-02 Data Date: 28-May-20 Print Date: 01-Jun-20 07:44
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work