Attachment_B_-Technical_Specifications.pdf
PDF 803 KB Posted
- Solicitation number
- B-8-26-29
- Issued by
- Brevard County, Florida
About this file
This is a Technical Specifications document for the Max Brewer Causeway Shoreline Restoration Project, a joint effort by Brevard County and AtkinsRealis, which details the requirements for truck-haul placement of approximately 12,000 cubic yards of sand for shoreline restoration along the north shoreline of the Max Brewer Causeway in the Indian River Lagoon, Florida. The project scope includes sand placement from an approved upland sand mine within a permitted shoreline template, installation of native plants from approved nurseries, erosion and sedimentation controls, turbidity monitoring, maintenance of traffic, environmental protection measures, and project closeout procedures. The Base Bid quantity is established at 9,000 cubic yards (75% of the estimated total), and the Owner may authorize additional sand placement up to the maximum 12,000 cubic yards at the contractor's Base Bid unit price at its sole discretion. The contractor must commence work within 15 days of receiving the limited Notice-to-Proceed, with a full Notice-to-Proceed issued following receipt of all final project permits; the contractor will be provided at least 50 days from full Notice-to-Proceed issuance to complete the project. Bid award will be made to the lowest responsive and responsible bidder based solely on the Base Bid amount, with the contractor required to submit preconstruction submittals including a Quality Control Plan, Environmental Protection Plan, Construction Progress Schedule, and Planting Plan prior to the preconstruction conference held within 10 days of Notice-to-Proceed.
Pricing is structured as a combination of lump-sum and unit-price bid items, including Mobilization/Demobilization (limited to 10% of total base bid value with 60% payment upon placement of the first 1,000 cubic yards and 40% upon project completion), Environmental Protection (lump sum with 75% payable upon completion of material placement and 25% upon closeout requirements satisfaction), Planting Installation (lump sum upon final acceptance), Irrigation Allowance (lump sum upon final acceptance), and Truck Haul Material and Transportation measured in tons at a unit price (with payment of 50% upon delivery to staging site and 50% upon final placement and grading to template). Sand is measured by certified weight tickets at a conversion rate of 1.35 tons per cubic yard in-place, and moisture content must not exceed 6%. The contractor is responsible for all costs associated with environmental protection, quality control, temporary facilities, traffic control, staging areas, and equipment security, with no separate payment for these activities. The project includes compliance with St. Johns River Water Management District and Department of the Army permits, Florida Department of Transportation approvals, turbidity monitoring conducted by an independent third party, manatee and endangered species protection measures, and a 90-day plant establishment and maintenance period with an 80% survival guarantee. Delays resulting from unusually severe weather or turbidity standard exceedances are not grounds for contract price or schedule adjustments.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
00 00 00-1 Max Brewer Causeway Shoreline Restoration Project
TECHNICAL SPECIFICATIONS
00 41 00 Bid Schedule
01 11 00 Summary of Work
01 22 00 Measurement and Payment
01 30 00 Administrative Procedures
01 32 16 Construction Progress Schedule
01 33 00 Submittal Procedures
01 45 05 Contractor Quality Control
01 50 02 Temporary Construction Facilities
01 55 26 Maintenance of Traffic
01 57 20 Environmental Protection
01 57 25 Turbidity Monitoring
01 71 13 Mobilization/Demobilization
01 77 00 Closeout Procedures
02 21 00 Surveys
31 25 00 Erosion and Sedimentation Controls
32 93 00 Plantings
32-92-23 Sodding
35 20 25 Shoreline Fill – Truck Haul Placement
List of Attachments
1. Florida Department of Environmental Protection Permit – Permit Number TBD
2. Department of the Army Permit – Permit Number TBD
3. Geotechnical Report
4. Upland Project As-Builts
The engineering material and data contained in the Drawings and Technical Specifications in relationship to the Max Brewer Causeway Shoreline Restoration Project were compiled under the responsible charge of the undersigned, whose seal as registered professional engineer is affixed below:
S. Marie Yarbrough, PE
Florida Registration No 70748
Max Brewer Shoreline Restoration Project
00 41 00-1
SECTION 00 41 00
BID SCHEDULE
PART 1: GENERAL
1.01 BASIS OF BIDS
A. Lump Sum and Unit Price Schedule
The project consists of restoration of shoreline at the Max Brewer Causeway.
Approximately 12,000 cubic yards (CY) of material is expected to be sourced and brought in from the approved upland sand mine. The material will be placed within the approved shoreline template along the north shoreline of the Max Brewer Causeway. Native plants sourced from approved nurseries will be planted as shown in the Drawings. The bid structure will involve using a Base Bid with Additive Options. The Base Bid quantity shall consist of 9,000 cubic yards (CY), representing seventy-five percent (75%) of the total estimated project quantity, and shall establish the basis for bid evaluation and contract award. The project will be awarded to the lowest responsive and responsible bidder based solely on the Base Bid amount. Following award, the OWNER may, at its sole discretion and subject to available funding, authorize the placement of additional sand beyond the Base Bid quantity, up to a maximum total project quantity of approximately 12,000 cubic yards, through written authorization. All additional sand placement shall be paid for at the per-ton unit price established in the Base Bid, with no adjustment to unit pricing. The OWNER’s intent is to place the maximum practicable quantity of sand, up to 12,000 cubic yards, within the available construction budget, without renegotiation of unit prices.
1.02 SCOPE
A. The project consists of the placement of approximately 12,000 CY of sand within the shoreline template as described herein and the drawings. Actual quantities will be based on the OWNER/ENGINEER’s preconstruction survey. The sand source shall come from an approved vendor and sediment quality shall comply with the Sediment QA/QC plan detailed herein and the regulatory permits.
B. Final St. Johns River Water Management District and U.S. Army Corps of Engineers regulatory permits are in progress and have not been issued at this time. Florida Department of Transportation approvals for Maintenance of Traffic, along with any other approvals shall be obtain by Contractor. Flexibility shall be scheduled into Contractor’s response based on final issuance of all permits. Contractor will be provided at least 50 days from issuance of the full Notice to Proceed to complete the project.
C. If the quantity of a unit-priced item in this contract is an estimated quantity which has been specifically identified as eligible for adjustments due to variations in estimated quantities, and the actual quantity of the unit-priced item varies more than 20 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 120 percent or below 80 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the CONTRACTOR may request, in writing with the demand, an extension of time consistent with associated
00 41 00-2 quantity variation. This variation in estimated quantity (VEQ) clause does not apply to all bid items, it only applies to bid items which specifically indicate eligibility under this clause in Section 01 22 00. For sand placement, the Base Bid quantity is established solely for bid evaluation purposes. Quantities of sand placed up to the estimated project quantity of approximately 12,000 cubic yards, whether included in the Base Bid or authorized by written authorization, shall not be considered variations in estimated quantities for purposes of this clause.
D. This bid shall be for a complete project and bid item prices shall include all components necessary for successful completion of the work as designed and specified.
PART 2: PRODUCTS
(Not Used)
PART 3: EXECUTION
END OF SECTION 00 41 00
01-11-00-1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 PROJECT INFORMATION
a. Project Name: Max Brewer Shoreline Restoration Project
b. OWNER: Brevard County
c. ENGINEER: The construction documents were prepared for this project by
AtkinsRéalis.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The project consists of truck-haul placement of material for shoreline restoration.
The work will entail placing approximately 12,000 cubic yards (CY) of sand from an approved upland sand mine. Sand shall be placed in the permitted shoreline template, as modified based upon the pre-construction survey completed by ENGINEER. Native plants will be installed as shown in the Drawings.
1.2.2 Location
The work is located in the Indian River Lagoon, on the north shoreline of the Max Brewer Causeway in Brevard County, Florida.
01-11-00-2
1.2.3 The project site, shown in red, is a public park that is open to visit by bidder at any time.
Work Restrictions See Sections 01 57 20 ENVIRONMENTAL PROTECTION for restrictions regarding environmental compliance and shoreline fill.
1.3
1.4
BASIS OF AWARD
Award of this bid shall be to the overall lowest, responsive, and responsible bidder based solely on the Base Bid quantity and amount, meeting or exceeding the requirements specified herein. The Base Bid quantity shall consist of 9,000 cubic yards (CY), representing seventy-five percent (75%) of the total estimated project quantity, and shall establish the minimum guaranteed scope of work and the basis for contractor selection. The OWNER reserves the right to reject the bid of any bidder who has previously failed to perform properly or on time, contracts of similar nature, or who, based on the review and recommendation of the Review and Qualification Committee, and in the sole discretion of the OWNER, is not in a position to satisfactorily perform the contract. If after bid opening the lowest bidder is deemed as not responsible based on the review of the pre-qualification information, the OWNER may reject the bid. The OWNER shall make a final determination regarding the bidder’s responsibility at the time of award of the contract. Following award, the OWNER may, at its sole discretion and subject to available funding, authorize the placement of additional sand beyond the Base Bid quantity, up to a maximum total project quantity of approximately 12,000 cubic yards, by written authorization, at the Base Bid per-ton unit price.
COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
a. The CONTRACTOR shall commence work within 15 days of receipt of contract limited
Notice-To-Proceed. The phrase “commence work” refers to mobilization efforts including submission of pre-construction submittals, surveying, equipment mobilization, etc. A full Notice-To-Proceed will be issued following receipt of all final project permits.
01-11-00-3
b. Work will be permitted during daylight hours, from dusk to till dawn, 7 days per week, including holidays.
c. Order of Work:
i. Truck hauled placed material shall be conducted in a continuous manner that works within the CONTRACTOR’s schedule so long as material is placed, vegetation installed, and equipment is demobilized from the limits of construction by contracted completion date.
1.5 PHYSICAL DATA
1.5.1 Physical Conditions
The physical conditions described in the project drawings and specifications are the result of topographic and visual surveys collected in 2022. The data from these site investigations will be made available at the CONTRACTOR’s request.
1.5.2 Weather, Water Stage, and Tide Data
The CONTRACTOR should investigate for himself the conditions that can be encountered at the project location. It is the CONTRACTOR’s responsibility to assess weather, water stage, and tide conditions and schedule for adverse weather in order to meet the schedule described in paragraph 1.4 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK of this section.
1.5.3 Contractor Investigation
It is the CONTRACTOR’s responsibility to perform their own investigation to confirm information depicted in the project plans and specifications.
1.5.4 Maritime Traffic
Marine traffic in the project area consists of small recreational vessels of all types and sizes.
1.5.5 Surveys
Electronic survey files are available at the CONTRACTOR’s request. Survey data is depicted in the project drawings, as dated May 6, 2022.
1.6 LAYOUT OF WORK
1.6.1 Established Project Control
Information concerning the location of the shoreline placement template can be found on G-001 of the project plans. Additional information regarding project control can be found on the same plan sheet.
1.6.2 Layout
The CONTRACTOR is responsible for establishing the layout of work based on the control data and elevations established in the contract documents. The layout is subject to modification by the ENGINEER/OWNER in order to accommodate changes in conditions. The shoreline placement template will be adjusted based on the pre-construction survey collected by ENGINEER/OWNER.
1.7 DAMAGE TO WORK
During prosecution of work, the CONTRACTOR is obligated to take reasonable precautions and exercise sound construction practices in order to prevent damage to the work or adjacent structures. Any damage as a result of the CONTRACTOR’s failure to do so must be repaired
01-11-00-4 at no expense to the OWNER. However, if any part of the permanent work is damaged due to circumstances beyond the CONTRACTOR’s control, including flood, earthquake, hurricane, or tornado, the OWNER may request the CONTRACTOR make the necessary repairs at the applicable contract unit price.
1.8 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
a. In order for the OWNER to grant a time extension for unusually severe weather, the following must be true:
i. The weather experienced at the project site during the contract period must be found to be unusually severe; that is, more severe than the adverse weather anticipated for the project location during any given month.
ii. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the
CONTRACTOR.
b. The CONTRACTOR should be responsible for documenting the occurrence of unusually severe weather days on their daily QC Reports. In order for a day to be considered an unusually severe weather day, the weather delay must prevent work on critical activities for more than 50 percent of the day and be accompanied by documentation – weather reports, craft advisories, or similar.
c. The project cannot be extended beyond the contract deadline without prior approval.
PART 2 PRODUCTS
(NOT USED)
PART 3 EXECUTION
(NOT USED)
END SECTION 01 11 00
01-22-00-1
AtkinsRéalis - Baseline / Référence
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUMMARY
This section describes how Line Items will be measured and paid when making progress and final payments. Work to be measured and applicable measurement procedures are described in their respective specification sections. For work that does not have a specific Line Item, such as administrative procedures, quality control, safety, and environmental monitoring, allocate costs proportionally across appropriate Line Items.
1.2 VARIATION IN ESTIMATED QUANTITIES
a. All unit-priced items in this contract are estimated quantities. If the actual quantity of any unit-priced items varies more than twenty percent (20%) above the maximum estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 120%. The Base Bid quantity is established solely for bid evaluation and budget control purposes. Authorization of quantities beyond the Base Bid amount, up to the maximum estimated project quantity, is at the sole discretion of the OWNER and shall not constitute a variation in estimated quantities under this section.
b. If the quantity variation is such as to cause an increase in the time necessary for completion, the CONTRACTOR may request in writing, an extension of time, to be received by the OWNER within ten (10) days from the beginning of the delay, or within such further period as may be granted by the OWNER before the date of final settlement of the contract. Upon the receipt of a written request for an extension, the OWNER shall ascertain the facts and make an adjustment for extending the completion date as, in the judgement of the OWNER, is justified.
1.3 JOB PAYMENT ITEMS
1.3.1 Bid Item 1.1: Mobilization and Demobilization
Payment will be made for costs associated with and incidental to mobilization and demobilization and establishment of initial project management and coordination. Sixty percent (60%) of the lump sum price will be paid upon confirmation and approval of the first one thousand (1,000) cubic yards of material placed within the permitted shoreline template and forty percent (40%) will be paid upon completion and final acceptance of all contracted work. This bid item shall be limited to 10% of the total base bid value.
1.3.2 Bid Item 1.2: Environmental Protection
This bid item shall include all costs associated with all environmental protection measures associated with the project. This may include, but not be limited to, turbidity curtains, turbidity monitoring, endangered species observation, spill prevention, the installation, maintenance, and removal of turbidity curtains, silt fences, and erosion control BMPs.
The work specified under this section shall be paid for at the Contract lump sum price based on the estimated percent complete of material placed. A maximum of 75% will be
01-22-00-2
AtkinsRéalis - Baseline / Référence payable at the completion of placement as applicable, with the remaining 25% payable after any applicable project close out requirements have been satisfied. See Section 01
57 25 TURBIDITY AND DISPOSAL MONITORING.
1.3.3 Bid Item 1.3: Planting Installation
This bid item shall include all costs associated with fixed (non-quantity dependent) costs associated with the installation of the plantings. Costs may include but are not limited to planting plan approval coordination and physical installation of the plantings.
The work specified under this section shall be paid for at the Contract lump sum price after final acceptance of planting installation.
1.3.4 Bid Item 1.4: Irrigation Allowance
This bid item shall include all costs associated with fixed (non-quantity dependent) costs associated with the planting irrigation necessary to ensure plants meet their survivability requirements. Costs may include but are not limited to a water truck and its usage.
The work specified under this section shall be paid for at the Contract lump sum price after final acceptance of planting installation.
1.4 UNIT PRICE PAYMENT ITEMS
1.4.1 Item 1.5: Truck Haul Material and Transportation (Unit Price)
a. Measurement – Tons (TN)
The construction documents indicate the total volume of sand in cubic yards to be delivered to the work site. Measurement for payment of sand delivered to the site shall be by certified weight tickets (tons), where 1.35 tons = 1.0 cubic yard in-place contract measure. Contractor shall provide the unit weight (tons per cubic yard of loose material as it is hauled) from either the upland sand supplier or third-party testing. Sand measured by weight shall be well-drained and free of excess water, with a moisture content of 6% or less (per ASTM C-566 Total Evaporable Moisture Content of Aggregate by Drying, or equivalent measure acceptable to the OWNER).
The OWNER reserves the right to make deductions for the weight of sand delivered if it is evident to the OWNER and its inspectors that the moisture content of the sand as weighed by the pay scale exceeds the nominal allowable moisture content of 6%. The truckload data reported in the CONTRACTOR 's daily reports shall be verified by the OWNER on-site monitor by means acceptable to both the CONTRACTOR and the OWNER. Volume delivered to a staging site will be eligible for 50% payment, while the final 50% payment will not be authorized until the sand has been transferred to the final location and graded to template. It is to be understood that all sand delivered to staging areas must be placed in final template as promptly as practical.
b. Payment Payment will be made for costs associated with and incidental to barricades and signs, transportation of sediment material from the borrow (sand mine) source to the project site, constructing the beach profile and final dressing, noise control, and survey.
01-22-00-3
AtkinsRéalis - Baseline / Référence
Hydrographic and topographic surveys for final measurement and payment and for placement acceptance must be performed under the oversight of, and certified by, a PLS licensed in the State of Florida. All surveys will be performed in accordance with USACE EM 1110-2-1003. Survey frequencies will be the same as described in SECTION 02 21 00 SURVEYS and will remain consistent throughout the contract.
1.4.2 Item 1.6: Truck Haul Placement (Unit Price)
a. Measurement – Tons (TN)
The construction documents indicate the total volume of sand in cubic yards placed along the shoreline between specified waypoint locations. Measurement for payment for placed sand shall be by certified weight tickets (tons), where 1.35 tons = 1.0 cubic yard of in-place contract measure.
b. Payment In place volumes in the template shall be documented by the CONTRACTOR using off-road truck volumes and reported to the OWNER. Payment shall not be made for sand volumes placed outside of the tolerances specified in Section 35 20 25 SHORELINE
FILLTRUCK HAUL PLACEMENT.
1.4.3 Item 1.7: Post & Rope Fencing with Signs (Unit Price)
a. Measurement – Tons (TN)
The construction documents indicate the linear feet of post and rope fencing to be installed in Sheet C-114 . Slight field adjustments to the actual location of the public beach access may be required based on the final layout of the parking lot constructed by others.
b. Payment Payment for this bid item shall be percent complete of installation of the post and rope fencing with signs.
1.1.1 Items 1.8 – 1.14: Plantings (Unit Price)
a. Measurement
The construction documents indicate the total number of plants to be placed along the shoreline. Sheet C-113 provides the Planting Layout and Detail based on the bid document design. Contractor shall provide a final Planting Plan for approval based on the final shoreline fill template following any adjustments prior to construction.
Measurement for payment of planting shall be by percent complete.
b. Payment Payment will be made for costs associated with acquisition of plants, transportation of plants from the source to the project site, and any soil amendments needed for the success of the installation.
PART 3 PRODUCTS (NOT APPLICABLE)
(Not Used)
PART 4 EXECUTION (NOT APPLICABLE)
01-22-00-4
END SECTION 01 22 00
01-30-00-1
01 30 00
ADMINISTRATIVE PROCEDURES
Project management and coordination activities shall be the responsibility of the CONTRACTOR. The cost for furnishing labor, equipment, and materials required to plan and execute project operations will not be paid under a separate line item.
1.2 PROJECT MEETINGS
The following meetings are required under this project:
a. Preconstruction Conference – held prior to the start of construction, within 10 days of
NTP. The OWNER will coordinate the preconstruction conference and notify the CONTRACTOR of time, place, and agenda. It is the CONTRACTOR’s responsibility to notify his personnel, including subcontractors and suppliers, to attend. Minutes taken by the OWNER will be supplied to the CONTRACTOR for review and signature. Signed minutes will become part of the project record. The following should be submitted prior to the preconstruction conference.
i. Project Schedule
ii. Contractor Quality Control Plan
iii. Environmental Protection Plan
iv. Turbidity Monitor Qualifications
v. Fill Plan
vi. Planting Plan
vii. Construction and Grade Stake Recovery Plan
b. Preparatory and Initial Phase Meetings – held prior to and after the start of each definable feature of work. See Section 01 45 05 CONTRACTOR QUALITY CONTROL for more details.
c. Progress Meetings – held weekly by the CONTRACTOR. The CONTRACTOR shall schedule and preside over progress meetings to review at a minimum the following:
i. Work progress
ii. Schedule
iii. Issues
iv. Status of submittals and RFIs
v. Testing
vi. Safety
vii. Upcoming work
viii. Other business as appropriate
d. The CONTRACTOR is responsible for ensuring the appropriate personnel are in attendance of the progress meetings. At a minimum, representatives from the following entities shall be included in the progress meeting invitation: Brevard County personnel (OWNER), AtkinsRéalis (ENGINEER), CONTRACTOR personnel. The ENGINEER shall take meeting minutes and distribute within three (3) days after each meeting.
1.3 NOTICE TO PROCEED
01-30-00-2
AtkinsRéalis - Baseline / Référence
Notice to proceed (NTP) will be issued within 15 calendar days after award or after all required bonds and CONTRACTOR submittals are received, whichever is later. If the CONTRACTOR has failed to submit and receive acceptance and/or approval of specified plans, including, but not limited to, Quality Control Plan - Section 01 45 05 CONTRACTOR QUALITY CONTROL and Environmental Protection Plan - Section 01 57 20 ENVIRONMENTAL PROTECTION, or has not yet received the OWNER’s conditional approval to work under an interim plan, the CONTRACTOR shall not proceed with the work and shall consider the work to be suspended. If the CONTRACTOR does not submit an acceptable plan within a reasonable time, as determined by the OWNER, the OWNER may order the CONTRACTOR to suspend work. Any suspension order issued for the CONTRACTOR’s failure to submit an acceptable plan will not constitute unreasonable delay and the CONTRACTOR will not be entitled to an equitable adjustment of either performance period or contract price.
PART 2 PRODUCTS (NOT APPLICABLE)
(Not Used)
PART 3 EXECUTION (NOT APPLICABLE)
END SECTION 01 30 00
Max Brewer Causeway Shoreline Restoration Project
01 32-16-1
SECTION 01 32 16
CONSTRUCTION PROGRESS SCHEDULE
PART 1: GENERAL
1.01 SUBMITTALS
A. One (1) day prior to the Preconstruction meeting, CONTRACTOR shall prepare and submit to the OWNER for review and acceptance a Construction Progress Schedule in the form of a Bar Chart Schedule.
B. The schedule shall include all mobilization/demobilizations and anticipated work schedule for hauling and placement of material in accordance with all regulatory permit restrictions, as well as construction site.
1.02 ACCEPTANCE
The acceptance of a Baseline Construction Schedule is a condition precedent to:
1. CONTRACTOR starting work on the construction stages of the contract.
2. Processing CONTRACTOR's invoice(s) for construction activities/items of work.
3. Review of any schedule updates.
B. Submittal of the Construction Progress Schedule and subsequent schedule updates, must be understood to be the CONTRACTOR's certification that the submitted schedule meets all of the requirements of the Contract Documents, represents the CONTRACTOR's plan on how the work must be accomplished, and accurately reflects the work that has been accomplished and how it was sequenced.
1.03 SCHEDULE FORMAT
A. Bar Chart Schedule
The Bar Chart must show work activities, submittals, OWNER review periods, material/equipment deliveries, site construction, placement sections, inspections and closeout activities. The Bar Chart must be time scaled and generated using an electronic spreadsheet or scheduling program.
B. Schedule Submittals and Procedures
Submit Bar Chart Schedules and updates in hard copy and digital format to OWNER and ENGINEER. Submit digital copy of the Construction Progress Schedule in a format that is acceptable to the OWNER.
1.04 WEEKLY SCHEDULE UPDATES
A. Update the Construction Progress Schedule and submit to the OWNER and ENGINEER at the weekly Construction Meetings or when the schedule has been revised. The updated schedule must be kept current, reflecting actual activity
01 32-16-2 progress and plan for completing the remaining Work. With each updated schedule submitted the CONTRACTOR shall provide the following:
1. Narrative Report: Provide a concise report with schedule updates. Identify and justify:
a. Progress made in each area of the Project;
b. Critical path;
c. Date/time constraints other than those required in the Contract;
d. Changes in the following; added or deleted activities, original and remaining durations for activities that have not started, logic, milestones planned sequence of operations and critical path;
e. Status of Contract Completion Date and interim milestones;
f. Current and anticipated delays (describe cause of delay and corrective action(s)and mitigation measures to minimize); and
g. Description of current and future schedule problem areas.
1.05 2-WEEK LOOK AHEAD SCHEDULE
The CONTRACTOR must prepare and issue a 2-Week Look Ahead Schedule to provide a more detailed day-to-day plan of upcoming work identified on the Construction Progress Schedule. The Look Ahead Schedule must be delivered in coordination with the Weekly Construction Progress Meeting.
1.06 WEEKLY PROGRESS MEETINGS
The CONTRACTOR shall prepare for and participate in a weekly progress meeting with the OWNER for the purpose of jointly reviewing the actual progress as compared to the planned progress, and to review planned activities for current week and the upcoming two weeks. Use the current approved schedule update for the purpose of this meeting.
PART 2: PRODUCTS
(Not Used)
END OF SECTION 01 32 16
01-33-00-1
SECTION 01 33 00
SUBMITTAL PROCEDURES
This section covers submittal procedures, submittal types, tracking, and review periods for submittals required under this contract.
1.2 SUBMITTAL TYPE
a. Preconstruction Submittal – required prior to start of work; includes schedules, data, information, etc. Preconstruction submittals must be submitted no later one (1) day before the pre-construction meeting.
b. Shop Drawings – drawings, diagrams, and schedules specifically prepared to illustrate some portion of the work.
c. Product Data – catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance, and other characteristics of materials or equipment for some portion of the work. Samples of warranty language.
d. Test Reports – report demonstrating findings of a test made at the job site or official testing laboratory of a material, equipment, prototype, or sample as required by this contract.
e. Certificates – document required of a CONTRACTOR, or of a supplier, installer, or subcontractor to describe procedures, acceptability of methods, or personnel qualifications.
f. Closeout Submittals – documentation to record compliance with technical or administrative requirements.
1.3 SUBMITTALS
Preconstruction submittals
a. Submittal Register: The CONTRACTOR should provide, for approval by the OWNER, an updated Submittal Register, described in paragraph 1.6 of this section, as part of the preconstruction submittal package.
b. Transmittal Form: The CONTRACTOR should submit a sample transmittal form to use for submittals to the Owner/Contracting Officer.
c. Quality Control Report – The CONTRACTOR should submit a sample daily QC report that will be produced daily once construction is commenced.
1.4 SUBMITTAL CLASSIFICATION
a. OWNER Approved – submittals requiring approval by the OWNER prior to proceeding with the associated task.
b. Information Only – submittals not requiring OWNER approval to proceed.
1.5 GENERAL
All submittals must be reviewed and approved by the CONTRACTOR’s Quality Control Manager prior to submission to the OWNER.
01-33-00-2
1.6 SUBMITTAL REGISTER
The submittal register outlines the submittals required under these specifications. It is the CONTRACTOR’s responsibility to ensure that the submittal register submitted as part of the preconstruction submittals includes all relevant submittals, including any additional submittals that may be required over the course of the work. The CONTRACTOR should update the submittal register as necessary.
1.7 SCHEDULING
The CONTRACTOR is responsible for scheduling submittals with sufficient time for OWNER review prior to delivery, mobilization, or execution of applicable work. If any work is performed prior to written approval by the OWNER of the respective submittal, the CONTRACTOR assumes any risk associated with that work. The CONTRACTOR should allow up to 15 calendar days for review of submittals requiring OWNER approval.
1.8 SUBMITTAL PROCEDURES
1.8.1 Submittal Review Codes
Submittals requiring OWNER approval will be reviewed and returned to the CONTRACTOR with one of the following designations:
A – Approved as submitted (complete) B – Approved as noted (complete) C – Not Approved, see comments (requires resubmission) D – For Record Only, see comments (complete)
1.8.2 Electronic Correspondence
All correspondence and contract-related documents shall be submitted in searchable Portable File format (PDF) with the only exceptions being those stated at the end of this paragraph. Any documents that require signature shall be submitted in PDF format with signature. Minimum scan quality shall be 150 dpi. The OWNER will discuss electronic correspondence procedures at Preconstruction and Coordination Meetings. These procedures may include sending files by e-mail, a CONTRACTOR provided FTP site, a website indicated by the OWNER at the Preconstruction Conference, or other methods approved by the OWNER. The CONTRACTOR will be responsible for the cost of the electronic media. E-mail correspondence does not have to be provided in PDF format.
END SECTION 01 33 00
01-45-05-1
SECTION 01 45 05
CONTRACTOR QUALITY CONTROL
1.1 REFERENCES
EM 385-1-1 – USACE Safety and Health Requirements Manual
1.2 SUBMITTALS
1.2.1 Preconstruction Submittals
a. Quality Control Plan
b. Project Schedule
1.2.2 Test Report
a. Daily Quality Control Report
1.3 PAYMENT
Separate payment will not be made for providing and maintaining an effective Quality Control (QC) Plan, and all costs associated therewith shall be included in the applicable unit or lump-sum prices contained in the Bid Schedule.
1.4 QUALITY CONTROL ORGANIZATION
QC Manager
a. The CONTRACTOR must provide a QC Manager at the work site to implement and manage the QC program. In addition to implementing and managing the QC program, the QC Manager may perform the duties of project superintendent, project manager, or project engineer.
b. The QC Manager is required to conduct the QC meetings, perform the three phases of control described in subpart 3.2 of this section, perform submittal review and approval, ensure testing is performed, and provide QC certifications and documentation required in this Contract.
c. The QC Manager is responsible for managing and coordinating the three phases of control and documentation performed by others.
d. The QC Manager must be an individual with a minimum of five (5) years combined experience as a superintendent, inspector, QC Manager, project manager, or construction manager on similar size and type construction contracts which included the major trades that are part of this Contract.
e. The individual must be familiar with the requirements of the EM 385-1-1 and have experience in the areas of hazard identification and safety compliance.
f. Submit the qualifications of the proposed QC Manager for approval with the Quality Control Plan.
1.5 QUALITY CONTROL PLAN
01-45-05-2
1.5.1 Provide, for acceptance by the OWNER, a QC plan that covers both on-site and off-site work and includes the following with a table of contents listing the major sections identified.
a. QC ORGANIZATION: A chart showing the QC organizational structure and its relationship to the production side of the organization.
b. NAMES AND QUALIFICATIONS: In resume format, for each person in the QC organization. Include copies of all referenced certifications.
c. DUTIES, RESPONSIBILITIES, AND AUTHORITY OF QC PERSONNEL: For each person in the QC organization.
d. REPORTING PROCEDURES: Including proposed reporting formats, timelines/schedules, and sample reports.
e. TESTING PLAN AND LOG: A Testing Plan and Log that includes control, verification, turbidity monitoring, and field testing procedures. Provide a list of specific instruments and tests. Provide information including work being tested, test frequency, and identify who (CONTRACTOR, subcontractor) is responsible for each test.
f. LIST OF DEFINABLE FEATURES OF WORK: A Definable Feature of Work (DFOW) is a task, which is separate and distinct from other tasks, that has the same control requirements and work crews. The list shall be cross-referenced to the CONTRACTOR's Construction Schedule and the specification sections. For projects requiring a Progress Chart, the list of definable features of work shall include, but not be limited to, all items of work on the schedule.
g. PROCEDURES FOR PERFORMING THREE PHASES OF CONTROL: For each DFOW, provide Preparatory and Initial Phase Checklists. Each list shall include a breakdown of quality checks that will be used when performing the quality control functions, inspections, and tests required by the Contract documents. The preparatory and initial phases shall be conducted with a view towards obtaining quality construction by planning ahead and identifying potential future problems. See paragraph 3.2 of this section.
1.5.2 Notify the OWNER in writing prior to proposed personnel or QC Plan procedure changes.
Proposed changes are subject to approval by the OWNER.
PART 2 PRODUCTS (NOT APPLICABLE)
3.1 GENERAL
The CONTRACTOR is responsible for establishing and implementing a quality control program.
3.2 THREE PHASES OF CONTROL
3.2.1 Preparatory Phase
Notify the OWNER at least two (2) working days in advance of each preparatory phase meeting. Conduct the preparatory phase meeting with the superintendent and the foreman responsible for the DFOW. Provide accommodations for the OWNER’s representative(s) to participate in preparatory phase meetings. Document the results of
01-45-05-3 the preparatory phase actions in the daily QC Report and in the QC checklist. Perform the following prior to beginning work on each DFOW:
a. Review each paragraph of the applicable specification sections;
b. Review the contract drawings;
c. Verify that appropriate shop drawings and submittals for materials and equipment have been submitted and approved. Verify receipt of approved factory test results, when required;
d. Review the testing plan and ensure that provisions have been made to provide the required QC testing;
e. Examine the work area to ensure that the required preliminary work has been completed;
f. Examine the required materials, equipment, and sample work to ensure that they are on hand and conform to the approved shop drawings and submitted data;
g. Review safety plans to ensure that applicable safety requirements are met, and that required Safety Data Sheets (SDS) are submitted; and
h. Discuss specific controls used and the construction methods and approach that will be used to provide quality construction by planning ahead and identifying potential problems for each DFOW.
3.2.2 Initial Phase
a. Notify the OWNER at least two (2) working days in advance of each Initial Phase meeting. When construction crews are ready to start work on a DFOW, conduct the Initial Phase meeting with the foreman responsible for that DFOW. Observe the initial segment of the work to ensure that it complies with Contract requirements. Document the results of the Initial Phase in the daily QC Report and in the QC checklist.
Perform the following for each DFOW:
i. Establish the quality of workmanship required;
ii. Resolve conflicts; and
iii. Ensure that testing performed is adequate and timely.
3.2.3 Follow-up Phase
a. Perform the following for on-going work daily, or more frequently as necessary, until the completion of each DFOW and document in the daily QC Report and in the QC checklist:
i. Ensure the work is in compliance with Contract requirements;
ii. Maintain the quality of workmanship required;
iii. Ensure that testing is adequate and timely; and
iv. Ensure that rework items are being corrected.
3.3 TESTS/TESTING PROCEDURE
Perform specified tests and required monitoring instrumentation or tests to verify control measures are adequate and provide an end product conforming to contract. When requested, CONTRACTOR shall furnish the OWNER duplicate samples of test specimens for possible testing by Contracting Officer. The CONTRACTOR shall perform the following activities and record and provide the following data:
01-45-05-4
a. Verify that testing standards or procedures comply with contract requirements.
b. Verify that facilities, instruments, and testing equipment are available and comply with testing standards.
c. Check test instrument calibration data against certified standards.
d. Verify that recording forms and test identification control number system, including all of the test documentation requirements, have been prepared.
e. Results of tests and monitoring instruments, both passing and failing, shall be recorded and reported for date taken. If approved by Contracting Officer, actual test reports may be submitted later with a reference to the test number and date taken. An information copy of tests performed by an offsite or commercial test facility shall be provided directly to the Contracting Officer. Failure to submit timely test reports or maintain adequate monitoring testing may result in nonpayment for related work performed.
3.4 COMPLETION INSPECTION
3.4.1 Post-Construction Measurement and Inspection
As the CONTRACTOR approaches completion, the CONTRACTOR shall notify the OWNER to conduct surveys. The CONTRACTOR should spot check grading for beach placement to confirm the beach fill meets the lines and grades required by the Contract drawings. All survey data collected will be processed and provided to the CONTRACTOR at the CONTRACTOR’s request. Once a survey showing the CONTRACTOR has filled to the required grade has been produced, the CONTRACTOR should schedule an inspection with the OWNER for final acceptance.
3.4.2 Pre-Final Inspection
Timing of the pre-final inspection must be coordinated between the OWNER and CONTRACTOR. The OWNER and QC Manager will perform this inspection to verify Contract compliance for demobilization of temporary facilities and cleanup of staging areas is adequately restored. An OWNER pre-final punch list may be developed as a result of this inspection. The QC Manager shall ensure that all items on this list are corrected prior to notifying the OWNER that a Final Acceptance Inspection with the OWNER can be scheduled. Any items noted on the Pre-Final Inspection shall be corrected in a timely manner and shall be accomplished before the Contract completion date for the work or any particular increment thereof if the project is divided into increments by separate completion dates.
3.4.3 Final Acceptance Inspection
The QC Manager, superintendent, or other CONTRACTOR management personnel and the OWNER will be in attendance at this inspection. The Final Acceptance Inspection will be formally scheduled by the OWNER based upon results of the Pre-Final Inspection.
Notice shall be given to the OWNER at least five (5) days prior to the Final Acceptance Inspection. The notice shall state that all specific items previously identified to the CONTRACTOR as being unacceptable will be complete by the date scheduled for the Final Acceptance Inspection. Failure of the CONTRACTOR to have all Contract work acceptably complete for this inspection will be cause for the OWNER to bill the CONTRACTOR for the OWNER's additional inspection cost.
01-45-05-5
3.5 DOCUMENTATION
The CONTRACTOR shall maintain current records providing factual evidence that required QC activities and/or tests have been performed. Records shall be produced daily in the form of daily Quality Control Reports and shall be submitted to the OWNER no later than noon of the following day. These records shall include the work of subcontractor and suppliers and shall be on an acceptable form that includes, as a minimum, the following information:
a. CONTRACTOR/subcontractor and their area of responsibility;
b. Operating plant/equipment with hours worked, idle, or down for repair;
c. Work performed each day, giving location, description, and by whom;
d. Test and/or control activities performed with results and references to specifications/drawings requirements to include material verification protocol. The control phase shall be identified (Preparatory, Initial, Follow-up). List of deficiencies shall be noted, along with corrective action;
e. Quantity of materials received at the site with statement as to acceptability, storage, and reference to specifications/drawings requirements; to include truck counts of material taken to the final disposal;
f. Submittals and deliverables reviewed, with Contract reference, by whom, and action taken;
g. Offsite surveillance activities, including actions taken;
h. Job safety evaluations stating what was checked, results, and instructions or corrective actions;
i. Instructions given/received and conflicts in plans and/or specifications; and
j. CONTRACTOR's verification statement.
3.6 PROJECT SCHEDULE
3.6.1 Within 10 days of NTP the CONTRACTOR shall submit for approval by the OWNER a project schedule. The schedule should represent all work under the Contract performance period.
3.6.2 The CONTRACTOR must provide schedule updates each month or with each progress payment request. The updated schedule will allow the OWNER/ENGINER to assess and track the CONTRACTOR’s work progress.
3.7 NOTIFICATION OF NON-COMPLIANCE
The OWNER will notify the CONTRACTOR of any detected non-compliance with the foregoing requirements. The CONTRACTOR shall take immediate corrective action. If the CONTRACTOR fails or refuses to correct the non-compliant work, the OWNER will issue a non-compliance notice. Such notice, when delivered to the CONTRACTOR at the work site, shall be deemed sufficient for the purpose of notification. If the CONTRACTOR fails or refuses to comply promptly, the OWNER may issue an order stopping all or part of the work until satisfactory corrective action has been taken. The CONTRACTOR shall make no part of the time lost due to such stop orders the subject of claim.
END SECTION 01 45 05
01-50-02-1
SECTION 01 50 02
TEMPORARY CONSTRUCTION FACILITIES
This section includes requirements for staging areas, temporary utilities, construction aids, vehicular access and parking, support facilities, and security and protection.
1.2.1 Pre-construction submittals
a. Staging Area Plan
The CONTRACTOR should indicate locations of any additional access or staging areas not indicated on the drawings. If the CONTRACTOR plans on obtaining additional access/staging areas, they shall submit proposed drawings depicting the areas for OWNER and ENGINEER approval.
1.3 EXISTING UTILITIES
The CONTRACTOR is responsible for investigating the availability of utilities at the project site. The CONTRACTOR is responsible for providing all utilities necessary to perform their work.
1.4 ACCESS ROAD AND STAGING AREA
1.4.1 Staging Areas
a. The CONTRACTOR shall thoroughly inspect all staging and access areas to determine potential needs and means and methods prior to submitting a bid. Staging and access areas are shown on the Contract drawings that have been identified for the CONTRACTOR's use. The final limits of the equipment and beach access areas provided shall be field determined by the OWNER in coordination with the CONTRACTOR. Within these final limits the CONTRACTOR shall determine what is used and how the sites are operated based upon their means and methods. It shall be the responsibility of the CONTRACTOR to investigate and obtain any additional areas which may be necessary for their construction operations at the CONTRACTOR’s expense. The additional areas will be subject to the approval of the OWNER/Contracting Officer.
1.4.2 CONTRACTOR Responsibilities
a. The CONTRACTOR is responsible for identifying and procuring permission and/or authorizations for all alternative staging and storage areas.
b. Access by lock on temporary fencing shall allow access to both CONTRACTOR and
OWNER/ENGINEER.
c. The CONTRACTOR shall be responsible for providing nighttime security to oversee protection of the construction site(s) during shutdown periods. Security shall oversee staging area(s), and all equipment.
d. It is the responsibility of the CONTRACTOR to exclude the public from their work area.
The CONTRACTOR shall minimize areas closed to the public. The CONTRACTOR shall install warning signs to warn the public of all construction activities.
01-50-02-2
e. The CONTRACTOR shall be responsible for providing and maintaining all access routes necessary for his equipment and plant to and from the work sites.
f. The CONTRACTOR shall ascertain the environmental conditions which can affect access, such as climate, terrain, and winds.
1.4.3 Adjacent property and structures
a. The CONTRACTOR is not permitted to damage private or public property or structures during his operations. Any damage caused by the CONTRACTOR will require prompt repair at the CONTRACTOR’s expense.
1.4.4 Permits and responsibilities
a. The CONTRACTOR is responsible for obtaining any permits, easements, or authorizations necessary for use of alternate staging areas and site accesses.
2.1 TEMPORARY SIGNAGE
The CONTRACTOR shall post temporary signs to give the public warning and caution of construction hazards. CONTRACTOR shall attach signs to perimeter fencing requiring unauthorized persons to keep out of the site and maintain a safe distance from moving equipment.
3.1 GENERAL REQUIREMENTS
3.1.1 Identification of Employees: CONTRACTOR and subcontractor personnel must wear identifying markings on hard hats clearly identifying the company for whom the employee works. The CONTRACTOR is responsible ensuring only authorized personnel is allowed to enter the work site.
3.1.2 Onsite Information: A copy of the Contract drawings, specifications, permits, and other Contract documents must be kept on the site at all times.
3.2 CONTRACTOR’S TEMPORARY FACILITIES
3.2.1 The CONTRACTOR shall install and maintain a silt fence along the perimeter of the
Staging area. At the conclusion of the project, prior to demobilization, the CONTRACTOR shall remove the silt fence, and it shall become the property of the CONTRACTOR. In no case shall the CONTRACTOR leave any silt fence except as directed by the Owner/Contracting Officer.
3.2.2 Maintenance of Storage Area – maintain staging and storage areas in clean, neat condition.
3.2.3 Waste Storage – the CONTRACTOR is responsible for providing suitable dumpsters for waste containment. Dumpsters should be covered to prevent windblown trash and be emptied as necessary.
3.3 ACCOMMODATIONS FOR INSPECTORS
The CONTRACTOR should furnish suitable transportation between a landside pick up location approved by the OWNER and the site whenever conditions allow.
01-50-02-3
3.4 RESTORATION OF STAGING AREA
After removal of all equipment and materials from the staging and access areas, the CONTRACTOR shall remove temporary fencing from the site. All areas used by the CONTRACTOR must be made free of ruts and potholes and graded to create a smooth path.
Any damage to grassed areas will require resodding in accordance with TECHNICAL
SPECIFICATION 32-92-23 SODDING.
END SECTION 01 50 02
01 55 26-1
SECTION 01 55 26
MAINTENANCE OF TRAFFIC
PART 1: GENERAL
1.01 DESCRIPTION
A. General: Work under this section consists of maintaining traffic within the limits of the project for the duration of construction in accordance with the U.S. Department of Transportation's Manual On Uniform Traffic Control Devices (MUTCD) Current Edition, FDOT Design Standards Index 600 Series.
B. CONTRACTOR shall submit notification to FDOT of MOT plan and anticipated impacts (ie lane closures, delays, etc.) expected for the duration of the project, as applicable.
C. The CONTRACTOR shall submit to the OWNER and ENGINEER a Temporary Traffic Control Plan(s) for review, no less than fourteen (14) days prior to the Pre- Construction Conference. The Temporary Traffic Control Plan shall be signed and sealed by a Professional ENGINEER registered in the State of Florida, for review and approval. The Temporary Traffic Control Plan(s) submitted shall conform with FDOT Standard Specification Section 102. The CONTRACTOR shall provide a Worksite Traffic Supervisor, per FDOT Standard Specification Section 102-3.2, who will be responsible for initiating, installing, and maintaining all traffic control devices as described in these Contract Specifications and Contract Plans and as described in FDOT Standard Specification Section 102.