Attachment_D_WO_1734938-P-009U Main Parking Improvements- Specifications Final 20230912.pdf
PDF 6 MB Posted
- Solicitation number
- N4008024R1740
About this file
This document provides specifications for a construction project to improve parking facilities at Marine Corps Base Quantico in Virginia. The project includes construction of three new asphalt parking lots with related site improvements. Small business contractors holding multiple award construction contracts with Naval Facilities Engineering Command are eligible to submit proposals by February 28, 2023. The specifications cover requirements for site demolition and excavation, concrete, asphalt paving, drainage, utilities, landscaping, lighting, and signage. Submittals and schedules must follow detailed formatting and reporting standards. Construction is to be completed according to a cost-loaded network analysis schedule, with progress payments tied to earned value reporting.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Maximo NO. SRCHMGPB
WORK ORDER NO. 1734938
Installation Project No. P009U
SPECIFICATIONS
P-009U MAIN SIDE PARKING IMPROVEMENTS
Marine Corp Base Quantico, VA
PREPARED BY:
NAVFAC Washington, Design & Construction
1314 Harwood St. SE, BLDG 212 Washington, DC 20374
Civil: Harshad Patel, P.E. Landscape: Brian Niemann Electrical: Ryan Burns, P.E. Geotechnical: Karl Hren, P.E.
Specifications: Harold L. Rodriguez, P.E.
Submitted By: Harold L. Rodriguez, P.E. Date: 26 FEBRUARY 2024 Gov. Design Manager
Project Manager: Sheena F. Spearman Date: 26 FEBRUARY 2024
Approved By: Graham Ruggie, R.A. Date: 26 FEBRUARY 2024 Design Production Director
P-009U MAIN SIDE PARKING IMPROVEMENTS W.O. 1734938
Marine Corps Base Quantico, VA
BLANK
This page intentionally left blank.
PROJECT TABLE OF CONTENTS
DI VI SI ON 00 - PROCUREMENT AND CONTRACTI NG REQUI REMENTS
00 01 15 02/11, CHG 1: 08/14 LIST OF DRAWINGS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 11 00 08/15, CHG 1: 05/21 SUMMARY OF WORK
01 14 00 11/11, CHG 12: 05/21 WORK RESTRICTIONS
01 20 00 11/20, CHG 1: 02/21 PRICE AND PAYMENT PROCEDURES
01 30 00 11/20 ADMINISTRATIVE REQUIREMENTS
01 31 23.13 20 05/17, CHG 6: 02/21 ELECTRONIC CONSTRUCTION AND FACILITY
SUPPORT CONTRACT MANAGEMENT SYSTEM
01 32 17.00 20 05/18, CHG 3: 08/20 COST-LOADED NETWORK ANALYSIS SCHEDULES
(NAS)
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 33 29 02/21 SUSTAINABILITY REQUIREMENTS AND
REPORTING
01 35 26 11/20 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 20 11/11, CHG 8: 02/21 QUALITY CONTROL
01 45 35 11/20 SPECIAL INSPECTIONS
01 50 00 11/20 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19 08/22 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 08/19, CHG 2: 11/20 PROJECT IDENTIFICATION
01 74 19 02/19, CHG 1: 08/20 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 00 05/19 CLOSEOUT SUBMITTALS
01 78 23 08/15, CHG 1: 11/20 OPERATION AND MAINTENANCE DATA
01 78 24.00 20 02/15, CHG 2: 11/20 FACILITY ELECTRONIC OPERATION AND
MAINTENANCE SUPPORT INFORMATION (eOMSI)
01 78 30.00 23 10/16 CADD DATA FOR GIS DELIVERABLES
01 91 00.15 05/23 BUILDING COMMISSIONING
DI VI SI ON 02 - EXI STI NG CONDI TI ONS
02 41 00 08/22 DEMOLITION
02 81 00 11/18 TRANSPORTATION AND DISPOSAL OF
HAZARDOUS MATERIALS
DI VI SI ON 03 - CONCRETE
03 30 00 02/19, CHG 3: 11/21 CAST-IN-PLACE CONCRETE
DI VI SI ON 05 - METALS
05 52 00 02/18, CHG 1: 02/20 METAL RAILINGS
DI VI SI ON 09 - FI NI SHES
09 90 00 02/21 PAINTS AND COATINGS
DI VI SI ON 11 - EQUI PMENT
11 11 37 11/18 ELECTRIC VEHICLE SUPPLY EQUIPMENT
DI VI SI ON 12 - FURNI SHI NGS
PROJECT TABLE OF CONTENTS Page 1
12 93 00 08/17, CHG 1: 08/18 SITE FURNISHINGS
DI VI SI ON 25 - I NTEGRATED AUTOMATI ON
25 05 11 05/21 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS
DI VI SI ON 26 - ELECTRI CAL
26 08 00 11/22 APPARATUS INSPECTION AND TESTING
26 12 19.10 05/19, CHG 1: 11/19 THREE-PHASE, LIQUID-FILLED PAD-MOUNTED
TRANSFORMERS
26 20 00 08/19, CHG 3: 11/21 INTERIOR DISTRIBUTION SYSTEM
26 27 14.00 20 02/21, CHG 1: 05/21 ELECTRICITY METERING
26 56 00 08/21 EXTERIOR LIGHTING
DI VI SI ON 31 - EARTHWORK
31 11 00 11/18 CLEARING AND GRUBBING
31 23 00.00 20 02/11, CHG 2: 08/15 EXCAVATION AND FILL
DI VI SI ON 32 - EXTERI OR I MPROVEMENTS
32 01 19.61 11/19 SEALING OF JOINTS IN RIGID PAVEMENT
32 05 33 08/17 LANDSCAPE ESTABLISHMENT
32 11 20 05/22 SUBBASE FOR FLEXIBLE PAVING
32 11 23 05/22 AGGREGATE BASE COURSE FOR FLEXIBLE
PAVING
32 11 23.23 08/22 BASE COURSE DRAINAGE LAYERS
32 11 26 05/20 HOT-MIX BITUMINOUS BASE COURSE FOR
ROADS AND STREETS
32 12 13 05/17 BITUMINOUS TACK AND PRIME COATS
32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING
32 13 13.06 05/20 PORTLAND CEMENT CONCRETE PAVEMENT FOR
ROADS AND SITE FACILITIES
32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 08/16, CHG 5: 11/18 PAVEMENT MARKINGS
32 92 23 04/06 SODDING
32 93 00 08/17 EXTERIOR PLANTS
DI VI SI ON 33 - UTI LI TI ES
33 40 00 11/21 STORMWATER UTILITIES
33 46 16 05/18 SUBDRAINAGE PIPING
33 71 01 05/19, CHG 1: 11/19 OVERHEAD TRANSMISSION AND DISTRIBUTION
33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 2
DOCUMENT 00 01 15
LIST OF DRAWINGS
02/ 11, CHG 1: 08/ 14
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
1.2.1 Main Side Parking Improvements - Area 1
Area 1 corresponds to the new parking lot located between Middle Street and Elliot Road
DRAWING NO. REVISION NO. NAVFAC DWG NO. TITLE
G-001 13149233 COVER SHEET
G-002 13149234 SHEET INDEX
BB101 13149235 GEOTECHNICAL BORING LOCATION AND
LOGS
BB102 13149236 GEOTECHNICAL BORING LOGS
BB103 13149237 GEOTECHNICAL BORING LOGS
C-001 13149238 LEGEND AND ABBREVIATIONS
C-002 13149239 GENERAL CIVIL AND DEMOLITION NOTES
CV001 13149240 TOPOGRAPHIC AND UTILITIY SURVEY DATA
CD101 13149241 EXISTING CONDITIONS & DEMOLITION
PLAN
CD102 13149242 EXISTING CONDITIONS AND DEMOLITION
PLNA
CS100 13149243 OVERALL SITE PLAN
CS101 13149244 SITE PLAN
CS102 13149245 SITE PLAN
CS201 13149246 SITE LAYOUT PLAN
CS202 13149247 SITE LAYOUT PLAN
DOCUMENT 00 01 15 Page 1
DRAWING NO. REVISION NO. NAVFAC DWG NO. TITLE
CS501 13149248 SITE DETAILS
CS502 13149249 SITE DETAILS
CS503 13149250 SITE DETAILS
CG001 13149251 EROSION AND SEDIMENT CONTROL NOTES
& LEGEND
CG002 13149252 EROSION AND SEDIMENT CONTROL NOTES
& SEQUENCE OF CONSTRUCTION
CG003 13149253 EROSION & SEDIMENT CONTROL NOTES
CG100 13149254 OVERALL GRADING AND DRAINAGE PLAN
CG101 13149255 GRADING AND DRAINAGE PLAN
CG102 13149256 GRADING AND DRAINAGE PLAN
CG111 13149257 EROSION & SEDIMENT CONTROL PLAN,
PHASE I
CG112 13149258 EROSION & SEDIMENT CONTROL, PHASE I
CG113 13149259 EROSION & SEDIMENT CONTROL, PHASE II
CG114 13149260 EROSION & SEDIMENT CONTROL, PHASE II
CG201 13149261 SWM ENLARGED PLAN
CG401 13149262 STORM DRAIN PROFILE
CG501 13149263 EROSION & SEDIMENT CONTROL DETAILS
CG502 13149264 EROSION & SEDIMENT CONTROL DETAILS
CG503 13149265 GRADING AND DRAINAGE DETAILS
CG504 13149266 GRADING AND DRAINAGE DETAILS
CG505 13149267 SWM - BMP DETAILS
CG506 13149268 SWM - BMP DETAILS
CG507 13149269 SWM - CHECKLIST AND SPECIFICATIONS
CG508 13149270 SWM - CHECKLIST AND SPECIFICATIONS
CU101 13149271 UTILITY PLAN
CU201 13149272 UTILITY PROFILE
L-101 13149273 LANDSCAPE PLAN
L-102 13149274 LANDSCAPE PLAN
DOCUMENT 00 01 15 Page 2
DRAWING NO. REVISION NO. NAVFAC DWG NO. TITLE
L-501 13149275 LANDSCAPE DETAILS
E-001 13149276 ELECTRICAL GENERAL NOTES AND
SCHEMATIC SYMBOLS LEGEND
E-002 13149277 ELECTRICAL ABBREVIATIONS AND
SYMBOLS LEGEND
ED101 13149278 ELECTRICAL SITE DEMOLITION
ED102 13149279 ELECTRICAL SITE DEMOLITION
ED103 13149280 ELECTRICAL SITE DEMOLITION
ES101 13149281 ELECTRICAL NEW SITE PLAN
ES102 13149282 ELECTRICAL NEW SITE PLAN
ES103 13149283 ELECTRICAL NEW SITE PLAN
E-501 13149284 ELECTRICAL DETAILS
E-502 13149285 ELECTRICAL DETAILS
E-503 13149286 ELECTRICAL DETAILS
E-504 13149287 ELECTRICAL DETAILS
E-505 13149288 ELECTRICAL DETAILS
E-601 13149289 ELECTRICAL SINGLE LINE DIAGRAMS
E-602 13149290 ELECTRICAL SINGLE LINE DIAGRAMS
E-603 13149291 ELECTRICAL SCHEDULES
1.2.2 Main Side Parking Improvements - Area 2
Area 2 corresponds to the new parking lot located northwest of the John Quick Road and Barnett Avenue intersection.
DRAWING NO. REVISION NO. NAVFAC DWG NO. TITLE
G-001 13149295 COVER SHEET
G-002 13149296 SHEET INDEX
BB101 13149297 GEOTECHNICAL BORING LOCATION
DOCUMENT 00 01 15 Page 3
DRAWING NO. REVISION NO. NAVFAC DWG NO. TITLE
BB102 13149298 GEOTECHNICAL BORING LOGS
C-001 13149299 LEGEND AND ABBREVIATIONS
C-002 13149300 GENERAL CIVIL AND DEMOLITION NOTES
CV001 13149301 TOPOGRAPHIC AND UTILITIY SURVEY DATA
CD101 13149302 EXISTING CONDITIONS & DEMOLITION
PLAN
CS101 13149303 SITE PLAN
CS201 13149304 SITE LAYOUT PLAN
CS501 13149305 SITE DETAILS
CS502 13149306 SITE DETAILS
CS503 13149307 SITE DETAILS
CG001 13149308 EROSION AND SEDIMENT CONTROL NOTES
& LEGEND
CG002 13149309 EROSION AND SEDIMENT CONTROL NOTES
& SEQUENCE OF CONSTRUCTION
CG003 13149310 EROSION & SEDIMENT CONTROL NOTES
CG101 13149311 GRADING AND DRAINAGE PLAN
CG111 13149312 EROSION & SEDIMENT CONTROL PLAN,
PHASE I
CG112 13149313 EROSION & SEDIMENT CONTROL, PHASE II
CG401 13149314 STORM DRAIN PROFILE AND SWM
ENLARGED PLAN
CG501 13149315 EROSION & SEDIMENT CONTROL DETAILS
CG502 13149316 EROSION & SEDIMENT CONTROL DETAILS
CG503 13149317 GRADING AND DRAINAGE DETAILS
CG504 13149318 SWM-BMP DETAILS
CG505 13149319 SWM-BMP DETAILS
CG506 13149320 SWM - CHECKLIST AND SPECIFICATIONS
L101 13149321 LANDSCAPE PLAN
L501 13149322 LANDSCAPE DETAILS
E-001 13149323 ELECTRICAL GENERAL NOTES AND
SCHEMATIC SYMBOLS LEGEND
E-002 13149324 ELECTRICAL ABBREVIATIONS AND
SYMBOLS LEGEND
DOCUMENT 00 01 15 Page 4
DRAWING NO. REVISION NO. NAVFAC DWG NO. TITLE
ES101 13149325 ELECTRICAL SITE PLAN
E-501 13149326 ELECTRICAL DETAILS
E-502 13149327 ELECTRICAL DETAILS
E-601 13149328 ELECTRICAL SINGLE LINE DIAGRAMS
E-602 13149329 ELECTRICAL SCHEDULES
1.2.3 Main Side Parking Improvements - Area 3
Area 3 corresponds to the new parking lot located northeast of the Anderson Avenue and Catlin Avenue intersection
DRAWING NO. REVISION NO. NAVFAC DWG NO. TITLE
G-001 13149334 COVER SHEET
G-002 13149335 SHEET INDEX
BB101 13149336 GEOTECHNICAL BORING LOCATION
BB102 13149337 GEOTECHNICAL BORING LOGS
C-001 13149338 LEGEND AND ABBREVIATIONS
C-002 13149339 GENERAL CIVIL AND DEMOLITION NOTES
CV001 13149340 TOPOGRAPHIC AND UTILITIY SURVEY DATA
CD101 13149341 EXISTING CONDITIONS & DEMOLITION
PLAN
CS101 13149342 SITE PLAN
CS201 13149343 SITE LAYOUT PLAN
CS501 13149344 SITE DETAILS
CS502 13149345 SITE DETAILS
CS503 13149346 SITE DETAILS
CG001 13149347 EROSION AND SEDIMENT CONTROL NOTES
& LEGEND
DOCUMENT 00 01 15 Page 5
DRAWING NO. REVISION NO. NAVFAC DWG NO. TITLE
CG002 13149348 EROSION AND SEDIMENT CONTROL NOTES
& SEQUENCE OF CONSTRUCTION
CG003 13149349 EROSION & SEDIMENT CONTROL NOTES
CG101 13149350 GRADING AND DRAINAGE PLAN
CG111 13149351 EROSION & SEDIMENT CONTROL PLAN,
PHASE I
CG112 13149352 EROSION & SEDIMENT CONTROL, PHASE II
CG401 13149353 STORM DRAIN PROFILE AND SWM
ENLARGED PLAN
CG501 13149354 EROSION & SEDIMENT CONTROL DETAILS
CG502 13149355 EROSION & SEDIMENT CONTROL DETAILS
CG503 13149356 SWM-BMP DETAILS
CG504 13149357 SWM-BMP DETAILS
CG505 13149358 SWM - CHECKLIST AND SPECIFICATIONS
CU101 13149359 UTILITY PLAN
CU201 13149360 UTILITY PROFILE
L101 13149361 LANDSCAPE PLAN
L501 13149362 LANDSCAPE DETAILS
E-001 13149363 ELECTRICAL GENERAL NOTES AND
SCHEMATIC SYMBOLS LEGEND
E-002 13149364 ELECTRICAL ABBREVIATIONS AND
SYMBOLS LEGEND
ED101 13149365 ELECTRICAL SITE DEMOLITION
ES101 13149366 ELECTRICAL NEW SITE PLAN
E-501 13149367 ELECTRICAL DETAILS
E-502 13149368 ELECTRICAL DETAILS
E-503 13149369 ELECTRICAL DETAILS
E-504 13149370 ELECTRICAL DETAILS
E-601 13149371 ELECTRICAL SINGLE LINE DIAGRAMS
E-602 13149372 ELECTRICAL SCHEDULES
DOCUMENT 00 01 15 Page 6
1.3 SUPPLEMENTARY DRAWINGS
These supplementary drawings may not be a part of the contract but are included with the drawings for information.
1.3.1 Boring Logs
The boring logs are provided in the contract drawings. The Government does not guarantee that borings indicate actual conditions, except for the exact locations and the time that they were made.
-- End of Document --
DOCUMENT 00 01 15 Page 7
SECTION 01 11 00
SUMMARY OF WORK
08/ 15, CHG 1: 05/ 21
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals Salvage Plan; G
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The project includes the construction of three (3) personal occupancy vehicle (POV) surface parking lots indentified as Main Side Parking Area 1, Area 2 and Area 3.
1.2.1.1 Main Side Parking - Area 1
Area 1 is an existing concrete slab, where a building once stood, but has since been demolished. A new asphalt parking lot with 91 perpendicular parking spaces will be constructed with vehicular access via Middle Street. Middle Street will be widened to provide 14 new parallel parking spaces. The existing asphalt parking lot will be milled, overlaid and restriped 114 perpendicular parking space. Improvement also include sidewalks, street lighting, and a SWM/BMP facility.
1.2.1.2 Main Side Parking - Area 2
Area 2 is an existing gravel parking lot in front of BLDG 2073. A new asphalt parking lot with 128 total spaces will be constructed. An existing seven (7) regular spaces and Four (4) motorcycle paces will be removed from the street to build this new parking lot. Improvement also include sidewalks, street lighting, and a SWM/BMP facility.
1.2.1.3 Main Side Parking - Area 3
Area 3 is an existing gravel parking lot at the corner of Anderson Avenue and Caitlin Avenue. A new asphalt parking lot with 80 total spaces will be constructed. Improvement also include sidewalks, street lighting, and a SWM/BMP facility.
1.2.2 Location
The work is located at Marine Corps Base Quantico in Quantico, Virginia, as shown in the contract drawings. The exact location will be shown by the Contracting Officer.
SECTION 01 11 00 Page 1
1.3 OCCUPANCY OF PREMISES
The project sites are located on near the east end of the installation in partially but uncoupied developed areas. The areas are identified as Main Side Parking Area 1, Area 2 and Area 3.
1.3.1 Main Side Parking - Area 1
Area 1 is an existing concrete slab, where a building once stood, but has since been demolished. Adjance to this area is existing asphalt parking lot that is to be milled, overlaid and restriped with this project. There are several power lines crossing the site supported by power poles. Other utilities run trough the site including but not limited to water, storm, communication, and gas. No building structures are located within this area.
1.3.2 Main Side Parking - Area 2
Area 2 is an existing gravel parking lot in front of BLDG 2073. There are existing wheels stops, curb & gutter, and grate inlets on the site.
Numerous existing utilities including gas, water, telco and electric run parallel with Barnett Avenue, behind the existing sidewalk and along the John Quick Road side. Seven (7) regular spaces and Four (4) motorcycle paces are sited along the south end of the west side. No building structures are located within this area.
1.3.3 Main Side Parking - Area 3
Area 3 is an existing gravel parking lot at the corner of Anderson Avenue and Caitlin Avenue. There are several power lines crossing the site supported by power poles. Other utilities run trough the site including but not limited to water, storm electric power and gas. No building structures are located within this area.
Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, and space for storage of materials and equipment.
1.4 ON-SITE PERMITS
1.4.1 Utility Outage Requests and Utility Connection Requests
Schedule work to minimize outages. For utility outages and connections required during the execution of work that affect existing systems, schedule outside the regular working hours or on weekends, as approved by the Contracting Officer. Schedule utility outages and connections to minimize disruptions to the Government. No additional payment will be provided for utility outages and connections required to be performed outside the regular work hours.
Submit requests for utility outages and connections in writing to the Contracting Officer for approval at least 21 calendar days in advance of the time required. In each request, state the system involved, area involved, approximate duration of outage, and the nature of work involved.
1.4.2 Excavation Permits
Provide Excavation Permits within 21 calendar days prior to work
SECTION 01 11 00 Page 2
1.5 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.6 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.
Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.
Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities,and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
Submit for an Excavation permit in accordance with the attached Standard Operating Procedures (SOP) for the MCB-Quantico Excavation Permit. An example EXCAVATION PERMIT REQUEST FORM is attached at the end of this section. Confirm with Contracting Officer at the Construction kick off meeting for the most updated permit process and forms.
1.6.1 Notification Prior to Excavation
Notify the Contracting Officer at least 48 hours prior to starting excavation work.
1.7 NAVY AND MARINE CORPS (GOVERNMENT) COORDINATION REQUIREMENTS
1.7.1 Government Contractor Access
Allow the Government Contractor access to the facility towards the end of construction (finishes 90 percent complete, rough-in 100 percent complete, Inside Plant (ISP)/Outside Plant (OSP) infrastructure in place) to provide equipment in the telecommunications rooms and make final connections.
Coordinate efforts with the Government Contractor to facilitate joint use of building spaces during the final phases of construction. After the Contracting Officer has facilitated coordination meetings between the two contractors, within one week, incorporate the effort of additional
SECTION 01 11 00 Page 3 coordination with the Government Contractor into the construction schedule to demonstrate a plan for maintaining the contract duration.
1.8 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated area in the MCBQ, as determined by the Contracting Officer.
Provide a salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Use a system of property control that is approved by the Contracting Officer. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 4
SECTION 01 14 00
WORK RESTRICTIONS
11/ 11, CHG 12: 05/ 21
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel
1.2 CONTRACTOR ACCESS AND USE OF PREMISES
1.2.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.
1.2.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.2.1.2 Installation Access
Obtain access to Navy installations through participation in the Defense Biometrics Identification System (DBIDS). Requirements for Contractor employee registration, and transition for employees currently under Navy Commercial Access Control System (NCACS), are available at https://www.cnic.navy.mil/om/dbids.html . No fees are associated with obtaining a DBIDS credential.
Participation in the DBIDS is not mandatory, and Contractor personnel may apply for One-Day Passes at the Base Visitor Control Office to access an installation.
1.2.1.2.1 Registration for DBIDS
Registration for DBIDS is available at https://www.cnic.navy.mil/om/dbids.html . Procedure includes:
a. Present a letter or official award document (i.e. DD Form 1155 or SF 1442) from the Contracting Officer, that provides the purpose for access, to the base Visitor Control Center representative.
SECTION 01 14 00 Page 1
b. Present valid identification, such as a passport or Real ID Act-compliant state driver's license.
c. Provide completed SECNAV FORM 5512/1 to the base Visitor Control Center representative to obtain a background check. This form is available for download at https://www.cnic.navy.mil/om/dbids.html .
d. Upon successful completion of the background check, the Government will complete the DBIDS enrollment process, which includes Contractor employee photo, fingerprints, base restriction and several other assessments.
e. Upon successful completion of the enrollment process, the Contractor employee will be issued a DBIDS credential, and will be allowed to proceed to worksite.
1.2.1.2.2 DBIDS Eligibility Requirements
Throughout the length of the contract, the Contractor employee must continue to meet background screen standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.
An adjudication process may be initiated when a background screen failure results in disqualification from participation in the DBIDS, and Contractor employee does not agree with the reason for disqualification.
The Government is the final authority.
1.2.1.2.3 DBIDS Notification Requirements
a. Immediately report instances of lost or stolen badges to the Contracting Officer.
b. Immediately collect DBIDS credentials and notify the Contracting Officer in writing under the following circumstances:
(1) An employee has departed the company without having properly returned or surrendered their DBIDS credentials.
(2) There is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the Installation or anyone therein.
1.2.1.2.4 One-Day Passes
Personnel applying for One-Day passes at the Base Visitor Control Office are subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government is not responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the DBIDS.
1.2.1.3 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under
SECTION 01 14 00 Page 2 renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.2.2 Working Hours
Regular working hours will consist of a 10 hour period between 7 a.m. and 5:30 p.m., Monday through Friday, excluding Government holidays.
1.2.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.
1.2.4 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, telecommunication systems, and any others are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS.
d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.
Sanitary sewer and water connection permits are required to be obtained through the Base PWB Utilities Section.
e. Connection to Existing Sanitary Sewer Line: Provide positive verification that the existing line conveys sanitary sewer; verify line is not incorrectly connected to a storm drain.
1.3 SECURITY REQUIREMENTS
1.3.1 Marine Corps Base Quantico (MCBQ), Quantico, VA
All Contractor and its employees performing services on Marine Corps Base, Quantico (MCBQ) requiring physical access to the installation must be properly screened. Screening consists of identity proofing and vetting in accordance with the standards set forth in Marine Corps Base Order 4200.3 (28 JUL 10). The Contractor must request a copy of this policy from the
SECTION 01 14 00 Page 3
Contracting Officer.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 14 00 Page 4
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
11/ 20, CHG 1: 02/ 21
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EP 1110-1-8 (2016) Construction Equipment Ownership and Operating Expense Schedule
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Earned Value Report; G
1.3 EARNED VALUE REPORT
1.3.1 Data Required
This Contract requires the use of a cost-loaded Network Analysis Schedule (NAS). Schedule of Prices must not be used with cost-loaded Network Analysis Schedule (NAS). Use Earned Value Report derived from cost-loaded NAS. Provide a detailed breakdown of the Contract price, giving quantities for each of the various kinds of work, unit prices and extended prices.
Contractor overhead and profit including salaries for field office personnel, if applicable, must be proportionately spread over all pay items and not included as individual pay items.
1.3.1.1 Additional Facility Price Data
For all projects over $500K, the Contractor shall electronically submit Additional Facility Price Data to the Contracting Officer as a formal submittal within 15 days of Contract award. The cost break out will be in first or second level WBS format that will include:
a. Each individual facility to the five foot line.
b. The total site work/utilities from the five foot line outward.
Use CLIN 0001AA, AB, AC, and AD from UFGS 00 22 13.00 20 SUPPLEMENTARY INSTRUCTIONS TO OFFERORS, as an example on how to prepare the cost breakout structure. Contact the NAVFAC Washington Cost Engineer for additional information and guidance on the development of the cost breakout.
SECTION 01 20 00 Page 1
1.3.2 Payment Schedule Instructions
Payments will not be made until the Earned Value Report from the cost-loaded NAS has been submitted to and accepted by the Contracting Officer.
Additionally, the Earned Value Report must be separated as follows:
a. Primary Facilities Cost Breakdown:
Defined as work on the primary facilities out to the 5 foot line.
Work out to the 5 foot line includes construction encompassed within a theoretical line 5 foot from the face of exterior walls and includes attendant construction, such as pad mounted HVAC cooling equipment, cooling towers, and transformers placed beyond the 5 foot line.
b. Supporting Facilities Cost Breakdown:
Defined as site work, including incidental work, outside the 5 foot line.
1.4 CONTRACT MODIFICATIONS
In conjunction with the Contract Clause DFARS 252.236-7000 Modification Proposals-Price Breakdown, and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, base equipment use rates upon the applicable provisions of the
EP 1110-1-8 .
1.5 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.5.1 Content of Invoice
Requests for payment will be processed in accordance with the Contract Clause FAR 52.232-27 Prompt Payment for Construction Contracts and FAR 52.232-5 Payments Under Fixed-Price Construction Contracts. Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies. The requests for payment shall include the documents listed below.
a. The Contractor's invoice, on NAVFAC Form 7300/30 furnished by the Government, showing in summary form, the basis for arriving at the amount of the invoice. Form 7300/30 must include certification by Quality Control (QC) Manager as required by the Contract.
b. The Earned Value Report from the cost-loaded NAS.
c. Contractor's Monthly Estimate for Voucher and Contractors Certification (NAVFAC Form 4330) with Subcontractor and supplier payment certification. Other documents, including but not limited to, that need to be received prior to processing payment include the following submittals as required. These items are still required monthly even when a pay voucher is not submitted.
d. Monthly Work-hour report.
e. Updated Construction Progress Schedule and tabular reports required by the contract.
SECTION 01 20 00 Page 2
f. Contractor Safety Self Evaluation Checklist.
g. Updated submittal register.
h. Solid Waste Disposal Report.
i. Certified payrolls.
j. Updated testing logs.
k. Other supporting documents as requested.
1.5.2 Submission of Invoices
If DFARS Clause 252.232-7006 Wide Area WorkFlow Payment Instructions is included in the Contract, provide the documents listed in above paragraph CONTENT OF INVOICE in their entirety as attachments in Wide Area Work Flow (WAWF) for each invoice submitted. The maximum size of each WAWF attachment is two megabytes, but there are no limits on the number of attachments. If a document cannot be attached in WAWF due to system or size restriction, provide it as instructed by the Contracting Officer.
Monthly invoices and supporting forms for work performed through the anniversary award date of the Contract must be submitted to the Contracting Officer within 5 calendar days of the date of invoice. For example, if Contract award date is the 7th of the month, the date of each monthly invoice must be the 7th and the invoice must be submitted by the 12th of the month.
1.5.3 Final Invoice
a. A final invoice must be accompanied by the certification required by DFARS 252.247.7023 Transportation of Supplies by Sea, and the Contractor's Final Release. If the Contractor is incorporated, the Final Release must contain the corporate seal. An officer of the corporation must sign and the corporate secretary must certify the Final Release.
b. For final invoices being submitted via WAWF, the original Contractor's Final Release Form and required certification of Transportation of Supplies by Sea must be provided directly to the respective Contracting Officer prior to submission of the final invoice. Once receipt of the original Final Release Form and required certification of Transportation of Supplies by Sea has been confirmed by the Contracting Officer, the Contractor must then submit final invoice and attach a copy of the Final Release Form and required certification of Transportation of Supplies by Sea in WAWF.
c. Final invoices not accompanied by the Contractor's Final Release and required certification of Transportation of Supplies by Sea will be considered incomplete and will be returned to the Contractor.
1.6 PAYMENTS TO THE CONTRACTOR
Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section, and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.
SECTION 01 20 00 Page 3
1.6.1 Obligation of Government Payments
The obligation of the Government to make payments required under the provisions of this Contract will, at the discretion of the Contracting Officer, be subject to reductions and suspensions permitted under the FAR and agency regulations including the following in accordance with FAR FAR
32.103 Progress Payments Under Construction Contracts:
a. Reasonable deductions due to defects in material or workmanship;
b. Claims which the Government may have against the Contractor under or in connection with this Contract;
c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and
d. Failure to maintain accurate "as-built" or record drawings in accordance with FAR 52.236.21.
1.6.2 Payment for Onsite and Offsite Materials
Progress payments may be made to the Contractor for materials delivered on the site, for materials stored off construction sites, or materials that are in transit to the construction sites under the following conditions:
a. FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.
b. Materials delivered on the site but not installed, including completed preparatory work, and off-site materials to be considered for progress payment must be major high cost, long lead, special order, or specialty items, not susceptible to deterioration or physical damage in storage or in transit to the construction site. Examples of materials acceptable for payment consideration include, but are not limited to, structural steel, non-magnetic steel, non-magnetic aggregate, equipment, machinery, large pipe and fittings, precast/prestressed concrete products, plastic lumber (e.g., fender piles/curbs), and high-voltage electrical cable. Materials not acceptable for payment include consumable materials such as nails, fasteners, conduits, gypsum board, glass, insulation, and wall coverings.
c. Materials to be considered for progress payment prior to installation must be specifically and separately identified in the Contractor's estimates of work submitted for the Contracting Officer's approval in accordance with Earned Value Report requirement of this Contract.
Requests for progress payment consideration for such items must be supported by documents establishing their value and that the title requirements of the clause at FAR 52.232-5 Payments Under Fixed-Price Construction Contracts have been met.
d. Materials are adequately insured and protected from theft and exposure.
e. Provide a written consent from the surety company with each payment request for offsite materials.
f. Materials to be considered for progress payments prior to installation must be stored in a safe place in the Continental United States as approved by the Contracting Officer and where he or she can oversee the materials or products. Other locations are subject to written
SECTION 01 20 00 Page 4 approval by the Contracting Officer.
g. Materials in transit to the job site or storage site are not acceptable for payment.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 20 00 Page 5
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
11/20
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety -- Safety and Health Requirements Manual
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
View Location Map
Progress and Completion Pictures
1.3 VIEW LOCATION MAP
Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.
1.4 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures.
Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file.
Include a date designator in file names. Photographs provided are for unrestricted use by the Government. Note: Photographs must not be taken of aircraft, military equipment, hangars, or restricted areas.
SECTION 01 30 00 Page 1
1.5 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by State law.
1.6 SUPERVISION
1.6.1 Superintendent Qualifications
Provide project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
1.6.2 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work.In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.
1.6.3 Duties
The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend Red Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.6.4 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.
Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
1.7 PRECONSTRUCTION MEETING
Immediately after award , prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Meeting . The meeting must take place within 35 calendar days after award of the contract, but prior to commencement of any work at the site. The purpose of this meeting is to discuss and develop a mutual understanding of the administrative requirements of the Contract including
SECTION 01 30 00 Page 2 but not limited to: daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out. Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.
1.7.1 Attendees
Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.
1.8 FACILITY TURNOVER PLANNING MEETINGS (Red Zone Meetings)
Meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start planning the turnover process at the Pre-Construction Conference meeting with a discussion of the Red Zone process and convene at regularly scheduled NRZ Meetings beginning at approximately 75 percent of project completion.
Include the following in the facility Turnover effort:
1.8.1 Red Zone Checklist
a. Contracting Officer's Technical Representative (COTR) will provide the Contractor a copy of the Red Zone Checklist template.
b. Prior to 75 percent completion, modify the Red Zone Checklist template by adding or deleting critical activities applicable to the project and assign planned completion dates for each activity. Submit the modified Red Zone Checklist to the Contracting Officer. The Contracting Officer may request additional activities be added to the Red Zone Checklist at any time as necessary.
1.8.2 Meetings
a. Conduct regular Red Zone Meetings beginning at approximately 75 percent project completion, or three to six months prior to Beneficial Occupancy Date (BOD), whichever comes first.
b. The Contracting Officer will establish the frequency of the meetings, which is expected to increase as the project completion draws nearer.
At the beginning, Red Zone meetings may be every two weeks then increase to weekly towards the final month of the project.
c. Using the Red Zone Checklist as a Plan of Action and Milestones (POAM) and basis for discussion, review upcoming critical activities and strategies to ensure work is completed on time.
d. During the Red Zone Meetings discuss with the COTR any upcoming activities that require Government involvement.
e. Maintain the Red Zone Checklist by documenting the actual completion dates as work is completed and update the Red Zone Checklist with revised planned completion dates as necessary to match progress.
Distribute copies of the current Red Zone Checklist to attendees at each Red Zone Meeting.
SECTION 01 30 00 Page 3
1.9 PARTNERING
To most effectively accomplish this Contract, the Contractor and Government must form a cohesive partnership with the common goal of drawing on the strength of each organization in an effort to achieve a successful project without safety mishaps, conforming to the Contract, within budget and on schedule. The partnering team must consist of personnel from both the Government and Contractor including project level and corporate level leadership positions. Key Personnel from the supported command, end user, NAVFAC, PWD, FEAD/ROICC, Contractor, key subcontractors and the Designer of Record are required to participate in the Partnering process.
1.9.1 Team-Led (Informal) Partnering
a. The Contracting Officer will coordinate the initial Team-Led (Informal) Partnering Session with key personnel of the project team, including Contractor and Government personnel. The Partnering Session will be co-led by the Government Construction Manager and Contractor's Project Manager.
b. The Initial Team-led Partnering session may be held concurrently with the Pre-Construction Post-Award Kickoff meeting. Partnering sessions will be held at a location mutually agreed to by the Contracting Officer and the Contractor, typically at a conference room on-base or at the Contractor's temporary trailer.
c. The Initial Team-Led Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by Contracting Officer.
d. The Partners will determine the frequency of the follow-on sessions.
e. Participants will bear their own costs for meals, lodging and transportation associated with Partnering.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 30 00 Page 4
SECTION 01 31 23.13 20
ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT MANAGEMENT SYSTEM
05/ 17, CHG 6: 02/ 21
PART 1 GENERAL
1.1 CONTRACT ADMINISTRATION
Utilize the Naval Facilities Engineering Command's (NAVFAC's) Electronic Construction and Facility Support Contract Management System (eCMS) for the transfer, sharing and management of electronic technical submittals and documents. The web-based eCMS is the designated means of transferring technical documents between the Contractor and the Government. Paper media or e-mail submission, including originals or copies, of the documents identified in Table 1 are not permitted, except where eCMS is unavailable, non-functional or specifically requested in addition to electronic submission. When specifically requested to provide documents outside of eCMS, upload all final project documentation (e.g. documents that are signed and/or adjudicated by the Government) mentioned in Table 1 into the subject eCMS document management folders that are associated with that document type. Include the identification number of the document, type of document; the name/subject or title; and for daily reports the date (day of work) with format YYYY/MM/DDin the filename. For example for RFI’s 0011_RFI_Roof_Leaking.doc; For submittals 0032a_Submittals_Light_Fixture.pdf; For Daily Reports 0132_Daily_Report_20190504.xls. Contact the Contracting Officer's Representative (COR) regarding availability of eCMS training and reference materials.
1.2 USER PRIVILEGES
The Contractor will be provided access to eCMS. All technical submittals and documents must be transmitted to the Government via the COR. Project roles and system roles will be established to control each user's menu, application, and software privileges, including the ability to create, edit, or delete objects.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List of Contractor's Personnel; G
1.4 SYSTEM REQUIREMENTS AND CONNECTIVITY
1.4.1 General
The eCMS requires a web-browser (platform-neutral) and Internet connection. Obtain from an approved vendor an External Certification Authority (ECA), Primary Key Infrastructure (PKI) certificate, or other similar digital identification to support two-factor authentication and access to eCMS. Provide and maintain computer hardware and software for
SECTION 01 31 23.13 20 Page 1 the eCMS access throughout the duration of the contract for all Contractor-designated users. Provide connectivity, speed, bandwidth, and access to the Internet to ensure adequate functionality. Neither upgrading of the Contractor's computer system nor delays associated from the usage of the eCMS will be justification or grounds for a time extension or cost adjustment to the Contract.
1.4.2 Contractor Personnel List
Within 20 calendar days of contract award, provide to the Contracting Officer a list of Contractor's personnel who will have the responsibility for the transfer, sharing and management of electronic technical submittals and documents and will require access to the eCMS. Project personnel roles to be filled in the eCMS include the Contractor's Project Manager, Superintendent, Quality Control (QC) Manager, and Site Safety and Health Officer (SSHO). Personnel must be capable of electronic document management. Notify the COR immediately of any personnel changes to the project.