- PIERS 15 AND 14 - REPAIR CLEATS AND BOLLARDS
- Solicitation number
- N4008524R2609
About this file
This price proposal form requests unit pricing for repair works at Pier 14 including removing and replacing mooring cleats, cleat foundations, 35-ton and 200-ton bollard fixtures, and bollard foundations. The contractor will provide fixed pricing for the base scope of line items 1A through 1F, totaling to the amount in line item 1. An option is included in line item 2 for concrete curb repair pricing. The solicitation is only open to five pre-qualified Small Business MAC contractors in the Hampton Roads, Virginia area. Award will be made based on the total of the required line items.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRICE SCHEDULE: PIER 14 – CLEAT AND BOLLARD REPAIRS
Provide line-item prices, where indicated by blank underlines, for the following items:
Line
Item
Description QTY Unit Unit Price Extended Total
1A
Price for the entire work for remove and replace mooring cleat fixture and connection hardware, complete in accordance with the drawings and specifications, but excluding work described in another line Item.
13 EA $__________ $_______________
1B
Price for the entire work for remove and replace mooring cleat concrete foundation in accordance with the drawings and specifications, but excluding work provided in another line item.
9 EA $__________ $_______________
1C
Price for the entire work for remove and replace 35-ton mooring bollard fixture and connection hardware in accordance with the drawings and specifications, but excluding work provided in another line item
3 EA $__________ $_______________
1D
Price for the entire work for remove and replace 35-ton mooring bollard concrete foundation in accordance with the drawings and specifications, but excluding work provided in another line item.
3 EA $__________ $_______________
1E
Price for the entire work for remove and replace 200-ton mooring bollard fixture and connection hardware in accordance with the drawings and specifications, but excluding work provided in another line item
2 EA $__________ $_______________
1F
Price for the entire work for remove and replace 200-ton mooring bollard concrete foundation in accordance with the drawings and specifications, but excluding work provided in another line item.
2 EA $__________ $_______________
LINE ITEM 1 - BASE PRICE: Total Price for the entire work for
Pier 14 Cleat and Bollard Repair in accordance with the drawings and specifications, complete, but excluding work provided in another Priced line Item.
(Total of Line Items 1A – 1F)
LINE ITEM 2 - OPTION ITEM 1: Price for providing all work in connection with concrete curb repair, complete in accordance with the drawings and specifications, but excluding work provided in another Priced line item.
(Line Item 2)
GENERAL BID NOTES:
a. Award will be made on the total sum of Contract Line Items 1A, 1B, 1C, 1D, 1E, and 1F. If there is a difference between a unit price and the extended total, the unit price will be held to be the intended bid and the total recomputed accordingly. If an Offeror provides a total but fails to enter a unit price, the total divided by the specified quantity will be held to be the intended unit price.
PRICE SCHEDULE: PIER 14 – CLEAT AND BOLLARD REPAIRS
The quantities provided in Items 1A through 1F are estimates only. The unit prices proposed will be the basis for any adjustment in accordance with FAR 52.211-18, Variation in Estimated Quantity.
b. The Government reserves the unilateral right to award CLIN 0002 to the Contractor at the proposed price within
60 calendar days after the contract award. A firm fixed proposed price is required for CLIN 0001 and CLIN
0002. No provision is made for economic price adjustment. If Options are exercised, the contract completion date remains 182 calendar days after award of the contract.
c. Evaluation of Options (JUL 1990). Except when it is determined in accordance with FAR 17.206(b) Evaluation not to be in the Government's best interest, the Government will evaluate offers for award purposes by adding the price for the Option(s) to the total price for CLIN 0001. In accordance with FAR 52.217-5 Evaluation of
Options, evaluation of options will not obligate the Government to exercise the Option(s).
d. The Government may reject an offer as nonresponsive if it is materially unbalanced as to prices for the basic requirement and the option quantities. An offer is unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.
e. If CLIN 0002 is exercised, additional bonding and consent of surety is required. Consequently, the Performance
Bond must reflect 100 percent of the aggregate amount of all Items.
File details come from the government source that posted it. Updated .