Attachment A -NUWC B47CC Warehouse Opt - IFC - Specifications_signed (1).pdf
PDF 14 MB Posted
- Solicitation number
- N4008526R0234
About this file
This is a specifications document and drawing list for a Design-Bid-Build construction project to optimize Building 47CC Warehouse at Naval Station Newport, Rhode Island. The project is issued for construction in July 2026 under A/E Contract No. N4008524D0047 and Task Order No. N4008525F1030. The specifications cover comprehensive warehouse renovation work including replacement of the fire alarm and mass notification systems with a new combined addressable system; replacement of the existing dry pipe sprinkler system with wet-pipe ESFR sprinklers and installation of a new fire pump room; installation of central emergency inverters in each bay for emergency lighting; addition of ventilation units and air curtains on overhead doors; creation of an opening in the CMU wall in Bay A for access to unoccupied space; and removal of existing two-story office space and restrooms in Bay A. The project includes four bid options: Option 1 covers material handling equipment and storage racking for Bay A and B disposal and receiving operations; Option 2 addresses removal and construction of new two-story office space in Bay B with renovations to existing office spaces and restroom upgrades in Bay C; Option 3 includes material handling equipment and double deep storage racking for Bay C; and Option 4 involves relocation of the server room in Bay D and installation of mobile racking systems.
The project requires an 8.5-hour work day between 7 a.m. and 3:30 p.m. excluding government holidays, with the building remaining occupied and operational throughout construction. The contractor must submit phasing and dust control plans for approval by NAVFAC CM and NUWC prior to work commencement. Key submittals include a cost-loaded Network Analysis Schedule (NAS) using Oracle Primavera P6, weekly three-week look-ahead schedules, monthly NAS updates, a designated project scheduler, a project superintendent with minimum 10 years experience and NICET Level I fire alarm certification, a quality control manager, and a site safety and health officer. All technical documents must be submitted through NAVFAC's Electronic Construction and Facility Support Contract Management System (eCMS). The contractor must obtain DBIDS credentials for all personnel, provide a salvage plan for designated government materials, and maintain compliance with environmental controls, waste management, and building commissioning requirements. Construction drawings total over 200 sheets covering civil, structural, architectural, fire protection, plumbing, mechanical, and electrical systems.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Prepared for:
NAVFAC MID-ATLANTIC
9324 VIRGINIA AVENUE
BUILDING Z140
NORFOLK VA 23511-3095
Building 47CC Warehouse Optimization
Naval Undersea Warfare Center
Naval Station Newport, Newport, Rhode Island
A/E Contract No.: N4008524D0047 Task Order No.: N4008525F1030 e-Projects No.: 1814702
Specifications
Issued for Construction Design Bid Build
July 2026
NUWC B47 Warehouse ISSUED FOR CONSTRUCTION
NAVAL STATION NEWPORT JULY 2026
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15 02/24 LIST OF DRAWINGS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 02/24 SUMMARY OF WORK
01 14 00 11/22, CHG 2: 05/24 WORK RESTRICTIONS
01 20 00 11/20, CHG 3: 02/23 PRICE AND PAYMENT PROCEDURES
01 30 00 11/20, CHG 3: 08/23 ADMINISTRATIVE REQUIREMENTS
01 31 23.13 20 08/23, CHG 1: 02/24 ELECTRONIC CONSTRUCTION AND FACILITY
SUPPORT CONTRACT MANAGEMENT SYSTEM
(eCMS)
01 32 17.00 20 05/25 COST-LOADED NETWORK ANALYSIS SCHEDULES
(NAS)
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 33 29 02/21, CHG 1: 08/25 SUSTAINABILITY REQUIREMENTS AND
REPORTING
01 35 26 05/24 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 05/24 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 08/23, CHG 1: 05/24 QUALITY CONTROL
01 45 35 05/24 SPECIAL INSPECTIONS
01 50 00 11/20, CHG 3: 08/24 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19 08/22 TEMPORARY ENVIRONMENTAL CONTROLS
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS
01 78 23 05/23 OPERATION AND MAINTENANCE DATA
01 78 24.00 20 05/23, CHG 1: 11/23 FACILITY DATA WORKBOOK (FDW)
01 91 00.15 05/23, CHG 3: 08/24 BUILDING COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 41 00 08/22 DECONSTRUCTION
02 82 00 08/25 ASBESTOS REMEDIATION
02 83 00 08/25 LEAD REMEDIATION
DIVISION 03 - CONCRETE
03 01 00 02/18 REHABILITATION OF CONCRETE: FLOOR
LEVELING
03 30 00 02/19, CHG 10: 08/25 CAST-IN-PLACE CONCRETE
03 45 33 05/16, CHG 1: 11/21 PRECAST STRUCTURAL CONCRETE
DIVISION 04 - MASONRY
04 20 00 05/25 UNIT MASONRY
DIVISION 05 - METALS
05 05 20 05/22, CHG 1: 08/24 POST-INSTALLED CONCRETE AND MASONRY
ANCHORS
05 05 23.13 10 08/18 ULTRASONIC INSPECTION OF WELDMENTS
05 12 00 08/18, CHG 2: 05/21 STRUCTURAL STEEL
05 21 00 05/15, CHG 1: 08/18 STEEL JOIST FRAMING
05 30 00 05/15, CHG 2: 08/18 STEEL DECKS
PROJECT TABLE OF CONTENTS Page 1
For Commander
NAVFAC:
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15 02/24 LIST OF DRAWINGS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 02/24 SUMMARY OF WORK
01 14 00 11/22, CHG 2: 05/24 WORK RESTRICTIONS
01 20 00 11/20, CHG 3: 02/23 PRICE AND PAYMENT PROCEDURES
01 30 00 11/20, CHG 3: 08/23 ADMINISTRATIVE REQUIREMENTS
01 31 23.13 20 08/23, CHG 1: 02/24 ELECTRONIC CONSTRUCTION AND FACILITY
SUPPORT CONTRACT MANAGEMENT SYSTEM
(eCMS)
01 32 17.00 20 05/25 COST-LOADED NETWORK ANALYSIS SCHEDULES
(NAS)
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 33 29 02/21, CHG 1: 08/25 SUSTAINABILITY REQUIREMENTS AND
REPORTING
01 35 26 05/24 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 05/24 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 08/23, CHG 1: 05/24 QUALITY CONTROL
01 45 35 05/24 SPECIAL INSPECTIONS
01 50 00 11/20, CHG 3: 08/24 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19 08/22 TEMPORARY ENVIRONMENTAL CONTROLS
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS
01 78 23 05/23 OPERATION AND MAINTENANCE DATA
01 78 24.00 20 05/23, CHG 1: 11/23 FACILITY DATA WORKBOOK (FDW)
01 91 00.15 05/23, CHG 3: 08/24 BUILDING COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 41 00 08/22 DECONSTRUCTION
02 82 00 08/25 ASBESTOS REMEDIATION
02 83 00 08/25 LEAD REMEDIATION
DIVISION 03 - CONCRETE
03 01 00 02/18 REHABILITATION OF CONCRETE: FLOOR
LEVELING
03 30 00 02/19, CHG 10: 08/25 CAST-IN-PLACE CONCRETE
03 45 33 05/16, CHG 1: 11/21 PRECAST STRUCTURAL CONCRETE
DIVISION 04 - MASONRY
04 20 00 05/25 UNIT MASONRY
DIVISION 05 - METALS
05 05 20 05/22, CHG 1: 08/24 POST-INSTALLED CONCRETE AND MASONRY
ANCHORS
05 05 23.13 10 08/18 ULTRASONIC INSPECTION OF WELDMENTS
05 12 00 08/18, CHG 2: 05/21 STRUCTURAL STEEL
05 21 00 05/15, CHG 1: 08/18 STEEL JOIST FRAMING
05 30 00 05/15, CHG 2: 08/18 STEEL DECKS
PROJECT TABLE OF CONTENTS Page 1
05 40 00 05/15, CHG 1: 08/18 COLD-FORMED METAL FRAMING
05 50 13 08/24, CHG 1: 08/25 MISCELLANEOUS METAL FABRICATIONS
05 51 00 08/23 METAL STAIRS
05 52 00 08/23 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 08/16, CHG 3: 05/25 ROUGH CARPENTRY
06 41 16.00 10 08/25 PLASTIC-LAMINATE-CLAD ARCHITECTURAL
CABINETS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 53 23 08/25 ETHYLENE-PROPYLENE-DIENE-MONOMER
ROOFING
07 60 00 08/23, CHG 1: 05/25 FLASHING AND SHEET METAL
07 84 00.00 22 07/24 FIRESTOPPING
07 92 00 08/23 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 08/20, CHG 1: 08/25 STEEL DOORS AND FRAMES
08 33 23 08/20, CHG 2: 02/26 OVERHEAD COILING DOORS
08 71 00 02/16, CHG 4: 02/22 DOOR HARDWARE
08 81 00 05/19 GLAZING
DIVISION 09 - FINISHES
09 22 00 08/24 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 08/24, CHG 1: 05/25 GYPSUM BOARD
09 30 10 08/20 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 08/20 ACOUSTICAL CEILINGS
09 65 00 11/24 RESILIENT FLOORING
09 68 00 11/24 CARPETING
09 90 00 02/21 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 14 00.20 08/20 INTERIOR SIGNAGE
10 21 13 08/20 TOILET COMPARTMENTS
10 28 13 08/20 TOILET ACCESSORIES
10 44 16 11/19 FIRE EXTINGUISHERS
10 56 13.01 08/24 SELECTIVE & DOUBLE DEEP PALLET RACKING
10 56 13.03 08/24 MOBILE PALLET RACKING
10 56 13.04 08/24 CANTILEVER RACKING
10 56 13.05 08/24 CASE STOCK RACKING
10 56 13.06 08/24 STAND-UP COUNTERBALANCE FORKLIFT
10 56 13.07 08/24 2 Deep Reach Truck
10 56 13.08 08/24 4-DIRECTIONAL FORKLIFT
10 56 13.09 08/24 ORDER PICKER
DIVISION 21 - FIRE SUPPRESSION
21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE
PROTECTION
21 13 16 08/20 DRY PIPE SPRINKLER SYSTEMS, FIRE
PROTECTION
21 30 00 04/08, CHG 1: 08/13 FIRE PUMPS
PROJECT TABLE OF CONTENTS Page 2
DIVISION 22 - PLUMBING
22 00 00 05/24, CHG 1: 11/24 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 03 00 11/25 BASIC MECHANICAL MATERIALS AND METHODS
23 05 15 05/22, CHG 2: 08/24 COMMON PIPING FOR HVAC
23 05 93 05/25 TESTING, ADJUSTING, AND BALANCING FOR
HVAC
23 07 00 08/24 THERMAL INSULATION FOR MECHANICAL
SYSTEMS
23 09 00 08/24, CHG 1: 08/25 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 11/15, CHG 2: 05/21 INSTRUMENTATION AND CONTROL DEVICES
FOR HVAC
23 09 23.02 08/24 BACNET DIRECT DIGITAL CONTROL FOR HVAC
AND OTHER BUILDING CONTROL SYSTEMS
23 22 26.00 20 02/10, CHG 1: 05/15 STEAM SYSTEM AND TERMINAL UNITS
23 23 00 08/21 REFRIGERANT PIPING
23 30 00 02/25 HVAC AIR DISTRIBUTION
23 72 00 05/24 ENERGY RECOVERY SYSTEMS
23 81 23 11/20 COMPUTER ROOM AIR CONDITIONING UNITS
23 82 00.00 20 02/16, CHG 1: 08/18 TERMINAL HEATING UNITS
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11.01 08/24 CYBERSECURITY FOR HVAC CONTROL SYSTEMS
25 05 11.02 08/24 CYBERSECURITY FOR FIRE AND LIFE SAFETY
CONTROL SYSTEMS
25 05 11.03 08/24 CYBERSECURITY FOR SMART WAREHOUSE
CONTROL SYSTEMS
DIVISION 26 - ELECTRICAL
26 05 73 08/23 POWER SYSTEM STUDIES
26 12 19 05/24 PAD-MOUNTED, LIQUID-FILLED,
MEDIUM-VOLTAGE TRANSFORMERS
26 20 00 08/23 INTERIOR DISTRIBUTION SYSTEM
26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING
SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 08/20 INTERIOR FIRE ALARM AND MASS
NOTIFICATION SYSTEM, ADDRESSABLE
DIVISION 31 - EARTHWORK
31 00 00 08/23 EARTHWORK
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 11 26 05/20 HOT-MIX BITUMINOUS BASE COURSE FOR
ROADS AND STREETS
32 12 13 05/24 BITUMINOUS TACK AND PRIME COATS
PROJECT TABLE OF CONTENTS Page 3
32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING
32 92 19 08/17, CHG 1: 08/21 SEEDING
DIVISION 33 - UTILITIES
33 11 00 08/24 WATER UTILITY DISTRIBUTION PIPING
33 30 00 05/18 SANITARY SEWERAGE
33 71 01 05/19, CHG 1: 11/19 OVERHEAD TRANSMISSION AND DISTRIBUTION
33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 4
DOCUMENT 00 01 15
LIST OF DRAWINGS
02/24
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
DRAWING NUMBER NAFVAC DRAWING
NUMBER
NAVSTA NUMBER TITLE
G-001 12948765 51000-437 COVER SHEET
G-002 12948766 51001-437 SHEET INDEX
G-101 12948767 51002-437 SITE ACCESS AND
LAYDOWN PLAN
G-102 12948768 51003-437 OVERALL PHASING PLAN
G-103 12948769 51004-437 PHASE 1 PLAN
G-104 12948770 51005-437 PHASE 2 PLAN
G-105 12948771 51006-437 PHASE 3 PLAN
G-106 12948772 51007-437 PHASE 4 PLAN
LS001 12948773 51008-437 LIFE SAFETY SUMMARY
LS101 12948774 51009-437 FIRST FLOOR LIFE
SAFETY PLAN - NORTH
LS102 12948775 51010-437 FIRST FLOOR LIFE
SAFETY PLAN - SOUTH
LS103 12948776 51011-437 MEZZANINE LIFE
SAFETY PLAN - NORTH
LS104 12948777 51012-437 MEZZANINE LIFE
SAFETY PLAN - SOUTH
LS105 12948778 51013-437 OCCUPANCY PLAN -
NORTH
LS106 12948779 51014-437 OCCUPANCY PLAN -
SOUTH
DOCUMENT 00 01 15 Page 1
LS107 12948780 51015-437 LIFE SAFETY PLAN
C-001 12948781 51016-437 CIVIL GENERAL NOTES
CJ101 12948782 51017-437 EXISITNG CONDITIONS
PLAN
CD101 12948783 51018-437 DEMOLITION PLAN
C-101 12948784 51019-437 SITE LAYOUT AND
UTILITY PLAN
C-401 12948785 51020-437 ENLARGED SITE
LAYOUT AND UTILITY
PLAN
C-402 12948786 51021-437 SITE GRADING PLAN
C-403 12948787 51022-437 EROSION AND
SEDIMENTATION
CONTROL PLAN
C-501 12948788 51023-437 EROSION AND
SEDIMENTATION
CONTROL NOTES AND
DETAILS
C-502 12948789 51024-437 CIVIL CONSTRUCTION
AND UTILITY DETAILS
(1 OF 2)
C-503 12948790 51025-437 CIVIL CONSTRUCTION
AND UTILITY DETAILS
(2 OF 2)
S-001 12948791 51026-437 GENERAL NOTES &
ABBREVIATIONS
S-002 12948792 51027-437 GENERAL NOTES
S-003 12948793 51028-437 GENERAL NOTES
SD101 12948794 51029-437 FIRST FLOOR PLAN
DEMOLITION - NORTH
SD102 12948795 51030-437 FIRST FLOOR PLAN
DEMOLITION - SOUTH
S-101 12948796 51031-437 FIRST FLOOR PLAN -
NORTH
S-102 12948797 51032-437 FIRST FLOOR PLAN -
SOUTH
S-401 12948798 51033-437 ENLARGED FRAMING
PLANS
S-501 12948799 51034-437 STRUCTURAL DETAILS
S-502 12948800 51035-437 STRUCTURAL DETAILS
S-503 12948801 51036-437 MISC. STRUCTURAL
STEEL DETAILS
DOCUMENT 00 01 15 Page 2
H-101 12948802 51037-437 FIRST FLOOR
HAZARDOUS MATERIALS
PLAN
H-102 12948803 51038-437 SECOND FLOOR
HAZARDOUS MATERIALS
PLAN
A-001 12948804 51039-437 GENERAL NOTES,
ABBREVIATIONS AND
LEGENDS
A-002 12948805 51040-437 TYPICAL MOUNTING
HEIGHTS AND
CLEARANCES
A-003 12948806 51041-437 TYPICAL MOUNTING
HEIGHTS AND
CLEARANCES CONT.
AD101 12948807 51042-437 FIRST FLOOR
DEMOLITION PLAN -
NORTH
AD102 12948808 51043-437 FIRST FLOOR
DEMOLITION PLAN -
SOUTH
AD111 12948809 51044-437 FIRST FLOOR
REFLECTED CEILING
DEMOLITION PLAN -
NORTH
AD112 12948810 51045-437 FIRST FLOOR
REFLECTED CEILING
DEMOLITION PLAN -
SOUTH
AD401 12948811 51046-437 ENLARGED DEMOLITION
PLANS
A-101 12948812 51047-437 FIRST FLOOR PLAN -
NORTH
A-102 12948813 51048-437 FIRST FLOOR PLAN -
SOUTH
A-103 12948814 51049-437 ROOF PLAN - NORTH
A-104 12948815 51050-437 ROOF PLAN - SOUTH
A-111 12948816 51051-437 FIRST FLOOR
REFLECTED CEILING
PLAN - NORTH
A-112 12948817 51052-437 FIRST FLOOR
REFLECTED CEILING
PLAN - SOUTH
A-301 12948818 51053-437 BUILDING SECTION
A-401 12948819 51054-437 ENLARGED FIRST
FLOOR PLANS
A-402 12948820 51055-437 ENLARGED MEZZANINE
PLANS
A-403 12948821 51056-437 STAIR PLANS,
SECTIONS AND DETAILS
DOCUMENT 00 01 15 Page 3
A-404 12948822 51057-437 ENLARGED BREAK ROOM
CASEWORK PLANS AND
ELEVATIONS
A-501 12948823 51058-437 PARTITION TYPES
A-502 12948824 51059-437 DETAILS
A-601 12948825 51060-437 ROOM FINISH
SCHEDULE AND DETAILS
A-602 12948826 51061-437 DOOR AND WINDOW
SCHEDULES AND
DRAWINGS
A-603 12948827 51062-437 DOOR AND WINDOW
DETAILS
FP001 12948828 51063-437 FIRE PROTECTION
GENERAL NOTES,
LEGENDS, AND
ABBREVIATIONS
FD101 12948829 51064-437 FIRST FLOOR FIRE
PROTECTION
DEMOLITION PART PLAN
FD102 12948830 51065-437 FIRST FLOOR FIRE
PROTECTION
DEMOLITION PART PLAN
FP101 12948831 51066-437 FIRST FLOOR FIRE
PROTECTION PART PLAN
FP102 12948832 51067-437 FIRST FLOOR FIRE
PROTECTION PART PLAN
FP401 12948833 51068-437 FIRE PROTECTION
ENLARGED PLANS
FP501 12948834 51069-437 FIRE PUMP DETAILS
FA001 12948835 51070-437 FIRE ALARM GENERAL
NOTES, LEGENDS AND
ABBREVIATIONS
FA101 12948836 51071-437 FIRST FLOOR FIRE
ALARM DEMOLITION
PART PLAN
FA102 12948837 51072-437 FIRST FLOOR FIRE
ALARM DEMOLITION
PART PLAN
FA103 12948838 51073-437 FIRST FLOOR FIRE
ALARM DEMOLITION
PART PLAN
FA104 12948839 51074-437 FIRST FLOOR FIRE
ALARM DEMOLITION
PART PLAN
DOCUMENT 00 01 15 Page 4
FA105 12948840 51075-437 FIRST FLOOR FIRE
ALARM DEMOLITION
PART PLAN
FA106 12948841 51076-437 FIRST FLOOR FIRE
ALARM DEMOLITION
PART PLAN
FA107 12948842 51077-437 FIRST FLOOR FIRE
ALARM DEMOLITION
PART PLAN
FA108 12948843 51078-437 FIRST FLOOR FIRE
ALARM DEMOLITION
PART PLAN
FA109 12948844 51079-437 FIRST FLOOR FIRE
ALARM DEMOLITION
PART PLAN
FA110 12948845 51080-437 FIRST FLOOR FIRE
ALARM DEMOLITION
PART PLAN
FA111 12948846 51081-437 FIRST FLOOR FIRE
ALARM PART PLAN
FA112 12948847 51082-437 FIRST FLOOR FIRE
ALARM PART PLAN
FA113 12948848 51083-437 FIRST FLOOR FIRE
ALARM PART PLAN
FA114 12948849 51084-437 FIRST FLOOR FIRE
ALARM PART PLAN
FA115 12948850 51085-437 FIRST FLOOR FIRE
ALARM PART PLAN
FA116 12948851 51086-437 FIRST FLOOR FIRE
ALARM PART PLAN
FA117 12948852 51087-437 FIRST FLOOR FIRE
ALARM PART PLAN
FA118 12948853 51088-437 FIRST FLOOR FIRE
ALARM PART PLAN
FA119 12948854 51089-437 FIRST FLOOR FIRE
ALARM PART PLAN
FA120 12948855 51090-437 FIRST FLOOR FIRE
ALARM PART PLAN
FA401 12948856 51091-437 FIRE ALARM ENLARGED
PLANS
FA501 12948857 51092-437 FIRE ALARM DETAILS
FA502 12948858 51093-437 FIRE ALARM RISER
DETAIL
P-001 12948859 51094-437 LEGEND,
ABBREVIATIONS AND
GENERAL NOTES
PD101 12948860 51095-437 FIRST FLOOR
PLUMBING DEMOLITION
PLAN - NORTH
DOCUMENT 00 01 15 Page 5
PD102 12948861 51096-437 FIRST FLOOR
PLUMBING DEMOLITION
PLAN - SOUTH
P-101 12948862 51097-437 FIRST FLOOR
PLUMBING PLAN -
NORTH
P-102 12948863 51098-437 FIRST FLOOR
PLUMBING PLAN -
SOUTH
P-401 12948864 51099-437 PLUMBING ENLARGED
PLANS
P-501 12948865 51100-437 PLUMBING DETAILS
P-601 12948866 51101-437 PLUMBING SCHEDULES
M-001 12948867 51102-437 LEGEND,
ABBREVIATIONS AND
GENERAL NOTES
MD101 12948868 51103-437 FIRST FLOOR
MECHANICAL
DEMOLITION PLAN
MD102 12948869 51104-437 FIRST FLOOR
MECHANICAL
DEMOLITION PLAN
MD103 12948870 51105-437 FIRST FLOOR
MECHANICAL
DEMOLITION PLAN
MD104 12948871 51106-437 FIRST FLOOR
MECHANICAL
DEMOLITION PLAN
MD105 12948872 51107-437 FIRST FLOOR
MECHANICAL
DEMOLITION PLAN
MD106 12948873 51108-437 FIRST FLOOR
MECHANICAL
DEMOLITION PLAN
MD107 12948874 51109-437 FIRST FLOOR
MECHANICAL
DEMOLITION PLAN
MD111 12948875 51110-437 ROOF DEMOLITION
PLAN - NORTH
M-101 12948876 51111-437 FIRST FLOOR
MECHANICAL PLAN
M-102 12948877 51112-437 FIRST FLOOR
MECHANICAL PLAN
M-103 12948878 51113-437 FIRST FLOOR
MECHANICAL PLAN
M-104 12948879 51114-437 FIRST FLOOR
MECHANICAL PLAN
M-105 12948880 51115-437 FIRST FLOOR
MECHANICAL PLAN
M-106 12948881 51116-437 FIRST FLOOR
MECHANICAL PLAN
DOCUMENT 00 01 15 Page 6
M-107 12948882 51117-437 FIRST FLOOR
MECHANICAL PLAN
M-108 12948883 51118-437 FIRST FLOOR
MECHANICAL PLAN
M-109 12948884 51119-437 FIRST FLOOR
MECHANICAL PLAN
M-110 12948885 51120-437 FIRST FLOOR
MECHANICAL PLAN
M-111 12948886 51121-437 ROOF PLAN - NORTH
M-112 12948887 51122-437 ROOF PLAN - SOUTH
M-401 12948888 51123-437 SECOND FLOOR
ENLARGED PLANS
M-501 12948889 51124-437 MECHANICAL DETAILS
M-502 12948890 51125-437 MECHANICAL DETAILS
M-601 12948891 51126-437 MECHANICAL SCHEDULES
M-602 12948892 51127-437 MECHANICAL SCHEDULES
M-701 12948893 51128-437 MECHANICAL SEQUENCES
M-702 12948894 51129-437 MECHANICAL SEQUENCES
M-703 12948895 51130-437 MECHANICAL SEQUENCES
E-001 12948896 51131-437 ELECTRICAL LEGEND
ABBREVIATIONS AND
GENERAL NOTES
ED101 12948897 51132-437 FIRST FLOOR
ELECTRICAL
DEMOLITION PART PLAN
ED102 12948898 51133-437 FIRST FLOOR
ELECTRICAL
DEMOLITION PART PLAN
ED103 12948899 51134-437 FIRST FLOOR
ELECTRICAL
DEMOLITION PART PLAN
ED104 12948900 51135-437 FIRST FLOOR
ELECTRICAL
DEMOLITION PART PLAN
ED105 12948901 51136-437 FIRST FLOOR
ELECTRICAL
DEMOLITION PART PLAN
DOCUMENT 00 01 15 Page 7
ED106 12948902 51137-437 FIRST FLOOR
ELECTRICAL
DEMOLITION PART PLAN
ED107 12948903 51138-437 FIRST FLOOR
ELECTRICAL
DEMOLITION PART PLAN
ED108 12948904 51139-437 FIRST FLOOR
ELECTRICAL
DEMOLITION PART PLAN
ED109 12948905 51140-437 FIRST FLOOR
ELECTRICAL
DEMOLITION PART PLAN
ED110 12948906 51141-437 FIRST FLOOR
ELECTRICAL
DEMOLITION PART PLAN
ED111 12948907 51142-437 ROOF ELECTRICAL
DEMOLITION PART PLAN
E-101 12948908 51143-437 FIRST FLOOR
ELECTRICAL PART PLAN
E-102 12948909 51144-437 FIRST FLOOR
ELECTRICAL PART PLAN
E-103 12948910 51145-437 FIRST FLOOR
ELECTRICAL PART PLAN
E-104 12948911 51146-437 FIRST FLOOR
ELECTRICAL PART PLAN
E-105 12948912 51147-437 FIRST FLOOR
ELECTRICAL PART PLAN
E-106 12948913 51148-437 FIRST FLOOR
ELECTRICAL PART PLAN
E-107 12948914 51149-437 FIRST FLOOR
ELECTRICAL PART PLAN
E-108 12948915 51150-437 FIRST FLOOR
ELECTRICAL PART PLAN
E-109 12948916 51151-437 FIRST FLOOR
ELECTRICAL PART PLAN
E-110 12948917 51152-437 FIRST FLOOR
ELECTRICAL PART PLAN
DOCUMENT 00 01 15 Page 8
E-111 12948918 51153-437 ROOF ELECTRICAL
PART PLAN
E-112 12948919 51154-437 ROOF ELECTRICAL
PART PLAN
EL101 12948920 51155-437 FIRST FLOOR
ELECTRICAL LIGHTING
PART PLAN
EL102 12948921 51156-437 FIRST FLOOR
ELECTRICAL LIGHTING
PART PLAN
EL103 12948922 51157-437 FIRST FLOOR
ELECTRICAL LIGHTING
PART PLAN
EL104 12948923 51158-437 FIRST FLOOR
ELECTRICAL LIGHTING
PART PLAN
EL105 12948924 51159-437 FIRST FLOOR
ELECTRICAL LIGHTING
PART PLAN
EL106 12948925 51160-437 FIRST FLOOR
ELECTRICAL LIGHTING
PART PLAN
EL107 12948926 51161-437 FIRST FLOOR
ELECTRICAL LIGHTING
PART PLAN
EL108 12948927 51162-437 FIRST FLOOR
ELECTRICAL LIGHTING
PART PLAN
EL109 12948928 51163-437 FIRST FLOOR
ELECTRICAL LIGHTING
PART PLAN
EL110 12948929 51164-437 FIRST FLOOR
ELECTRICAL LIGHTING
PART PLAN
E-401 12948930 51165-437 ENLARGED SECOND
FLOOR PLANS
E-501 12948931 51166-437 DIAGRAM -
DEMOLITION SERVICE
#1 ONE-LINE
E-502 12948932 51167-437 DIAGRAM - NEW WORK
SERVICE #1 AND #2
ONE-LINE
E-503 12948933 51168-437 DETAILS - TYPICAL
POLE RISER AND
GROUNDING
E-504 12948934 51169-437 DIAGRAMS - LIGHTING
INVERTER BAYS A-D
E-601 12948935 51170-437 SCHEDULES -
LIGHTING FIXTURES
AND CONTROLS
SEQUENCE
DOCUMENT 00 01 15 Page 9
E-602 12948936 51171-437 SCHEDULES -
EXISTING PANELS A &
E
E-603 12948937 51172-437 SCHEDULES -
EXISTING PANELS K &
P-000
E-604 12948938 51173-437 SCHEDULES -
EXISTING PANELS P1
& PP1
E-605 12948939 51174-437 SCHEDULES -
EXISTING PANELS
PP21 & RP2
E-606 12948940 51175-437 SCHEDULES -
EXISTING PANELS TPP
BAY B & D, NEW
PANEL FA
E-607 12948941 51176-437 SCHEDULES - NEW
PANELS LP1 & LP2
E-608 12948942 51177-437 SCHEDULES - NEW
PANELS PP1B & RP1
E-609 12948943 51178-437 SCHEDULES -
EXISTING PANEL P2
Q-101 12948944 51179-437 OVERALL FIRST FLOOR
PLAN
Q-102 12948945 51180-437 FIRST FLOOR PLAN -
NORTH
Q-103 12948946 51181-437 FIRST FLOOR PLAN -
BAY C
Q-104 12948947 51182-437 FIRST FLOOR PLAN -
BAY D
Q-201 12948948 51183-437 DOUBLE DEEP PALLET
RACKING ELEVATIONS
Q-202 12948949 51184-437 SELECTIVE PALLET
RACKING ELEVATIONS
Q-203 12948950 51185-437 MOBILE PALLET
RACKING & BIN RACKS
ELEVATIONS
Q-204 12948951 51186-437 CANTILEVER RACKING
ELEVATIONS
-- End of Document --
DOCUMENT 00 01 15 Page 10
SECTION 01 11 00
SUMMARY OF WORK
02/24
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Salvage Plan ; G
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The project will replace the existing fire alarm and mass notification systems with a new combined addressable fire alarm and mass notification system. The existing systems will remain in place and active until the new system has finished final acceptance testing.
The existing dry pipe sprinkler system will be replaced with a wet-pipe sprinkler systems utilizing ESFR (Early Suppression Fast Response) sprinklers. A fire pump room will be installed to serve the building sprinkler systems. The fire doors separating the Bays B and bay C will be replaced.
New central emergency inverters will be installed in each bay to provide one or several branch circuits with emergency power. This will address the emergecny lighting in the warehouse.
Venational units will be installed in each bay of the warehouse to bring in more outside air. Air currents will be installed on the overhead doors that are primarily used to better maintain the interior warehouse temperature.
An opening will be installed in the CMU wall in Bay A to give access to the currently unoccupied space. The unoccupied space will be renovated to meet the needs of the warehouse operations and will provide additional office and laydown space.
The existing two story office space and the restroom in Bay A will be removed to allow for more laydown space for the warehouse operations.
Bid Option 1 includes the material handling equipment and storage racking for the Bay A and Bay B disposal, small parts, and receiving operations.
Bid Option 2 includes removal of the existing office space on the exterior wall of Bay B and construct a new two story office space. The existing office space on the bay b and bay c wall will get renovated to provide additional cooling for the server room and some walls will be removed to improve the office space usage. Renovation of the existing restrooms in Bay C. The break room and office space in Bay C will be combined into a
SECTION 01 11 00 Page 1 two story facility.
Bid Option 3 includes material handling equipment and double deep storage racking for Bay C.
Bid Option 4 includes relocation of the server room in Bay D to allow for the drive lane to be opened. Bay D will be installed with mobile racking system.
1.2.2 Location
The work is located at the Building 47 at the Naval Undersea Warefare Center Division Newport(NUWC)at the Newport Naval Station, Newport, RI, approximately as indicated. The exact location will be shown by the Contracting Officer.
1.3 OCCUPANCY OF PREMISES
Thebuilding will be occupied during performance of work under this Contract.
Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways. Provide Phasing Plan and Dust Control plan prior to start of work, these must be approved by the NAVFAC CM and NUWC prior to start of work.
1.4 EXISTING WORK
Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.5 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits (including Dig Safe approval) prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities. Contact local utility locating service a minimum of 48 hoursprior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday.
Verify existing utility locations indicated on contract drawings, within area of work.
Identify and mark all other utilities not managed and located by the local utility companies. The Contractor must hire a private utility company for locating all utilities for the work area. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities,and any type of underground obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work
SECTION 01 11 00 Page 2 closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.5.1 Notification Prior to Excavation
Notify the Contracting Officer at least 15 days prior to starting excavation work. 1.6 NAVY AND MARINE CORPS INTRANET (NMCI) COORDINATION
REQUIREMENTS
1.6.1 NMCI Contractor Access
Allow the NMCI Contractor access to the facility towards the end of construction (finishes 90 percent complete, rough-in 100 percent complete, Inside Plant (ISP)/Outside Plant (OSP) infrastructure in place) to provide equipment in the telecommunications rooms and make final connections.
Coordinate efforts with the NMCI Contractor to facilitate joint use of building spaces during the final phases of construction. After the Contracting Officer has facilitated coordination meetings between the two contractors, within one week, incorporate the effort of additional coordination with the NMCI Contractor into the construction schedule to demonstrate a plan for maintaining the contract duration.
1.7 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property within the building to the Contracting Officer for receipt.
Provide a salvage plan , listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Provide a system for property control in the salvage plan. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 3
SECTION 01 14 00
WORK RESTRICTIONS
11/22, CHG 2: 05/24
PART 1 GENERAL
1.1 SPECIAL SCHEDULING REQUIREMENTS
a. The Building 47 Warehouse is an active warehouse and will maintain continuous operation throughout the completion of this project.
Accordingly, the KTR shall not interfere with operations or impede access. Access to emergency response vessels and the ability to go underway shall be continuously maintained.
b. The KTR shall be responsible for obtaining approval to begin in coordination with the COR.
c. The KTR shall have all materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.
d. Areas of the facility not under construction shall remain in operation during construction. Keep all construction activities and personnel clear of facility operations.
e. Permission to interrupt any activity roads, parking areas, storage areas, access, and/or utility service shall be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
f. The KTR shall identify on the construction schedule each factor which constitutes a potential interruption to Unit operations.
g. The KTR shall be responsible for issuing the pre- and post-construction notifications required by the State and Federal Permits.
h. The project requires specific phasing and sequencing requirements to maintain the operations throughout all construction activities. Refer to the phasing requirements in this section and the phasing drawings for additional information.
1.2 Submittals
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Phasing Plan ; G
List of Contact Personnel
Dust Control Plan ; G
1.3 SPECIAL SCHEDULING REQUIREMENTS
a. The building will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.
b. Permission to interrupt any Activity roads, railroads, or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
SECTION 01 14 00 Page 1
c. The work under this contract requires special attention to the scheduling and conduct of the work in connection with existing operations. Identify on the construction schedule each factor which constitutes a potential interruption to operations.
1.4 PROJECT PHASING REQUIREMENTS
The project shall be phased to maintain operations throughout the project duration. The work shall be sequenced and scheduled to minimize the impacts to operations and system outages.
A phasing plan is included in the drawings which identifies the overall sequencing of events and allowable areas to be accessed during each phase of work as well as schedule restrictions. The Contractor must submit a phasing plan indentifying the proposed approach indicating the proposed approach including sequences within each phase to to complete the project requirements. The phasing plan must be approved by NAVFAC CM and NUWC prior to start of work.
The phasing plan must be revised and resubmitted for bid options that are executed throughout the duration of the project.
1.5 CONTRACTOR ACCESS AND USE OF PREMISES
1.5.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, include delivery vehicles, are clearly identified with their company name.
1.5.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.5.1.2 Additional Personnel Requirements
1.5.1.2.1 General Construction and Finish Work
General construction and finish work must be performed by U.S. firms using U.S. citizens. General construction includes construction activities such as building sitework, utilities, foundations, structure, and enclosure or shell, including doors, windows and façade work. Finish Work includes construction activities such as insulation, floor, partition, and ceiling systems; cabinet work; conveyor systems; specialties; building furnishings, fixtures, and equipment; and mechanical and electrical services and equipment including those specialized for fire protection, security, communication, control, energy conservation, safety, comfort, convenience, and similar purposes.
1.5.1.3 Installation Access
Obtain access to Navy installations through participation in the Defense
SECTION 01 14 00 Page 2
Biometrics Identification System (DBIDS). Requirements for Contractor employee registration, and transition for employees currently under Navy Commercial Access Control System (NCACS), are available at https://www.cnic.navy.mil/Operations-and-Management/Base-Support/DBIDS/ .
No fees are associated with obtaining a DBIDS credential.
1.5.1.3.1 Registration for DBIDS
Registration for DBIDS is available at https://www.cnic.navy.mil/Operations-and-Management/Base-Support/DBIDS/ .
Procedure includes:
a. Present a letter or official award document (i.e. DD Form 1155 or SF 1442) from the Contracting Officer, that provides the purpose for access, to the base Visitor Control Center representative.
b. Present valid identification, such as a passport or Real ID Act-compliant state driver's license.
c. Provide completed SECNAV FORM 5512/1 to the base Visitor Control Center representative to obtain a background check. This form is available for download at https://www.cnic.navy.mil/Operations-and-Management/Base-Support/DBIDS/ .
d. Upon successful completion of the background check, the Government will complete the DBIDS enrollment process, which includes Contractor employee photo, fingerprints, base restriction and several other assessments.
e. Upon successful completion of the enrollment process, the Contractor employee will be issued a DBIDS credential, and will be allowed to proceed to worksite.
1.5.1.3.2 DBIDS Eligibility Requirements
Throughout the length of the contract, the Contractor employee must continue to meet background screen standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.
An adjudication process may be initiated when a background screen failure results in disqualification from participation in the DBIDS, and Contractor employee does not agree with the reason for disqualification.
The Government is the final authority.
1.5.1.3.3 DBIDS Notification Requirements
a. Immediately report instances of lost or stolen badges to the Contracting Officer.
b. Immediately collect DBIDS credentials and notify the Contracting Officer in writing under the following circumstances:
(1) An employee has departed the company without having properly returned or surrendered their DBIDS credentials.
SECTION 01 14 00 Page 3
(2) There is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the Installation or anyone therein.
1.5.1.4 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.5.2 Working Hours
Regular working hours will consist of an 8 1/2 hour between 7 a.m. and 3:30 p.m., excluding Government holidays.
1.5.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer.
1.5.4 Occupied Building
The Contractor shall be working in an existing building which is occupied.
Do not enter the building without prior approval of the Contracting Officer.
The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.
Provide dust covers or protective enclosures to protect existing work that remains, and Government material located in the spaces during the construction period. Contractor must submit a dust control plan to identify the means, methods, and procedures for controlling dust to adjacent occupied and operational areas for each phase of construction.
Relocate movable furniture approximately 6 feet away from the Contractor's working areaas required to perform the work, protect the furniture, and replace the furniture in their original locations upon completion of the work. Leave attached equipment in place, and protect them against damage, or temporarily disconnect, relocate, protect, and reinstall them at the completion of the work.
1.5.5 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.
b. Ensure that new utility lines are complete, except for the connection, SECTION 01 14 00 Page 4 before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, and compressed air, are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS.
d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 14 00 Page 5
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
11/20, CHG 3: 02/23
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Schedule of Prices ; G
1.2 SCHEDULE OF PRICES
1.2.1 Data Required
This Contract requires the use of a cost-loaded Network Analysis Schedule (NAS). Schedule of Prices must not be used with cost-loaded Network Analysis Schedule (NAS). Use Earned Value Report derived from cost-loaded NAS. Provide a detailed breakdown of the Contract price, giving quantities for each of the various kinds of work, unit prices and extended prices. Contractor overhead and profit including salaries for field office personnel, if applicable, must be proportionately spread over all pay items and not included as individual pay items.
1.2.2 Payment Schedule Instructions
Payments will not be made until the Schedule of Prices has been submitted to and accepted by the Contracting Officer.
Additionally, the Schedule of Prices must be separated as follows:
a. Primary Facilities Cost Breakdown:
Defined as work on the primary facilities out to the 5 foot line.
Work out to the 5 foot line includes construction encompassed within a theoretical line 5 foot from the face of exterior walls and includes attendant construction, such as pad mounted HVAC cooling equipment, cooling towers, and transformers placed beyond the 5 foot line.
b. Supporting Facilities Cost Breakdown:
Defined as site work, including incidental work, outside the 5 foot line.
1.3 CONTRACT MODIFICATIONS
In conjunction with the Contract Clause DFARS 252.236-7000 Modification Proposals-Price Breakdown, and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, base equipment use rates upon the applicable provisions of the
EP 1110-1-8 .
SECTION 01 20 00 Page 1
1.4 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.4.1 Content of Invoice
Requests for payment will be processed in accordance with the Contract Clause FAR 52.232-27 Prompt Payment for Construction Contracts and FAR 52.232-5 Payments Under Fixed-Price Construction Contracts. Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies. The requests for payment shall include the documents listed below.
a. The Contractor's invoice, on NAVFAC Form 7300/30 furnished by the Government, showing in summary form, the basis for arriving at the amount of the invoice. Form 7300/30 must include certification by Quality Control (QC) Manager as required by the Contract.
b. The Earned Value Report from the cost-loaded NAS.
c. Contractor's Monthly Estimate for Voucher and Contractors Certification (NAVFAC Form 4330) with Subcontractor and supplier payment certification. Other documents, including but not limited to, that need to be received prior to processing payment include the following submittals as required. These items are still required monthly even when a pay voucher is not submitted.
d. Monthly Work-hour report.
e. Updated Construction Progress Schedule and tabular reports required by the contract.
f. Contractor Safety Self Evaluation Checklist.
g. Updated submittal register.
h. Solid Waste Disposal Report.
i. Certified payrolls.
j. Updated testing logs.
k. Other supporting documents as requested.
1.4.2 Submission of Invoices
If DFARS Clause 252.232-7006 Wide Area WorkFlow Payment Instructions is included in the Contract, provide the documents listed in above paragraph CONTENT OF INVOICE in their entirety as attachments in Wide Area Work Flow (WAWF) for each invoice submitted. The maximum size of each WAWF attachment is two megabytes, but there are no limits on the number of attachments. If a document cannot be attached in WAWF due to system or size restriction, provide it as instructed by the Contracting Officer.
Monthly invoices and supporting forms for work performed through the anniversary award date of the Contract must be submitted to the Contracting Officer within 5 calendar days of the date of invoice. For example, if Contract award date is the 7th of the month, the date of each monthly invoice must be the 7th and the invoice must be submitted by the 12th of the month.
SECTION 01 20 00 Page 2
1.4.3 Final Invoice
a. A final invoice must be accompanied by the certification required by DFARS 252.247.7023 Transportation of Supplies by Sea, and the Contractor's Final Release. If the Contractor is incorporated, the Final Release must contain the corporate seal. An officer of the corporation must sign and the corporate secretary must certify the Final Release.
b. For final invoices being submitted via WAWF, the original Contractor's Final Release Form and required certification of Transportation of Supplies by Sea must be provided directly to the respective Contracting Officer prior to submission of the final invoice. Once receipt of the original Final Release Form and required certification of Transportation of Supplies by Sea has been confirmed by the Contracting Officer, the Contractor must then submit final invoice and attach a copy of the Final Release Form and required certification of Transportation of Supplies by Sea in WAWF.
c. Final invoices not accompanied by the Contractor's Final Release and required certification of Transportation of Supplies by Sea will be considered incomplete and will be returned to the Contractor.
1.5 PAYMENTS TO THE CONTRACTOR
Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section, and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.
1.5.1 Obligation of Government Payments
The obligation of the Government to make payments required under the provisions of this Contract will, at the discretion of the Contracting Officer, be subject to reductions and suspensions permitted under the FAR and agency regulations including the following in accordance with FAR
32.103 Progress Payments Under Construction Contracts:
a. Reasonable deductions due to defects in material or workmanship;
b. Claims which the Government may have against the Contractor under or in connection with this Contract;
c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and
d. Failure to maintain accurate "as-built" or record drawings in accordance with FAR 52.236.21.
1.5.2 Payment for Onsite and Offsite Materials
Progress payments may be made to the Contractor for materials delivered on the site, for materials stored off construction sites, or materials that are in transit to the construction sites under the following conditions:
a. FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.
b. Materials delivered on the site but not installed, including completed
SECTION 01 20 00 Page 3 preparatory work, and off-site materials to be considered for progress payment must be major high cost, long lead, special order, or specialty items, not susceptible to deterioration or physical damage in storage or in transit to the construction site. Examples of materials acceptable for payment consideration include, but are not limited to, structural steel, non-magnetic steel, non-magnetic aggregate, equipment, machinery, large pipe and fittings, precast/prestressed concrete products, plastic lumber (e.g., fender piles/curbs), and high-voltage electrical cable. Materials not acceptable for payment include consumable materials such as nails, fasteners, conduits, gypsum board, glass, insulation, and wall coverings.
c. Materials to be considered for progress payment prior to installation must be specifically and separately identified in the Contractor's estimates of work submitted for the Contracting Officer's approval in accordance with Schedule of Prices requirement of this Contract.
Requests for progress payment consideration for such items must be supported by documents establishing their value and that the title requirements of the clause at FAR 52.232-5 Payments Under Fixed-Price Construction Contracts have been met.
d. Materials are adequately insured and protected from theft and exposure.
e. Provide a written consent from the surety company with each payment request for offsite materials.
f. Materials to be considered for progress payments prior to installation must be stored either in Hawaii, Guam, Puerto Rico, or the Continental United States. Other locations are subject to written approval by the Contracting Officer.
g. Materials in transit to the job site or storage site are not acceptable for payment.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 20 00 Page 4
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
11/20, CHG 3: 08/23
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
View Location Map
Progress and Completion Pictures
1.2 VIEW LOCATION MAP
Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.
1.3 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures.
Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file.
Include a date designator in file names. Photographs provided are for unrestricted use by the Government.
1.4 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by State law.
1.5 SUPERVISION
Provide three seperate oversight prositions project superintendent, Quality control Manager, and SSHO.
1.5.1 Superintendent Qualifications
Provide a project superintendent with a minimum of 10 years of experience in
SECTION 01 30 00 Page 1 construction, with at least 5 of those years as superintendent on projects similar in size, complexity, and scope. For projects with fire alarm system scope, the superintendent shall possess NICET Level I certification or higher in Fire Alarm Systems. The individual must be familiar with the requirements of EM 385-1-1 and have experience in hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent.
The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
1.5.2 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work. In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.
1.5.3 Duties
The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend Red Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.The superintendent cannot serve as the SSHO.
1.5.4 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.
Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .