Attachment_D_01 33 00 SUBMITTAL REGISTER.xlsx
XLSX spreadsheet 65 KB Posted
- Solicitation number
- N4008024R1740
About this file
This is a submittal register for the federal contract opportunity P009U Main Side Parking at Marine Corps Base Quantico in Virginia. The project involves improvements to the main side parking area including new asphalt paving, lighting, electrical work, landscaping, and site utilities. Only Small Business Multiple Award Construction contract holders for N4008019D0011 through 0020 are eligible to submit a proposal, which is due by the dates listed for each required submittal in the register. Key submittals include plans, shop drawings, product data, test reports, certificates of compliance, and operation and maintenance manuals for items like asphalt and concrete work, lighting, landscaping, fencing and utilities. The register provides the framework for contractors to receive approvals from the government for all construction materials and methods before starting work on site.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table 1
SUBMITTAL REGISTER CONTRACT NO.
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR | ||
| A C T I V I T Y | |||
| N O | T R A N S M I T T A L | ||
| N O | S P E C | ||
| S E C T | DESCRIPTION ITEM SUBMITTED | P A R A |
G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W
| N R | CONTRACTOR: SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | MAILED TO CONTR/ | ||||||||||||||
| DATE RCD FRM APPR AUTH | REMARKS | |||||||||||||||||
| SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | DATE FWD TO APPR AUTH/ | ||||||||||||||||
| DATE RCD FROM CONTR | DATE FWD TO OTHER REVIEWER | DATE RCD FROM OTH REVIEWER | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | |||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |
| 01 11 00 | SD-01 Preconstruction Submittals | |||||||||||||||||
| Salvage Plan | 1.8 | G | ||||||||||||||||
| 01 14 00 | SD-01 Preconstruction Submittals | |||||||||||||||||
| List of Contact Personnel | 1.2.1.1 | |||||||||||||||||
| 01 20 00 | SD-01 Preconstruction Submittals | |||||||||||||||||
| Earned Value Report | 1.3 | G | ||||||||||||||||
| 01 30 00 | SD-01 Preconstruction Submittals | |||||||||||||||||
| View Location Map | 1.3 | |||||||||||||||||
| Progress and Completion | 1.4 | |||||||||||||||||
| Pictures | ||||||||||||||||||
| 01 31 23.13 20 | SD-01 Preconstruction Submittals | |||||||||||||||||
| List of Contractor's Personnel | 1.4.2 | G | ||||||||||||||||
| 01 32 17.00 20 | SD-01 Preconstruction Submittals | |||||||||||||||||
| Baseline NAS | 1.2.2 | G | ||||||||||||||||
| Designated Project Scheduler | 1.9 | G | ||||||||||||||||
| SD-07 Certificates | ||||||||||||||||||
| Three-Week Look Ahead | 1.3 | G | ||||||||||||||||
| Schedule | ||||||||||||||||||
| Monthly Network Analysis | 1.4.1 | G | ||||||||||||||||
| Updates | ||||||||||||||||||
| SD-11 Closeout Submittals | ||||||||||||||||||
| As-Built Schedule | 1.4.2 | G | ||||||||||||||||
| 01 33 00 | SD-01 Preconstruction Submittals | |||||||||||||||||
| Submittal Register | 1.8 | G | ||||||||||||||||
| 01 33 29 | SD-01 Preconstruction Submittals |
SUBMITTAL REGISTER CONTRACT NO.
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR | ||
| A C T I V I T Y | |||
| N O | T R A N S M I T T A L | ||
| N O | S P E C | ||
| S E C T | DESCRIPTION ITEM SUBMITTED | P A R A |
G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W
| N R | CONTRACTOR: SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | MAILED TO CONTR/ | ||||||||||||||
| DATE RCD FRM APPR AUTH | REMARKS | |||||||||||||||||
| SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | DATE FWD TO APPR AUTH/ | ||||||||||||||||
| DATE RCD FROM CONTR | DATE FWD TO OTHER REVIEWER | DATE RCD FROM OTH REVIEWER | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | |||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |
| 01 33 29 | Preliminary Sustainability | 1.4.2.2 | G | |||||||||||||||
| eNotebook | ||||||||||||||||||
| SD-11 Closeout Submittals | ||||||||||||||||||
| Final Sustainability eNotebook | 1.4.2.2 | G | ||||||||||||||||
| 01 35 26 | SD-01 Preconstruction Submittals | |||||||||||||||||
| APP - Construction | 1.8.1 | G | ||||||||||||||||
| Accident Prevention Plan (APP) | 1.8 | G | ||||||||||||||||
| SD-06 Test Reports | ||||||||||||||||||
| Monthly Exposure Reports | 1.4 | |||||||||||||||||
| Notifications and Reports | 1.13 | |||||||||||||||||
| Accident Reports | 1.13.2 | G | ||||||||||||||||
| LHE Inspection Reports | 1.13.3 | |||||||||||||||||
| SD-07 Certificates | ||||||||||||||||||
| Contractor Safety Self-Evaluation | 1.5 | |||||||||||||||||
| Checklist | ||||||||||||||||||
| Standard Lift Plan | 1.8.3.2 | G | ||||||||||||||||
| Critical Lift Plan | 1.8.3.3 | G | ||||||||||||||||
| Activity Hazard Analysis (AHA) | 1.9 | |||||||||||||||||
| Confined Space Entry Permit | 1.10.1 | |||||||||||||||||
| Hot Work Permit | 1.10.1 | |||||||||||||||||
| Certificate of Compliance | 1.13.4 | |||||||||||||||||
| License Certificates | 1.15 | |||||||||||||||||
| Radiography Operation Planning | 1.15.1 | G | ||||||||||||||||
| Work Sheet | ||||||||||||||||||
| Portable Gauge Operations | 1.15.1 | G | ||||||||||||||||
| Planning Worksheet | ||||||||||||||||||
| SUBMITTAL REGISTER | CONTRACT NO. |
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR | ||
| A C T I V I T Y | |||
| N O | T R A N S M I T T A L | ||
| N O | S P E C | ||
| S E C T | DESCRIPTION ITEM SUBMITTED | P A R A |
G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W
| N R | CONTRACTOR: SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | MAILED TO CONTR/ | ||||||||||||||
| DATE RCD FRM APPR AUTH | REMARKS | |||||||||||||||||
| SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | DATE FWD TO APPR AUTH/ | ||||||||||||||||
| DATE RCD FROM CONTR | DATE FWD TO OTHER REVIEWER | DATE RCD FROM OTH REVIEWER | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | |||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |
| 01 35 26 | Machinery & Mechanized | 3.6.3 | ||||||||||||||||
| Equipment Certification Form | ||||||||||||||||||
| 01 45 00.00 20 | SD-01 Preconstruction Submittals | |||||||||||||||||
| Construction Quality Control (QC) | 1.6.1 | G | ||||||||||||||||
| Plan | ||||||||||||||||||
| 01 45 35 | SD-06 Test Reports | |||||||||||||||||
| Daily Reports | 3.1.2 | |||||||||||||||||
| Biweekly Reports | 3.1.1 | |||||||||||||||||
| SD-07 Certificates | ||||||||||||||||||
| Special Inspector | 1.5 | G | ||||||||||||||||
| SD-11 Closeout Submittals | ||||||||||||||||||
| Comprehensive Final Report | 3.1.2 | G | ||||||||||||||||
| 01 50 00 | SD-01 Preconstruction Submittals | |||||||||||||||||
| Construction Site Plan | 1.3 | G | ||||||||||||||||
| Traffic Control Plan | 3.3.1 | G | ||||||||||||||||
| Haul Road Plan | 2.2.1 | G | ||||||||||||||||
| Contractor Computer | 1.6.1.4 | G | ||||||||||||||||
| Cybersecurity Compliance | ||||||||||||||||||
| Statements | ||||||||||||||||||
| Contractor Temporary Network | 1.6.6 | G | ||||||||||||||||
| Cybersecurity Compliance | ||||||||||||||||||
| Statements | ||||||||||||||||||
| SD-06 Test Reports | ||||||||||||||||||
| Backflow Preventer Tests | 3.4 | |||||||||||||||||
| SD-07 Certificates | ||||||||||||||||||
| Backflow Tester | 1.4.1 | |||||||||||||||||
| SUBMITTAL REGISTER | CONTRACT NO. |
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR | ||
| A C T I V I T Y | |||
| N O | T R A N S M I T T A L | ||
| N O | S P E C | ||
| S E C T | DESCRIPTION ITEM SUBMITTED | P A R A |
G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W
| N R | CONTRACTOR: SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | MAILED TO CONTR/ | ||||||||||||||
| DATE RCD FRM APPR AUTH | REMARKS | |||||||||||||||||
| SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | DATE FWD TO APPR AUTH/ | ||||||||||||||||
| DATE RCD FROM CONTR | DATE FWD TO OTHER REVIEWER | DATE RCD FROM OTH REVIEWER | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | |||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |
| 01 50 00 | Backflow Preventers | 1.4 | ||||||||||||||||
| 01 57 19 | SD-01 Preconstruction Submittals | |||||||||||||||||
| Preconstruction Survey | 1.6.1 | |||||||||||||||||
| Regulatory Notifications | 1.6.2 | G | ||||||||||||||||
| Environmental Manager | 1.6.4 | G | ||||||||||||||||
| Qualifications | ||||||||||||||||||
| Employee Training Records | 1.6.5 | G | ||||||||||||||||
| Environmental Protection Plan | 1.7 | G | ||||||||||||||||
| Dirt and Dust Control Plan | 1.7.9.1 | G | ||||||||||||||||
| Solid Waste Management Permit | 1.10 | G | ||||||||||||||||
| Stormwater Pollution Prevention | 3.2.1.1 | G | ||||||||||||||||
| Plan | ||||||||||||||||||
| Stormwater Notice of Intent | 3.2.1.2 | G | ||||||||||||||||
| Spill Prevention Control And | 3.10.2 | G | ||||||||||||||||
| Countermeasure (SPCC) Plan | ||||||||||||||||||
| SD-06 Test Reports | ||||||||||||||||||
| Monthly Solid Waste Disposal | 1.10.1 | G | ||||||||||||||||
| Report | ||||||||||||||||||
| Inspection Reports | 3.2.1.3 | |||||||||||||||||
| SD-07 Certificates | ||||||||||||||||||
| ECATTS Certificate Of | 1.4.1.2 | G | ||||||||||||||||
| Completion | ||||||||||||||||||
| Employee Training Records | 1.6.5 | G | ||||||||||||||||
| Erosion and Sediment Control | 1.6.5 | |||||||||||||||||
| Inspector | ||||||||||||||||||
| SD-11 Closeout Submittals | ||||||||||||||||||
| SUBMITTAL REGISTER | CONTRACT NO. |
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR | ||
| A C T I V I T Y | |||
| N O | T R A N S M I T T A L | ||
| N O | S P E C | ||
| S E C T | DESCRIPTION ITEM SUBMITTED | P A R A |
G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W
| N R | CONTRACTOR: SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | MAILED TO CONTR/ | ||||||||||||||
| DATE RCD FRM APPR AUTH | REMARKS | |||||||||||||||||
| SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | DATE FWD TO APPR AUTH/ | ||||||||||||||||
| DATE RCD FROM CONTR | DATE FWD TO OTHER REVIEWER | DATE RCD FROM OTH REVIEWER | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | |||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |
| 01 57 19 | Regulatory Notifications | 1.6.2 | G | |||||||||||||||
| Assembled Employee Training | 1.6.5 | G | ||||||||||||||||
| Records | ||||||||||||||||||
| Solid Waste Management Permit | 1.10 | G | ||||||||||||||||
| Stormwater Pollution Prevention | 3.2.1.4 | G | ||||||||||||||||
| Plan Compliance Notebook | ||||||||||||||||||
| Stormwater Notice of Termination | 3.2.1.5 | G | ||||||||||||||||
| As-Built Topographic Survey | 3.2.1.5 | |||||||||||||||||
| Waste Determination | 3.7.1 | G | ||||||||||||||||
| Documentation | ||||||||||||||||||
| Project Solid Waste Disposal | 3.7.2.1 | G | ||||||||||||||||
| Documentation Report | ||||||||||||||||||
| Sales Documentation | 3.7.2.1 | G | ||||||||||||||||
| Contractor Certification | 3.7.2.1 | |||||||||||||||||
| Hazardous Waste/Debris | 3.7.3.1 | G | ||||||||||||||||
| Management | ||||||||||||||||||
| Disposal Documentation for | 3.7.3.5 | G | ||||||||||||||||
| Hazardous and Regulated Waste | ||||||||||||||||||
| Contractor Hazardous Material | 3.8.1 | G | ||||||||||||||||
| Inventory Log | ||||||||||||||||||
| 01 58 00 | SD-02 Shop Drawings | |||||||||||||||||
| Preliminary Drawing Indicating | 1.3.1 | G | ||||||||||||||||
| Layout And Text Content | ||||||||||||||||||
| 01 74 19 | SD-01 Preconstruction Submittals | |||||||||||||||||
| Construction Waste Management | 1.7 | G | ||||||||||||||||
| Plan | ||||||||||||||||||
| SUBMITTAL REGISTER | CONTRACT NO. |
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR | ||
| A C T I V I T Y | |||
| N O | T R A N S M I T T A L | ||
| N O | S P E C | ||
| S E C T | DESCRIPTION ITEM SUBMITTED | P A R A |
G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W
| N R | CONTRACTOR: SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | MAILED TO CONTR/ | ||||||||||||||
| DATE RCD FRM APPR AUTH | REMARKS | |||||||||||||||||
| SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | DATE FWD TO APPR AUTH/ | ||||||||||||||||
| DATE RCD FROM CONTR | DATE FWD TO OTHER REVIEWER | DATE RCD FROM OTH REVIEWER | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | |||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |
| 01 74 19 | SD-11 Closeout Submittals | |||||||||||||||||
| Final Construction Waste | 1.9 | S | ||||||||||||||||
| Diversion Report | ||||||||||||||||||
| 01 78 00 | SD-03 Product Data | |||||||||||||||||
| Warranty Management Plan | 1.6.1 | |||||||||||||||||
| Warranty Tags | 1.6.4 | |||||||||||||||||
| Final Cleaning | 3.3 | |||||||||||||||||
| Spare Parts Data | 1.5 | |||||||||||||||||
| SD-08 Manufacturer’s Instructions | ||||||||||||||||||
| Instructions | 1.6.1 | |||||||||||||||||
| SD-11 Closeout Submittals | ||||||||||||||||||
| As-Built Drawings | 3.1 | G | ||||||||||||||||
| Record Drawings | 3.2 | G | ||||||||||||||||
| As-Built Record of Equipment | 1.6.1 | |||||||||||||||||
| and Materials | ||||||||||||||||||
| Certification of EPA Designated | 2.1 | G | ||||||||||||||||
| Items | ||||||||||||||||||
| Certification Of USDA Designated | 2.2 | G | ||||||||||||||||
| Items | ||||||||||||||||||
| Interim DD FORM 1354 | 3.4.1 | G | ||||||||||||||||
| Checklist for DD FORM 1354 | 3.4.2 | G | ||||||||||||||||
| High Performance and | 3.4.2 | G | ||||||||||||||||
| Sustainable Building (HPSB) | ||||||||||||||||||
| Checklist | ||||||||||||||||||
| 01 78 23 | SD-10 Operation and Maintenance | |||||||||||||||||
| Data | ||||||||||||||||||
| SUBMITTAL REGISTER | CONTRACT NO. |
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR | ||
| A C T I V I T Y | |||
| N O | T R A N S M I T T A L | ||
| N O | S P E C | ||
| S E C T | DESCRIPTION ITEM SUBMITTED | P A R A |
G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W
| N R | CONTRACTOR: SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | MAILED TO CONTR/ | ||||||||||||||
| DATE RCD FRM APPR AUTH | REMARKS | |||||||||||||||||
| SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | DATE FWD TO APPR AUTH/ | ||||||||||||||||
| DATE RCD FROM CONTR | DATE FWD TO OTHER REVIEWER | DATE RCD FROM OTH REVIEWER | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | |||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |
| 01 78 23 | Training Plan | 3.1.1 | G | |||||||||||||||
| Training Outline | 3.1.3 | G | ||||||||||||||||
| Training Content | 3.1.2 | G | ||||||||||||||||
| SD-11 Closeout Submittals | ||||||||||||||||||
| Training Video Recording | 3.1.4 | G | ||||||||||||||||
| Validation of Training Completion | 3.1.6 | G | ||||||||||||||||
| 01 78 24.00 20 | SD-11 Closeout Submittals | |||||||||||||||||
| eOMSI, Progress Submittal | 1.4.1 | G | ||||||||||||||||
| eOMSI, Prefinal Submittal | 1.4.2 | G | ||||||||||||||||
| eOMSI, Final Submittal | 1.4.3 | G | ||||||||||||||||
| 01 78 30.00 23 | SD-02 Shop Drawings | |||||||||||||||||
| GIS Record Drawings | 1.9 | G | ||||||||||||||||
| SD-11 Closeout Submittals | ||||||||||||||||||
| CADD Data for GIS | 1.7 | G | ||||||||||||||||
| Survey Report | 1.6.2 | G | ||||||||||||||||
| Survey Control Database | 1.6.3 | G | ||||||||||||||||
| Underground Utility Location Plan | 1.9.1 | G | ||||||||||||||||
| Non-Disclosure Letter | 1.5 | G | ||||||||||||||||
| 01 91 00.15 | SD-06 Test Reports | |||||||||||||||||
| Completed Construction | 3.6 | G | ||||||||||||||||
| Observation Checklists | ||||||||||||||||||
| Design Review Report | 3.1 | G | ||||||||||||||||
| Interim Construction Phase | 3.5 | G | ||||||||||||||||
| Commissioning Plan | ||||||||||||||||||
| Final Construction Phase | 3.5 | G | ||||||||||||||||
| Commissioning Plan | ||||||||||||||||||
| SUBMITTAL REGISTER | CONTRACT NO. |
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR | ||
| A C T I V I T Y | |||
| N O | T R A N S M I T T A L | ||
| N O | S P E C | ||
| S E C T | DESCRIPTION ITEM SUBMITTED | P A R A |
G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W
| N R | CONTRACTOR: SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | MAILED TO CONTR/ | ||||||||||||||
| DATE RCD FRM APPR AUTH | REMARKS | |||||||||||||||||
| SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | DATE FWD TO APPR AUTH/ | ||||||||||||||||
| DATE RCD FROM CONTR | DATE FWD TO OTHER REVIEWER | DATE RCD FROM OTH REVIEWER | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | |||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |
| 01 91 00.15 | Initial Commissioning Report | 3.9 | G | |||||||||||||||
| Issues Log | 1.13 | G | ||||||||||||||||
| SD-07 Certificates | ||||||||||||||||||
| Commissioning Firm | 1.11 | G | ||||||||||||||||
| SD-11 Closeout Submittals | ||||||||||||||||||
| Final Commissioning Report | 3.9 | G | ||||||||||||||||
| Updated Final Commissioning | 3.10 | G | ||||||||||||||||
| Report | ||||||||||||||||||
| 02 41 00 | SD-01 Preconstruction Submittals | |||||||||||||||||
| Demolition Plan | 1.2.2 | G | ||||||||||||||||
| Existing Conditions | 1.11 | |||||||||||||||||
| SD-07 Certificates | ||||||||||||||||||
| Notification | 1.7 | G | ||||||||||||||||
| SD-11 Closeout Submittals | ||||||||||||||||||
| Receipts | 3.3.4 | |||||||||||||||||
| 02 81 00 | SD-03 Product Data | |||||||||||||||||
| Packaging Notifications | 2.1.1 | |||||||||||||||||
| Hazardous Waste Management | 3.1 | G | ||||||||||||||||
| Plan | ||||||||||||||||||
| Onsite Hazardous Waste | 3.2 | G | ||||||||||||||||
| Management | ||||||||||||||||||
| Notices of Non-Compliance and | 3.3 | |||||||||||||||||
| Notices of Violation | ||||||||||||||||||
| SD-06 Test Reports | ||||||||||||||||||
| Recordkeeping | 3.7 | G | ||||||||||||||||
| Exception Report | 3.7 | G | ||||||||||||||||
| SUBMITTAL REGISTER | CONTRACT NO. |
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR | ||
| A C T I V I T Y | |||
| N O | T R A N S M I T T A L | ||
| N O | S P E C | ||
| S E C T | DESCRIPTION ITEM SUBMITTED | P A R A |
G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W
| N R | CONTRACTOR: SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | MAILED TO CONTR/ | ||||||||||||||
| DATE RCD FRM APPR AUTH | REMARKS | |||||||||||||||||
| SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | DATE FWD TO APPR AUTH/ | ||||||||||||||||
| DATE RCD FROM CONTR | DATE FWD TO OTHER REVIEWER | DATE RCD FROM OTH REVIEWER | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | |||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |
| 02 81 00 | Spill Response | 3.8 | ||||||||||||||||
| SD-07 Certificates | ||||||||||||||||||
| Transportation and Disposal | 1.4.1 | G | ||||||||||||||||
| Coordinator | ||||||||||||||||||
| Training | 1.4.2 | G | ||||||||||||||||
| Certification | 1.4.3 | |||||||||||||||||
| Shipping Documents and | 3.3.3 | G | ||||||||||||||||
| Packagings Certification | ||||||||||||||||||
| Security Plan | 3.3.4 | |||||||||||||||||
| Certificates of Disposal | 3.3.5 | |||||||||||||||||
| Waste Minimization | 3.6 | |||||||||||||||||
| 03 30 00 | SD-01 Preconstruction Submittals | |||||||||||||||||
| Quality Control Plan | 1.6.5 | G | ||||||||||||||||
| Quality Control Personnel | 1.6.6 | G | ||||||||||||||||
| Certifications | ||||||||||||||||||
| Quality Control Organizational | 1.6.6 | |||||||||||||||||
| Chart | ||||||||||||||||||
| Laboratory Accreditation | 1.6.8 | G | ||||||||||||||||
| Maturity Method Data | 3.3.10 | |||||||||||||||||
| SD-02 Shop Drawings | ||||||||||||||||||
| Reinforcing Steel | 1.6.2.1 | G | ||||||||||||||||
| SD-03 Product Data | ||||||||||||||||||
| Joint Sealants | 2.4.5 | |||||||||||||||||
| Joint Filler | 2.4.4 | |||||||||||||||||
| Formwork Materials | 2.1 | |||||||||||||||||
| Recycled Aggregate Materials | 2.3.3.3 | |||||||||||||||||
| SUBMITTAL REGISTER | CONTRACT NO. |
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR | ||
| A C T I V I T Y | |||
| N O | T R A N S M I T T A L | ||
| N O | S P E C | ||
| S E C T | DESCRIPTION ITEM SUBMITTED | P A R A |
G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W
| N R | CONTRACTOR: SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | MAILED TO CONTR/ | ||||||||||||||
| DATE RCD FRM APPR AUTH | REMARKS | |||||||||||||||||
| SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | DATE FWD TO APPR AUTH/ | ||||||||||||||||
| DATE RCD FROM CONTR | DATE FWD TO OTHER REVIEWER | DATE RCD FROM OTH REVIEWER | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | |||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |
| 03 30 00 | Cementitious Materials | 2.3.1 | ||||||||||||||||
| Vapor Retarder | 2.4.6 | |||||||||||||||||
| Concrete Curing Materials | 2.4.1 | |||||||||||||||||
| Reinforcement | 2.6 | |||||||||||||||||
| Liquid Chemical Floor Hardeners | 2.4.3.1 | |||||||||||||||||
| and Sealers | ||||||||||||||||||
| Admixtures | 2.3.4 | |||||||||||||||||
| Biodegradable Form Release | 2.2.2 | |||||||||||||||||
| Agent | ||||||||||||||||||
| Nonshrink Grout | 2.4.2 | |||||||||||||||||
| SD-05 Design Data | ||||||||||||||||||
| Concrete Mix Design | 1.6.1.1 | G | ||||||||||||||||
| SD-06 Test Reports | ||||||||||||||||||
| Concrete Mix Design | 1.6.1.1 | G | ||||||||||||||||
| Fly Ash | 1.6.3.1 | |||||||||||||||||
| Pozzolan | 1.6.3.1 | |||||||||||||||||
| Slag Cement | 1.6.3.2 | |||||||||||||||||
| Aggregates | 1.6.3.3 | |||||||||||||||||
| Compressive Strength Tests | 3.12.3.3 | G | ||||||||||||||||
| Air Content | 3.12.3.4 | |||||||||||||||||
| Slump Tests | 3.12.3.1 | |||||||||||||||||
| Water | 2.3.2 | |||||||||||||||||
| SD-07 Certificates | ||||||||||||||||||
| Reinforcing Bars | 2.6.1 | |||||||||||||||||
| Field Testing Technician and | 1.6.6.2 | |||||||||||||||||
| Testing Agency | ||||||||||||||||||
| SUBMITTAL REGISTER | CONTRACT NO. |
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR | ||
| A C T I V I T Y | |||
| N O | T R A N S M I T T A L | ||
| N O | S P E C | ||
| S E C T | DESCRIPTION ITEM SUBMITTED | P A R A |
G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W
| N R | CONTRACTOR: SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | MAILED TO CONTR/ | ||||||||||||||
| DATE RCD FRM APPR AUTH | REMARKS | |||||||||||||||||
| SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | DATE FWD TO APPR AUTH/ | ||||||||||||||||
| DATE RCD FROM CONTR | DATE FWD TO OTHER REVIEWER | DATE RCD FROM OTH REVIEWER | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | |||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |
| 03 30 00 | SD-08 Manufacturer’s Instructions | |||||||||||||||||
| Liquid Chemical Floor Hardeners | 2.4.3.1 | |||||||||||||||||
| and Sealers | ||||||||||||||||||
| Joint Sealants | 2.4.5 | |||||||||||||||||
| Curing Compound | 2.4.1 | |||||||||||||||||
| 05 52 00 | SD-02 Shop Drawings | |||||||||||||||||
| Fabrication Drawings | 1.2.1 | G | ||||||||||||||||
| Iron and Steel Hardware | 3.2 | G | ||||||||||||||||
| Steel Shapes, Plates, Bars and | 3.2 | G | ||||||||||||||||
| Strips | ||||||||||||||||||
| Steel Railings And Handrails | 2.2.1 | |||||||||||||||||
| SD-03 Product Data | ||||||||||||||||||
| Structural-Steel Plates, Shapes, | 1.2.1 | G | ||||||||||||||||
| and Bars | ||||||||||||||||||
| Concrete Inserts | 2.1 | G | ||||||||||||||||
| Protective Coating | 2.1.2 | G | ||||||||||||||||
| Anchorage and Fastening | 1.2.1 | G | ||||||||||||||||
| Systems | ||||||||||||||||||
| SD-07 Certificates | ||||||||||||||||||
| Welding Procedures | 1.4.1 | G | ||||||||||||||||
| Welder Qualification | 1.4.2 | G | ||||||||||||||||
| SD-08 Manufacturer’s Instructions | ||||||||||||||||||
| Installation Instructions | 3.2 | |||||||||||||||||
| 09 90 00 | SD-02 Shop Drawings | |||||||||||||||||
| Piping Identification | 3.9 | |||||||||||||||||
| SD-03 Product Data | ||||||||||||||||||
| SUBMITTAL REGISTER | CONTRACT NO. |
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR | ||
| A C T I V I T Y | |||
| N O | T R A N S M I T T A L | ||
| N O | S P E C | ||
| S E C T | DESCRIPTION ITEM SUBMITTED | P A R A |
G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W
| N R | CONTRACTOR: SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | MAILED TO CONTR/ | ||||||||||||||
| DATE RCD FRM APPR AUTH | REMARKS | |||||||||||||||||
| SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | DATE FWD TO APPR AUTH/ | ||||||||||||||||
| DATE RCD FROM CONTR | DATE FWD TO OTHER REVIEWER | DATE RCD FROM OTH REVIEWER | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | |||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |
| 09 90 00 | Coating | 2.1 | G | |||||||||||||||
| Product Data Sheets | 2.1 | |||||||||||||||||
| SD-04 Samples | ||||||||||||||||||
| Color | 2.2 | G | ||||||||||||||||
| Textured Wall Coating System | 1.6.4 | G | ||||||||||||||||
| SD-07 Certificates | ||||||||||||||||||
| Qualification Testing | 1.6.3.2 | G | ||||||||||||||||
| SD-08 Manufacturer’s Instructions | ||||||||||||||||||
| Mixing | 2.1 | |||||||||||||||||
| Manufacturer's Safety Data | 1.8.1 | |||||||||||||||||
| Sheets | ||||||||||||||||||
| SD-10 Operation and Maintenance | ||||||||||||||||||
| Data | ||||||||||||||||||
| Coatings | 2.1 | G | ||||||||||||||||
| 11 11 37 | SD-02 Shop Drawings | |||||||||||||||||
| Cords | 2.2.3 | G | ||||||||||||||||
| Level 2 Pedestal Mounted EVSE | 2.2.2.1 | G | ||||||||||||||||
| SD-03 Product Data | ||||||||||||||||||
| Cords | 2.2.3 | G | ||||||||||||||||
| Level 2 Pedestal Mounted EVSE | 2.2.2.1 | G | ||||||||||||||||
| SD-07 Certificates | ||||||||||||||||||
| Qualifications | 1.6.2.1 | G | ||||||||||||||||
| Certified Installers | 1.2.2 | G | ||||||||||||||||
| SD-08 Manufacturer’s Instructions | ||||||||||||||||||
| Cords | 2.2.3 | G | ||||||||||||||||
| Level 2 Pedestal Mounted EVSE | 2.2.2.1 | G | ||||||||||||||||
| SUBMITTAL REGISTER | CONTRACT NO. |
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR | ||
| A C T I V I T Y | |||
| N O | T R A N S M I T T A L | ||
| N O | S P E C | ||
| S E C T | DESCRIPTION ITEM SUBMITTED | P A R A |
G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W
| N R | CONTRACTOR: SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | MAILED TO CONTR/ | ||||||||||||||
| DATE RCD FRM APPR AUTH | REMARKS | |||||||||||||||||
| SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | DATE FWD TO APPR AUTH/ | ||||||||||||||||
| DATE RCD FROM CONTR | DATE FWD TO OTHER REVIEWER | DATE RCD FROM OTH REVIEWER | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | |||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |
| 11 11 37 | SD-09 Manufacturer’s Field | |||||||||||||||||
| Reports | ||||||||||||||||||
| Testing of Electric Vehicle Supply | 3.7.1 | G | ||||||||||||||||
| Equipment | ||||||||||||||||||
| SD-10 Operation and Maintenance | ||||||||||||||||||
| Data | ||||||||||||||||||
| Electric Vehicle Supply | 2.2 | |||||||||||||||||
| Equipment | ||||||||||||||||||
| SD-11 Closeout Submittals | ||||||||||||||||||
| Warranty | 1.7 | G | ||||||||||||||||
| 12 93 00 | SD-02 Shop Drawings | |||||||||||||||||
| Bollards | 2.2 | G | ||||||||||||||||
| SD-03 Product Data | ||||||||||||||||||
| Bollards | 2.2 | |||||||||||||||||
| SD-06 Test Reports | ||||||||||||||||||
| Testing | 3.3 | |||||||||||||||||
| SD-07 Certificates | ||||||||||||||||||
| recycled content for steel | 2.1.1 | |||||||||||||||||
| components | ||||||||||||||||||
| recycled content for aluminum | 2.1.5 | |||||||||||||||||
| components | ||||||||||||||||||
| Primer Certificate | 1.3.1 | |||||||||||||||||
| 25 05 11 | SD-01 Preconstruction Submittals | |||||||||||||||||
| Wireless and Wired Broadcast | 3.2.1.3 | G | ||||||||||||||||
| Communication Request |
SUBMITTAL REGISTER CONTRACT NO.
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR | ||
| A C T I V I T Y | |||
| N O | T R A N S M I T T A L | ||
| N O | S P E C | ||
| S E C T | DESCRIPTION ITEM SUBMITTED | P A R A |
G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W
| N R | CONTRACTOR: SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | MAILED TO CONTR/ | ||||||||||||||
| DATE RCD FRM APPR AUTH | REMARKS | |||||||||||||||||
| SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | DATE FWD TO APPR AUTH/ | ||||||||||||||||
| DATE RCD FROM CONTR | DATE FWD TO OTHER REVIEWER | DATE RCD FROM OTH REVIEWER | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | |||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |
| 25 05 11 | Device Account Lock Exception | 3.3.2 | G | |||||||||||||||
| Request | ||||||||||||||||||
| Multiple Ethernet Connection | 3.2.3.2 | G | ||||||||||||||||
| Device Request | ||||||||||||||||||
| Contractor Computer | 1.8.1.6 | G | ||||||||||||||||
| Cybersecurity Compliance | ||||||||||||||||||
| Statements | ||||||||||||||||||
| Contractor Temporary Network | 1.8.6 | G | ||||||||||||||||
| Cybersecurity Compliance | ||||||||||||||||||
| Statements | ||||||||||||||||||
| Cybersecurity Interconnection | 1.6.2 | G | ||||||||||||||||
| Schedule | ||||||||||||||||||
| Proposed STIG and SRG | 1.6.1 | G | ||||||||||||||||
| Applicability Report | ||||||||||||||||||
| SD-02 Shop Drawings | ||||||||||||||||||
| Network Communication Report | 1.6.3 | G | ||||||||||||||||
| Cybersecurity Riser Diagram | 1.6.6 | G | ||||||||||||||||
| SD-03 Product Data | ||||||||||||||||||
| Control System Cybersecurity | 1.6.8 | G | ||||||||||||||||
| Documentation | ||||||||||||||||||
| SD-06 Test Reports | ||||||||||||||||||
| Control System Cybersecurity | 3.13.1 | G | ||||||||||||||||
| Testing Procedures | ||||||||||||||||||
| Control System Cybersecurity | 3.13.3 | G | ||||||||||||||||
| Testing Report | ||||||||||||||||||
| SD-07 Certificates | ||||||||||||||||||
| SUBMITTAL REGISTER | CONTRACT NO. |
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR | ||
| A C T I V I T Y | |||
| N O | T R A N S M I T T A L | ||
| N O | S P E C | ||
| S E C T | DESCRIPTION ITEM SUBMITTED | P A R A |
G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W
| N R | CONTRACTOR: SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | MAILED TO CONTR/ | ||||||||||||||
| DATE RCD FRM APPR AUTH | REMARKS | |||||||||||||||||
| SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | DATE FWD TO APPR AUTH/ | ||||||||||||||||
| DATE RCD FROM CONTR | DATE FWD TO OTHER REVIEWER | DATE RCD FROM OTH REVIEWER | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | |||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |
| 25 05 11 | Software Licenses | 1.7 | G | |||||||||||||||
| SD-11 Closeout Submittals | ||||||||||||||||||
| Password Change Summary | 3.4.5.5 | G | ||||||||||||||||
| Report | ||||||||||||||||||
| Enclosure Keys | 3.3.5 | G | ||||||||||||||||
| Software and Configuration | 1.6.5 | G | ||||||||||||||||
| Backups | ||||||||||||||||||
| Device Audit Record Upload | 3.5.3.1 | G | ||||||||||||||||
| Software | ||||||||||||||||||
| System Maintenance Tool | 3.9 | G | ||||||||||||||||
| Software | ||||||||||||||||||
| Control System Scanning Tools | 3.10.2 | G | ||||||||||||||||
| STIG, SRG and Vendor Guide | 1.6.7 | G | ||||||||||||||||
| Compliance Result Report | ||||||||||||||||||
| Control System Inventory Report | 1.6.4 | G | ||||||||||||||||
| 26 08 00 | SD-06 Test Reports | |||||||||||||||||
| Acceptance Tests and | 3.1 | G | ||||||||||||||||
| Inspections | ||||||||||||||||||
| SD-07 Certificates | ||||||||||||||||||
| Qualifications | 1.4.1 | G | ||||||||||||||||
| Acceptance Test and Inspections | 1.4.3 | G | ||||||||||||||||
| Procedure | ||||||||||||||||||
| 26 12 19.10 | SD-02 Shop Drawings | |||||||||||||||||
| Pad-mounted Transformer | 1.5.1 | G | ||||||||||||||||
| Drawings | ||||||||||||||||||
| SD-03 Product Data | ||||||||||||||||||
| SUBMITTAL REGISTER | CONTRACT NO. |
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR | ||
| A C T I V I T Y | |||
| N O | T R A N S M I T T A L | ||
| N O | S P E C | ||
| S E C T | DESCRIPTION ITEM SUBMITTED | P A R A |
G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W
| N R | CONTRACTOR: SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | MAILED TO CONTR/ | ||||||||||||||
| DATE RCD FRM APPR AUTH | REMARKS | |||||||||||||||||
| SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | DATE FWD TO APPR AUTH/ | ||||||||||||||||
| DATE RCD FROM CONTR | DATE FWD TO OTHER REVIEWER | DATE RCD FROM OTH REVIEWER | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | |||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |
| 26 12 19.10 | Pad-mounted Transformers | 2.2 | G | |||||||||||||||
| SD-06 Test Reports | ||||||||||||||||||
| Acceptance Checks and Tests | 3.6.1 | G | ||||||||||||||||
| SD-07 Certificates | ||||||||||||||||||
| Transformer Efficiencies | 2.2.2.1 | G | ||||||||||||||||
| SD-09 Manufacturer’s Field | ||||||||||||||||||
| Reports | ||||||||||||||||||
| Transformer Test Schedule | 2.7.1 | G | ||||||||||||||||
| Design Tests | 2.7.2 | G | ||||||||||||||||
| Routine and Other Tests | 2.7.3 | G | ||||||||||||||||
| SD-10 Operation and Maintenance | ||||||||||||||||||
| Data | ||||||||||||||||||
| Transformer(s) | 1.6.1 | G | ||||||||||||||||
| 26 20 00 | SD-02 Shop Drawings | |||||||||||||||||
| Panelboards | 2.9 | G | ||||||||||||||||
| Marking Strips | 3.1.6.1 | G | ||||||||||||||||
| SD-03 Product Data | ||||||||||||||||||
| Circuit Breakers | 2.9.3 | G | ||||||||||||||||
| Switches | 2.8 | G | ||||||||||||||||
| Enclosed Circuit Breakers | 2.10 | G | ||||||||||||||||
| SD-06 Test Reports | ||||||||||||||||||
| 600-volt Wiring Test | 3.5.2 | G | ||||||||||||||||
| Grounding System Test | 3.5.4 | G | ||||||||||||||||
| Transformer Tests | 3.5.3 | G | ||||||||||||||||
| SD-09 Manufacturer’s Field | ||||||||||||||||||
| Reports | ||||||||||||||||||
| SUBMITTAL REGISTER | CONTRACT NO. |
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR | ||
| A C T I V I T Y | |||
| N O | T R A N S M I T T A L | ||
| N O | S P E C | ||
| S E C T | DESCRIPTION ITEM SUBMITTED | P A R A |
G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W
| N R | CONTRACTOR: SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | MAILED TO CONTR/ | ||||||||||||||
| DATE RCD FRM APPR AUTH | REMARKS | |||||||||||||||||
| SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | DATE FWD TO APPR AUTH/ | ||||||||||||||||
| DATE RCD FROM CONTR | DATE FWD TO OTHER REVIEWER | DATE RCD FROM OTH REVIEWER | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | |||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |
| 26 20 00 | Transformer Factory Tests | 2.17.1 | ||||||||||||||||
| SD-10 Operation and Maintenance | ||||||||||||||||||
| Data | ||||||||||||||||||
| Electrical Systems | 1.5.1 | G | ||||||||||||||||
| 26 27 14.00 20 | SD-02 Shop Drawings | |||||||||||||||||
| Installation Drawings | 1.3.1 | G | ||||||||||||||||
| SD-03 Product Data | ||||||||||||||||||
| Current Transformer | 2.1.3 | G | ||||||||||||||||
| Potential Transformer | 2.1.2 | G | ||||||||||||||||
| Communications | 2.2 | G | ||||||||||||||||
| Configuration Software | 3.1.3 | G | ||||||||||||||||
| SD-06 Test Reports | ||||||||||||||||||
| Acceptance Checks and Tests | 3.2.1 | G | ||||||||||||||||
| System Functional Verification | 3.2.2 | G | ||||||||||||||||
| Building Meter Installation Sheet, | 3.2.1 | G | ||||||||||||||||
| per Building | ||||||||||||||||||
| Completed Meter Installation | 3.2.1 | G | ||||||||||||||||
| Schedule | ||||||||||||||||||
| Completed Meter Data Schedule | 3.2.1 | G | ||||||||||||||||
| Meter Configuration Template | 2.1.1 | G | ||||||||||||||||
| Meter Configuration Report | 3.2.1 | G | ||||||||||||||||
| SD-10 Operation and Maintenance | ||||||||||||||||||
| Data | ||||||||||||||||||
| Electricity Meters and | 1.4.1 | G | ||||||||||||||||
| Accessories | ||||||||||||||||||
| SD-11 Closeout Submittals | ||||||||||||||||||
| SUBMITTAL REGISTER | CONTRACT NO. |
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR | ||
| A C T I V I T Y | |||
| N O | T R A N S M I T T A L | ||
| N O | S P E C | ||
| S E C T | DESCRIPTION ITEM SUBMITTED | P A R A |
G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W
| N R | CONTRACTOR: SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | MAILED TO CONTR/ | ||||||||||||||
| DATE RCD FRM APPR AUTH | REMARKS | |||||||||||||||||
| SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | DATE FWD TO APPR AUTH/ | ||||||||||||||||
| DATE RCD FROM CONTR | DATE FWD TO OTHER REVIEWER | DATE RCD FROM OTH REVIEWER | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | |||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |
| 26 27 14.00 20 | System Functional Verification | 3.2.2 | G | |||||||||||||||
| 26 56 00 | SD-02 Shop Drawings | |||||||||||||||||
| Luminaire Drawings | 1.5.1.1 | G | ||||||||||||||||
| Pole Drawings | 1.5.1.2 | G | ||||||||||||||||
| Control System One-Line | 1.8.2 | G | ||||||||||||||||
| Diagram | ||||||||||||||||||
| Sequence of Operation for | 2.5.1 | G | ||||||||||||||||
| Exterior Lighting Control System | ||||||||||||||||||
| SD-03 Product Data | ||||||||||||||||||
| Luminaires | 2.2 | G | ||||||||||||||||
| Light Sources | 2.3 | G | ||||||||||||||||
| LED Drivers | 2.4 | G | ||||||||||||||||
| Luminaire Warranty | 1.7.1 | G | ||||||||||||||||
| Lighting Controls Warranty | 1.7.2 | G | ||||||||||||||||
| Pole Warranty | 1.7.3 | G | ||||||||||||||||
| Dimming Panel | 2.5.1.2 | G | ||||||||||||||||
| Photosensors | 2.5.2.2 | G | ||||||||||||||||
| Time Clock | 2.5.2.1 | G | ||||||||||||||||
| Lighting Contactor | 2.5.2.3 | G | ||||||||||||||||
| Poles | 2.6 | G | ||||||||||||||||
| Brackets | 2.6.2 | |||||||||||||||||
| SD-05 Design Data | ||||||||||||||||||
| Luminaire Design Data | 1.5.2 | G | ||||||||||||||||
| SD-06 Test Reports | ||||||||||||||||||
| ANSI/IES LM-79 Test Report | 1.5.3 | G | ||||||||||||||||
| ANSI/IES LM-80 Test Report | 1.5.4 | G | ||||||||||||||||
| SUBMITTAL REGISTER | CONTRACT NO. |
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR | ||
| A C T I V I T Y | |||
| N O | T R A N S M I T T A L | ||
| N O | S P E C | ||
| S E C T | DESCRIPTION ITEM SUBMITTED | P A R A |
G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W
| N R | CONTRACTOR: SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | MAILED TO CONTR/ | ||||||||||||||
| DATE RCD FRM APPR AUTH | REMARKS | |||||||||||||||||
| SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | DATE FWD TO APPR AUTH/ | ||||||||||||||||
| DATE RCD FROM CONTR | DATE FWD TO OTHER REVIEWER | DATE RCD FROM OTH REVIEWER | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | |||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |
| 26 56 00 | ANSI/IES TM-21 Test Report | 1.5.5 | G | |||||||||||||||
| SD-08 Manufacturer’s Instructions | ||||||||||||||||||
| Poles | 2.6 | |||||||||||||||||
| SD-10 Operation and Maintenance | ||||||||||||||||||
| Data | ||||||||||||||||||
| Lighting System | 1.8.1 | G | ||||||||||||||||
| Exterior Lighting Control System | 1.8.2 | G | ||||||||||||||||
| Maintenance Staff Training Plan | 3.3.1.1 | G | ||||||||||||||||
| End-User Training Plan | 3.3.1.2 | G | ||||||||||||||||
| 31 11 00 | SD-01 Preconstruction Submittals | |||||||||||||||||
| Herbicide Application Plan | 3.1.1 | |||||||||||||||||
| SD-03 Product Data | ||||||||||||||||||
| Tree Wound Paint | 2.1.1 | |||||||||||||||||
| Herbicides | 1.3.2 | G | ||||||||||||||||
| SD-07 Certificates | ||||||||||||||||||
| Qualifications | 1.3.2 | G | ||||||||||||||||
| SD-11 Closeout Submittals | ||||||||||||||||||
| Pest Management Report | 3.5.1 | |||||||||||||||||
| 31 23 00.00 20 | SD-01 Preconstruction Submittals | |||||||||||||||||
| Shoring and Sheeting Plan | 1.7.1 | |||||||||||||||||
| Dewatering work plan | 1.7.2 | |||||||||||||||||
| SD-06 Test Reports | ||||||||||||||||||
| Borrow Site Testing | 1.6 | G | ||||||||||||||||
| Fill and backfill | 3.12.2.1 | |||||||||||||||||
| Select material | 3.12.2.2 | |||||||||||||||||
| Porous fill | 3.12.2.3 | |||||||||||||||||
| SUBMITTAL REGISTER | CONTRACT NO. |
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR | ||
| A C T I V I T Y | |||
| N O | T R A N S M I T T A L | ||
| N O | S P E C | ||
| S E C T | DESCRIPTION ITEM SUBMITTED | P A R A |
G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W
| N R | CONTRACTOR: SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | MAILED TO CONTR/ | ||||||||||||||
| DATE RCD FRM APPR AUTH | REMARKS | |||||||||||||||||
| SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | DATE FWD TO APPR AUTH/ | ||||||||||||||||
| DATE RCD FROM CONTR | DATE FWD TO OTHER REVIEWER | DATE RCD FROM OTH REVIEWER | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | |||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |
| 31 23 00.00 20 | Density tests | 3.12.2.4 | ||||||||||||||||
| 32 01 19.61 | SD-03 Product Data | |||||||||||||||||
| Sealants | 2.1 | |||||||||||||||||
| Manufacturer's | 3.5.2 | |||||||||||||||||
| Recommendations | ||||||||||||||||||
| SD-04 Samples | ||||||||||||||||||
| Sealants | 2.1 | |||||||||||||||||
| Blocking Media/Backup Materials | 2.3.1 | |||||||||||||||||
| Backer Rod | 3.3.4.1 | |||||||||||||||||
| Bond Breaking Tapes | 2.3.2 | |||||||||||||||||
| SD-07 Certificates | ||||||||||||||||||
| Equipment List | 3.1 | |||||||||||||||||
| SD-08 Manufacturer’s Instructions | ||||||||||||||||||
| Sealants | 2.1 | |||||||||||||||||
| 32 05 33 | SD-03 Product Data | |||||||||||||||||
| Fertilizer | 2.1 | G | ||||||||||||||||
| SD-07 Certificates | ||||||||||||||||||
| Maintenance Inspection Report | 3.5.1 | |||||||||||||||||
| Plant Quantities | 3.5.2 | G | ||||||||||||||||
| SD-11 Closeout Submittals | ||||||||||||||||||
| Tree Staking and Guying | 3.5.3 | |||||||||||||||||
| Removal | ||||||||||||||||||
| 32 11 20 | SD-03 Product Data | |||||||||||||||||
| Plant, Equipment, and Tools | 2.3 | G | ||||||||||||||||
| SD-06 Test Reports | ||||||||||||||||||
| Initial Tests | 2.2.1 | G | ||||||||||||||||
| SUBMITTAL REGISTER | CONTRACT NO. |
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR | ||
| A C T I V I T Y | |||
| N O | T R A N S M I T T A L | ||
| N O | S P E C | ||
| S E C T | DESCRIPTION ITEM SUBMITTED | P A R A |
G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W
| N R | CONTRACTOR: SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | MAILED TO CONTR/ | ||||||||||||||
| DATE RCD FRM APPR AUTH | REMARKS | |||||||||||||||||
| SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | DATE FWD TO APPR AUTH/ | ||||||||||||||||
| DATE RCD FROM CONTR | DATE FWD TO OTHER REVIEWER | DATE RCD FROM OTH REVIEWER | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | |||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |
| 32 11 20 | In-Place Tests | 3.12.1 | G | |||||||||||||||
| Test Section Report | 1.6.2 | G | ||||||||||||||||
| 32 11 23 | SD-03 Product Data | |||||||||||||||||
| Plant, Equipment, and Tools | 2.4 | G | ||||||||||||||||
| SD-06 Test Reports | ||||||||||||||||||
| Initial Tests | 2.3.1 | G | ||||||||||||||||
| In-Place Tests | 3.13.1 | G | ||||||||||||||||
| Test Section Report | 1.6.2 | G | ||||||||||||||||
| 32 11 23.23 | SD-03 Product Data | |||||||||||||||||
| Plants, Equipment, and Tools | 2.2.1 | G | ||||||||||||||||
| SD-06 Test Reports | ||||||||||||||||||
| Initial Tests | 1.3.3.1 | G | ||||||||||||||||
| Test Section Construction Report | 1.5.2.7 | G | ||||||||||||||||
| SD-07 Certificates | ||||||||||||||||||
| Geotextile | 2.1.3.2 | |||||||||||||||||
| Geotextile | 2.1.3.2 | |||||||||||||||||
| 32 11 26 | SD-03 Product Data | |||||||||||||||||
| Sources of Aggregates | 1.4.4 | |||||||||||||||||
| Job Mix Formula | 2.4.2 | G | ||||||||||||||||
| SD-06 Test Reports | ||||||||||||||||||
| Sources of Aggregates | 1.4.4 | |||||||||||||||||
| Bituminous Materials | 1.4.6 | |||||||||||||||||
| Bituminous Materials | 2.2 | |||||||||||||||||
| Test Section | 1.6.2 | G | ||||||||||||||||
| Service Record | 1.4.4 | G |
SUBMITTAL REGISTER CONTRACT NO.
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR | ||
| A C T I V I T Y | |||
| N O | T R A N S M I T T A L | ||
| N O | S P E C | ||
| S E C T | DESCRIPTION ITEM SUBMITTED | P A R A |
G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W
| N R | CONTRACTOR: SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | MAILED TO CONTR/ | ||||||||||||||
| DATE RCD FRM APPR AUTH | REMARKS | |||||||||||||||||
| SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | DATE FWD TO APPR AUTH/ | ||||||||||||||||
| DATE RCD FROM CONTR | DATE FWD TO OTHER REVIEWER | DATE RCD FROM OTH REVIEWER | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | |||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |
| 32 11 26 | SD-09 Manufacturer’s Field | |||||||||||||||||
| Reports | ||||||||||||||||||
| Batch Tickets | 1.4.3 | |||||||||||||||||
| 32 12 13 | SD-03 Product Data | |||||||||||||||||
| Local/Regional Materials | 2.2.4 | |||||||||||||||||
| Local/Regional Materials | 2.2.4 | |||||||||||||||||
| SD-06 Test Reports | ||||||||||||||||||
| Sampling and Testing | 3.7 | |||||||||||||||||
| 32 12 16.16 | SD-02 Shop Drawings | |||||||||||||||||
| Placement Plan | 2.1 | G | ||||||||||||||||
| SD-03 Product Data | ||||||||||||||||||
| Diamond Grinding Plan | 2.1.6 | G | ||||||||||||||||
| Mix Design | 2.4 | G | ||||||||||||||||
| Contractor Quality Control | 3.1 | G | ||||||||||||||||
| SD-04 Samples | ||||||||||||||||||
| Aggregates | 2.2 | |||||||||||||||||
| Asphalt Cement Binder | 2.3 | |||||||||||||||||
| SD-06 Test Reports | ||||||||||||||||||
| Aggregates | 2.2 | G | ||||||||||||||||
| QC Monitoring | 3.1.3.9 | |||||||||||||||||
| SD-07 Certificates | ||||||||||||||||||
| Asphalt Cement Binder | 2.3 | G | ||||||||||||||||
| Laboratory Accreditation and | 1.3.11 | |||||||||||||||||
| Validation | ||||||||||||||||||
| 32 13 13.06 | SD-03 Product Data | |||||||||||||||||
| Cementitious Materials | 2.1.1 | |||||||||||||||||
| SUBMITTAL REGISTER | CONTRACT NO. |
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR | ||
| A C T I V I T Y | |||
| N O | T R A N S M I T T A L | ||
| N O | S P E C | ||
| S E C T | DESCRIPTION ITEM SUBMITTED | P A R A |
G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W
| N R | CONTRACTOR: SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | MAILED TO CONTR/ | ||||||||||||||
| DATE RCD FRM APPR AUTH | REMARKS | |||||||||||||||||
| SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | DATE FWD TO APPR AUTH/ | ||||||||||||||||
| DATE RCD FROM CONTR | DATE FWD TO OTHER REVIEWER | DATE RCD FROM OTH REVIEWER | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | |||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |
| 32 13 13.06 | Curing Materials | 2.1.6 | ||||||||||||||||
| Reinforcement | 2.1.5.3 | |||||||||||||||||
| Epoxy Resin | 2.1.9 | |||||||||||||||||
| Epoxy Resin | 2.1.9 | |||||||||||||||||
| Dowel Bars | 2.1.5.1 | |||||||||||||||||
| Expansion Joint Filler | 2.1.10.1 | |||||||||||||||||
| SD-04 Samples | ||||||||||||||||||
| Test Section | 1.5.2 | G | ||||||||||||||||
| SD-05 Design Data | ||||||||||||||||||
| Mix Design Report | 2.2.2 | G | ||||||||||||||||
| SD-06 Test Reports | ||||||||||||||||||
| Concrete Slump Tests | 3.7.2 | |||||||||||||||||
| Concrete Uniformity | 2.3.1 | |||||||||||||||||
| Flexural Strength | 3.7.3 | |||||||||||||||||
| Air Content | 3.7.4 | |||||||||||||||||
| SD-07 Certificates | ||||||||||||||||||
| Batch Tickets | 1.3.3 | |||||||||||||||||
| NRMCA Certificate Of | 1.3.1 | |||||||||||||||||
| Conformance | ||||||||||||||||||
| SD-08 Manufacturer’s Instructions | ||||||||||||||||||
| Diamond Grinding Plan | 3.7.5.4 | |||||||||||||||||
| 32 16 19 | SD-03 Product Data | |||||||||||||||||
| Concrete | 2.1 | |||||||||||||||||
| Biodegradable Form Release | 2.6.5 | |||||||||||||||||
| Agent |
SUBMITTAL REGISTER CONTRACT NO.
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR | ||
| A C T I V I T Y | |||
| N O | T R A N S M I T T A L | ||
| N O | S P E C | ||
| S E C T | DESCRIPTION ITEM SUBMITTED | P A R A |
G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W
| N R | CONTRACTOR: SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | MAILED TO CONTR/ | ||||||||||||||
| DATE RCD FRM APPR AUTH | REMARKS | |||||||||||||||||
| SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | DATE FWD TO APPR AUTH/ | ||||||||||||||||
| DATE RCD FROM CONTR | DATE FWD TO OTHER REVIEWER | DATE RCD FROM OTH REVIEWER | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | |||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |
| 32 16 19 | Biodegradable Form Release | 3.2 | ||||||||||||||||
| Agent | ||||||||||||||||||
| SD-06 Test Reports | ||||||||||||||||||
| Field Quality Control | 3.8 | |||||||||||||||||
| 32 17 23 | SD-03 Product Data | |||||||||||||||||
| Surface Preparation Equipment | 2.1.1.1 | G | ||||||||||||||||
| List | ||||||||||||||||||
| Application Equipment List | 2.1.2 | G | ||||||||||||||||
| Exterior Surface Preparation | 3.2 | |||||||||||||||||
| Safety Data Sheets | 1.3.1 | G | ||||||||||||||||
| Reflective media for roads | 2.2.9.1 | G | ||||||||||||||||
| Waterborne Paint | 2.2.1 | G | ||||||||||||||||
| Solventborne Paint | 2.2.2 | G | ||||||||||||||||
| Thermoplastic compound | 2.2.5 | G | ||||||||||||||||
| Thermoplastic compound | 3.3.2 | G | ||||||||||||||||
| Raised Pavement Markers | 2.2.8 | G | ||||||||||||||||
| Primers and Adhesives | ||||||||||||||||||
| SD-06 Test Reports | ||||||||||||||||||
| Reflective Media for Roads | 2.2.9.1 | G | ||||||||||||||||
| Waterborne Paint | 2.2.1 | G | ||||||||||||||||
| Solventborne Paint | 2.2.2 | G | ||||||||||||||||
| High Build Acrylic Coating | 2.2.6 | G | ||||||||||||||||
| (HBAC) | ||||||||||||||||||
| Thermoplastic Compound | 2.2.5 | G | ||||||||||||||||
| Thermoplastic Compound | 3.3.2 | G |
SUBMITTAL REGISTER CONTRACT NO.
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR | ||
| A C T I V I T Y | |||
| N O | T R A N S M I T T A L | ||
| N O | S P E C | ||
| S E C T | DESCRIPTION ITEM SUBMITTED | P A R A |
G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W
| N R | CONTRACTOR: SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | MAILED TO CONTR/ | ||||||||||||||
| DATE RCD FRM APPR AUTH | REMARKS | |||||||||||||||||
| SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | DATE FWD TO APPR AUTH/ | ||||||||||||||||
| DATE RCD FROM CONTR | DATE FWD TO OTHER REVIEWER | DATE RCD FROM OTH REVIEWER | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | |||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |
| 32 17 23 | Raised Pavement Markers | 2.2.8 | G | |||||||||||||||
| Primers and Adhesives | ||||||||||||||||||
| Test Reports | 3.4.1 | |||||||||||||||||
| SD-07 Certificates | ||||||||||||||||||
| Qualifications | 1.3.2 | G | ||||||||||||||||
| Reflective Media for Roads | 2.2.9.1 | |||||||||||||||||
| Waterborne Paint | 2.2.1 | |||||||||||||||||
| Solventborne Paint | 2.2.2 | |||||||||||||||||
| Volatile Organic Compound | 1.3.1 | G | ||||||||||||||||
| Volatile Organic Compound | 2.2.6 | G | ||||||||||||||||
| Thermoplastic Compound | 2.2.5 | |||||||||||||||||
| Thermoplastic Compound | 3.3.2 | |||||||||||||||||
| SD-08 Manufacturer’s Instructions | ||||||||||||||||||
| Waterborne Paint | 2.2.1 | G | ||||||||||||||||
| Solventborne Paint | 2.2.2 | G | ||||||||||||||||
| Thermoplastic Compound | 2.2.5 | G | ||||||||||||||||
| Thermoplastic Compound | 3.3.2 | G | ||||||||||||||||
| 32 92 23 | SD-03 Product Data | |||||||||||||||||
| Fertilizer | 2.4 | |||||||||||||||||
| SD-06 Test Reports | ||||||||||||||||||
| Topsoil composition tests | 2.2.3 | |||||||||||||||||
| SD-07 Certificates | ||||||||||||||||||
| sods | 2.1 | |||||||||||||||||
| 32 93 00 | SD-01 Preconstruction Submittals | |||||||||||||||||
| State Landscape Contractor's | 1.4.3 | |||||||||||||||||
| License | ||||||||||||||||||
| SUBMITTAL REGISTER | CONTRACT NO. |
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR | ||
| A C T I V I T Y | |||
| N O | T R A N S M I T T A L | ||
| N O | S P E C | ||
| S E C T | DESCRIPTION ITEM SUBMITTED | P A R A |
G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W
| N R | CONTRACTOR: SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | MAILED TO CONTR/ | ||||||||||||||
| DATE RCD FRM APPR AUTH | REMARKS | |||||||||||||||||
| SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | DATE FWD TO APPR AUTH/ | ||||||||||||||||
| DATE RCD FROM CONTR | DATE FWD TO OTHER REVIEWER | DATE RCD FROM OTH REVIEWER | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | |||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |
| 32 93 00 | Time Restrictions and Planting | 1.6 | ||||||||||||||||
| Conditions | ||||||||||||||||||
| SD-03 Product Data | ||||||||||||||||||
| Fertilizer | 2.5 | |||||||||||||||||
| SD-06 Test Reports | ||||||||||||||||||
| Topsoil Composition Tests | 2.2.4 | |||||||||||||||||
| SD-07 Certificates | ||||||||||||||||||
| Nursery Certifications | 2.1.1 | |||||||||||||||||
| 33 40 00 | SD-07 Certificates | |||||||||||||||||
| Frame and Cover or Gratings | 2.3.6 | G | ||||||||||||||||
| SD-08 Manufacturer’s Instructions | ||||||||||||||||||
| Placing Pipe and Box Culvert | 3.3 | G | ||||||||||||||||
| SD-11 Closeout Submittals | ||||||||||||||||||
| LID Verification Report | 3.7.2.1 | G | ||||||||||||||||
| 33 46 16 | SD-04 Samples | |||||||||||||||||
| Geotextile | 2.2 | |||||||||||||||||
| Pipe and Pipe Fittings | 2.1 | |||||||||||||||||
| SD-07 Certificates | ||||||||||||||||||
| Geotextile | 2.2 | |||||||||||||||||
| Pipe and Pipe Fittings | 2.1 | |||||||||||||||||
| 33 71 01 | SD-03 Product Data | |||||||||||||||||
| Conductors | 2.6 | G | ||||||||||||||||
| Insulators | 2.5 | G | ||||||||||||||||
| Wood Poles | 2.2.1 | |||||||||||||||||
| Nameplates | 2.18 | G | ||||||||||||||||
| Pole Top Switch | 3.1.9 | G | ||||||||||||||||
| SUBMITTAL REGISTER | CONTRACT NO. |
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR | ||
| A C T I V I T Y | |||
| N O | T R A N S M I T T A L | ||
| N O | S P E C | ||
| S E C T | DESCRIPTION ITEM SUBMITTED | P A R A |
G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W
| N R | CONTRACTOR: SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | MAILED TO CONTR/ | ||||||||||||||
| DATE RCD FRM APPR AUTH | REMARKS | |||||||||||||||||
| SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | DATE FWD TO APPR AUTH/ | ||||||||||||||||
| DATE RCD FROM CONTR | DATE FWD TO OTHER REVIEWER | DATE RCD FROM OTH REVIEWER | A C T I O N | |||||||||||||||
| C O D E | DATE OF ACTION | |||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |
| 33 71 01 | Cutouts | 2.13 | G | |||||||||||||||
| Transformer | 2.15 | G | ||||||||||||||||
| Surge Arresters | 2.12 | G | ||||||||||||||||
| Guy Strand | 2.8 | |||||||||||||||||
| Anchors | 2.10 | |||||||||||||||||
| SD-06 Test Reports | ||||||||||||||||||
| Wood Crossarm Inspection | 1.5.4 | |||||||||||||||||
| Report | ||||||||||||||||||
| Field Test Plan | 1.5.4.1 | G | ||||||||||||||||
| Field Quality Control | 3.5 | G | ||||||||||||||||
| Ground Resistance Test Reports | 1.5.3 | G | ||||||||||||||||
| Medium-Voltage Preassembled | 3.5.3 | G | ||||||||||||||||
| Cable Test | ||||||||||||||||||
| Sag and Tension Test | 3.5.4 | G | ||||||||||||||||
| Low-Voltage Cable Test | 3.5.5 | G | ||||||||||||||||
| Acceptance Checks and Tests | 3.5.7 | |||||||||||||||||
| SD-07 Certificates | ||||||||||||||||||
| Wood Poles | 2.2.1 | G | ||||||||||||||||
| Wood Crossarms | 2.3.1 | G | ||||||||||||||||
| Transformer Efficiencies | 2.15.1 | G | ||||||||||||||||
| SD-09 Manufacturer’s Field | ||||||||||||||||||
| Reports | ||||||||||||||||||
| Operation and Maintenance | 1.6 | G | ||||||||||||||||
| Manuals | ||||||||||||||||||
| Operation and Maintenance | 1.6.1 | G | ||||||||||||||||
| Manuals | ||||||||||||||||||
| SUBMITTAL REGISTER | CONTRACT NO. |
P-009U
| TITLE AND LOCATION | |||
| P-009U MAIN SIDE PARKING IMPROVEMENTS | CONTRACTOR |
This is the start of the file's text. The full file is on GovTribe.