ATTACHMENT E - Key Milestone Dates - Revised 07-30-2020.xlsx
XLSX spreadsheet 24 KB Posted
- Attached to
- Q702--Rapid City Community Based Outpatient Clinic (CBOC) RFQ (VA-20-00011079) Amendment 0004
- Solicitation number
- 36A77620Q0302
About this file
This combined synopsis and solicitation requests quotes for initial outfitting, transition, and activation services for a Rapid City Community-Based Outpatient Clinic in South Dakota. The Department of Veterans Affairs requires a contractor to provide services including acquisition of furniture, fixtures, and equipment; installation and configuration of medical and IT systems; and staff training and move coordination. Quotes are due by August 2020 from verified Service-Disabled Veteran-Owned Small Businesses with a size standard of $15 million or less. The contract will be awarded on a firm-fixed-price basis and run from August 2020 through September 2022. The solicitation incorporates standard FAR clauses and requires acceptance of terms and conditions or notation of any exceptions.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Integrated Project Schedule
| Task Name | Duration | Start | Finish | Owner | Status |
| Congressional Schedule | |||||
| Choice Law Passed | 0 | 8/12/17 | 8/12/17 | 100% | |
| Award Lease | 0 | 10/12/19 | 10/12/19 | 75% | |
| Construction completed | 0 | 12/12/21 | 12/12/21 | 0% | |
| activation completed | 0 | 6/12/22 | 6/12/22 | 0% | |
| Current GSA Schedule | 0 | ||||
| Award Lease | 1 | 8/7/20 | 8/7/20 | 75% | |
| Construction Completed | 1 | 5/20/22 | 5/20/22 | 0% | |
| Activation Completed | 0 | 8/13/22 | 8/13/22 | 0% | |
| Beneficial Occupancy Date (BoD) | 1 | 5/20/22 | 5/20/22 | 0% | |
| IOTA Award process | 327 | 6/19/19 | 9/25/20 | 50% | |
| create the PWS | 190 | 6/19/19 | 3/13/20 | 100% | |
| IOTA Acquisition Process | 93 | 3/13/20 | 7/23/20 | 100% | |
| IOTA RFP on street | 22 | 7/23/20 | 8/21/20 | 50% | |
| IOTA contract awarded | 6 | 8/28/20 | 9/4/20 | 0% | |
| IOTA on boarded | 14 | 9/8/20 | 9/25/20 | 0% |
| Determine FFE list | 103 | 10/5/20 | 3/5/21 | 0% |
| Current Inventory FFE | 20 | 10/5/20 | 11/2/20 | 0% |
| validate SEPS list via user meetings | 19 | 11/2/20 | 11/30/20 | 0% |
| Develop reuse plan | 22 | 11/30/20 | 12/30/20 | 0% |
| Determine FFE to purchase | 28 | 1/9/21 | 2/19/21 | 0% |
| Identify long lead time items | 5 | 2/22/21 | 2/26/21 | 0% |
| determine acquisition strategy | 5 | 3/1/21 | 3/5/21 | 0% |
| Acquisition Process | 260 | 3/8/21 | 3/18/22 | 0% |
| build acquisition packages | 45 | 3/8/21 | 5/7/21 | 0% |
| Funding from OCAMES | 25 | 5/10/21 | 6/14/21 | 0% |
| create the award (RFP) | 153 | 5/10/21 | 12/16/21 | 0% |
| rfp on street | 224 | 2/17/21 | 1/6/22 | 0% |
| select RFP | 9 | 1/7/22 | 1/20/22 | 0% |
| award contract | 1 | 1/21/22 | 1/21/22 | 0% |
| vendor accepts award | 10 | 1/24/22 | 2/4/22 | 0% |
| build, ship, receive | 29 | 2/7/22 | 3/18/22 | 0% |
| Acquisition process long leads | 432 | 6/1/20 | 2/21/22 | 0% |
| build acquisition package | 179 | 6/1/20 | 2/17/21 | 0% |
| Funding from OCAMES | 51 | 2/19/21 | 4/30/21 | 0% |
| create the award (RFP) | 65 | 5/3/21 | 8/3/21 | 0% |
| RFP on street | 15 | 8/9/21 | 8/27/21 | 0% |
| select RFP | 10 | 8/30/21 | 9/13/21 | 0% |
| Award contract | 1 | 9/14/21 | 9/14/21 | 0% |
| Vendor accepts award | 11 | 9/15/21 | 9/29/21 | 0% |
| build, ship, receive | 75 | 10/30/21 | 2/21/22 | 0% |
| Activation start per GSA Schedule | 126 | 2/28/22 | 8/24/22 | 0% |
| Install system furniture | 29 | 5/23/22 | 7/1/22 | 0% |
| Install OIT technology | 9 | 7/4/22 | 7/15/22 | 0% |
| Radiology | 18 | 5/23/22 | 6/16/22 | 0% |
| install - possibly prior ?? | 107 | 1/1/22 | 6/3/22 | 0% |
| connect to network | 2 | 6/6/22 | 6/7/22 | 0% |
| test and certify | 5 | 6/8/22 | 6/14/22 | 0% |
| Train staff | 2 | 6/15/22 | 6/16/22 | 0% |
| Audiology | 67 | 2/28/22 | 6/1/22 | 0% |
| install prior to BoD | 5 | 2/28/22 | 3/4/22 | 0% |
| connect to network | 1 | 5/23/22 | 5/23/22 | 0% |
| test and certify | 2 | 5/24/22 | 5/25/22 | 0% |
| Train staff | 4 | 5/26/22 | 6/1/22 | 0% |
| Telehealth | 11 | 5/23/22 | 6/7/22 | 0% |
| install | 1 | 5/23/22 | 5/23/22 | 0% |
| connect to network | 1 | 5/24/22 | 5/24/22 | 0% |
| test and certify | 4 | 5/25/22 | 5/31/22 | 0% |
| Train staff | 5 | 6/1/22 | 6/7/22 | 0% |
| Pharmacy Dispensing Machine | 11 | 5/23/22 | 6/7/22 | 0% |
| install | 1 | 5/23/22 | 5/23/22 | 0% |
| connect to network | 1 | 5/24/22 | 5/24/22 | 0% |
| test and certify | 4 | 5/25/22 | 5/31/22 | 0% |
| Train staff | 5 | 6/1/22 | 6/7/22 | 0% |
| Canteen Services Vending Machine | 11 | 5/23/22 | 6/7/22 | 0% |
| install | 1 | 5/23/22 | 5/23/22 | 0% |
| connect to network | 1 | 5/24/22 | 5/24/22 | 0% |
| test and certify | 4 | 5/25/22 | 5/31/22 | 0% |
| Train staff | 5 | 6/1/22 | 6/7/22 | 0% |
| Medical Equipment | 33 | 5/23/22 | 7/8/22 | 0% |
| install | 9 | 5/23/22 | 6/3/22 | 0% |
| connect to network | 5 | 6/6/22 | 6/10/22 | 0% |
| test and certify | 10 | 6/13/22 | 6/24/22 | 0% |
| Train staff | 9 | 6/27/22 | 7/8/22 | 0% |
| Move Staff | 18 | 8/1/22 | 8/24/22 | 0% |
| supply stocking in new facility | 10 | 8/1/22 | 8/12/22 | 0% |
| pack staff | 5 | 8/15/22 | 8/19/22 | 0% |
| move staff office equipment | 1 | 8/22/22 | 8/22/22 | 0% |
| staff equipment set up | 1 | 8/23/22 | 8/23/22 | 0% |
| Train staff | 1 | 8/24/22 | 8/24/22 | 0% |
| 0 | ||||
| 1st Patient | 1 | 9/19/22 | 9/19/22 | 0% |
Holidays
| 2020-2023 Federal Holidays | |
| 1/1/20 | New Years |
| 1/20/20 | MLK |
| 2/17/20 | Presidents' Day |
| 5/25/20 | Memorial Day |
| 7/3/20 | Independence Day |
| 9/7/20 | Labor Day |
| 10/12/20 | Columbus Day |
| 11/11/20 | Veterans Day |
| 11/26/20 | Thanksgiving |
| 12/25/20 | Christmas |
| 1/1/21 | New Years |
| 1/18/21 | MLK |
| 2/15/21 | Presidents' Day |
| 5/31/21 | Memorial Day |
| 7/5/21 | Independence Day |
| 9/6/21 | Labor Day |
| 10/11/21 | Columbus Day |
| 11/11/21 | Veterans Day |
| 11/25/21 | Thanksgiving |
| 12/24/21 | Christmas |
| 12/31/21 | New Years |
| 1/17/22 | MLK |
| 2/21/22 | Presidents' Day |
| 5/30/22 | Memorial Day |
| 7/4/22 | Independence Day |
| 9/5/22 | Labor Day |
| 10/10/22 | Columbus Day |
| 11/11/22 | Veterans Day |
| 12/26/22 | Christmas |
| 1/2/23 | New Years |
| 1/16/23 | MLK |
| 2/20/23 | Presidents' Day |
| 5/29/23 | Memorial Day |
| 7/4/23 | Independence Day |
| 9/4/23 | Labor Day |
| 10/9/23 | Columbus Day |
| 11/10/23 | Veterans Day |
| 11/23/23 | Thanksgiving |
| 12/25/23 | Christmas |