Attachment_J6_TechSpecs.docx

DOCX document 143 KB Posted

Attached to
Nez Perce-Clearwater NFs - Crooked River Valley Restoration Phase 4
Solicitation number
12363N21R4001
Issued by

About this file

This federal contract solicitation seeks restoration services along the Crooked River Valley in Idaho. Key work includes removing a temporary bridge, grading tailings piles and a levee/haul road to complete floodplain construction and fill a temporary bypass channel. Additional efforts involve constructing floodplain, installing instream habitat features and riparian plants. Material may be hauled from stockpiled locations. The solicitation is issued by the USDA Forest Service Nez Perce-Clearwater National Forests for Phase 4 of an ongoing restoration project addressing impacts from historical dredge mining. Responses are due based on the listed solicitation number.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USDA – Forest service and NEz Perce Tribe Crooked River Valley Rehabilitation Technical Specifications Phase 4 and Planting

Last Revision 4/30/2021

LIST OF TECHNICAL SPECIFICATIONS

Section 01200Measurement and Payment
Section 01201Pay Items
Section 01300Submittals
Section 01400Construction Staking
Section 01505Mobilization/Demobilization
Section 01560Environmental Controls
Section 01600Protection of Materials
Section 01640Government Supplied Materials
Section 01720As-Built Records
Section 02140Water Management
Section 02930Vegetative Fill
Section 05000Large Wood Structures- Type 1
Section 05100Large Wood Structures- Type 2
Section 05010Microtopography
Section 06000Bridge Removal and Haul
Section B 200Plant Delivery from Nursery
Section B 300Planting in Bank Stability Structures
Section B 400Trench Planting
Section B 500Single Hole Planting, 8 Gallon

i

SECTION 1200

MEASUREMENT AND PAYMENT

Measurement of Work Methods of Measurement One of the following methods of measurement for determining final payment is DESIGNATED IN THE SCHEDULE OF ITEMS for each PAY ITEM (Section 01201):

a) Actual Quantities (AQ).

b) Design Quantities (DQ).

c) Lump Sum Quantities (LSQ).

Measurement Terms and Definitions

1. Acre (AC). 43,560 square feet. Make longitudinal and transverse measurements for area computations horizontally unless specified on the ground surface. Do not make deductions from the area computation for individual fixtures having an area of 500 square feet or less.

2. Actual Quantities (AQ). These quantities are determined from measurements of completed work.

3. Design quantity (DQ). The quantity to be paid is the quantity shown in the bid schedule. The design quantity will be adjusted for authorized changes that affect the quantity or for errors made in computing this quantity. If there is evidence that a quantity specified as a design quantity is incorrect, submit calculations, drawings, or other evidence indicating why the quantity is in error and request, in writing, that the quantity be adjusted. Design quantities will be adjusted only when there are errors in the original design of 15% or more. Changes in the number of units DESIGNATED IN THE SCHEDULE OF ITEMS may be authorized under any of the following conditions:

a) Changes in the work authorized by the Contracting Officer.

b) A determination by the Contracting Officer that errors exist in the original design that cause a PAY ITEM quantity to change by 15 percent or more.

c) A written request submitted to the Contracting Officer showing evidence of errors in the original design that cause the quantity of a PAY ITEM to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is in error.

4. Cubic yard (CY).

a) Cubic yard in place. Measure solid volumes by a method approved by the Contracting Officer or by the average end area method as follows:

(a) Take cross-sections of the original ground and use with design or staked templates or take other comparable measurements to determine the end areas. Do not measure work outside of the established lines or slopes.

(b) If any portion of the work is acceptable but is not completed to the established lines and slopes, retake cross-sections or comparable measurements of that portion of the work. Deduct any quantity outside the designated or staked limits. Use these measurements to calculate new end areas.

(c) Compute the quantity using the average end areas multiplied by the horizontal distance along a centerline or reference lines between the end areas. Deduct any quantity outside the designed or staked limits.

b) Cubic yard in the hauling vehicle. Measure the cubic yard volume in the hauling vehicle using three-dimensional measurements at the point of delivery. Use vehicles bearing a legible identification mark with the body shaped so the actual contents may be readily and accurately determined. Before use, mutually agree in writing on the volume of material to be hauled by each vehicle. Vehicles carrying less than the agreed volume may be rejected or accepted at the reduced volume.

Level selected loads. If leveling reveals the vehicle was hauling less than the approved volume, reduce the quantity of all material received since the last leveled load by the same ratio as the current leveled load volume is to the agreed volume. Payment will not be made for material in excess of the agreed volume.

Material measured in the hauling vehicle may be weighed and converted to cubic yards for payment purposes if the conversion factors are mutually agreed to in writing.

c) Cubic yard in the structure. Measure according to the lines of the structure as shown on the plans except as altered by the Contracting Officer to fit field conditions. Make no deduction for the volume occupied by reinforcing steel, anchors, weep holes, piling, or pipes less than 8 inches in diameter.

d) Cubic yard by metering. Use an approved metering system.

5. Each (EA). One entire unit. The quantity is the actual number of units completed and accepted.

6. Hour. Measure the actual number of hours ordered by the Contracting Officer and performed by the contractor.

7. Linear foot. As applicable, measure the work along its length from end-to-end; parallel to the base or foundation; along the top; along the front face; or along the invert. Do not measure overlaps.

8. Mile. 5,280 linear feet. Measure horizontally along the centerline of each roadway, approach road, or ramp.

9. Lump sum quantity (LSQ). These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. Do not measure directly. The bid amount is complete payment for all work described.

10. Station. 100 linear feet. Measure horizontally along centerline or reference line of each roadway, approach road, or ramp.

Weighing Procedures and Devices

Batch masses may be acceptable for determination of pay quantities when an approved automatic weighing, cycling, and monitoring system is included as part of the batching equipment.

When a weighing device is determined to indicate less than true mass, no additional payment will be made for material previously weighed and recorded. When a weighing device is determined to indicate more than true mass, all material received after the last previously correct weighing accuracy test will be reduced by the percentage of error in excess of 0.5 percent.

When material is proportioned or measured and paid for by mass, provide one of the following:

(a) Commercial weighing system. Use permanently-installed and certified commercial scales.

(b) Invoices. If bulk material is shipped by truck or rail and is not passed through a mixing plant, furnish a supplier's invoice with net mass or volume converted to mass. Periodic check weighing may be required.

Receiving Procedures

When the method of measurement requires weighing or volume measurement in the hauling vehicle, furnish a person to direct the spreading and distribution of material and to record the location and placement of the material on the project. During the placement, maintain a record of each delivery and document it in an acceptable manner. Include the following information as applicable:

(a) Project identification;

(b) Contract pay item number and description;

(c) Location where placed;

(d) Date;

(e) Load number;

(f) Truck identification;

(g) Time of arrival;

(h) Mass or volume; and

(i) Spread person's signature.

Use an approved format for the delivery record(s). Furnish the original record(s) and a written certification of the delivery of the material at the end of each shift.

Scope of Payment

Payment for all contract work is provided, either directly or indirectly, under the pay items shown in the bid schedule.

1. Direct payment. Payment is provided directly under a pay item shown in the bid schedule when one of the following applies:

a. The work is measured in the Measurement Subsection of the Section ordering the work, and the bid schedule contains a pay item for the work from the Section ordering the work.

b. The Measurement Subsection, of the Section ordering the work, references another Section for measuring the work and the bid schedule contains a pay item for the work from the referenced Section.

2. Indirect payment. Work for which direct payment is not provided is a subsidiary obligation of the Contractor. Payment for such work is indirectly included under other pay items shown in the bid schedule. This includes instances when the Section ordering the work references another Section for performing the work and the work is not referenced in the Measurement Subsection of the Section ordering the work.

Compensation provided by the pay items included in the contract bid schedule is full payment for performing all contract work in a complete and acceptable manner. All risk, loss, damage, or expense arising out of the nature or prosecution of the work is included in the compensation provided by the contract pay items.

Work measured and paid for under one pay item will not be paid for under any other pay item.

The quantities shown in the bid schedule (Section 01201) are approximate unless designated as a design quantity. Limit pay quantities to the quantities staked, ordered, or otherwise authorized before performing the work. Payment will be made for the actual quantities of work performed and accepted or material furnished according to the contract. No payment will be made for work performed in excess of that staked, ordered, or otherwise authorized.

SECTION 01201

PAY ITEMS

General Individual pay items will be paid in accordance with Section 01200 and Section 01201. This section will outline the individual pay items and requirements of each.

SCHEUDLE OF ITEMS

PAY ITEM
DESCRIPTION
METH. MEAS.
PAY UNIT
EST. QTY
UNIT PRICE
TOTAL PRICE

Crooked River Valley Rehabilitation Phase 3

A1
Mobilization and Demobilization
LSQ
LS
1
XXXX

A2

Water Management and Environmental Controls
LSQ
LS
1
XXXX
A3
Survey and Staking
LSQ
LS
1
XXXX
A4
Bridge Removal and Haul
LSQ
LS
1
A5
Large Wood Structure Type 1
AQ
EA
2
A6
Large Wood Structure Type 2
AQ
LF
190
A7
Earthwork- Regrade Levee/Road and Temp Bypass Channel
DQ
CY
37,420
A8
Earthwork- Import Fill and Regrade Temp Bypass Channel
AQ
CY
19,150
A9
Riffle Construction
AQ
LF
150
A10
Floodplain Micro-topography
AQ
ACRES
16.3
A11
Equipment Rental Rate for Excavator and Operator
AQ
HOURS
10
A12
Equipment Rental Rate for Dump Truck and Operator
AQ
HOURS
10
A13
Equipment Rental Rate for Bulldozer and Operator

AQ

HOURS

A14 Optional

Earthwork -Construct High Terrace South End of Project Area
AQ
CY
400
B1
Mobilization and Demobilization
LSQ
LS
1
XXXX

B2

Plant Delivery (from Nursery to Project Site)
LSQ
LS
1
XXXX
B3
Trench Planting along Main/ Side Channel 2 gal, 5 gal
AQ
LF
1,485
B4
Single Hole Planting in Floodplain Micro-topography, 2 gal
AQ
EA
3,851
B5
Single Hole Planting in Floodplain Micro-topography, 8 gal
AQ
EA
278
B6
Water Individual Plants
LSQ
LS
ALL
B7
Equipment Rental Rate for Mini Excavator
AQ
HOURS
10
B8
Equipment Rental Rate for Compact Loader

AQ

HOURS

Designated Method of Measurement:

DQ – Designed Quantities; AQ - Actual Quantities, LSQ - Lump Sum Quantities;

LF – Linear Feet

SCHEUDLE OF ITEMS:

PHASE 3

Item A1 Mobilization and Demobilization Payment for Bid Item A1- Mobilization and Demobilization will be based on the lump sum price bid as shown on the Bid Form. Fifty percent (50%) payment for this Bid Item will be allowed once the Contractor fully mobilizes to the Site and obtains approval on all submittals required before starting construction. Full Payment for this item will be allowed once the Contractor completes the specified Work and fully demobilizes equipment and materials from the Site. The lump sum bid price for this item must not exceed ten percent (10%) of the total bid price. Mobilization and Demobilization applies to Section 01300, 01505.

Incidental to Item The contractor shall complete all work necessary to access the project area.

The Contractor shall complete maintenance of County Road 233 commensurate with use.

Item A2 Water Management and Environmental Controls Payment for Bid Item A2- will be based on the lump sum price bid as shown on the Bid Form. This Work includes but is not limited to, modification to the Storm Water and Pollution Prevention Plan, controlling turbidity, installing coffer dams or other structures to control turbidity during instream work, installing erosion control devices, and meeting turbidity standards throughout the project. Erosion control devices and pumps, as specified in Section 01560, shall be onsite prior to Work commencing. At minimum, 1 six-inch pumps on site during the project. These controls shall remain on site for the duration of the project. The bid item amount is complete payment for all work described in the contract in Specification 01560 and necessary to complete the work for this pay item.

Item A3 Survey and Staking Payment for Bid Item A3 will be based on the lump sum price bid as shown on the Bid Form. This work includes, but is not limited to, machine control operations, and staking the floodplain elevations every 200 feet for the length of the bypass channel, staking the beginning and end of the riffle section, and the new channel at the diversion structure. The Government will provide survey control and grading surfaces for equipment with GPS machine control capability for the north end 4 acre work area, and the new floodplain along the extent of the levee. The Contractor shall work with the Government to field fit the connection between the existing channel and new channel and the floodplain features, including the depressions, swales, and high terraces, if constructed. The Contractor shall set up the base station, load surface files, and ensure proper calibration of machine controls. The contractor shall verify, throughout the project, that the machine controls are accurate and within project tolerance. The bid item amount is complete payment for all work described in the contract in Specification 01400 and necessary to complete the work for this pay item.

Item A4 Bridge Removal and Haul

Payment for Bid Item A4 will be based on the lump sum price bid as shown in the Bid Form. This work includes, but is not limited to the dismantling and hauling of the Big R Steel Girder Bridge, the Eco block abutments and all associated fill material and rock. The Big R Steel Girder Bridge, rail, decking, bearing beam and hardware shall be hauled to the Forest Service storage yard in Grangeville, Idaho. The concrete Eco blocks and substructure hardware will become the property of the Contractor to dispose of, and the rock and fill material shall be spread as fill for the bypass channel. The Big R Steel Girder Bridge plans have been included in the RFP as an Appendix. The bid item amount is complete payment for all work described in the contract in Specification 0600 and necessary to complete the work for this pay item.

Item A5 Large Wood Structure Type 1

The accepted quantities will be paid at the contract price per unit of measurement for the pay items listed in the bid schedule. This work includes all equipment, materials, and labor to install Large Wood Structure Type 1, as per Drawing Sheet 7.0. Payment will be full compensation for the Large Wood Structure construction as prescribed in Section 05000, using backfill material as specified in Section 01640. These structures will utilize tree material salvaged from within the Project Limits or from stockpile areas along the floodplain.

Item A6 Large Wood Structure Type 2 The accepted quantities will be paid at the contract price per unit of measurement for the pay items listed in the bid schedule. This work includes all equipment, materials, and labor to install Large Wood Structure Type 2, as per Drawing Sheet 7.1. Materials for Large Wood Structure Type 2 are stockpiled on site. Excess material from the excavations shall be hauled and stockpiled along the levee road. Payment will be full compensation for the work prescribed in 05100.

Incidental to Item If unsuitable material is found in the excavations, this material shall be mixed into the adjacent floodplain and suitable material borrowed from the floodplain shall be excavated and used to backfill the structures.

Item A7 Earthwork- Regrade Levee/Road and Temp Bypass Channel The accepted quantities will be paid at the contract price per unit of measurement for the pay items listed in the bid schedule. This work includes all equipment, materials, and labor to regrade the tailings piles within the floodplain and complete floodplain grading including construction of the new river channel depressions and swales, as per Drawing Sheet Numbers 5.0, 5.1, and 5.2. It is anticipated that floodplain fill will be available within the construction limits and at the south staging area. Terraces higher than adjacent floodplain may be ordered by the CO as noted in the Appendix. If floodplain material is short, larger depressions have been noted in the Appendix to reduce the amount of material required for floodplain grading and balance material available. Payment will be full compensation for the Earthwork work prescribed in Sections, 02200, 05000, 05001.

Incidental to Item Vegetation salvage and transplant is incidental to floodplain grading. Shrubs within construction limits shall be salvaged and transplanted locally on floodplain along the side channel. Whenever possible shrubs shall be transplanted without stockpiling. Vegetation including, but not limited to alders, willows, cottonwoods, sedge mats, and cattails, may be transplanted.

Item A8 Earthwork- Import Fill and Regrade Temp Bypass Channel The accepted quantities will be paid at the contract price per unit of measurement for the pay items listed in the bid schedule. This work shall include, but is not limited to, loading, hauling and placing the appropriate material class from the South End Staging Area for floodplain fill. This Item includes hauling approximately 2,000 cy soil material from stockpiles along the levee road and the south end staging area to the floodplain for use as vegetative fill. Payment will be full compensation for the import of excess material work prescribed in Sections 02200, 05010.

Item A9 Riffle Construction

The accepted quantities will be paid at the contract price per unit of measurement for the pay item listed in the bid schedule. Payment will be full compensation for the Riffle Construction work prescribed in Section 05001 and the drawing sheet 7.2.

Item A10 Floodplain Micro-Topography

The accepted quantities will be paid at the contract price per unit of measurement for the pay items listed in the bid schedule. This work includes, but is not limited to, all materials, equipment, and labor necessary to place floodplain roughness features, including soil spread, and complete wood placement as shown on Drawing Sheet Number 7.3. Payment will be full compensation for the Floodplain Roughness work prescribed in Section 05010.

Incidental to Item Vegetative fill material is stockpiled on the floodplain. This material shall be spread and mixed into the top 6” to 12” of the floodplain during floodplain roughness work.

Item A11 Equipment Rental Rate for 300 Class Excavator and Operator The accepted quantities will be paid at the contract price per unit of measurement for the pay items listed in the bid schedule. Payment will be full compensation per hour of equipment rental as ordered by the Contracting Officer under Pay Item 11.

Item A12 Equipment Rental Rate for Dump Truck and Operator The accepted quantities will be paid at the contract price per unit of measurement for the pay items listed in the bid schedule. Payment will be full compensation per hour of equipment rental as ordered by the Contracting Officer under Pay Item 12.

Item A13 Equipment Rental Rate for Bulldozer and Operator The accepted quantities will be paid at the contract price per unit of measurement for the pay items listed in the bid schedule. Payment will be full compensation per hour of equipment rental as ordered by the Contracting Officer under Pay Item 13.

Optional Item A14 Earthwork – Construct High Terrace at South End of Project Area

The accepted quantities will be paid at the contract price per unit of measurement for the pay items listed in the bid schedule. Payment will be full compensation for the actual quantity of material hauled and placed in accordance with the Phase 4 Appendix, if this Option is exercised.

PLANTING:

Item B1 Mobilization and Demobilization Payment for Bid Item B1- Mobilization and Demobilization will be based on the lump sum price bid as shown on the Bid Form. Fifty percent (50%) payment for this Bid Item will be allowed once the Contractor fully mobilizes to the Site and obtains approval on all submittals required before starting construction. Full Payment for this item will be allowed once the Contractor completes the specified Work and fully demobilizes equipment and materials from the Site. The lump sum bid price for this item must not exceed ten percent (10%) of the total bid price. Mobilization and Demobilization applies to Section 01505.

Item B2 Plant Delivery from Nursery to Project Site Payment for Bid Item B2- Plant Delivery from Nursery will be based on the lump sum price as shown on the Bid Form. Payment will be allowed after each delivery and inspection of the plants upon arrival. Full Payment for this item will be allowed once the Contractor completes the specified Work and fully demobilizes equipment and materials from the Site. Plant Delivery from Nursery applies to Section B 200.

Item B3 Trench Planting-, 2, 5- gal The accepted quantities will be paid at the contract price per unit of measurement for the pay items listed in the bid schedule. This work includes all equipment, materials, and labor to dig 12” wide by 12” deep trenches and plant 2-gallon plants in the specified quantities along sections of side channel, as per Drawing Sheet Numbers 4.0, and 4.1, or field fit where noted and directed by the Government. This work also includes digging 18” deep by 12” wide trenches to plant 2-gallon Drummond willow and 5- gallon alder along the river channel as shown on Sheet 4.0. Payment will be full compensation for the work prescribed in Section B 400.

Item B4 Single Hole Planting, 2 gal The accepted quantities will be paid at the contract price per unit of measurement for the pay items listed in the bid schedule. This work includes all equipment, materials, and labor to plant 2-gallon plants, as per Drawing Sheet Numbers 4.0, 4.1, 4.2, and 5.0, or field fit where noted and directed by the Government. Payment will be full compensation for the work prescribed in Section B 300.

Item B5 Single Hole Planting, 8 gal The accepted quantities will be paid at the contract price per unit of measurement for the pay items listed in the bid schedule. This work includes all equipment, materials, and labor to plant 8-gallon plants in the specified quantities, as per Drawing Sheet Numbers 4.0 and 4.2, or field fit where noted and directed by the Government. Payment will be full compensation for the work prescribed in Section B 300.

Item B6 Water Individual Plants Payment for this bid item will be for all work completed under Item B6. Each plant shall be watered within 24 hours of planting to ensure root to soil contact and to saturate the surrounding soil. The Contractor shall provide necessary equipment to water each plant, either in single holes or trench planting. Payment will be full compensation for the work prescribed in Sections B400 and B500

Item B7 Equipment Rental Rate for Mini Excavator The accepted quantities will be paid at the contract price per unit of measurement for the pay items listed in the bid schedule. Payment will be full compensation per hour of equipment rental as ordered by the Contracting Officer under Pay Item B7.

Item B8 Equipment Rental Rate for Compact Loader The accepted quantities will be paid at the contract price per unit of measurement for the pay items listed in the bid schedule. Payment will be full compensation per hour of equipment rental as ordered by the Contracting Officer under Pay Item B8.

** End of Section**

SECTION 01300

SUBMITTALS

GENERAL

Submittals covered by these requirements include manufacturers’ information, test procedures, test results, samples, requests for substitutions, and miscellaneous work-related submittals. Submittals shall also include, but not be limited to, rock sources, and fabricated items. The Contractor shall furnish all drawings, specifications, descriptive data, certificates, samples, tests, methods, and schedules and other instructions as specifically required in the contract documents to demonstrate fully that the materials and equipment to be furnished and the methods of work comply with the provisions and intent of the contract documents.

CONTRACTOR’S RESPONSIBILITIES

The Contractor shall be responsible for the accuracy and completeness of the information contained in each submittal and shall assure that the material, equipment or method of work shall be as described in the submittal. The Contractor shall verify that all features of all products conform to the specified requirements. Submittal documents shall be clearly edited to indicate only those items which are being submitted for review. All extraneous materials shall be crossed out or otherwise removed. The Contractor shall ensure that there is no conflict with other submittals and notify the Contracting Officer in each case where his submittal may affect the work of another contractor. The Contractor shall coordinate submittals among his subcontractors and suppliers including those submittals complying with unit responsibility requirements specified in applicable technical sections.

The Contractor shall coordinate submittals with the work so that work will not be delayed. The Contractor shall coordinate and schedule different categories of submittals, so that one will not be delayed for lack of coordination with another. No extension of time will be allowed because of failure to properly schedule submittals. The Contractor shall not proceed with work related to a submittal until the submittal process is complete. This requires that submittals for review and comment shall be returned to the Contractor stamped “NO EXCEPTIONS TAKEN” or “MAKE CORRECTIONS NOTED.”

The Contractor shall certify on each submittal document that he has reviewed the submittal, verified field conditions, and complied with the contract documents.

The Contractor may authorize in writing a material or equipment supplier to deal directly with the Contracting Officer with regard to a submittal. These dealings shall be limited to contract interpretations to clarify and expedite the work.

STANDARD COMPLIANCE

1. When materials or equipment must conform to the standards of organizations such as, but not limited to, the American National Standards Institute (ANSI), American Society for Testing and Materials (ASTM), National Electrical Manufacturers Association (NEMA) and Underwriter’s Laboratories (UL) documents showing, or proving, conformance shall be submitted.

2. If an organization uses a label or listing to indicate compliance with a particular standard, the label or listing will be acceptable evidence, unless otherwise specified in the individual Sections. In lieu of the label or listing, the Contractor shall submit a certificate from an independent testing organization, which is competent to perform acceptable tests, and is approved by the Contracting Officer. The certificate shall state that the item has been tested in accordance with the specified organization’s standard. For materials and equipment whose compliance with organizational standards or specifications is not regulated by an organization using its own listing or label as proof of compliance, a certificate of compliance from the manufacturer shall be submitted for approval. The certificate shall identify the manufacturer, the product, and the referenced standard and shall state that the manufacturer certifies that the product conforms to all requirements of the project Specification and of the referenced standards listed.

REVIEW OF CONTRACTOR’S INFORMATION

1. When review and checking for acceptance is required of any drawing, or information regarding materials and equipment, the Contractor shall prepare or secure, and submit for review, two (2) copies. The Contracting Officer, after taking appropriate action, will return (1) marked copies to the Contractor.

Within 7 calendar days after receipt of said submittal copies, the Contracting Officer will return the marked copies indicating one of the following four (4) actions:

a. If review and checking indicates no exceptions, copies will be returned marked “NO EXCEPTIONS TAKEN” and work may begin immediately on incorporating the material and equipment covered by the submittal into the work.

b. If review and checking indicates limited corrections are required, copies will be returned marked “MAKE CORRECTIONS NOTED”. Work may begin immediately on incorporating into the work the material and equipment covered by the corrected submittal.

c. If review and checking indicates insufficient, or incorrect data, has been submitted, copies will be returned marked, “AMEND AND RESUMIT”. No work may begin on incorporating the material and equipment covered by this submittal into the work until the submittal is revised, resubmitted, and returned marked either “NO EXCEPTIONS TAKEN” or “MAKE CORRECTIONS NOTED”.

d. If review and checking indicates the material and equipment submittal is unacceptable, copies will be returned marked “REJECTED-RESUBMIT”. No work may begin on incorporating the material and equipment into the work until a new submittal is made and returned marked either “NO EXCEPTIONS TAKEN” or “MAKE CORRECTIONS NOTED”.

Approval by the Contracting Officer shall not relieve Contractor from responsibility for any errors or omissions in such drawings, nor from responsibility for complying with requirements of this Contract.

EFFECT OF REVIEW OF CONTRACTOR’S SUBMITTALS

Review of contract drawings, methods of work, or information regarding materials or equipment the Contractor proposes to provide, shall not relieve the Contractor of his responsibility for errors therein and shall not be regarded as an assumption of risks or liability by the Contracting Officer, or by any officer or employee thereof, and the Contractor shall have no claim under the contract on account of the failure, or partial failure, of the method of work, material, or equipment so reviewed. A mark of “NO EXCEPTIONS TAKEN or MAKE CORRECTIONS NOTED” shall mean that the Contracting Officer has no objection to the Contractor, upon his own responsibility, using the plan or method of work proposed, or providing the materials or equipment proposed.

PRODUCTS

MANUFACTURER’S DATA

Submittals for each manufactured item shall be comprised of manufacturer’s descriptive literature, drawings, diagrams, performance and characteristic curves, and catalog cuts. Manufacturer’s name, trade name, model or catalog number, nameplate data, size, layout dimensions, capacity, project specification references, and any other additional information necessary to establish contract compliance shall be clearly indicated.

At a minimum, the Contractor shall provide project submittals as shown on the following Submittal Log. Submittal requirements are listed in the Technical Specifications and Drawings.

Submittal Log 01300

Submittal #
Item
Type of Submittal
Notification
Requirement Location
Bid Item
1
Equipment Inspection
Notification
72 hours
Specification 01505
Mobilization
2
Stormwater Pollution Prevention Plan
Drawing and narrative/EPA permit process
20 days
Specification 01560
Mobilization
3
Access and Staging Plan
Drawing and Narrative
Prior to beginning work
Specification 01505
Mobilization
4
Construction Staking and Quality Control Plan
Narrative and notification
Pre-Work Meeting
Specification 01400
Mobilization
5
Weed Free Certifications for straw bales and other materials
Certificates
72 hours
Specification 02140
Water Management and Environmental Controls
6
Water Management Plan
Drawing and narrative
15 days
Specification 02140

Water Management and Environmental Controls

7
Turbidity Monitoring
Notification
72 hours prior to any ground disturbing activity
Specification 02140
Water Management and Environmental Controls
10
Plant Care Plan
Narrative
Prior to beginning work
Specification B 200
Plant Delivery
11
Bridge Removal
Notification
1 Week
Specification 06000
Bridge Removal

EXECUTION

1.At least 7 calendar days prior to the Contractors need for approval, contractor shall forward to the Contracting Officer all submittals required by the individual Sections of the Specifications.
2.All submittals shall be identified by submittal number and specification section number on the letter of transmittal. Submittals shall be numbered consecutively and resubmittals shall have a letter suffix. For example:
a.1st submittal:05001
b.1st resubmittal:05001A
c.2nd resubmittal:05001B, etc.

Items to be submitted are specified in individual Sections of these Specifications. Submittals for each Section shall be bound together in one book. Book shall have numbered tab dividers for each item. Submittals that are related to, or affect, each other shall be forwarded simultaneously as a package to facilitate coordinated review. Uncoordinated submittals will be rejected. Do not combine unrelated materials in the same submittal. Submittals shall be arranged in same order as they appear in the Specification Section. Items shall be clearly marked with the same identification number as indicated on the drawings. The Contractor shall include submittal time appropriate within each item of work on the Construction Schedule. The Contracting Officer will receive submittals at the preconstruction meeting.

***END OF SECTION***

SECTION 01400

CONSTRUCTION STAKING

GENERAL

CONSTRUCTION STAKING

The Contractor shall provide survey staking for construction. The Government will provide survey control and grading surfaces for equipment with GPS machine control capability covering the north end 4 acre work area, and the new floodplain along the extent of the levee. The Contractor, even if using the GPS equipment, is responsible for marking, with stakes, bank stability structure beginning and ending stations. Aspen clump locations shall be staked and agreed to prior to planting.

METHODS

STAKEOUT AND MEASUREMENT TO BE PERFORMED BY CONTRACTOR

The Contracting Officer will provide an initial layout of the restoration design in consultation with the Contractor. After the initial layout, the Contractor shall be responsible for staking reference points/markers to complete the work from the initial control points and grading surfaces provided by the Contracting Officer, and shall be responsible for all measurements required for the execution of the work. The Contractor shall protect all stakes and shall pay for the time and materials required to replace stakes that have been disturbed or obliterated if necessary.

The Contractor shall use information provided by the Contracting Officer to stake structure locations. Upon completion of the project, the any original survey control points that are disturbed will be re-set.

The Contractor shall furnish at the Contractor’s own expense, such stakes, equipment, tools, materials, and all labor as required in stakeout of any parts of the work from the control points and grading surfaces provided by the Contracting Officer. The Contractor shall verify periodically that grades and locations are accurate.

The Contracting Officer may require that work be suspended at any time when location and limit marks established by the Contractor are not reasonably adequate to permit checking of the work.

***END OF SECTION***

SECTION 01505

MOBILIZATION AND DEMOBILIZATION

GENERAL

MOBILIZATION

Mobilization shall consist of preparatory work and operations, including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the site; for the establishment of all facilities necessary for work on the project; and for all other work and operations which must be performed, or costs incurred prior to beginning work, on the various items on the project site. Mobilization includes obtaining project-specific bonds and obtaining any permits, including the EPA’s Construction General Permit NOI (electronic NOI system, “eNOI”) for stormwater runoff, not provided by the Contracting Officer. Contractors shall note the 14 day waiting period between submittal to the eNOI system and breaking ground. The Contractor shall have erosion control devices on site, including, but not limited to, 1 6-inch pump, silt fence, stakes, waddles, and straw bales, in accordance with Section 02140 prior to any ground disturbance.

Mobilization shall also include the construction of temporary ramps and access ways, staging areas, grading, and the necessary preparatory work required to allow for the safe and stable movement of all vehicles that are required to construct the improvements outlined in the Contract Documents. Maintenance of the levee road and Road 233 is incidental to mobilization. An access management and staging plan including consideration of loads scheduled to cross the temporary bridge is required before starting work.

There is a temporary bridge in place between the South staging area and stockpiles and the project location. Contractor shall ensure no loads crossing this bridge exceed its capacity. The temp bridge has been rated as follows:

42 ton GVW for a type 3 truck axel configuration 66 ton GVW for a type 3S2 truck axel configuration 81 ton GVW for a type 3-3 truck axel configuration 44 ton GVW for a 336 Excavator 43 ton GVW for a D8 Caterpillar Komatsu HM300-2 articulated dump truck with a 53,000 lb vehicle weight, 40,300 lb payload, and a gross weight of 113,400 lb. This vehicle rated out at .88. It would be limited to 2/3 capacity load crossing the bridge.

No tracked vehicles shall operate on bridge without approved bridge deck protection. Contractor shall submit an overload permit for any GVW over 60 ton and GVW over 40 ton for a vehicle with less than 4 axels.

1. Notify the Contracting Officer in writing at least 72 hours before moving any construction equipment onto the National Forest. Notification will include an agreed upon location where the equipment will be available for inspection by the Nez Perce Tribe or Forest Service. Subsequent move-ins of equipment shall be treated the same as the initial move-in and will require notification.

2. All equipment shall be washed prior to mobilization to the Forest to minimize the introduction of foreign materials and fluids to the project site. All equipment shall be free of oil, hydraulic fluid, and diesel fuel leaks. To prevent invasion of noxious weeds or the spread of whirling disease spores, all equipment shall be power washed or cleaned to remove all dirt, plant parts and material prior to mobilization. Truck beds and dump boxes hauling to the project site shall also be cleaned prior to entering the Forest. It will be the contractor's responsibility to insure that adequate measures have been taken. Equipment shall be inspected by the Inspector prior to mobilizing to the Forest. Only construction equipment that has passed inspection by the Nez Perce Tribe or Forest Service will be allowed to operate within the project area.

3. Equipment shall be in a well-maintained condition to minimize the likelihood of a fluid leak. Any leaks or accumulations of grease would be corrected before entering the project area. If a fluid leak does occur, the project Inspector and COR shall be notified immediately, and all work ceased until the leak has been rectified. At all times during the construction phase, fluid spill containment equipment adequately sized for specific quantities of fuel shall be present on-site and ready for deployment should an accidental spill occur. Fuel spill kit shall include an oil-absorbing floating boom and absorbent pads. Contractor and Contractor’s representatives shall be knowledgeable on use of the spill containment equipment. The Contracting Officer reserves the right to refuse equipment that does not meet criteria.

4. Equipment that will be used in live water shall utilize hydraulic fluid that is non-toxic to salmonids. The following criteria should be met to determine if a hydraulic fluid is nontoxic to salmonids during acute exposure: (a) The test species used should be a salmonid (most often this will be rainbow trout, but occasionally Chinook salmon or Coho salmon are tested); (b) The test duration should be 96 hours; (c) The test should be conducted using the water accommodated fraction (WAF) (the WAF is used in testing hydrophobic materials to provide a "worst case scenario" for exposure to aquatic organisms); and (d) The value of the LC50 should be >1000 mg/L. Several products on the market meet these specifications.

According to the guidance provided by the National Oceanic and Atmospheric Administration, the following products meet the required criteria:

· Chevron Clarity Hydraulic Oil A W

· Ecoterra Hydraulic Oil

· GreesCare Plus

· Mobil EAL 224H

· ENVIRONTM AW Hydraulic Fluids These products and companies are not endorsed by the government and the contractor should perform independent research regarding the performance characteristics of each product.

5. All construction equipment shall be staged in a location and manner to minimize air, soil and water pollution. Storage of fuel and lubricants - all fuel and lubricants shall be stored in containers and areas that are in conformance with the Idaho State Department of Environmental Quality, NMFS and USFWS biological opinion terms and conditions, and local regulations.

6. Servicing and refueling equipment - all fuel and lubricants used in the servicing of construction equipment shall be done in a manner that avoids spills and over filling and shall be at least 150 feet from all waterbodies. Stationary power equipment, such as generators and pumps, within 150 feet of water shall be diapered to prevent leaks. All power equipment within 150 feet of the water shall be inspected daily for fluid leaks and repaired. The contractor must keep daily inspection reports in a diary.

7.The Idaho State Department of Environmental Quality shall be notified immediately of any spill and the operator shall contain the spillage. If a spill of chemical pollutants such as fuel or hydraulic fluid should occur, immediately attempt to contain the spilled material. The following procedures shall be followed:
(a)for spillage on land, construct earthen berms or use other suitable barricade material of sufficient size to contain the spell and keep it from spreading.

(b) for spillage on water, attempt to isolate and contain the spilled material. Commercial booms or other suitable materials shall be kept on site during construction to contain fuel and oil spills on water.

8. Sanitary facilities - sanitary facilities such as chemical toilets shall be located at least 150 feet from water bodies to prevent contamination of surface or subsurface water.

9. A description of hazardous materials that will be used including inventory, storage and handling procedures will be available on site.

10. If elemental mercury is found during project work, work in the immediate vicinity will stop and every reasonable effort will be made to contain the material in such a manner that it will not reach surface or groundwater. The COR shall be contacted immediately.

SITE PREPARATION

1. Existing Conditions The Contractor shall determine the actual condition of the site as it affects this portion of the work. Particularly, Contractor shall inspect the temporary haul road for erosion and repair as necessary for use. There is one location where the temp road fill was removed to allow for fall/spring drainage. The Contractor shall insert a temporary 18” minimum culvert and backfill. This fill and any culvert(s) shall be removed upon completion of Phase 2. Any fill and maintenance of the temp road shall be compacted with heavy equipment.

2. Protection of Existing Facilities and Improvements Site preparation shall not damage existing structures, landscaping, or vegetation adjacent to the areas designated for site preparation. The Contractor shall repair or replace any and all damaged property.

3. Vegetation Preservation and Salvage Preservation of existing vegetation and trees is of utmost importance. The Contractor will stake and walk the entire site with the Inspector and Contracting Officer. The Contractor may plant in the areas already preserved, however, utmost care shall be used to protect the exiting vegetation.

DEMOBILIZATION AND SITE RECLAMATION

1. Demobilization shall consist of work and operations necessary to disband all mobilized items and clean up the site. The removal of all temporary ramps, access ways, roads, signs, temporary fencing, construction debris including rock chips, wood debris, construction stakes, and other construction-related refuse, and temporary facilities or works and the restoration of surfaces to an equal or better than existing condition shall also be included as part of demobilization. No erosion control debris, including brush mats used to control erosion, may be left in the channel upon completion of work.

2. Site reclamation is included under demobilization. Site reclamation includes reclamation of areas disturbed during construction, including staging areas, and temporary access roads. Staging areas shall be decompacted and graded to match elevation specified on the plan sheets.

3. All damaged or disturbed streambanks are to be restored to a natural slope pattern and profile for establishment of permanent woody vegetation. Leave native materials, e.g., down wood, where they are found, the floodplain is at grade. If native materials (e.g., downed wood) are destroyed, replace them with a functional equivalent during site restoration.

4. Stockpiled materials (i.e. trees, vegetation, topsoil, and other excavated material from restoration project areas) salvaged under Phases 1-2, shall be used as specified in the plan sheets.

5. All brush mats, straw bales, and erosion control devices shall be removed from below the ordinary high water mark upon completion of the project. Small straw bales may be scattered upon the project site above the ordinary high water mark.

6. All scrap metal that was left at the south staging area shall be removed and disposed of by the Contractor.

SUBMITTALS

Stormwater Pollution Plan The Contractor shall submit for approval by the Contracting Officer updates and particular details to the Government prepared Stormwater Pollution Prevention Plan (SWPP). Once the SWPP modifications are approved, the Contractor shall file for coverage under EPA's Construction General Permit using the “eNOI” system. Refer to https://www.epa.gov/npdes/epas-2017-construction-general-permit-cgp-and-related-documents

Equipment Inspection Notification The Contractor shall notify the Contracting Officer in writing at least 72 hours before moving any construction equipment onto the National Forest.

Access and Staging Plan The Contractor shall submit for approval by the Contracting Officer an access and staging plan that includes anticipated temporary bridge loads and any overload permits necessary. This plan shall be submitted prior to work beginning on site and will be updated as plans change.

***END OF SECTION***

SECTION 01560

ENVIRONMENTAL CONTROLS

GENERAL

SITE MAINTENANCE

The Contractor shall keep the work site, staging areas, and Contractor’s facilities clean and free from rubbish and debris. The Contractor staging area is noted on the drawings. Additional staging areas may be identified by the Contracting Officer and Inspector. Materials and equipment shall be removed from the site when they are no longer necessary. Upon completion of the work and before final acceptance, the work site shall be cleared of equipment, unused materials, and rubbish to present a clean and neat appearance. Staging areas and machine access areas created for project use will be decompacted and receive appropriate treatments (i.e. placement of small logs and brush).

CLEAN-UP:

a) Waste material, such as used erosion control devices, camping refuse, old culverts or found materials, of any kind will not be permitted to remain on the site of the work or on adjacent roads. Immediately upon such materials becoming unfit for use in the work, they shall be collected, carried off the site, and properly disposed of by the Contractor. There is the potential to find old mining refuse such as cables, culverts, and small garbage. This becomes the property of the Contractor and shall be removed from the site.

b) The Contractor may provide temporary restroom and cleanup facilities for Contractor’s employees and shall keep these areas clear of all refuse, rubbish, and debris that may accumulate from any source and shall keep them in a neat condition to the satisfaction of the Contracting Officer.

c) In the event that waste material, refuse, debris, and/or rubbish are not removed from the work by the Contractor, the Contracting Officer reserves the right to have the waste material, refuse, debris, and/or rubbish removed and the expense of the removal and disposal charged to the Contractor.

AIR POLLUTION CONTROL

The Contractor shall not discharge smoke, dust, and other contaminants into the atmosphere that violate the air pollution regulations for the area. The Contractor shall maintain construction vehicles and equipment in good repair. Exhaust emissions that are determined to be excessive by the Contracting Officer shall be repaired or replaced. If determined to be necessary by the Project Inspector, Contractor shall provide a water truck to manage project area dust.

NOISE CONTROL

The Contractor shall comply with all local controls and noise level rules, regulations, and ordinances which apply to any…

This is the start of the file's text. The full file is on GovTribe.