ATTACHMENT E - Key Milestone Dates.xlsx
XLSX spreadsheet 30 KB Posted
- Attached to
- Q702--Rapid City Community Based Outpatient Clinic (CBOC) RFQ (VA-20-00011079) Amendment 0004
- Solicitation number
- 36A77620Q0302
About this file
This combined synopsis and solicitation requests quotes for initial outfitting, transition, and activation services at a new Rapid City Community-Based Outpatient Clinic in South Dakota. The Department of Veterans Affairs seeks these services between August 2020 and September 2022 through a firm-fixed price contract awarded to a verified Service-Disabled Veteran-Owned Small Business. Quotes are due by the date specified in block 8 of the SF1449. The requirement is set aside 100% for SDVOSBs with a size standard of $15 million. The solicitation includes an attachment outlining performance work statement requirements but no other substantive attachments.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Integrated Project Schedule
| Task Name | Duration | Start | Finish | Owner | Status | FY2020 | FY2021 | FY2022 | FY2023 | ||||||||||||||||||||||||||||||||
| Congressional Schedule | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | |||||
| Choice Law Passed | 0 | 8/12/17 | 8/12/17 | 100% | |||||||||||||||||||||||||||||||||||||
| Award Lease | 0 | 10/12/19 | 10/12/19 | 75% | |||||||||||||||||||||||||||||||||||||
| Construction completed | 0 | 12/12/21 | 12/12/21 | 0% | |||||||||||||||||||||||||||||||||||||
| activation completed | 0 | 6/12/22 | 6/12/22 | 0% | |||||||||||||||||||||||||||||||||||||
| Current GSA Schedule | 0 | ||||||||||||||||||||||||||||||||||||||||
| Award Lease | 1 | 6/18/20 | 6/18/20 | 75% | |||||||||||||||||||||||||||||||||||||
| Construction Completed | 1 | 5/20/22 | 5/20/22 | 0% | |||||||||||||||||||||||||||||||||||||
| Activation Completed | 0 | 8/13/22 | 8/13/22 | 0% | |||||||||||||||||||||||||||||||||||||
| Beneficial Occupancy Date (BoD) | 1 | 5/20/22 | 5/20/22 | 0% | |||||||||||||||||||||||||||||||||||||
| IOTA Award process | 267 | 6/19/19 | 7/1/20 | 50% | |||||||||||||||||||||||||||||||||||||
| create the PWS | 190 | 6/19/19 | 3/13/20 | Justin | 75% | ||||||||||||||||||||||||||||||||||||
| IOTA Acquisition Process | 17 | 3/13/20 | 4/6/20 | 0% | |||||||||||||||||||||||||||||||||||||
| IOTA RFP on street | 23 | 4/6/20 | 5/6/20 | 0% | |||||||||||||||||||||||||||||||||||||
| IOTA contract awarded | 18 | 5/6/20 | 6/1/20 | 0% | |||||||||||||||||||||||||||||||||||||
| IOTA on boarded | 23 | 6/1/20 | 7/1/20 | 0% |
| Determine FFE list | 109 | 3/27/20 | 8/28/20 | 0% |
| Current Inventory FFE | 20 | 3/27/20 | 4/23/20 | 0% |
| validate SEPS list via user meetings | 29 | 4/24/20 | 6/4/20 | 0% |
| Develop reuse plan | 10 | 6/5/20 | 6/18/20 | 0% |
| Determine FFE to purchase | 44 | 6/19/20 | 8/20/20 | 0% |
| Identify long lead time items | 1 | 8/21/20 | 8/21/20 | 0% |
| determine acquisition strategy | 5 | 8/24/20 | 8/28/20 | 0% |
| Acquisition Process | 387 | 8/31/20 | 3/18/22 | 0% |
| build acquisition packages | 172 | 8/31/20 | 5/7/21 | 0% |
| Funding from OCAMES | 30 | 3/8/21 | 4/16/21 | 0% |
| create the award (RFP) | 153 | 5/10/21 | 12/16/21 | 0% |
| rfp on street | 224 | 2/17/21 | 1/6/22 | 0% |
| select RFP | 9 | 1/7/22 | 1/20/22 | 0% |
| award contract | 1 | 1/21/22 | 1/21/22 | 0% |
| vendor accepts award | 10 | 1/24/22 | 2/4/22 | 0% |
| build, ship, receive | 29 | 2/7/22 | 3/18/22 | 0% |
| Acquisition process long leads | 496 | 3/2/20 | 2/21/22 | 0% |
| build acquisition packages | 60 | 3/2/20 | 5/22/20 | 0% |
| Funding from OCAMES | 30 | 3/23/20 | 5/1/20 | 0% |
| create the award (RFP) | 171 | 5/25/20 | 1/29/21 | 0% |
| RFP on street | 14 | 2/1/21 | 2/19/21 | 0% |
| select RFP | 10 | 2/22/21 | 3/5/21 | 0% |
| Award contract | 1 | 3/8/21 | 3/8/21 | 0% |
| Vendor accepts award | 10 | 3/9/21 | 3/22/21 | 0% |
| build, ship, receive | 230 | 3/23/21 | 2/21/22 | 0% |
| Activation start per GSA Schedule | 126 | 2/28/22 | 8/24/22 | 0% |
| Install system furniture | 29 | 5/23/22 | 7/1/22 | 0% |
| Install OIT technology | 9 | 7/4/22 | 7/15/22 | 0% |
| Radiology | 18 | 5/23/22 | 6/16/22 | 0% |
| install - possibly prior ?? | 107 | 1/1/22 | 6/3/22 | 0% |
| connect to network | 2 | 6/6/22 | 6/7/22 | 0% |
| test and certify | 5 | 6/8/22 | 6/14/22 | 0% |
| Train staff | 2 | 6/15/22 | 6/16/22 | 0% |
| Audiology | 67 | 2/28/22 | 6/1/22 | 0% |
| install prior to BoD | 5 | 2/28/22 | 3/4/22 | 0% |
| connect to network | 1 | 5/23/22 | 5/23/22 | 0% |
| test and certify | 2 | 5/24/22 | 5/25/22 | 0% |
| Train staff | 4 | 5/26/22 | 6/1/22 | 0% |
| Telehealth | 11 | 5/23/22 | 6/7/22 | 0% |
| install | 1 | 5/23/22 | 5/23/22 | 0% |
| connect to network | 1 | 5/24/22 | 5/24/22 | 0% |
| test and certify | 4 | 5/25/22 | 5/31/22 | 0% |
| Train staff | 5 | 6/1/22 | 6/7/22 | 0% |
| Pharmacy Dispensing Machine | 11 | 5/23/22 | 6/7/22 | 0% |
| install | 1 | 5/23/22 | 5/23/22 | 0% |
| connect to network | 1 | 5/24/22 | 5/24/22 | 0% |
| test and certify | 4 | 5/25/22 | 5/31/22 | 0% |
| Train staff | 5 | 6/1/22 | 6/7/22 | 0% |
| Canteen Services Vending Machine | 11 | 5/23/22 | 6/7/22 | 0% |
| install | 1 | 5/23/22 | 5/23/22 | 0% |
| connect to network | 1 | 5/24/22 | 5/24/22 | 0% |
| test and certify | 4 | 5/25/22 | 5/31/22 | 0% |
| Train staff | 5 | 6/1/22 | 6/7/22 | 0% |
| Medical Equipment | 33 | 5/23/22 | 7/8/22 | 0% |
| install | 9 | 5/23/22 | 6/3/22 | 0% |
| connect to network | 5 | 6/6/22 | 6/10/22 | 0% |
| test and certify | 10 | 6/13/22 | 6/24/22 | 0% |
| Train staff | 9 | 6/27/22 | 7/8/22 | 0% |
| Move Staff | 18 | 8/1/22 | 8/24/22 | 0% |
| supply stocking in new facility | 10 | 8/1/22 | 8/12/22 | 0% |
| pack staff | 5 | 8/15/22 | 8/19/22 | 0% |
| move staff office equipment | 1 | 8/22/22 | 8/22/22 | 0% |
| staff equipment set up | 1 | 8/23/22 | 8/23/22 | 0% |
| Train staff | 1 | 8/24/22 | 8/24/22 | 0% |
| 0 | ||||
| 1st Patient | 1 | 9/19/22 | 9/19/22 | 0% |
Holidays
| 2020-2023 Federal Holidays | |
| 1/1/20 | New Years |
| 1/20/20 | MLK |
| 2/17/20 | Presidents' Day |
| 5/25/20 | Memorial Day |
| 7/3/20 | Independence Day |
| 9/7/20 | Labor Day |
| 10/12/20 | Columbus Day |
| 11/11/20 | Veterans Day |
| 11/26/20 | Thanksgiving |
| 12/25/20 | Christmas |
| 1/1/21 | New Years |
| 1/18/21 | MLK |
| 2/15/21 | Presidents' Day |
| 5/31/21 | Memorial Day |
| 7/5/21 | Independence Day |
| 9/6/21 | Labor Day |
| 10/11/21 | Columbus Day |
| 11/11/21 | Veterans Day |
| 11/25/21 | Thanksgiving |
| 12/24/21 | Christmas |
| 12/31/21 | New Years |
| 1/17/22 | MLK |
| 2/21/22 | Presidents' Day |
| 5/30/22 | Memorial Day |
| 7/4/22 | Independence Day |
| 9/5/22 | Labor Day |
| 10/10/22 | Columbus Day |
| 11/11/22 | Veterans Day |
| 12/26/22 | Christmas |
| 1/2/23 | New Years |
| 1/16/23 | MLK |
| 2/20/23 | Presidents' Day |
| 5/29/23 | Memorial Day |
| 7/4/23 | Independence Day |
| 9/4/23 | Labor Day |
| 10/9/23 | Columbus Day |
| 11/10/23 | Veterans Day |
| 11/23/23 | Thanksgiving |
| 12/25/23 | Christmas |
File details come from the government source that posted it. Updated .