About this file

This file contains architectural and structural bidding documents for the Aloha High School Athletic Program Improvements project, a state and local contract opportunity in Washington County, Oregon, managed by the Beaverton School District. The project encompasses two primary components: construction of a new 2,160 square foot indoor batting cage facility with pre-engineered metal building construction, and expansion of the existing 1,082 square foot concessions stand with restroom renovation, totaling 1,234 square feet. The batting cage is classified as A-3 Assembly/B Occupancy with an occupant load of 44 persons and Construction Type V-B, while the concessions stand expansion is classified as B-Business occupancy, also Construction Type V-B. The project is located at Aloha High School, 18550 SW Kinnaman Road, Aloha, Oregon 97007. The bidding documents include comprehensive architectural drawings, structural plans, and civil/engineering documents prepared by multiple firms including Novak Architecture Inc., Froelich Engineers, AKS Engineering & Forestry LLC, and R&W Engineering LLC. The drawing set includes floor plans, elevations, sections, details, grading plans, and specialized construction notes. The drawing issue date for bidding is November 4, 2025, with permits anticipated November 5, 2025, and construction to follow.

The project is governed by the 2022 Oregon Structural Specialty Code, 2023 Oregon Plumbing Code, 2023 Oregon Electrical Code, 2023 Oregon Fire Code, and 2021 Oregon Energy Efficiency Code. Design criteria include wind speeds of 103 mph, ground snow load of 12 psf with design roof snow load of 25 psf, and seismic design category D. Special inspection and testing requirements are mandated per building code Section 1705, with continuous and periodic inspection required for concrete, masonry, steel, and post-installed anchors. All concrete work must conform to ACI 318 standards with 3,000 psi strength for footings and stemwalls, and 4,000 psi for exterior slabs. Reinforcing steel must conform to ASTM A615 Grade 60, and structural steel must meet ASTM A992 Grade 50 for wide-flange sections. The contractor is responsible for coordinating all trades, verifying existing conditions, and ensuring compliance with all applicable building codes and standards. Requests for information and substitution requests must be submitted through the general contractor to the architect for consideration.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRELIMINARY

NOT FOR

CONSTRUCTION

EN

G

IN

EE

R

IN

G

SU

R

VE

YI

N

G

FO

R

ES

TR

Y

N A

TU

R

A L

R

ES

O U

R C

ES

LA

N D

SC

A

PE

A

R C

H

IT

EC

TU

R E

PL

A

N N

IN

G

A L

O H

A H

IG

H

S C

H O

O L

A T

H L

E T

IC

P

R O

G R

A M

IM

P

R O

V M

E N

T S

W A

S H

IN

G

T O

N C

O U

N T

Y O

R E

G O

N

ALOHA HIGH SCHOOL

BIDDING DOCUMENTS

VICINITY MAP

SITE MAP

EXISTING LAND USE:

IMPERVIOUS AREA SUMMARY:

PROPERTY LOCATION:

PROJECT PURPOSE:

PROJECT TEAM

LEGEND

GEOTECHNICAL:

PROPERTY DESCRIPTION:

VERTICAL DATUM:

C000

C O

V E

R S

H E

E T

W

IT

H V

IC

IN

T Y

, S

IT

E M

A P

L

E G

E N

D

ARCHITECT:OWNER/APPLICANT:

ATTENTION EXCAVATORS Know what'sbelow.

before you dig.Call

R

PROJECT RECORD DRAWING

CIVIL ENGINEERING/

SURVEYING/LANDSCAPE

ARCHITECTURE FIRM:

ATHLETIC PROGRAM IMPROVEMENTS

SHEET INDEX

CONSTRUCTION

EN

G

IN

EE

R

IN

G

SU

R

VE

YI

N

G

FO

R

ES

TR

Y

N A

TU

R

A L

R

ES

O U

R C

ES

LA

N D

SC

A

PE

A

R C

H

IT

EC

TU

R E

PL

A

N N

IN

G

A L

O H

A H

IG

H

S C

H O

O L

A T

H L

E T

IC

P

R O

G R

A M

IM

P

R O

V M

E N

T S

W A

S H

IN

G

T O

N C

O U

N T

Y O

R E

G O

N

C001

G E

N E

R A

L C

O N

S T

R U

C T

IO

N

N O

T E

S

CONSTRUCTION

EN

G

IN

EE

R

IN

G

SU

R

VE

YI

N

G

FO

R

ES

TR

Y

N A

TU

R

A L

R

ES

O U

R C

ES

LA

N D

SC

A

PE

A

R C

H

IT

EC

TU

R E

PL

A

N N

IN

G

A L

O H

A H

IG

H

S C

H O

O L

A T

H L

E T

IC

P

R O

G R

A M

IM

P

R O

V M

E N

T S

W A

S H

IN

G

T O

N C

O U

N T

Y O

R E

G O

N

C002

G E

N E

R A

L C

O N

S T

R U

C T

IO

N

N O

T E

S

SW MADELINE STRET

EN

G

IN

EE

R

IN

G

SU

R

VE

YI

N

G

FO

R

ES

TR

Y

N A

TU

R

A L

R

ES

O U

R C

ES

LA

N D

SC

A

PE

A

R C

H

IT

EC

TU

R E

PL

A

N N

IN

G

A L

O H

A H

IG

H

S C

H O

O L

A T

H L

E T

IC

P

R O

G R

A M

IM

P

R O

V M

E N

T S

W A

S H

IN

G

T O

N C

O U

N T

Y O

R E

G O

N

C003

E X

IS

T

IN

G

C O

N D

IT

IO

N S

P L

A N

SW MADELINE STREET

PRELIMINARY

NOT FOR

CONSTRUCTION

EN

G

IN

EE

R

IN

G

SU

R

VE

YI

N

G

FO

R

ES

TR

Y

N A

TU

R

A L

R

ES

O U

R C

ES

LA

N D

SC

A

PE

A

R C

H

IT

EC

TU

R E

PL

A

N N

IN

G

A L

O H

A H

IG

H

S C

H O

O L

A T

H L

E T

IC

P

R O

G R

A M

IM

P

R O

V M

E N

T S

W A

S H

IN

G

T O

N C

O U

N T

Y O

R E

G O

N

LEGEND

C030

C

LE

A R

IN

G

D

E M

O

LI

TI

O

N P

LA

NOT FOR

CONSTRUCTION

EN

G

IN

EE

R

IN

G

SU

R

VE

YI

N

G

FO

R

ES

TR

Y

N A

TU

R

A L

R

ES

O U

R C

ES

LA

N D

SC

A

PE

A

R C

H

IT

EC

TU

R E

PL

A

N N

IN

G

A L

O H

A H

IG

H

S C

H O

O L

A T

H L

E T

IC

P

R O

G R

A M

IM

P

R O

V M

E N

T S

W A

S H

IN

G

T O

N C

O U

N T

Y O

R E

G O

N

C050

E R

O S

IO

N

A N

D S

E D

IM

E

N T

C O

N

TR

O L

P

LA

N

ESC AND GRADING LEGEND

PRELIMINARY

NOT FOR

CONSTRUCTION

EN

G

IN

EE

R

IN

G

SU

R

VE

YI

N

G

FO

R

ES

TR

Y

N A

TU

R

A L

R

ES

O U

R C

ES

LA

N D

SC

A

PE

A

R C

H

IT

EC

TU

R E

PL

A

N N

IN

G

A L

O H

A H

IG

H

S C

H O

O L

A T

H L

E T

IC

P

R O

G R

A M

IM

P

R O

V M

E N

T S

W A

S H

IN

G

T O

N C

O U

N T

Y O

R E

G O

N

C070

G R

A D

IN

G

P

LA

N

GRADING LEGEND

ADA EGRESS GATE DETAIL 3

C070

STEP DETAIL 1

C070

FILTER CATCHBASIN 2

C070

PRELIMINARY

NOT FOR

CONSTRUCTION

EN

G

IN

EE

R

IN

G

SU

R

VE

YI

N

G

FO

R

ES

TR

Y

N A

TU

R

A L

R

ES

O U

R C

ES

LA

N D

SC

A

PE

A

R C

H

IT

EC

TU

R E

PL

A

N N

IN

G

A L

O H

A H

IG

H

S C

H O

O L

A T

H L

E T

IC

P

R O

G R

A M

IM

P

R O

V M

E N

T S

W A

S H

IN

G

T O

N C

O U

N T

Y O

R E

G O

N

LEGEND

C100

D

IM

E N

S

IO

N E

D S

IT

E

P

LA

N

ADA EGRESS GATE 1

C100

PRELIMINARY

NOT FOR

CONSTRUCTION

EN

G

IN

EE

R

IN

G

SU

R

VE

YI

N

G

FO

R

ES

TR

Y

N A

TU

R

A L

R

ES

O U

R C

ES

LA

N D

SC

A

PE

A

R C

H

IT

EC

TU

R E

PL

A

N N

IN

G

A L

O H

A H

IG

H

S C

H O

O L

A T

H L

E T

IC

P

R O

G R

A M

IM

P

R O

V M

E N

T S

W A

S H

IN

G

T O

N C

O U

N T

Y O

R E

G O

N

C200

S

TO

R M

D R

A

IN

A G

E P

LA

LEGEND

R

O S

IO

N

A N

D S

E D

IM

E

N T

C O

N T

R O

L D

E T

A

IL

S

C500

PRELIMINARY

NOT FOR

CONSTRUCTION

EN

G

IN

EE

R

IN

G

SU

R

VE

YI

N

G

FO

R

ES

TR

Y

N A

TU

R

A L

R

ES

O U

R C

ES

LA

N D

SC

A

PE

A

R C

H

IT

EC

TU

R E

PL

A

N N

IN

G

A L

O H

A H

IG

H

S C

H O

O L

A T

H L

E T

IC

P

R O

G R

A M

IM

P

R O

V M

E N

T S

W A

S H

IN

G

T O

N C

O U

N T

Y O

R E

G O

CONSTRUCTION

EN

G

IN

EE

R

IN

G

SU

R

VE

YI

N

G

FO

R

ES

TR

Y

N A

TU

R

A L

R

ES

O U

R C

ES

LA

N D

SC

A

PE

A

R C

H

IT

EC

TU

R E

PL

A

N N

IN

G

A L

O H

A H

IG

H

S C

H O

O L

A T

H L

E T

IC

P

R O

G R

A M

IM

P

R O

V M

E N

T S

W A

S H

IN

G

T O

N C

O U

N T

Y O

R E

G O

N

C501

D E

T A

IL

CONSTRUCTION

EN

G

IN

EE

R

IN

G

SU

R

VE

YI

N

G

FO

R

ES

TR

Y

N A

TU

R

A L

R

ES

O U

R C

ES

LA

N D

SC

A

PE

A

R C

H

IT

EC

TU

R E

PL

A

N N

IN

G

A L

O H

A H

IG

H

S C

H O

O L

A T

H L

E T

IC

P

R O

G R

A M

IM

P

R O

V M

E N

T S

W A

S H

IN

G

T O

N C

O U

N T

Y O

R E

G O

N

C502

D E

T A

J

NOT FOR

CONSTRUCTION

EN

G

IN

EE

R

IN

G

SU

R

VE

YI

N

G

FO

R

ES

TR

Y

N A

TU

R

A L

R

ES

O U

R C

ES

LA

N D

SC

A

PE

A

R C

H

IT

EC

TU

R E

PL

A

N N

IN

G

A L

O H

A H

IG

H

S C

H O

O L

A T

H L

E T

IC

P

R O

G R

A M

IM

P

R O

V M

E N

T S

W A

S H

IN

G

T O

N C

O U

N T

Y O

R E

G O

N

C503

D E

T A

DIRECTORY

OWNER

STRUCTURAL

ARCHITECTURAL

SHEET INDEX

ARCHITECT

BEAVERTON SCHOOL DISTRICT | Facilities Development 16550 SW Merlo Road Beaverton, OR 97003 CONTACT: Chris Hansen, Project Manager T: (503) 356-4321 E: Christopher_Hansen@beaverton.k12.or.us

NOVAK ARCHITECTURE INC

11174 SW Oneida Street Tualatin, OR 97062 CONTACT: Terry J Novak, AIA T: (503) 352-4987 E: tnovak@novakarchitecture.com

CIVIL (under separate permit)

STRUCTURAL

ALOHA HIGH SCHOOL - NEW BATTING CAGES

18550 SW Kinnaman Road

Aloha, OR 97007

VICINITY MAP

A000 COVER SHEET

A001 SYMBOLS, NOTES, MATERIALS AND ADA DETAILS

A002 GENERAL NOTES AND ABBREVIATIONS

A201 FLOOR PLANS AND CEILING PLAN

A301 EXTERIOR ELEVATIONS & SECTION

A601 DOOR & WINDOW SCHEDULE AND DETAILS

S001 COVER SHEET

S002 GENERAL STRUCTURAL NOTES

S003 GENERAL STRUCTURAL NOTES

S004 SPECIAL INSPECTIONS TABLES

S102 FOUNDATION PLAN

S500 DETAILS

MECHANICAL

M0.1 MECHANICAL LEGEND & SCHEDULES

M1.1 MECHANICAL FLOOR PLAN

CIVIL

C070 GRADING PLAN (FOR REFERENCE ONLY)

AKS ENGINEERING & FORESTRY, LLC

12965 SW Herman Road, Suite 100 Tualatin, OR 97062 CONTACT: Chris Knight, PE T: (503) 563-6151 E: KnightC@aks-eng.com

FROELICH ENGINEERS

17700 SW Upper Boones Ferry Road, Suite 115 Portland, OR 97224 CONTACT: Rod Hammerberg, PE T: (503) 624-7005 E: rhammerberg@froelich-engineers.com

MECHANICAL

R&W Engineering, LLC 9615 SW Allen Blvd, Suite 107 Beaverton, OR 97005 CONTACT: Kameron Jones T: (503) 292-6000 E: kjones@rweng.com

ELECTRICAL

R&W Engineering, LLC 9615 SW Allen Blvd, Suite 107 Beaverton, OR 97005 CONTACT: Jonathon Lilly, PE T: (503) 292-6000 E: jlilly@rweng.com

N O R T H

PROJECT SUMMARY

PROJECT SUMMARY

WORK SCOPE: construction of new indoor batting cage structure

JURISDICTION: BEAVERTON, OREGON

BUILDING AREA: 2,160 SF

OCCUPANCY GROUP: A-3 ASSEMBLY / (2) BATTING CAGES

CLASSIFIED AS B OCCUPANCY DUE TO OCCUPANT LOAD

BELOW 50 (PER OSSC 303.1.1)

OCCUPANT LOAD: "EXERCISE ROOM" AT 1:50 SF

2,160 / 50 = 44 OCCUPANTS

CONSTRUCTION TYPE: V-B

NOTICE TO %IDDING SU%�CONTRACTORS AND

SUPP/IERS�

ALL REQUESTS FOR INFORMATION AND SUBSTITUTION REQUESTS MUST

BE SUBMITTED TO AN GENERAL CONTRACTOR FOR REVIEW AND

FORWARDING TO THE ARCHITECT FOR CONSIDERATION. THE

ARCHITECT, ENGINEERS OR owner ARE NOT TO BE CONTACTED

DIRECTLY.

NOTICE TO %IDDING GENERA/ CONTRACTORS�

ALL REQUESTS FOR INFORMATION AND SUBSTITUTION REQUESTS MUST

BE SUBMITTED ONLY TO THE GENERAL CONTRACTOR FOR

CONSIDERATION. THE architect, ENGINEERS or owner ARE NOT TO

BE CONTACTED DIRECTLY.

GOVERNING CODES

BUILDING CODE: 2017 OREGON STRUCTURAL SPECIALTY CODE

PLUMBING CODE: 2014 OREGON PLUMBING SPECIALTY CODE

MECHANICAL CODE: 2014 OREGON MECHANICAL SPECIALTY CODE

ELECTRICAL CODE: 2014 OREGON ELECTRICAL SPECIALTY CODE

FIRE CODE: 2014 OREGON FIRE CODE

ENERGY CODE: 2014 OREGON ENERGY EFFICIENCY SPECIALTY CODE

GENERA/ NOTICE�

CHANGES OF ANY KIND ARE TO BE MADE TO DRAWING SET

WITHOUT THE EXPRESS WRITTEN CONSENT OF THE ARCHITECT.

ELECTRICAL

E0.1 ELECTRICAL LEGEND & ABBREVIATIONS

E1.1 ELECTRICAL FLOOR PLAN

E2.1 ONE-LINE DIAGRAM & SCHEDULES

DRAWING ISSUE

BIDDING 11/04/25

PERMITS 11/05/25

CONSTRUCTION --

PRE�ENGINEERED META/ %UI/DING�

GENERAL CONTRACTOR WILL BE RESPONSIBLE FOR THE DESIGN AND

ENGINEERING OF THE PRE-ENGINEERED METAL BUILDING, INCLUDING

ALL EXTERIOR FINISHES, DOOR AND WINDOW OPENINGS AS SHOWN IN

DRAWINGS. STRUCTURAL FOUNDATION DESIGN shown in these drawings IS FOR BUDGETING PURPOSES ONLY.

A000

FO

R

ES

TR

Y

SU

R

VE

YI

N

G

EN

G

IN

EE

R

IN

G

N A

TU

R

A L

R

ES

O U

R C

ES

LA

N D

SC

A

PE

A

R C

H

IT

EC

TU

R E

PL

A

N N

IN

G

A L

O H

A H

IG

H

S C

H O

O L

B

A T

T

IN

G C

A G

E S

B E

A V

E R

T O

N S

C H

O O

L D

IS

T

R

IC

T W

A S

H

IN

G T

O N

C O

U N

T Y

, O R

E G

O N

SW

2n d

AV

EN

UE

, S

UI

TE

TU

AL

AT

IN

, O

R

P

3.

2.

BATTING CAGES

SECOND LEVEL

+10'-0"

TYPICAL SECTION

SECTION NUMBER

DIRECTION OF VIEW

SHEET NUMBER

NORTH ARROW REFERENCE

PROJ NORTH

LAYOUT GRID LINES

LEVEL LINE

REVISION NUMBER AND EXTENT

ROOM NAME AND NUMBER

PLAN DETAIL REFERENCE

SECTION DETAIL REFERENCE

DETAIL REFERENCE

EXTERIOR / INTERIOR ELEVATION

WALL TYPE IDENTIFICATION MARK

ELEVATION NUMBER AND

DIRECTION

SHEET WHERE DRAWN,

HYPHEN INDICATES DETAIL

ON SAME SHEET.

DETAIL NUMBER

DETAIL NUMBER

SHEET WHERE DRAWN,

DASH TEXT INDICATES

DETAIL ON SAME SHEET

SHEET WHERE DRAWN

ELEVATION NUMBER AND

DIRECTION

GLAZING / WINDOW TYPE MARK

SEE ELEVATIONS AND

EXT WINDOW SCHEDULE

NAME OF LEVEL

INDICATES HEIGHT ABOVE

PROJECT DATUM

REVISION NUMBER - SEE

REVISION HISTORY ON THE

TITLE BLOCK OF EACH

SHEET

EXTENT OF CURRENT

REVISION

KEYED NOTE MARK

DRAWING TITLE

SEE CORRESPONDING

NUMBERED KEY NOTE ON

SHEET WHERE

REFERENCE OCCURS

A101

SIM

A101

SIM

AE101

SIM

SEE PLANS AND INTERIOR

GLAZING TYPES

TRUE NORTH

INTERIOR FINISH TAG

SEE MATERIAL FINISH SCHEDULE

EARTH

AGGREGATE BASE COURSE

CONCRETE

CONCRETE MASONRY UNIT/

TERRA COTTA

BRICK MASONRY

PRECAST CONCRETE

LIMESTONE, SANDSTONE, GRANITE

MARBLE

STEEL, STAINLESS STEEL

(LARGE SCALE)

ALUMINUM (LARGE SCALE)

OTHER METALS (LARGE

SCALE)

WOOD FRAMING -

CONTINUOUS (LARGE SCALE)

WOOD FRAMING - DISCONTINUOUS

(LARGE SCALE)

PLYWOOD

(LARGE SCALE)

FINISH WOOD (LARGE SCALE)

EIFS INSULATION BOARD

(LARGE SCALE)

SEMI-RIGID INSULATION

(LARGE SCALE)

BATT INSULATION

(LARGE SCALE)

MORTAR, SAND, FIREPROOFING,

STUCCO, GYPSUM BOARD

TERRAZZO (LARGE SCALE)

COMPOSITE BOARD

(LARGE SCALE)

ACOUSTIC TILE (LARGE SCALE)

PROTECTION BOARD

(LARGE SCALE)

CERAMIC TILE (LARGE SCALE)

GLASS (LARGE SCALE)

PLAN AND SECTION

TRAFFIC COATING

DETECTABLE WARNING FLOOR

SURFACING

ARCHITECTURAL REFERENCE SYMBOLS AND REFERENCE TAGS ARCHITECTURAL MATERIAL INDICATIONS

AREA

ROOM NAME

ROOM NAME

ROOM NAME

X

A

A

SIM

2 3

A1

A100

SECTION NUMBER

SHEET NUMBER

A

PT-1

A

EXTERIOR FINISH TAG

EXTERIOR MATERIAL

EXTERIOR COLOR

DOOR REFERENCE

M

IN

7"

1/

C L R

3'-6"1'-0"

3'-4"

1'

M

IN

M A X3

6" 3'-0"

1'-6"

1'

T O R

IM

WALL-MOUNTED

SINK

W.C., GRAB BARS,

ETC.

PAPER TOWEL

DISPENSER

MIRROR

T O B

O T T O M

O F

R E F L E C T

IN

G

S U F A C E

T O B

O T T O M

O F

D

IS

P E N S E R

3'-0"

M

IN

M

A X

GRAB BARW.C., GRAB BARS,

ETC.

RESTROOM

DOOR

C L

P U S H P

L A T E S

H A N D

L E S P

U S H

B A R

S

C L

D E A D

B O L T S

S

IG

N A G

E

C L

1'-6" 1'-6"

C L

5'-0" MIN

1'

M

IN

1'

M

IN

1'-0" MAX

SINK 60" X 60"

CLEAR

FLOOR

SPACE

CLEAR FLOOR SPACE

AT W.C.

CLEAR FLOOR SPACE

AT SINKS

4'-0" MIN

1'-7"

MAX

1'-5" MIN

M

IN

4'-0"

MAX FORWARD REACH

OVER OBSTRUCTION

17"-19"

4'-0"

MAX HIGH AND LOW

SIDE REACH

M A X

SALES AND SERVICE

COUNTERTOP HEIGHT

904.3.2 PARALLEL

APPROACH

M A X

2'-0" MAX SIDE

REACH

1'

M A X

1'-8

MAX

M A X

M A X

1'-8" to 1'-11"

MAX

REACH w/ 0"-20"

OBSTRUCTION

REACH w/ 20"-23"

OBSTRUCTION

MAX HIGH AND LOW

FRONT REACH

MIN. CLEAR OF

OBSTRUCTION

PLUMBING FIXTURES AND ACCESSORIES

REACHING HEIGHTS AND LENGTHS

SCALE:E1 FLOOR PLAN

1/4" = 1'-0"

N O R T H

N O R T H

PER 2017 ICC A117.1

PER 2017 ICC A117.1

FO

R

ES

TR

Y

SU

R

VE

YI

N

G

EN

G

IN

EE

R

IN

G

N A

TU

R

A L

R

ES

O U

R C

ES

LA

N D

SC

A

PE

A

R C

H

IT

EC

TU

R E

PL

A

N N

IN

G

A L

O H

A H

IG

H

S C

H O

O L

B

A T

T

IN

G C

A G

E S

B E

A V

E R

T O

N S

C H

O O

L D

IS

T

R

IC

T W

A S

H

IN

G T

O N

C O

U N

T Y

, O R

E G

O N

SW

2n d

AV

EN

UE

, S

UI

TE

TU

AL

AT

IN

, O

R

P

3.

2.

A001

ABV

ABOVE

ACOUS ACOUSTICAL

ACP

AD

ACOUSTICAL CEILING PANEL

AREA DRAIN

ADDL ADDITIONALADDITIONAL

ADJ

AFF

ADJACENT

AFG

ABOVE FINISH FLOOR

ABOVE FINISH GRADE

AGGR

ALUM

AGGREGATE

ALT

ALUMINUM

ANOD

ALTERNATE

APPROX

ANODIZED

ARCH

APPROXIMATE(LY)

ARCHITECT(URAL)

ASPH ASPHALT

AUTO AUTOMATIC

BB

B

BULLETIN BOARD

BD BOARD

BTWN

BLDG

BETWEEN

BUILDING

BM

BOT

BEAM

BOTTOM

BITUM BITUMINOUS

BOS BOTTOM OF STEEL

BRG BEARING

BSMT BASEMENT

CAB

C

CABINET

CB CATCH BASIN

CCT

CG

CUBICLE CURTAIN TRACK

CORNER GUARD

CEM CEMENT, CEMENTITIOUS

CCTV CLOSED CIRCUIT TELEVISION

CH BD CHALKBOARD

CI CAST IRON

CJ CONTROL JOINT

CL

CLG

CLR

CMU

CNTR

COL

CONC

CONF

CONN

CONSTR

CONT

CONTR

CPT

CSK

CSP

CSWK

CW

CENTER LINE

CEILING

CLEAR

CONCRETE MASONRY UNIT

COUNTER

COLUMN

CONCRETE

CONFERENCE

CONNECTION

CONSTRUCTION

CONTINUOUS

CONTRACTOR

CARPET

COUNTERSUNK

COMBINATION STANDPIPE

CASEWORK

COLD WATER

D

D

DEPTH

DBL DOUBLE

DBL ACT DOUBLE ACTING

DEG DEGREE

DEMO DEMOLISH

DEPT DEPARTMENT

DET DETAIL

DF DRINKING FOUNTAIN

DIA DIAMETER

DIAG DIAGONAL

DIFF DIFFUSER

DIM DIMENSION

DIM PT DIMENSION POINT

DISP DISPENSER

DIST DISTANCE

DN DOWN

DR DRAIN

DS DOWNSPOUT

DSP DRY STANDPIPE

DT DRAPERY TRACK

DWG DRAWING

DWGS DRAWINGS

(E)

E

EXISTING

EA EACH

EDR EQUIPMENT DRAIN

EG EDGE GUARD

EIFS EXTERIOR INSULATION FINISH SYSTEM

EL ELEVATION

ELAST ELASTOMERIC

ELEC ELECTRICAL

ELEV ELEVATOR

EMER EMERGENCY

ENCL ENCLOSURE

ENGR ENGINEER

EOS EDGE OF SLAB

EP ELECTRICAL PANEL

EPDM ETHYLENE PROPYLENE DIENE MONOMER

EQ EQUAL

EQL SP EQUALLY SPACED

EQUIP EQUIPMENT

EQUIV EQUIVALENT

EST ESTIMATE(D)

EWC ELECTRIC WATER COOLER

EXP EXPANSION

EXP JT EXPANSION JOINT

EXT EXTERIOR

FURN FURNITURE

FXTR FIXTURE

G

G

GAS

H

H

HIGH

GA GAUGE, GAGE

GAL GALLON

GALV GALVANIZED

GB GRAB BAR

GC GENERAL CONTRACTOR

GFRC GLASS FIBER REINFORCED CONCRETE

GFRG GLASS FIBER REINFORCED GYPSUM

GL GLASS

GLU LAM GLUE LAMINATED

GLZ GLAZING

GR GRADE OR GRADING

GVL GRAVEL

GYP GYPSUM

GYP BD GYPSUM BOARD

GYP PLAS GYPSUM PLASTER

ID

I

INSIDE DIAMETER

JAN

J

JANITOR

KG

K

KILOGRAM

L L

LENGTH, LONG

M

M

METER (S)

(N)

N

NEW

QT

Q

QUARRY TILE

R

R

RISER

S SOUTH

T

T

TREAD

W

W

WEST

XFMR

X

TRANSFORMER

YD

Y

YARD

HB HOSE BIBB

HC HOLLOW CORE

HD HEAD

HDBD HARDBOARD

HDW HARDWARE

HDWD HARDWOOD

HGT HEIGHT

HM HOLLOW METAL

HNDRL HANDRAIL

HORIZ HORIZONTAL

HPT HIGH POINT

HR HOUR

HVAC HEATING-VENTILATION-AIR CONDITIONING

IN INCH

INCL INCLUDE, INCLUDING

INFO INFORMATION

INSUL INSULATION

INTR INTERIOR

INV INVERT

IVT INTRAVENOUS TRACK

JST JOIST

JT JOINT

KIT KITCHEN

KPL KICK PLATE

KS KNEE SPACE

LAB LABORATORY

LAM LAMINATE, LAMINATION

LAV LAVATORY

LB POUND

LED LIGHT EMITTING DIODE

LF LINEAR FOOT

LIN LINEAR

LL LEAD LINED

LPT LOW POINT

LT LIGHT

LT WT LIGHT WEIGHT

LTG LIGHTING

LVR LOUVER

HW HOT WATER

S

MACH MACHINE

MATL MATERIAL

MATV MASTER ANTENNA TELEVISION SYSTEM

MAX MAXIMUM

MB MACHINE BOLT

MC MEDICINE CABINET

MDF MEDIUM DENSITY FIBERBOARD

MECH MECHANICAL

MED MEDIUM

MEMB MEMBRANE

MFR MANUFACTURER

MH MANHOLE

MIN MINIMUM

MISC MISCELLANEOUS

MELD MOLDING

MM MILLIMETERS

MO MASONRY OPENING

MOD MODULE, MODULAR

MTD MOUNTED

MTG MOUNTING

MOVABLE MOVABLE

MULL MULLION

DNA NOT APPLICABLE

NAT NATURAL

NE NORTHEAST

NIC NOT IN CONTRACT

NO NUMBER

NOM NOMINAL

RC NOISE REDUCTION COEFFICIENT

NTS NOT TO SCALE

NW NORTHWEST

PLAS PLASTER

PLBG PLUMBING

PLF POUNDS PER LINEAR FOOT

PLYWD PLYWOOD

PNL PANEL

PNL BD PANEL BOARD

PNT PAINT

PORT PORTABLE

PP PUSH PLATE

PPM PARTS PER MILLION

PR PAIR

PRCST PRECAST

PREP PREPARATION / PREPARE

PREFAB PREFABRICATED

PRKG PARKING

PROJ PROJECT

PROP PROPERTY

PSF POUNDS PER SQUARE FOOT

PSI POUNDS PER SQUARE INCH

PT POINT

PTN PARTITION

PTS PNEUMATIC TUBE STATION / SYSTEM

PVC POLYVINYL CHLORIDE

PVG PAVING

PVMT PAVEMENT

PWR POWER

QTR QUARTER

QTY QUANTITY

RA RETURN AIR

RAD RADIUS

RB RESILIENT BASE

RCP REFLECTED CEILING PLAN

RCPT RECEPTACLE

RD ROOF DRAIN

RECT RECTANGULAR

REF REFERENCE

REFR REFRIGERATOR

REG REGISTER

REINF REINFORCE (D) (ING) (MENT)

REQD REQUIRED

REQT REQUIREMENT

RESIL RESILIENT

RET RETURN

REV REVISION

RF RESILIENT FLOORING / RADIO FREQUENCY

RH RIGHT HAND

RHMS ROUND HEAD MACHINE SCREW

RHWS ROUND HEAD WOOD SCREW

RM ROOM

RND ROUND

RO ROUGH OPENING

ROW RIGHT OF WAY

RWL RAIN WATER LEADER

SB SPLASH BLOCK

SC SOLID CORE

SCHED SCHEDULE, SCHEDULED

SCRN SCREEN

SD STORM DRAIN

SE SOUTHEAST

SECT SECTION

SEG SEGMENT

SEP SEPARATION OR SEPARATE

SEP JT SEPARATION JOINT

SHT SHEET, SHEETING

SHWR SHOWER

SIM SIMILAR

SJ SEISMIC JOINT

SK SINK

SMS SHEET METAL SCREW

SP SPACE, SPACED, SPACING

SPEC SPECIFICATION

SPKLR SPRINKLER

SPKR SPEAKER

SQ SQUARE

SS SANITARY SEWER

SSK SERVICE SINK

SST STAINLESS STEEL

ST STREET

STA STATION

STAG STAGGERED

STC SOUND TRANSMISSION COEFFICIENT

STD STANDARD

STL STEEL

STOR STORAGE

STRUCT STRUCTURAL

STS SELF-TAPPING SCREW

SUSP SUSPENDED

SUSP CLG SUSPENDED CEILING

SW SOUTHWEST

SYMM SYMMETRICAL

SYST SYSTEM

T&B TOP AND BOTTOM

T&G TONGUE AND GROOVE

TC TOP OF CONCRETE, TOP OF CURB

TD TRENCH DRAIN

TEL TELEPHONE

TEMP TEMPORARY

THERM THERMAL

THK THICK, THICKNESS

THRES THRESHOLD

THRU THROUGH

TMPD GL TEMPERED GLASS

TO TOP OF

TOR TOP OF RAILING

TOS TOP OF STEEL

TOT TOTAL

TOW TOP OF WALL

TP TOP OF PAVEMENT

TV TELEVISION

UC

U

UNDER COUNTER

TYP TYPICAL

UL UNDERWRITERS LABORATORIES

Uno UNLESS NOTED OTHERWISE

UPS UNINTERRUPTABLE POWER SUPPLY

UTIL UTILITY

W/ WITH

W/O WITHOUT

WC WATER CLOSET OR WALL COVERING

WD WOOD

WDW WINDOW

WGL WIRE GLASS

WCHR WHEELCHAIR

WM WIRE MESH

WO WHERE OCCURS

WPT WORKING POINT

WR WATER RESISTANT

WSCT WAINSCOT

WSP WET STANDPIPE

WT WEIGHT

WTHPRF WEATHERPROOF

WWF WELDED WIRE FABRIC

WWM WELDED WIRE MESH

CR CARD READER

BUR BUILT UP ROOFING SYSTEM

CT CERAMIC TILE / COMPUTED TOMOGRAPHY

F

FA FIRE ALARM

FBD FIBERBOARD

FCU FAN COIL UNIT

FD FLOOR DRAIN

FDC FIRE DEPARTMENT CONNECTION

FDN FOUNDATION

FEC FIRE EXTINGUISHER CABINET

FE FIRE EXTINGUISHER

FF FINISH FACE

FHC FIRE HOSE CABINET

FHMS FLAT HEAD MACHINE SCREW

FHWS FLAT HEAD WOOD SCREW

FHY FIRE HYDRANT

FLAM FLAMMABLE

FLASH FLASHING

FLEX FLEXIBLE

FLUOR FLUORESCENT

FO FACE OF

FSB FOLDING SHOWER BENCH

FSTNR FASTENER

FT FOOT, FEET

OC

O

ON CENTER

PA PUBLIC ADDRESS

OA OVERALL

OD OUTSIDE DIAMETER

OFCI

OFOI

OPP OPPOSITE

ORD OVERFLOW ROOF DRAIN

OVHD OVERHEAD

OZ OUNCE

PART PARTIAL

PBD PARTICLEBOARD

PCF POUNDS PER CUBIC FOOT

PCI POUNDS PER CUBIC INCH

PERF PERFORATED

PERIM PERIMETER

PERM PERMANENT

PERP PERPENDICULAR

PL PLATE OR PROPERTY LINE

PLAM PLASTIC LAMINATE

P

OWNER FURNISHED-CONTRACTOR INSTALLED

OWNER FURNISHED-OWNER INSTALLED

V

VB VALVE BOX

VCT VINYL COMPOSITION TYLE

VERT VERTICAL

VEST VESTIBULE

VIT VITREOUS

VP VENT PIPE

VOL VOLUME

VWC VINYL WALL COVERING

SYMBOLS AS

ABBREVIATIONS

ANGLE

@ AT

C CENTER LINEL

Ø DIAMETER

= EQUAL

> GREATER THAN

< LESS THAN

± PLUS OR MINUS (TOLERANCE)

# POUND(S)

' FOOT OR FEET

" INCH OR INCHES

FOF FACE OF FINISH

OH OPPOSITE HAND

HSS HOLLOW STRUCTURAL STEEL

SA SUPPLY AIR

A AIR

AB ANCHOR BOLT

ACT ACOUSTICAL CEILING TILE

AVG AVERAGE

BKG BACKING

BLW BELOW

BG BUMPER GUARD

EJ EXPANSION JOINT

EF EACH FACE

E EAST

FB FLAT BAR

O OXYGEN

N NORTH

MRI MAGNETIC RESONANCE IMAGING

LVT LUXURY VINYL TILES

FHV FIRE HOSE VALVE

FTG FOOTING

WP WATERPROOF (ING)

UR URINAL

VIF VERIFY IN FIELD

VNR VENEER

DEGREE (S) OF ANGULAR

MEASURE

o

MTL METAL

VC VA PROVIDED, CONTRACTOR INSTALLED

VV VA PROVIDED AND INSTALLED

COORD COORDINATE

PL PLATE

AESS ARCHITECTURALLY EXPOSED STRUCTURAL STEEL

PCF POUNDS PER CUBIC FOOT

FLRG FLOORING

TRANS TRANSITION

LLV LONG LEG VERTICAL

FSK FOIL SCRIM KRAFT

S

GENERAL NOTES

1. VERIFY AND COORDINATE SITE CONDITIONS AND DIMENSIONS. BRING INCONSISTENCIES TO

ATTENTION OF ARCHITECT BEFORE PROCEEDING WITH WORK.

2. PROVIDE SHORING AND BRACING AS NECESSARY TO ENSURE STRUCTURAL INTEGRITY WHEN

WORK INCLUDES STRUCTURAL MEMBERS.

3. IMMEDIATELY BRING ERRORS AND OMISSIONS FOUND IN THESE DRAWINGS TO ATTENTION OF

ARCHITECT. WHERE CONTRACTOR IS AWARE OF CONFLICTS OR OMISSIONS AND HAS NOT

BROUGHT THEM TO ARCHITECT'S ATTENTION, IT IS UNDERSTOOD THAT CONTRACTOR HAS

MADE PROVISIONS FOR MORE COSTLY AND STRINGENT METHOD. WHERE CONFLICTS,

ERRORS OR OMISSIONS OCCUR IN DRAWINGS, PROJECT MANUAL, OR OTHER RELATED

CONTRACT DOCUMENT PROVISIONS SUCH AS MANUFACTURER'S INSTRUCTIONS, REFERENCE

STANDARDS, AND REGULATORY AGENCIES AND CODES, ASSUME MORE STRINGENT

REQUIREMENTS AND VERIFY WITH ARCHITECT BEFORE BEGINNING WORK.

4. DO NOT SCALE DRAWINGS. FOLLOW DIMENSIONS SHOWN ON DRAWINGS AND ACTUAL FIELD

MEASUREMENTS. NOTIFY ARCHITECT OF DISCREPANCIES.

5. ALL DIMENSIONS ARE TO FACE OF STUD, FACE OF CONCRETE AND MASONRY, FACE OF

FRAMING OR CENTERLINE OF COLUMNS, UNLESS NOTED OTHERWISE.

6. COMPLY WITH BUILDING CODES AND OTHER APPLICABLE CODES AND ORDINANCES.

7. WORK INSTALLED IN CONFLICT WITH CONSTRUCTION DOCUMENTS IS NON-CONFORMING WORK

AND REQUIRES CORRECTION AT NO ADDITIONAL COST TO OWNER AS DIRECTED BY

ARCHITECT.

8. COORDINATE WORK IN COMPLIANCE WITH DRAWINGS AND SPECIFICATIONS TO ACCURATELY

LOCATE MECHANICAL, ELECTRICAL, AND OTHER PENETRATIONS AND SYSTEMS WITH

RESPECT TO STRUCTURAL FRAMING. DO NOT PENETRATE STRUCTURAL FRAMING EXCEPT

AS ACCEPTED BY ARCHITECT.

9. FOLLOW MANUFACTURERS' INSTRUCTIONS EXCEPT WHERE MORE STRINGENT REQUIREMENTS

ARE INDICATED OR REQUIRED BY CODE.

10. VERIFY WITH ARCHITECT AND PROVIDE REQUIRED BLOCKING AND BACKING FOR WALL OR

CEILING MOUNTED ITEMS.

11. COORDINATE SIZES AND LOCATIONS OF OPENINGS AND ROUGH-INS FOR MECHANICAL

EQUIPMENT WITH MECHANICAL CONTRACTOR, AND SHOP DRAWINGS APPROVED BY

ARCHITECT, BEFORE PROCEEDING WITH THE WORK.

12. ALL PIPE, CONDUIT, DUCTS AND STRUCTURE TO BE CONCEALED BEHIND FINISHED

CONSTRUCTION UNLESS NOTED AS EXPOSED TO VIEW ON DRAWINGS OR APPROVED BY

ARCHITECT.

13. OFFSET AND ADJUST NON-LOAD BEARING FRAMING AS NECESSARY TO MAKE FINISHED

SURFACES FLUSH AND TRUE TO LINE.

14. PROVIDE GALVANIC ISOLATION BETWEEN DISSIMILAR METALS.

15. VERIFY BLOCKING & BACKING REQUIREMENTS WITH EQUIPMENT SUPPLIERS

16. NOTES INCLUDING "AS REQUIRED" INDICATE AS REQUIRED BY LOCAL JURISDICTION, VERIFY

REQUIREMENTS PRIOR TO BID AND BEGINNING THE WORK.

17. NOTES INCLUDING "COMPLETE" INDICATE ALL ASSEMBLIES & APPURTENANCES ASSOCIATED

WITH AN ASSEMBLY THAT ARE REQUIRED FOR THE PROPER INSTALLATION AND OPERATION

OF THAT ASSEMBLY OR THE FULL AND ENTIRE REMOVAL OF THAT ASSEMBLY

18. THE DRAWINGS ARE INTENDED TO GRAPHICALLY ILLUSTRATE THE OVERALL NATURE OF THE

WORK; THE CONFIGURATION, ARRANGEMENT, AND LOCATION OF THE WORK AND ITS PARTS;

AND THE PHYSICAL DIMENSIONS OF THE WORK - THE DRAWINGS TAKE PRECEDENCE OVER

THE SPECIFICATIONS WITH RESPECT TO INFORMATION OF THIS NATURE.

19. THE SPECIFICATIONS ARE INTENDED TO COMMUNICATE THE DETAILED PROPERTIES AND

QUALITY OF THE INDIVIDUAL MATERIALS, ASSEMBLIES, AND SYSTEMS THAT COMPRISE THE

WORK; THE FUNCTIONAL AND PERFORMANCE REQUIREMENTS FOR THE INDIVIDUAL PARTS OF

THE WORK; AND THE FABRICATION AND INSTALLATION REQUIREMENTS FOR INDIVIDUAL PARTS

OF THE WORK - THE SPECIFICATIONS TAKE PRECEDENCE OVER THE DRAWINGS WITH

RESPECT TO INFORMATION OF THIS NATURE.

20. AS PART OF THE CONTRACTOR'S RESPONSIBILITY TO COORDINATE THE WORK OF ALL SUB-

CONTRACTORS, TRADES, AND SUPPLIERS, THE CONTRACTOR SHALL ENDEAVOR TO IDENTIFY

AND NOTIFY THE VA REPRESENTATIVE OF ANY CONFLICTS AT THE EARLIEST POSSIBLE DATE

SO AS TO ALLOW REASONABLE AND ADEQUATE TIME FOR THE CONFLICT TO BE RESOLVED

WITHOUT DELAYING THE WORK, ALL DEVIATIONS FROM THAT WHICH IS REQUIRED BY THE

CONTRACT DOCUMENTS MUST BE APPROVED IN ADVANCE BY THE VA REPRESENTATIVE.

21. THE ARCHITECTURAL DRAWINGS ARE A PART OF A LARGER SET OF DRAWINGS WHICH, WHEN

COMPLETE, CONSISTS OF ALL DRAWINGS LISTED BY THE INDEX OF DRAWINGS, THE WORK

DESCRIBED BY THE DRAWINGS OF ANY ONE DISCIPLINE MAY BE AFFECTED BY THE WORK

DESCRIBED ON DRAWINGS OF ANOTHER DISCIPLINE AND MAY REQUIRE REFERENCE TO

THE DRAWINGS OF ANOTHER DISCIPLINE. PARTIAL SETS OF DRAWINGS ARE INCOMPLETE

AND SHOULD NOT BE DISTRIBUTED OR UTILIZED BY THE CONTRACTOR. IT IS THE

CONTRACTOR'S RESPONSIBILITY TO REVIEW AND COORDINATE THE WORK OF ALL

SUB-CONTRACTORS, TRADES, AND SUPPLIERS WITH ALL REQUIREMENTS OF THE CONTRACT

DOCUMENTS BEFORE COMMENCING CONSTRUCTION, AND TO ASSURE THAT ALL PARTIES ARE

AWARE OF ALL REQUIREMENTS, REGARDLESS OF WHERE THE REQUIREMENTS OCCUR IN THE

CONTRACT DOCUMENTS, WHICH MIGHT AFFECT THE WORK OF THAT PARTY.

22. THE ARCHITECTURAL DRAWINGS ESTABLISH AND COORDINATE THE FINISHED APPEARANCE

AND EXACT LOCATION OF ALL EXPOSED ELEMENTS OF THE WORK OF ALL TRADES,

INCLUDING THAT WORK WHICH IS ILLUSTRATED PRIMARILY ON DRAWINGS OF OTHER

DISCIPLINES, LOCATIONS SHOWN ON OTHER DRAWINGS ARE SCHEMATIC, UNLESS OTHERWISE

NOTED ON THE ARCHITECTURAL DRAWINGS. THE ARCHITECTURAL DRAWINGS TAKE

PRECEDENCE FOR THE FINISHED APPEARANCE AND EXACT LOCATION OF ALL PARTS OF

THE WORK.

EXCEPTION: DIMENSIONED LOCATIONS SHOWN ON DRAWINGS OF OTHER DISCIPLINES SHALL

GOVERN ONLY WHERE:

1. SPECIFICALLY AND INDIVIDUALLY INDICATED BY SYMBOL, KEYED NOTE, OR NOTATION

ON THE ARCHITECTURAL DRAWINGS.

2. OCCURRING WITHIN A ROOM OR OTHER IDENTIFIED SPACE FOR WHICH ARCH SHEET OR

SCHEDULE NOTES INDICATE THAT DIMENSIONS PROVIDED ELSEWHERE SHALL GOVERN.

23. THE ARCHITECTURAL FLOOR PLANS, REFLECTED CEILING PLANS, SECTIONS, AND ELEVATIONS

ILLUSTRATE THE EXACT LOCATION OF MANY, BUT NOT ALL, EXPOSED PARTS OF THE WORK,

APPLY THE RULES INDICATED BY THE DRAWING "TYPICAL MOUNTING HEIGHTS AND

CONFIGURATION DIAGRAMS" TO DETERMINE THE EXACT LOCATION OF EACH EXPOSED PART

OF THE WORK.

24. REFER TO THE STRUCTURAL, MECHANICAL, ELECTRICAL, AND PLUMBING DRAWINGS FOR THE

DETAILED DESIGN OF STRUCTURAL, MECHANICAL, ELECTRICAL, AND PLUMBING SYSTEMS, OF

WHICH PORTIONS MAY BE SHOWN ON THE ARCHITECTURAL DRAWINGS.

25. FINISH FLOOR ELEVATIONS ARE TO TOP OF CONCRETE FLOOR SLAB, Uno. WHERE THE

CONCRETE IS DEPRESSED TO ACCOMMODATE MORTAR BEDS, SETTING BEDS, RAISED

ACCESS FLOORS, AND OTHER SIMILAR FLOOR ASSEMBLIES, FINISHED FLOOR ELEVATIONS

ARE TO TOP OF FINISH FLOOR ASSEMBLY INDICATED.

26. CEILING HEIGHT DIMENSIONS ARE TO FINISHED SURFACES, UNLESS OTHERWISE NOTED.

FO

R

ES

TR

Y

SU

R

VE

YI

N

G

EN

G

IN

EE

R

IN

G

N A

TU

R

A L

R

ES

O U

R C

ES

LA

N D

SC

A

PE

A

R C

H

IT

EC

TU

R E

PL

A

N N

IN

G

A L

O H

A H

IG

H

S C

H O

O L

B

A T

T

IN

G C

A G

E S

B E

A V

E R

T O

N S

C H

O O

L D

IS

T

R

IC

T W

A S

H

IN

G T

O N

C O

U N

T Y

, O R

E G

O N

SW

2n d

AV

EN

UE

, S

UI

TE

TU

AL

AT

IN

, O

R

P

3.

2.

A002

36'-0"

5'-8" 12'-4" 12'-4" 5'-8"

5'-8" 12'-4" 12'-4" 5'-8"

9'-4"

8'-0" 8'-0"

E

Q U A L S

P A C E S

A201

SCALE:1 FLOOR PLAN

3/16" = 1'-0"

FLOOR PLAN KEYNOTES

1. pemb steel stucture (tbd)

2. potential brace frame (tbd)

3. steel canopy above (by pemb)

4. 3'-4"W X 4'-8"H WHITE FIXED vinyl windows W/ TEMPERED GLASS

5. 8' x 8' high lift INSULATED overhead door

6. 55'L x 12'w x 12'h batting cage netting - of/oi

7. 2" x 2" 10 gage wire mesh in 1" x 1/4" steel frame window guard - cf/ci

8. artificial turf, to be selected by owner - cf/ci

9. 5/8" high impact gyp board over 1-1/2" metal furring on all walls

FO

R

ES

TR

Y

SU

R

VE

YI

N

G

EN

G

IN

EE

R

IN

G

N A

TU

R

A L

R

ES

O U

R C

ES

LA

N D

SC

A

PE

A

R C

H

IT

EC

TU

R E

PL

A

N N

IN

G

A L

O H

A H

IG

H

S C

H O

O L

B

A T

T

IN

G C

A G

E S

B E

A V

E R

T O

N S

C H

O O

L D

IS

T

R

IC

T W

A S

H

IN

G T

O N

C O

U N

T Y

, O R

E G

O N

SW

2n d

AV

EN

UE

, S

UI

TE

TU

AL

AT

IN

, O

R

P

3.

2.

SCALE:2 CEILING PLAN

3/16" = 1'-0" SCALE:3 ROOF PLAN

3/16" = 1'-0"

CEILING PLAN KEYNOTES

1. pendant light fixtures with wire impact protection cages, see electrical

ROOF PLAN KEYNOTES

1. sheet metal gutters

2. sheet metal downspout, see civil for storm connections

A301

A301

A301

1 2 1 2 1 2

A

B

C

D

A

B

C

D

A

B

C

D

1 1

2 2

A A

A A

N O R T H N

N O R T H N

N O R T H N

2'-0"

3'-0"

20'-0"

4'-3" 4'-3"

19'-6"

2'-0"

2'-0"

T Y P

" 2

2'-0"

2'-0"

9'-4"

1"

A301

SCALE:3 WEST ELEVATION

3/16" = 1'-0"

FO

R

ES

TR

Y

SU

R

VE

YI

N

G

EN

G

IN

EE

R

IN

G

N A

TU

R

A L

R

ES

O U

R C

ES

LA

N D

SC

A

PE

A

R C

H

IT

EC

TU

R E

PL

A

N N

IN

G

A L

O H

A H

IG

H

S C

H O

O L

B

A T

T

IN

G C

A G

E S

B E

A V

E R

T O

N S

C H

O O

L D

IS

T

R

IC

T W

A S

H

IN

G T

O N

C O

U N

T Y

, O R

E G

O N

SW

2n d

AV

EN

UE

, S

UI

TE

TU

AL

AT

IN

, O

R

P

3.

2.

SCALE:1 SOUTH ELEVATION

3/16" = 1'-0"

BUILDING ELEVATION KEYNOTES

1. vertical ribbed seam siding (by pemb)

2. horizontal 1-1/2" corrugated siding (by pemb)

3. 3'-4"W X 4'-8"H WHITE FIXED vinyl windows W/ TEMPERED GLASS

4. insulated HOLLOW METAL door

5. 8'w x 8'h insulated manual overhead door

6. school signage (tbd)

7. steel canopy and tie rods (by pemb)

8. standing seam metal roofing (by pemb)

9. sheet metal gutter (by pemb)

10. sheet metal downspouts (by pemb)

11. wall pack light fixtures, cf/ci

12. 6" exposed SEALED concrete stem wall

13. 1/2" PAINTED STEEL SUPPORT RODS AND TURNBUCKLES

14. METAL SOFFIT, BY PEMB SUPPLIER, TYP.

SCALE:5 BUILDING SECTION

1/4" = 1'-0"

SCALE:2 NORTH ELEVATION

3/16" = 1'-0"

SCALE:4 EAST ELEVATION

3/16" = 1'-0"

A3

01 5 A3

BUILDING SECTION KEYNOTES

1. pemb structure

2. pendent lights with wire cages, see electrical

3. 12'h batting cage netting of/oi

4. steel mesh window guard, see 6/a601

5. insulated high lift overhead doors

6. artificial turf over compacted crushed gravel base.

per manufacturers recommendation

7. batt insulation with banded liner system, by pemb supplier; 1-1/2" METAL FURRING WITH 5/8" GYP. BOARD ON

ALL WALLS

8. standing seam metal roofing, per pemb supplier

9. asphalt paving, see civil

10. r-15 rigid insulation at perimeter, typ

11. SEALED EXPOSED CONCRETE STEM WALL., TYP.

12. METAL SOFFIT, BY PEMB SUPPLIER, TYP.

13. 5/8" high impact gyp board over 1-1/2" metal furring on all walls

A B C D

1 2 2 1

D C B A

X

5 2 1

4 4

6 910

A301

SCALE:6 STEM WALL

1-1/2" = 1'-0" metal siding, per elevations by pemb supplier

BASE FLASHING, by pemb supplier

STEM WALLTURF OVER 6" COMPACTED

GRAVEL BASE

14 14

3'-4"

A601

FO

R

ES

TR

Y

SU

R

VE

YI

N

G

EN

G

IN

EE

R

IN

G

N A

TU

R

A L

R

ES

O U

R C

ES

LA

N D

SC

A

PE

A

R C

H

IT

EC

TU

R E

PL

A

N N

IN

G

A L

O H

A H

IG

H

S C

H O

O L

B

A T

T

IN

G C

A G

E S

B E

A V

E R

T O

N S

C H

O O

L D

IS

T

R

IC

T W

A S

H

IN

G T

O N

C O

U N

T Y

, O R

E G

O N

SW

2n d

AV

EN

UE

, S

UI

TE

TU

AL

AT

IN

, O

R

P

3.

2.

DOOR SCHEDULE

DOORSIZE FRAME

HEIGHTWIDTH THK. MATERIAL MATERIAL FINISH NOTES:FINISH

DOOR TAG

HARDWARE

GROUP

MANUF. 8'-0" 1 3/4"8'-0"OVERHEAD MANUFSTEEL STEEL

A 7'-0" 1 3/4"3'-0"FLUSH PAINTHM HM

INSULATED MANUAL OPERATION

Type A ENTRANCE LOCKSET (EXTERIOR SIDE); KEYING PER SCHOOL DISTRICT STANDARD

PANIC DEVICE (INTERIOR SIDE)

1-1/2 PAIR STAINLESS STEEL BUTTS (NRP)

WEATHER SEALS

DOOR BOTTOM

max. 1/2' high ADA compliantaluminum THRESHOLD

HARDWARE SCHEDULE

INSULATED DOOR AND FRAME

DOOR

TYPE

MANUF

PAINT

SCALE:

DOOR TYPES

3/8" = 1'-0" SCALE:

WINDOW TYPES

3/8" = 1'-0"

A1 2

SCALE:1 DOOR THRESHOLD

3" = 1'-0" SCALE:2 DOOR HEAD

3" = 1'-0" SCALE:3 DOOR JAMB

3" = 1'-0"

HOLLOW METAL DOOR/FRAME

FACE OF PEMB

SLOPE CONCRETE SLAB AWAY FROM

BUILDING

THRESHOLD TO MEET ADA

ACCESSIBILITY REQUIREMENTS; SET IN

CONTINUOUS BED OF SEALANT

EXTERIOR PAVEMENT

5/8" high impact GYP. BOARD

INTERIOR FINISH; PAINTED

1-1/2" LIGHT GAGE FURRING on all walls

METAL PANEL SIDING, PER ELEVATIONS

INSULATION LINER, PER PEMB SUPPLIER

STEEL GIRT, BY PEMB SUPPLIER

FLASHING BY PEMB SUPPLIER

INSULATED METAL DOOR FRAME

INSULATED HOLLOW METAL DOOR

EXTERIORINTERIOR

METAL SIDING, PER ELEVATIONS

FLASHING, PER PEMB SUPPLIER

SEALANT, ALL AROUND DOOR FRAME

INSULATED HOLLOW METAL DOOR

INSULATED METAL DOOR FRAME

INSULATION LINER, BY PEMB

SEALANT ALL AROUND DOOR FRAME

STEEL JAMB FRAMING BY PEMB

SUPPLIER

1-1/2" LIGHT GAGE FURRING

5/8" high impact GYP. BOARD

INTERIOR FINISH; PAINTED

SCALE:4 OVERHEAD DOOR HEAD

3" = 1'-0"

OVERHEAD DOOR AND TRACK; BY GC

METAL SIDING, PER ELEVATIONS

INSULATION LINER, PER PEMB

STEEL GIRT HEAD AND JAMB FRAMING,

BY PEMB

FLASHING ON ALL SIDES OF OPENING, BY

PEMB

EXTERIORINTERIOR

SCALE:5 OVERHEAD DOOR JAMB

3" = 1'-0"

METAL SIDING, PER ELEVATIONS

FLASHING AROUND OPENING, BY PEMB

STEEL JAMB FRAMING, BY PEMB

INSULATION LINER, BY PEMB

OVERHEAD DOOR AND TRACK, BY GC

1-1/2" LIGHT GAGE FURRING

5/8" high impact GYP. BOARD

INTERIOR FINISH; PAINTED

A6

01 2 A6

A601

A601 1

A6

SCALE:6 WINDOW JAMB

3" = 1'-0" cover trim on all sides, by pemb vinyl window

4" x 2" lag bolt with spacer washer

(2) 1/8" welded steel frame

1.5" x 1.5" x .0120" wire mesh, weld to frame

A601

NOT FOR

CONSTRUCTION

EN

G

IN

EE

R

IN

G

SU

R

VE

YI

N

G

FO

R

ES

TR

Y

N A

TU

R

A L

R

ES

O U

R C

ES

LA

N D

SC

A

PE

A

R C

H

IT

EC

TU

R E

PL

A

N N

IN

G

A L

O H

A H

IG

H

S C

H O

O L

A T

H L

E T

IC

P

R O

G R

A M

IM

P

R O

V M

E N

T S

W A

S H

IN

G

T O

N C

O U

N T

Y O

R E

G O

N

C070

G R

A D

IN

G

P

LA

N

GRADING LEGEND

ADA EGRESS GATE DETAIL 3

C070

STEP DETAIL 1

C070

FILTER CATCHBASIN 2

C070

FO

ES

TR

Y

SU

R

VE

YI

N

G

EN

G

IN

EE

R

IN

G

N A

TU

R

A L

R

ES

O U

R C

ES

LA

N D

SC

A

PE

A

R C

H

IT

EC

TU

R E

PL

A

N N

IN

G

SW

2n d

AV

EN

UE

, S

UI

TE

TU

AL

AT

IN

, O

R

P

3.

2.

Po rtl an d, O R

Be nd , O

R

D en ve r, C O e n g in e e r s fro el ic h-en gi ne er s.

co m

FE

-T inc

C

IV

IL

à S

T R

U C

T U

R A L

S T

RUCTURAL

PRELIM

IN

ARY

NOT FOR

CONSTRUCTIO

N

A L

O H

A H

IG

H

S C

H O

O L

B

A T

T

IN

G C

A G

E S

B E

A V

E R

T O

N S

C H

O O

L D

IS

T

R

IC

T W

A S

H

IN

G T

O N

C O

U N

T Y

, O R

E G

O N

S001

C O

V E

R S

H E

E T

STRUCTURAL SYMBOLS / LEGEND:

- INDICATES FOOTING TYPE, REF SCHEDULE.-

- INDICATES STRUCTURAL COLUMN STARTING AT THIS LEVEL.

REF COLUMN SCHEDULE.

XX

- INDICATES CONCRETE WALL

- INDICATES CMU WALL.

- INDICATES STRUCTURAL WALL.

- INDICATES NON-STRUCTURAL WALL.

- INDICATES LINTEL TYPE. REF. SCHEDULE.L-

- INDICATES DIRECTION DECK OR SHEATHING TO SPAN.

- INDICATES ELEVATION.

- INDICATES KEYED NOTE.#

- INDICATES SNOW DRIFT LOAD. JOIST MANUFACTURER SHALL MAKE

PROVISION FOR THESE IN THE DESIGN OF THE JOISTS REF PLANS

FOR LOAD & EXTENT.

XX PSF

XX'-XX"

ALOHA, OREGON

DESIGN DEVELOPMENT - 07/11/2025

ALOHA HIGH SCHOOL - BATTING CAGES

" INCH DBA DEFORMED BAR ANCHOR HAS HEADED ANCHOR STUD OC ON CENTER T AND B TOP AND BOTTOM

# NUMBER, POUND DBL DOUBLE HC HOLLOW-CORE OD OUTSIDE DIAMETER T-AND-G TONGUE-AND-GROOVE

' FEET DEFL DEFLECTION HCP HOLLOW-CORE PLANK OH OVERHEAD TAN TANGENT

(E) EXISTING DEMO DEMOLITION HDD HEADED ANCHOR STUD OPNG OPENING THK THICK

(N) NEW DEPT DEPARTMENT HDR HEADER OPP OPPOSITE, OPPOSITE HAND THRD THREADED

DETL DETAIL HEX HEXAGONAL OSWJ OPEN-WEB STEEL JOIST TOB TOP OF BEAM

AB ANCHOR BOLT DF DOUG FIR (DOUGLAS FIR) HM HOLLOW METAL TOC TOP OF COLUMN, TOP OF CURB

ACI AMERICAN CONCRETE INSTITUTE DIA DIAMETER HORIZ HORIZONTAL P/L PROPERTY LINE TOF TOP OF FOOTING

ADD ADDENDUM, ADDITION DIAG DIAGONAL HSS HOLLOW STRUCTURAL SHAPE PAF POWER-ACTUATED FASTENERS TOJ TOP OF JOIST

ADJ ADJUST, ADJUSTABLE DIAPH DIAPHRAGM HT HEIGHT PC PRECAST TOL TOP OF LINTEL, LANDING

AESS ARCHITECTURALLY EXPOSED STRUCTURAL STEEL DIM DIMENSION HVAC HEATING, VENTILATION, AIR CONDITIONING PCF POUNDS PER CUBIC FOOT TOL TOLERANCE

AFF ABOVE FINISH FLOOR DKG DECKING PERF PERFORATE, PERFORATED, PERFORMANCE TOP TOP OF PIER, TOP OF PLATE

ALT ALTERNATE DL DEAD LOAD IBC INTERNATIONAL BUILDING CODE PERIM PERIMETER TOPV TOP OF PAVEMENT

ALUM ALUMINUM DWG DRAWING ICF INSULATED CONCRETE FORMS PE PROFESSIONAL ENGINEER TOS TOP OF SLAB, TOP OF STEEL

APPROX APPROXIMATELY DWGS DRAWINGS ID INSIDE DIAMETER PERP PERPENDICULAR TOW TOP OF WALL

ARCH ARCHITECTURE DWL DOWEL IN INCH, INCHES PL PLATE TRANS TRANSVERSE

ASTM AMERICAN SOCIETY FOR TESTING AND MATERIALS INFO INFORMATION PLF POUNDS PER LINEAL FOOT TRANSL TRANSLUCENT

AVG AVERAGE EIFS EXTERIOR INSULATED FINISH SYSTEM INSP INSPECTION PLWD PLYWOOD TYP TYPICAL

AWS AMERICAN WELDING SOCIETY ELEV ELEVATOR INSUL INSULATION PNL PANEL

ENGR ENGINEER INT INTERIOR PRE-MANUF PRE-MANUFACTURED UNO UNLESS NOTED OTHERWISE

BALC BALCONY EOR ENGINEER OF RECORD PREFAB PREFABRICATED UTIL UTILITY

BD BOARD EQ EQUAL JST JOIST PREFIN PREFINISHED

BEV BEVEL EQPT EQUIPMENT JT JOINT, JOINTS PSF POUNDS PER SQUARE FOOT VERT VERTICAL

BKR BACKER ES EACH SIDE PSI POUNDS PER SQUARE INCH VFY VERIFY

BLDG BUILDING EW EACH WAY K KILOPOUND (1000 POUNDS) PSL PARALLEL STRAND LUMBER VIF VERIFY IN FIELD

BLK BLOCK EXIST EXISTING KIP KILOPOUND (1000 POUNDS) PT PRESERVATIVE-TREATED, POST-TENSIONED

BLKG BLOCKING EXP EXPANSION W/ WITH

BM BEAM EXT EXTERIOR L ANGLE, LEFT, LENGTH QTY QUANTITY W/O WITHOUT

BOC BOTTOM OF CURB LAM LAMINATE, LAMINATED WD WOOD

BOT/BTM BOTTOM F TO F FACE TO FACE LAT LATERAL RAD RADIUS WF WIDE-FLANGE (STRUCTURAL STEEL)

BOW BOTTOM OF WALL FAB FABRICATIONS / FABRICATED LB POUND RCP REFLECTED CEILING PLAN WP WORK POINT OR WORKING POINT

BP BASE PLATE FDTN FOUNDATION LF LINEAL FEET, LINEAR FOOTAGE RD ROOF DRAIN WR WATER-RESISTANT, WATER-RESISTIVE

BRDG BRIDGE, BRIDGING FE FROELICH ENGINEERS LIN LINEAR REF REFERENCE WS WATERSTOP

BRG BEARING FF FINISH FLOOR LIN FT LINEAL FEET, LINEAR FOOTAGE REINF REINFORCED, REINFORCING WT WEIGHT

BRK BRICK FFE FINISH FLOOR ELEVATION LL LIVE LOAD REQ REQUIREMENTS WWF WELDED WIRE FABRIC

BSMT BASEMENT FIN FINISH LLH LONG LEG HORIZONTAL REQD REQUIRED

BU BUILT-UP FLR FLOOR LLV LONG LEG VERTICAL REV REVISION

FOC FACE OF CONCRETE LNTL LINTEL RO ROUGH OPENING

CEM CEMENT, CEMENTITIOUS FOF FACE OF FINISH LONG LONGITUDINAL

CGS CENTER OF GRAVITY OF STRAND FOM FACE OF MASONRY LSL LAMINATED STRAND LUMBER SCHED SCHEDULE

CIP CAST-IN-PLACE FOS FACE OF STUD LT WT LIGHTWEIGHT SE STRUCTURAL ENGINEER

CJ CONTROL JOINT FR FIRE-RATED, FIRE RESISTIVE LVL LAMINATED VENEER LUMBER SECT SECTION

CL CENTER LINE FRM FRAMED, FRAMING SF SQUARE FEET

CLG CEILING FRR FIRE-RESISTANCE-RATED MANUF MANUFACTURER, MANUFACTURED SGL SINGLE

CLR CLEAR FRT FIRE-RETARDANT-TREATED MAX MAXIMUM SHT SHEET

CMU CONCRETE MASONRY UNIT FT FOOT, FEET MB MACHINE BOLT SHTG SHEATHING

COL COLUMN FTG FOOTING MECH MECHANICAL SHTH SHEATHING

COMP COMPOSITE, COMPENSATION FUT FUTURE MEZZ MEZZANINE SIM SIMILAR

CONC CONCRETE MFR MANUFACTURER, MANUFACTURED SIMP SIMPSON STRONG-TIE

COND CONDITION GA GAUGE MIN MINIMUM SL SNOW LOAD

CONN CONNECTION GALV GALVANIZED MISC MISCELLANEOUS SOG SLAB-ON-GRADE

CONSTR CONSTRUCTION GC GENERAL CONTRACTOR MTL METAL SPEC SPECIFICATION, SPECIFICATIONS

CONT CONTINUOUS GEN GENERAL MUL MULLION SQ SQUARE

CORR CORRIDOR GL GLUED-LAMINATED SS STAINLESS STEEL

CTR CENTER GLB GLUED-LAMINATED BEAM N NORTH STD STANDARD

CTRL CONTROL GLULAM GLUED-LAMINATED NIC NOT IN CONTRACT STIFF STIFFENER

CU CUBIC GND GROUND NO NUMBER STL STEEL

CUST CUSTOM GR GRADE NOM NOMINAL STRUCT STRUCTURAL

GYP GYPSUM NTS NOT TO SCALE SUSP SUSPENDED

GYP BD GYPSUM BOARD SYM SYMMETRICAL

STRUCTURAL SHEETS:

SHEET NUMBER SHEET TITLE

S001 COVER SHEET

S002 GENERAL STRUCTURAL NOTES

S003 GENERAL STRUCTURAL NOTES

S004 SPECIAL INSPECTIONS

S102 FOUNDATION PLAN

S500 DETAILS

ES

TR

Y

SU

R

VE

YI

N

G

EN

G

IN

EE

R

IN

G

N A

TU

R

A L

R

ES

O U

R C

ES

LA

N D

SC

A

PE

A

R C

H

IT

EC

TU

R E

PL

A

N N

IN

G

SW

2n d

AV

EN

UE

, S

UI

TE

TU

AL

AT

IN

, O

R

P

3.

2.

Po rtl an d, O R

Be nd , O

R

D en ve r, C O e n g in e e r s fro el ic h-en gi ne er s.

co m

FE

-T inc

C

IV

IL

à S

T R

U C

T U

R A L

ST

RUCTURAL

PRELIM

IN

ARY

NOT FOR

CONSTRUCTIO

N

A L

O H

A H

IG

H

S C

H O

O L

B

A T

T

IN

G C

A G

E S

B E

A V

E R

T O

N S

C H

O O

L D

IS

T

R

IC

T W

A S

H

IN

G T

O N

C O

U N

T Y

, O R

E G

O N

GENERAL STRUCTURAL NOTES

PROJECT DESCRIPTION:

● ADDITION TO EXISTING CONCESSION STAND

● CONVENTIONAL SPREAD AND STRIP CONCRETE FOUNDATIONS

● CONCRETE SLAB-ON-GRADE

● REINFORCED CMU WALLS

● STEEL CANOPY

GENERAL:

1. THE STRUCTURAL DRAWINGS ARE A PORTION OF THE CONTRACT DOCUMENTS AND ARE

INTENDED TO BE USED IN CONJUNCTION WITH THE ARCHITECTURAL, CIVIL, MECHANICAL, AND

ELECTRICAL DRAWINGS. THE CONTRACTOR IS RESPONSIBLE FOR COORDINATING THE

REQUIREMENTS FROM THE ENTIRE SET OF CONTRACT DOCUMENTS (INCLUDING THE PROJECT

SPECIFICATIONS) INTO THEIR WORK.

2. THESE GENERAL NOTES SUPPLEMENT THE PROJECT SPECIFICATIONS. REFER TO THE

PROJECT SPECIFICATIONS FOR ADDITIONAL REQUIREMENTS.

3. NOTES AND DETAILS ON THE STRUCTURAL DRAWINGS TAKE PRECEDENCE OVER THE GENERAL

STRUCTURAL NOTES AND TYPICAL DETAILS.

4. CONTRACTOR TO VERIFY ALL DIMENSIONS AND ELEVATIONS PROVIDED ON STRUCTURAL

DRAWINGS WITH ALL DISCIPLINES INCLUDING, BUT NOT LIMITED TO ARCHITECTURAL,

GEOTECHNICAL ENGINEER, AND CIVIL ENGINEER PRIOR TO CONSTRUCTION.

5. DETAILS ON THESE PLANS DEPICT THE GENERAL CONSTRUCTION METHODS FOR THIS

STRUCTURE. CONNECTIONS, DETAILS AND CONDITIONS NOT SPECIFICALLY SHOWN THAT ARE

SIMILAR TO THOSE THAT ARE SPECIFIED SHALL BE ASSUMED ONE AND THE SAME. IF

QUESTIONS REGARDING THE APPLICATION OF DETAILS ARE ENCOUNTERED, NOTIFY THE

ARCHITECT/ENGINEER FOR CLARIFICATION IN A TIMELY MANNER PRIOR TO BID OPENING.

CODE REQUIREMENTS:

1. CONFORM TO THE 2022 OREGON STRUCTURAL SPECIALTY CODE (OSSC), BASED UPON THE

2021 INTERNATIONAL BUILDING CODE (IBC), HERETOFORE REFERENCED IN THE STRUCTURAL

PLANS AS THE BUILDING CODE.

2. ALL REFERENCE TO OTHER CODES AND STANDARDS (ACI, AISC, AWS, NDS, ASTM, ETC.) SHALL

BE FOR THE EDITIONS NOTED IN CHAPTER 35 OF THE IBC/OSCC.

TEMPORARY CONDITIONS:

1. THE STRUCTURE HAS BEEN DESIGNED TO FUNCTION AS A UNIT UPON COMPLETION. THE

CONTRACTOR IS RESPONSIBLE FOR FURNISHING ALL TEMPORARY BRACING AND / OR

SUPPORT REQUIRED AS A RESULT OF THE CONTRACTOR’S CONSTRUCTION METHODS AND / OR

SEQUENCES.

2. CONTRACTOR’S CONSTRUCTION METHODS AND / OR SEQUENCES SHALL RECOGNIZE AND

CONSIDER THE EFFECTS OF THERMAL MOVEMENTS OF STRUCTURAL ELEMENTS DURING THE

CONSTRUCTION PERIOD.

3. RETAINING WALLS THAT TIE TO UPPER SLABS SHALL NOT BE BACKFILLED UNTIL THE UPPER

SLABS REACH FULL STRENGTH UNLESS ADEQUATE BRACING IS PROVIDED AT THE TOP OF THE

WALL.

4. FOR EXISTING BUILDINGS, ADDED STRUCTURAL MEMBERS, HARDWARE, CONNECTORS,

STRAPS, FASTENERS, ETC. SHOWN ON THE STRUCTURAL DRAWINGS MAY NECESSITATE THE

UNCOVERING / EXPOSURE OF PART OF THE EXISTING STRUCTURAL SYSTEM. THIS MAY

INCLUDE, BUT IS NOT LIMITED TO PARTIAL DEMOLITION OF ELEMENTS SUCH AS CLADDING,

FINISHES, CEILING, ROOFING, INSULATION, ELECTRICAL, PLUMBING, MECHANICAL, SPRINKLERS, ARCHITECTURAL, STRUCTURAL, ETC. THE CONTRACTOR IS RESPONSIBLE FOR DETERMINING

THE MEANS, METHODS, AND EXTENT OF EXPOSURE / DEMOLITION REQUIRED TO EXECUTE AND

INSTALL ELEMENTS SHOWN ON THE STRUCTURAL DRAWINGS. REMOVED / DEMOLISHED

ELEMENTS AS PREVIOUSLY NOTED THAT ARE PART OF THE FINAL PRODUCT SHALL BE

RESTORED TO THEIR ORIGINAL STATE UPON COMPLETION AND SHALL COMPLY WITH

REQUIREMENTS OF THE SPECIFICATIONS, ARCHITECT, OTHER DISCIPLINES AND CURRENT

BUILDING CODES AND STANDARDS.

5. FOR EXISTING BUILDINGS, SHORING OF PORTIONS OF THE EXISTING STRUCTURE MAY BE

NECESSARY PRIOR TO REMOVAL / DEMOLITION. TAKE CARE TO AVOID DAMAGE AND DISTRESS

TO THE EXISTING STRUCTURE BEYOND THE DEMOLITION EXTENTS INDICATED. THE

CONTRACTOR IS RESPONSIBLE FOR AND PROVIDE ALL MEASURES NECESSARY TO PROTECT

THE STRUCTURE (EXISTING AND NEW) DURING CONSTRUCTION. THE CONTRACTOR IS

RESPONSIBLE FOR FURNISHING ALL TEMPORARY BRACING AND / OR SUPPORT REQUIRED AS A

RESULT OF THE CONTRACTOR’S CONSTRUCTION METHODS AND / OR SEQUENCES.

EXISTING CONDITIONS:

1. FIELD VERIFY ALL EXISTING CONDITIONS, DIMENSIONS, AND ELEVATIONS - ONLY FIELD

VERIFIED DIMENSIONS ARE TO BE USED IN CREATION OF THE SHOP DRAWINGS. THE

CONTRACTOR SHALL NOTIFY THE ARCHITECT AND ENGINEER OF ANY SIGNIFICANT

DISCREPANCIES FROM DIMENSIONS AND CONDITIONS SHOWN ON THE DRAWINGS.

2. X-RAY OR GPR SHALL BE USED PRIOR TO DRILLING OR CUTTING INTO CONCRETE

CONSTRUCTION TO LOCATE AND AVOID REINFORCEMENT AND/OR TENDONS. APPROVED

HOLES (APPROVED BY FROELICH ENGINEERS) THROUGH EXISTING CONCRETE CONSTRUCTION

SHALL BE CORE-DRILLED OR SAWCUT. DO NOT CUT THROUGH ANY REINFORCING STEEL OR

POST-TENSIONED TENDONS.

3. APPROVED HOLES (APPROVED BY FROELICH ENGINEERS) THROUGH EXISTING STEEL

STRUCTURE SHALL BE CUT CAREFULLY AND CLEANLY. DO NOT TORCH OR FLAME CUT.

4. DUE TO LIMITED OBSERVATION AND ACCESS TO THE EXISTING STRUCTURE PRIOR TO THE

PREPARATION OF THE STRUCTURAL DRAWINGS, FROELICH ENGINEERS ASSUMES THAT THE

EXISTING STRUCTURE IS IN LIKE-NEW CONDITION WITH NO CORROSION, DETERIORATION,

DAMAGE, ETC. AND WAS CONSTRUCTED IN ACCORDANCE WITH THE ORIGINAL CONSTRUCTION

DOCUMENTS (IF AVAILABLE). GENERAL CONTRACTOR SHALL VERIFY THE ABOVE ASSUMPTIONS

AND NOTIFY THE ENGINEER OF RECORD OF CONCERNS, DAMAGE, OR DISCREPANCIES.

5. FOR NEW EQUIPMENT OR CONSTRUCTION ADDED ATOP OR BENEATH EXISTING

CONSTRUCTION, THE GENERAL CONTRACTOR SHALL VERIFY THAT PROPER ROOF SLOPE AND

DRAINAGE IS STILL IN PLACE.

DESIGN CRITERIA:

1. DESIGN WAS BASED ON THE STRENGTH AND DEFLECTION CRITERIA OF THE BUILDING CODE.

IN ADDITION TO THE DEAD LOADS, THE FOLLOWING LOADS AND ALLOWANCES WERE USED

FOR DESIGN, WITH LIVE LOADS (LL) REDUCED IN ACCORDANCE WITH THE IBC:

DESIGN CRITERIA

GEOTECHNICAL CRITERIA

DESIGN BASED ON

GEOTECHNICAL REPORT BY: NONE

ALLOWABLE SOIL BEARING

PRESSURE

1500 PSF (ASSUMED)

BUILDING RISK CATEGORY

RISK CATEGORY III

LIVE LOAD CRITERIA

ROOF CRITERIA

ROOF LIVE LOAD 20 PSF

SNOW CRITERIA

DESIGN ROOF SNOW LOAD 25 PSF MINIMUM IN ACCORDANCE WITH THE BUILDING CODE

SNOW DRIFT PER OSSC AS SHOWN ON PLANS (IN ADDITION TO DESIGN ROOF

SNOW LOAD, NOT FLAT ROOF SNOW LOAD)

GROUND SNOW LOAD P g = 12 PSF

IN ACCORDANCE WITH THE BUILDING CODE

FLAT ROOF SNOW LOAD P f = 15 PSF SNOW EXPOSURE FACTOR C e = 1.0

SNOW LOAD IMPORTANCE

FACTOR I

s = 1.0

THERMAL FACTOR C t = 1.0

WIND CRITERIA

MAIN WIND FORCE RESISTING

SYSTEM 103 MPH BASIC WIND SPEED

COMPONENTS AND CLADDING 103 MPH BASIC WIND SPEED

EXPOSURE CATEGORY B

GUST/INTERNAL PRESSURE GC pi = +/- 0.18

COMPONENT AND CLADDING

PRESSURES

WALL CLADDING, TYP ZONE +19.3 -20.9

WALL CLADDING, EDGE ZONE +19.3 -25.8

ROOF CLADDING, TYP ZONE +7.9 -19.3

ROOF CLADDING, EDGE ZONE +7.9 -32.3

ROOF CLADDING, CORNER ZONE +7.9 -48.7

PRESSURES GIVEN ARE FOR AN AREA OF 10 SQUARE FEET. ADDITIONAL DATA AVAILABLE UPON

REQUEST.

SEISMIC CRITERIA

SITE CLASS C

IMPORTANCE FACTOR I e = 1.25

SEISMIC DESIGN CATEGORY D

MCE SPECTRAL

ACCELERATIONS S

S = 0.96 S

= 0.38

DESIGN SPECTRAL

ACCELERATIONS S

DS

= 0.8 S

D1 = 0.54

ANALYSIS PROCEDURE EQUIVALENT LATERAL FORCE, REF ASCE 7-16 SECTION 12.8

NORTH-SOUTH DIRECTION EAST-WEST DIRECTION

SEISMIC LOAD RESISTING

SYSTEM

REINFORCED MASONRY SHEAR

WALLS

REINFORCED MASONRY SHEAR

WALLS

RESPONSE MODIFICATION

FACTOR R = 5 R = 5

SEISMIC RESPONSE

COEFFICIENT C

S = 0.20 C

S = 0.20

STRUCTURAL OBSERVATION:

1. THE STRUCTURAL ENGINEER OF RECORD (SER) WILL PERFORM STRUCTURAL OBSERVATIONS

BASED ON THE REQUIREMENTS OF THE BUILDING CODE AT THE STAGES OF CONSTRUCTION

LISTED BELOW. THE CONTRACTOR SHALL PROVIDE SUFFICIENT NOTICE AND ACCESS FOR THE

SER TO PERFORM THESE OBSERVATIONS:

STRUCTURAL OBSERVATIONS

CONSTRUCTION PHASE OBSERVATION BY SER COMMENTS

AS REQUIRED TO ADDRESS STRUCTURAL

ISSUES X REF FOOTNOTE A, B

A. STRUCTURAL OBSERVATIONS ARE INTENDED TO VERIFY GENERAL CONFORMANCE WITH

THE STRUCTURAL DRAWINGS. SPECIAL INSPECTIONS AND TESTING ARE STILL REQUIRED.

B. A FIELD REPORT WILL BE SUBMITTED TO THE BUILDING DEPARTMENT FOLLOWING EACH

VISIT.

C. STRUCTURAL OBSERVATION TO OCCUR AFTER THE REINFORCING STEEL HAS BEEN

INSTALLED.

SPECIAL INSPECTION AND TESTING:

1. SPECIAL INSPECTION WILL BE PROVIDED BY THE OWNER BASED ON THE REQUIREMENTS OF

THE BUILDING CODE AS SUMMARIZED IN THE SPECIAL INSPECTION AND TESTING PROGRAM ON

SHEET ***S0.0X***. THE CONTRACTOR SHALL PROVIDE SUFFICIENT NOTICE AND ACCESS FOR

THE SPECIAL INSPECTOR TO PERFORM THESE INSPECTIONS.

2. SPECIAL INSPECTIONS SHALL CONFORM TO SECTION 1705 OF THE BUILDING CODE, CONTRACT

DOCUMENTS AND APPROVED SUBMITTALS. REFER TO SPECIAL INSPECTION AND TESTING

TABLES FOR PROJECT REQUIREMENTS.

3. SPECIAL INSPECTIONS AND ASSOCIATED TESTING SHALL BE PERFORMED BY AN APPROVED

ACCREDITED INDEPENDENT AGENCY MEETING THE REQUIREMENTS OF ASTM E329

(MATERIALS). THE INSPECTION AND TESTING AGENCY SHALL FURNISH TO THE STRUCTURAL

ENGINEER ARCHITECT A COPY OF THEIR SCOPE OF ACCREDITATION. SPECIAL INSPECTORS

SHALL BE APPROVED BY THE BUILDING OFFICIAL. WELDING INSPECTORS SHALL BE QUALIFIED

PER SECTION 6.1.4.1(1) OF AWS D1.1.

4. THE SPECIAL INSPECTOR SHALL OBSERVE THE INDICATED WORK FOR COMPLIANCE WITH THE

APPROVED CONSTRUCTION DOCUMENTS. ALL DISCREPANCIES SHALL BE BROUGHT TO THE

ATTENTION OF THE CONTRACTOR FOR CORRECTION AND NOTED IN THE INSPECTION REPORTS.

5. THE SPECIAL INSPECTOR AND GEOTECHNICAL ENGINEER SHALL FURNISH INSPECTION

REPORTS FOR EACH INSPECTION TO THE BUILDING OFFICIAL, STRUCTURAL ENGINEER,

ARCHITECT, CONTRACTOR, AND OWNER. THE SPECIAL INSPECTION AGENCY SHALL SUBMIT A

FINAL REPORT STATING THAT THE WORK REQUIRING SPECIAL INSPECTION WAS INSPECTED

AND IS IN CONFORMANCE WITH THE APPROVED CONSTRUCTION DOCUMENTS AND THAT ALL

DISCREPANCIES NOTED IN THE INSPECTION REPORTS HAVE BEEN CORRECTED.

6. QUALITY ASSURANCE (QA) IS REQUIRED FOR STRUCTURAL STEEL ITEMS PER AISC 360 AND 341

UNLESS SPECIFICALLY NOTED OTHERWISE. QUALITY CONTROL (QC) TO BE PROVIDED BY THE

FABRICATOR, ERECTOR OR OTHER RESPONSIBLE CONTRACTOR AS APPLICABLE. CONTRACTOR

AND SPECIAL INSPECTOR TO DOCUMENT QUALITY CONTROL AS REQUIRED IN AISC 360

SECTION N3 AND AISC 341 SECTION J2.

7. INSPECTION TYPES:

CONTINUOUS: THE FULL-TIME OBSERVATION OF WORK REQUIRING SPECIAL INSPECTION BY AN

APPROVED SPECIAL INSPECTOR WHO IS PRESENT IN THE AREA WHERE THE WORK IS BEING

PERFORMED.

PERIODIC: THE PART-TIME OR INTERMITTENT OBSERVATION OF WORK REQUIRING SPECIAL

INSPECTION BY AN APPROVED SPECIAL INSPECTOR WHO IS PRESENT IN THE AREA WHERE THE

WORK HAS BEEN OR IS BEING PERFORMED AND AT THE COMPLETION OF THE WORK.

PERIODIC (FOR POST-INSTALLED ANCHORS): WHERE PERIODIC INSPECTION IS ALLOWED BY

THE ANCHOR ICC/IAPMO EVALUATION REPORT, INSPECTIONS SHALL BE AS FOLLOWS:

A. INSPECTIONS SHALL BE IN STRICT CONFORMANCE WITH THE EVALUATION REPORT AND

MANUFACTURER'S INSTALLATION REQUIREMENTS. ANCHOR INSTALLERS SHALL BE

QUALIFIED AS REQUIRED BY JURISDICTION REQUIREMENTS.

B. THE SPECIAL INSPECTOR SHALL BE ONSITE INITIALLY DURING ANCHOR INSTALLATION

TO VERIFY ANCHOR PARAMETERS (AS THEY APPLY TO THE PARTICULAR ANCHOR TYPE):

DRILL BIT TYPE AND SIZE, ANCHOR TYPE OR BAR TYPE, ANCHOR DIMENSIONS,

CONCRETE TYPE, CONCRETE COMPRESSIVE STRENGTH, ADHESIVE IDENTIFICATION

AND EXPIRATION DATE, HOLE DIMENSIONS, HOLE CLEANING PROCEDURES, ANCHOR OR

BAR EMBEDMENT, TIGHTENING TORQUE (WHERE APPLICABLE), ANCHOR SPACING AND

EDGE DISTANCE, AND ADHERENCE TO THE MANUFACTURER'S WRITTEN INSTALLATION

INSTRUCTIONS.

C. THE SPECIAL INSPECTOR SHALL BE ONSITE TO CONTINUOUSLY INSPECT THE

INSTALLATION OF THE FIRST 10 ANCHORS INSTALLED BY EACH INSTALLER FOR

CONFORMANCE WITH THE EVALUATION REPORT AND THE CONSTRUCTION DOCUMENTS.

PROVIDED ALL ANCHORS ARE INSTALLED IN ACCORDANCE WITH MANUFACTURER'S

WRITTEN INSTRUCTIONS AND CONFORM TO THE CONSTRUCTION DOCUMENTS,

SUBSEQUENT INSTALLATIONS OF THE SAME ANCHOR TYPE AND SIZE BY THE SAME

INSTALLER IS PERMITTED TO BE PERFORMED IN THE ABSENCE OF THE SPECIAL

INSPECTOR. PROVIDE PERIODIC INSPECTION ON A MINIMUM OF 10% OF THE NEXT 1000

ANCHORS BY EACH INSTALLER AND A MINIMUM OF 5% OF THE REMAINING ANCHORS BY

EACH INSTALLER. INSPECTIONS SHALL OCCUR A MINIMUM OF ONCE PER WEEK AT A

RANDOM TIME WHILE ANCHOR INSTALLATION IS UNDERWAY. ANY NON-COMPLIANCE

ISSUES SHALL RESET THE INSPECTION REQUIREMENTS TO (10) CONTINUOUS

INSPECTIONS AND REQUIRE ALL PREVIOUS ANCHORS TO BE INSPECTED.

NON-COMPLIANT ANCHORS SHALL BE BROUGHT TO THE ATTENTION OF THE ENGINEER

OF RECORD FOR REVIEW AND SHALL BE BROUGHT INTO COMPLIANCE BY EITHER

TESTING OR RE-INSTALLATION.

D. FOR ALL ANCHORS, PRIOR TO CONCEALMENT, VERIFY: ANCHOR TYPE OR BAR TYPE,

ANCHOR DIMENSIONS, TIGHTENING TORQUE (WHERE APPLICABLE), ANCHOR SPACING

AND EDGE DISTANCE.

E. POST-INSTALLED ANCHOR INSPECTION REPORTS SHALL IDENTIFY NAMES OF

INSTALLERS, LOCATION(S) AND CONDITION(S) OF ANCHORS INSPECTED, ANCHOR

IDENTIFICATION AND EXPIRATION DATE (WHERE APPLICABLE), ANCHOR TYPE AND SIZE,

HOLE DIMENSIONS, HOLE CLEANING PROCEDURES OBSERVED, DRILL BIT TYPE AND

SIZE, AND TIGHTENING TORQUE.

F. SPECIAL INSPECTOR SHALL PROVIDE DOCUMENTATION AT THE END OF ANCHOR

INSTALLATIONS STATING THAT THE MINIMUM NUMBER OF ANCHORS WERE INSPECTED

PER APPROVED ANCHOR EVALUATION REPORT.

OBSERVE: OBSERVE THESE FUNCTIONS ON A RANDOM, DAILY BASIS. OPERATIONS NEED NOT

BE DELAYED PENDING OBSERVATIONS.

PERFORM: INSPECTIONS SHALL BE PERFORMED PRIOR TO THE FINAL ACCEPTANCE OF THE

ITEM.

8. PERFORM INSPECTION PRIOR TO FINAL ACCEPTANCE OF THE ITEM FOR TEN WELDS TO BE

MADE BY A GIVEN WELDER, WITH THE WELDER DEMONSTRATING UNDERSTANDING OF

REQUIREMENTS AND POSSESSION OF SKILLS AND TOOLS TO VERIFY THESE ITEMS, THE

PERFORM DESIGNATION OF THIS TASK SHALL BE REDUCED TO OBSERVE, AND THE WELDER

SHALL PERFORM THIS TASK. SHOULD THE INSPECTOR DETERMINE THAT THE WELDER HAS

DISCONTINUED PERFORMANCE OF THIS TASK, THE TASK SHALL BE RETURNED TO PERFORM

UNTIL SUCH TIME AS THE INSPECTOR HAS RE-ESTABLISHED ADEQUATE ASSURANCE THAT THE

WELDER WILL PERFORM THE INSPECTION TASKS LISTED.

9. TESTING ABBREVIATIONS:

NDT - NON-DESTRUCTIVE TESTING

CJP - COMPLETE JOINT PENETRATION

MT - MAGNETIC PARTICLE TESTING

RBS - REDUCED BEAM SECTION

10. DOCUMENT (D): INDICATES CONTRACTOR AND SPECIAL INSPECTOR TO PROVIDE

DOCUMENTATION IN ACCORDANCE WITH AISC 341.

11. EACH CONTRACTOR RESPONSIBLE FOR THE CONSTRUCTION OF THE MAIN WIND-OR

SEISMIC-FORCE-RESISTING SYSTEM, DESIGNATED SEISMIC SYSTEM OR A WIND-OR

SEISMIC-RESISTING COMPONENT LISTED IN THE TABLES SHALL SUBMIT A WRITTEN STATEMENT

OF RESPONSIBILITY TO THE BUILDING OFFICIAL AND THE OWNER PRIOR TO THE

COMMENCEMENT OF WORK ON THE SYSTEM OR COMPONENT. THE CONTRACTOR'S

STATEMENT OF RESPONSIBILITY SHALL CONTAIN THE FOLLOWING:

A. ACKNOWLEDGEMENT OF AWARENESS OF THE SPECIAL REQUIREMENTS CONTAINED IN

THE STATEMENT OF SPECIAL INSPECTIONS.

B. ACKNOWLEDGEMENT THAT CONTROL WILL BE EXERCISED TO OBTAIN CONFORMANCE

WITH THE CONSTRUCTION DOCUMENTS APPROVED BY THE BUILDING OFFICIAL.

C. PROCEDURES FOR EXERCISING CONTROL WITHIN THE CONTRACTOR'S ORGANIZATION,

THE METHOD AND FREQUENCY OF REPORTING AND DISTRIBUTION OF THE REPORTS.

D. IDENTIFICATION AND QUALIFICATIONS OF THE PERSON(S) EXERCISING SUCH CONTROL

AND THEIR POSITION(S) IN THE ORGANIZATION.

SUBMITTALS:

1. REVIEW OF THE SUBMITTALS IS ONLY FOR REVIEW OF GENERAL CONFORMANCE WITH THE

DESIGN CONCEPT OF THE PROJECT AND GENERAL COMPLIANCE WITH THE INFORMATION

GIVEN IN THE CONTRACT DOCUMENTS. NO RESPONSIBILITY IS ASSUMED BY THE STRUCTURAL

ENGINEER FOR CORRECTNESS, DIMENSIONS OR DETAILS CONTAINED WITHIN THE SUBMITTALS.

THE CONTRACTOR IS SOLELY RESPONSIBLE FOR CONFIRMING AND CORRELATING ALL

QUANTITIES AND DIMENSIONS; SELECTING FABRICATION PROCESSES AND…