WORK ORDER NO. 1626397
A/E CONTRACT NO.
N40085-15-D-0068
APPROPRIATION: MCON
SOF NSWG-2 Combat Service Support Facilities
At the
JEB Little Creek-Fort Story, Virginia Beach, Virginia
(Q997)
FINAL RFP Submittal
VOLUME I of II – PARTS 1 – 6 (Attachments A-O)
SUBMITTED BY:
Clark Nexsen 4525 Main Street, Suite 1400
Virginia Beach, VA 23462
PREPARED BY:
Architectural: Rose A. Moser, AIA Interior Design Melodi E. Terhune, CID, LEED AP BD+C Landscape Architecture: J. Thomas Dalton, PLA, ASLS, LEED AP Structural: Peter P. Allen, PE Mechanical: John R. Banschenbach, PE Electrical: Scott P. Schwerin, PE Fire Protection: Kari E. Crane, PE Civil: Robert M. Silver, PE Geotechnical: GET Solutions, Inc.
APPROVED BY:
For Commander, NAVFAC [Insert Command]:
Date: [Month Day, Year]
Principal-In-Charge: Samuel K. Estep, PE Project Manager: Steve Bennett, PE A/E Firm Name: Clark Nexsen, Inc.
Date: April 23, 2020
James E. Donahue, R.A.
Samuel K. Estep
[THIS PAGE INTENTIONALLY LEFT BLANK]
Q997, SOF NSWG-2 Combat Service Support Facilities 1626397
PART ONE - PROPOSAL FORMS & DOCUMENTS - Page 1
PART ONE - PROPOSAL FORMS & DOCUMENTS
PROVIDED SEPARATELY BY NAVFAC.
1.0 Table of Contents (RFP Parts 2-6)
1. PART 2 – GENERAL REQUIREMENTS
01 14 00 WORK RESTRICTIONS
01 20 00.05 20 PRICE AND PAYMENT PROCEDURES FOR DESIGN-BUILD
01 30 00.05 20 ADMINISTRATIVE REQUIREMENTS FOR DESIGN-BUILD
01 31 19.05 20 POST AWARD MEETINGS
01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT
MANAGEMENT SYSTEM
01 32 17.00 20 COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS)
01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES
01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES
01 33 29.05 20 SUSTAINABILITY REPORTING FOR DESIGN-BUILD
01 35 13.05 20 SPECIAL PROJECT PROCEDURES FOR DESIGN-BUILD
01 35 26.05 20 GOVERNMENT SAFETY REQUIREMENTS FOR DESIGN-BUILD
01 45 00.05 20 DESIGN AND CONSTRUCTION QUALITY CONTROL
01 45 35.05 20 SPECIAL INSPECTIONS FOR DESIGN-BUILD
01 50 00.05 20 TEMPORARY FACILITIES AND CONTROLS FOR DESIGN-BUILD
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 57 19.01 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS
01 74 19.05 20 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT FOR
DESIGN-BUILD
01 78 23 OPERATION AND MAINTENANCE DATA
01 78 24.00 20 FACILITY ELECTRONIC OPERATION AND MAINTENANCE SUPPORT
INFORMATION (eOMSI)
01 91 00.15 TOTAL BUILDING COMMISSIONING
2. PART 3 – PROJECT PROGRAM
CHAPTER 1. PROJECT DESCRIPTION
CHAPTER 2. PROJECT OBJECTIVES
CHAPTER 3. SITE ANALYSIS
CHAPTER 4. SPACE TABULATION FORM
CHAPTER 5. ROOM REQUIREMENTS
CHAPTER 6. ENGINEERING SYSTEMS REQUIREMENTS
3. PART 4 – PERFORMANCE TECHNICAL SPECIFICATIONS
A10 FOUNDATIONS
A20 BASEMENT CONSTRUCTION
B10 SUPERSTRUCTURE
B20 EXTERIOR ENCLOSURE
B30 ROOFING
C10 INTERIOR CONSTRUCTION
C20 STAIRS
C30 INTERIOR FINISHES
D10 CONVEYING
D20 PLUMBING
D30 HVAC
D40 FIRE PROTECTION
D50 ELECTRICAL
E10 EQUIPMENT
E20 FURNISHINGS
F10 SPECIAL CONSTRUCTION
F20 SELECT BLDG DEMOLITION
G10 SITE PREPARATIONS
G20 SITE IMPROVEMENTS
G30 SITE CIVIL/MECHANICAL UTILITIES
G40 SITE ELECTRICAL UTILITIES
H10 WATERFRONT STRUCTURES Not used H20 GRAVING DRYDOCKS Not used H30 COASTAL PROTECTION Not used H40 NAVIGATION DREDGING AND RECLAMATION Not used H50 WATERFRONT UTILITIES Not used H60 WATERFRONT DEMOLITION Not used H70 WATERFRONT ATFP Not used
4. PART 5 – PRESCRIPTIVE SPECIFICATIONS
25 05 11.01 CYBERSECURITY FOR FACILITY-RELATED CONTRTOL SYSTEMS
25 05 11.02 CYBERSECURITY FOR HEATING, VENTILATION, AIR CONDITIONGS
(HVAC) CONTROL SYSTEMS
31 62 50 DISPLACEMENT AGGREGATE PIERS
5. PART 6 – ATTACHMENTS
A. Q997 FF&E SUMMARY
B. 28 31 76.00 22 INTERIOR COMBINATION EMERGENCY COMMUNICATIONS
SYSTEMS
C. HYDRANT FLOW TEST RESULTS
D. Q997 GEOTECHNICAL REPORT – (UNDER SEPARATE COVER)
E. A/V SYSTEM REQUIREMENTS SHEETS
F. NSW COASTAL CAMPUS ADP LIGHTING
G. PKG 3 P334 LOGSU IFC DRAWINGS BOAT STORAGE - (ELECTRONICALLY ONLY)
H. CRANE INFORMATION FORM FOR OVER HEAD ELECTRIC TRAVELING CRANE(S)
I. HAZARDOUS MATERIALS REPORT
J. ABOVEGROUND STORAGE TANK (AST) CLOSURE REPORT FORM
K. TOPGOGRAPHIC SURVEY
L. PERMIT RECORD OF DECISION (PROD)
M. UTILITY CONNECTION PERMIT APPLICATION AND INSTRUCTIONS
N. LOW IMPACT DEVELOPMENT (LID)
O. LOGSU SOCOM Little Creek-Armory Gear and Supply Rev1 Dwgs_01-27-20
P. Q997 FINAL DRAWINGS
PART TWO - GENERAL REQUIREMENTS - Page 1
PART TWO - GENERAL REQUIREMENTS
SECTION 01 14 00
WORK RESTRICTIONS
11/11
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29.05 20 SUSTAINABILITY REPORTING FOR DESIGN-BUILD. Submit the following in accordance with Section 01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel; G
1.2 SPECIAL SCHEDULING REQUIREMENTS
a. The project site must be ready for operation as approved by Contracting Officer before work is started which would interfere with normal operation.
b. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.
c. The surrounding buildings and parking will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.
d. Permission to interrupt any Activity roads, railroads, or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
e. The work under this contract requires special attention to the scheduling and conduct of the work in connection with existing operations. Identify on the construction schedule each factor which constitutes a potential interruption to operations.
f. Construction sequence shall be as follows:
1. Construct Ordinance Operations, Vehicle Maintenance, and Boat Shop. Prepare site at Ordinance Operations building to receive portable armories.
1a. When Ordinance Operations is complete, and after Government move period of 30 days, Bldg 772 may be demolished.
1b. When Vehicle Maintenance is complete, and after Government move period of 60 days, construct new fence around 3897. After such time, Bldg 3807 and 3859 may be demolished, and parking created.
2. Relocate portable armories (3) to new Ordinance Operations building site.
SECTION 01 14 00 Page 1
3. Construct new Armory addition and Boat Storage canopy.
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.
1.3.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.3.1.2 Additional Personnel Requirements
1.3.1.2.1 General Construction
General construction of the secure annex area must be performed by U.S.
firms using U.S. citizens. General construction includes construction activities such as building sitework, utilities, foundations, structure, and enclosure or shell, including doors, windows and façade work. Utility work that penetrates the secure annex area and installation of doors in these areas are not general construction.
1.3.1.2.2 Finish Work
Finish Work within the secure annex area must be accomplished by U.S. TOP SECRET-cleared personnel. Finish Work includes construction activities such as insulation, floor/partition/ceiling systems, cabinet work, conveyor systems, specialties, building furnishings/ fixtures/equipment, mechanical/electrical services and equipment including those specialized for fire protection, security, communication, control, energy conservation, safety, comfort, convenience, and similar purposes.
1.3.1.2.3 Electronic Security Systems Equipment
Electronic Security Systems equipment such as processing control units, workstations, field panels, sensors, card readers, cable installation, and system programming, testing and training must be performed by U.S.
companies using U.S. citizens who have been subjected to a trustworthiness determination, U.S. TOP SECRET-cleared personnel.
1.3.1.3 Installation Access
Obtain access to Navy installations through participation in the Defense Biometrics Identification System (DBIDS). Requirements for Contractor employee registration, and transition for employees currently under Navy Commercial Access Control System (NCACS), are available at https://www.cnic.navy.mil/om/dbids.html. No fees are associated with obtaining a DBIDS credential.
SECTION 01 14 00 Page 2
Participation in the DBIDS is not mandatory, and Contractor personnel may apply for One-Day Passes at the Base Visitor Control Office to access an installation.
1.3.1.3.1 Registration for DBIDS
Registration for DBIDS is available at https://www.cnic.navy.mil/om/dbids.html. Procedure includes:
a. Present a letter or official award document (i.e. DD Form 1155 or SF 1442) from the Contracting Officer, that provides the purpose for access, to the base Visitor Control Center representative.
b. Present valid identification, such as a passport or Real ID Act-compliant state driver's license.
c. Provide completed SECNAV FORM 5512/1 to the base Visitor Control Center representative to obtain a background check. This form is available for download at https://www.cnic.navy.mil/om/dbids.html.
d. Upon successful completion of the background check, the Government will complete the DBIDS enrollment process, which includes Contractor employee photo, finger prints, base restriction and several other assessments.
e. Upon successful completion of the enrollment process, the Contractor employee will be issued a DBIDS credential, and will be allowed to proceed to worksite.
1.3.1.3.2 DBIDS Eligibility Requirements
Throughout the length of the contract, the Contractor employee must continue to meet background screen standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.
An adjudication process may be initiated when a background screen failure results in disqualification from participation in the DBIDS, and Contractor employee does not agree with the reason for disqualification.
The Government is the final authority.
1.3.1.3.3 DBIDS Notification Requirements
a. Immediately report instances of lost or stolen badges to the Contracting Officer.
b. Immediately collect DBIDS credentials and notify the Contracting Officer in writing under the following circumstances:
(1) An employee has departed the company without having properly returned or surrendered their DBIDS credentials.
(2) There is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the Installation or anyone therein.
SECTION 01 14 00 Page 3
1.3.1.3.4 One-Day Passes
Personnel applying for One-Day passes at the Base Visitor Control Office are subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government is not responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the DBIDS.
1.3.2 Working Hours
Regular working hours must consist of an 8 1/2 hour period between 7 a.m.
and 3:30 p.m., Monday through Friday, excluding Government holidays.
1.3.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer.
1.3.4 Exclusionary Period
No work must be performed during basewide annual security exercises or the period 3:30 p.m. to 7:00 a.m., inclusive, without prior written approval of the Contracting Officer. This period has not been considered in computing the time allowed for the performance of this contract.
1.3.5 Occupied and Existing Buildings
The Contractor must be working around existing buildings which are occupied. Do not enter the buildings without prior approval of the Contracting Officer.
The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.
1.3.6 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, are considered utility cutovers pursuant to the paragraph WORK
OUTSIDE REGULAR HOURS.
d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal
SECTION 01 14 00 Page 4 conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.
1.4 SECURITY REQUIREMENTS
Contract Clause FAR 52.204-2 Security Requirements and Alternate II "FAC 5252.236-9301, Special Working Conditions and Entry to Work Area," apply.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section --
SECTION 01 14 00 Page 5
THIS PAGE INTENTIONALLY LEFT BLANK
SECTION 01 14 00 Page 6
SECTION 01 20 00.05 20
PRICE AND PAYMENT PROCEDURES FOR DESIGN-BUILD
01/12
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EP 1110-1-8 (2016) Construction Equipment Ownership and Operating Expense Schedule
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29.05 20 SUSTAINABILITY REPORTING FOR DESIGN-BUILD. Submit the following in accordance with Section 01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES and 01 33 10.05 20
DESIGN SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Earned Value Report; G
1.3 EARNED VALUE REPORT
1.3.1 Data Required
This contract requires the use of a cost-loaded Network Analysis Schedule (NAS). The information required for the Schedule of Prices will be entered as an integral part of the Network Analysis Schedule. 15 calendar days of notice of award, prepare and deliver to the Contracting Officer an Earned Value Report (construction contract) as directed by the Contracting Officer. Provide a detailed breakdown of the contract price, giving quantities for each of the various kinds of work, unit prices, and extended prices. Costs must be summarized and totals provided for each construction category.
1.3.2 Schedule Instructions
Payments will not be made until the Earned Value Report from cost-loaded NAS has been submitted to and accepted by the Contracting Officer. For design phase progress payment(s), the Schedule of Prices or Earned Value Report from the Cost Loaded CPM must include detailed design activities and general (summarized) approach for the construction phase(s) of the project. The Schedule of Prices or Earned Value Report must be fully developed with detailed construction line items as design progresses. The complete design and construction Schedule of Prices or Earned Value Report must be submitted and accepted prior to starting construction work.
SECTION 01 20 00.05 20 Page 1
For Fast-Tracked or Critical Path Submittals of construction projects, the Earned Value Report must include detailed design and construction line items for each fast-tracked/critical path phase(s), submitted to and accepted by the Contracting Officer during the Post Award Kickoff Meetings and confirmed prior to starting construction work in that phase.
Additionally, the Earned Value Report must be separated as follows:
a. Primary Facility/s Cost Breakdown:
Defined as work on the primary facility/s out to the 5 foot line. Work out to the 5 foot line includes construction encompassed within a theoretical line 5 foot from the face of exterior walls and includes attendant construction, such as pad mounted HVAC equipment, that may extend beyond the5 foot line.
Provide a cost breakout for all Primary Facility features that support Low Impact Development (LID), such as vegetated roof and rainwater harvesting features. The sum of the Primary Facility Cost above - a. and these Primary Facility LID sub-items - (1) must equal the total Primary Facility cost. Provide a subtotal cost of all Primary Facility LID sub-items on the Earned Value Report at design complete and project closeout.
b. Supporting Facilities Cost Breakdown:
Defined as site work, including incidental work, outside the 5 foot line.
Provide a cost breakout for all Supporting Facilities features that support LID, such as bioswales, permeable paving, infiltration basins, tree box filters, etc.. The sum of the Supporting Facilities Cost above -
b. and these Supporting Facilities LID sub-items - (1) must equal the total Supporting Facilities cost. Provide a subtotal cost of all Supporting Facilities LID sub-items on the Earned Value Report at design complete and project closeout.
1.3.3 Real Property Assets
Provide the Draft and Interim DD Form 1354, Transfer and Acceptance of Military Real Property filled in with the appropriate Real Property Unique Identifiers (RPUID) and related construction Category Codes. Provide the Draft DD Form 1354 that uses the appropriate division of the RPUIDs/ Category Codes to represent the designed real property assets that apply to this contract and include all associated cost. The Contractor must meet with the Contracting Officer and the Real Property Accounting Officer during the Post Award Kickoff Meeting and the Project Closeout Meetings to modify and include any necessary changes to the DD Form 1354. The Contractor must provide the Interim DD Form 1354 that uses the appropriate division of the RPUIDs/ Category Codes to represent the final constructed facility and include all associated cost. Coordinate the Contractor's Price and Payment structure with the structure of the RPUIDs/Category Codes.
Divide detailed asset breakdown into the RPUIDs and related construction Category Codes and populate associated costs which represent all aspects of the work. Where assets diverge into multiple RPUID/Category Codes, divide the asset and provide the proportion of the assets in each RPUID/ Category Code. Assets and related RPUID/ Category Codes may be modified by the Contracting Officer as necessary during the course of the work.
Coordinate identification and proportion of these assets with the Government Real Property Accounting Officer.
SECTION 01 20 00.05 20 Page 2
Cost data accumulated under this section are required in the preparation of DD Form 1354. Coordinate with Section 01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES in paragraph titled "DD Form 1354".
1.3.4 Schedule Requirements for HVAC TAB
The field work requirements of TAB work required by RFP Part 4 D30, HVAC must be broken down in the Earned Value Report from the cost-loaded NAS by separate line items which reflect measurable deliverables. Specific payment percentages for each line item will be determined on a case by case basis for each contract. The line items are as follows:
a. Approval of Design Review Report: The TABS Agency is required to conduct a review of the project plans and specifications to identify any feature, or the lack thereof, that would preclude successful testing and balancing of the project HVAC systems. The resulting findings must be submitted to the Government to allow correction of the design. The progress payment will be issued after review and approval of the report.
b. Approval of the pre-field engineering report: The TABS Agency submits a report which outlines the scope of field work. The report must contain details of what systems will be tested, procedures to be used, sample report forms for reporting test results and a quality control checklist of work items that must be completed before TABS field work commences.
c. Season I field work: Incremental payments are issued as the TABS field work progresses. The TABS Agency mobilizes to the project site and executes the field work as outlined in the pre-field engineering report. The HVAC water and air systems are balanced and operational data must be collected for one seasonal condition (either summer or winter depending on project timing).
d. Approval of Season I report: On completion of the Season I field work, the data is compiled into a report and submitted to the Government. The report is reviewed, and approved, after ensuring compliance with the pre-field engineering report scope of work.
e. Completion of Season I field QA check: Contract QC and Government representatives meet the TABS Agency at the jobsite to retest portions of the systems reported in the Season I report. The purpose of these tests are to validate the accuracy and completeness of the previously submitted Season I report.
f. Approval of Season II report: The TABS Agency completes all Season II field work, which is normally comprised mainly of taking heat transfer temperature readings, in the season opposite of that under which Season I performance data was compiled. This data must be compiled into a report and submitted to the Government. On completion of submittal review to ensure compliance with the pre-field engineering report scope, progress payment is issued. Progress payment is less than that issued for the Season I report since most of the water and air balancing work effort is completed under Season I.
1.4 CONTRACT MODIFICATIONS
In conjunction with the Contract Clause "DFARS 252.236-7000, Modification
SECTION 01 20 00.05 20 Page 3
Proposals-Price Breakdown," and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, equipment use rates will be based upon the applicable provisions of the EP 1110-1-8.
1.5 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.5.1 Content of Invoice
Requests for payment will be processed in accordance with the Contract.
Clause FAR 52.232-27, Prompt Payment Construction Contracts and FAR 52.232-5, Payments Under Fixed-Price Construction Contracts. The Requests for payment must include the documents listed below:
a. The Contractor's invoice, on NAVFAC Form 7300/30 furnished by the Government, showing in summary form, the basis for arriving at the amount of the invoice. Form 7300/30 must include certification by Quality Control (QC) Manager as required by the contract.
b. The Earned Value Report from the cost-loaded NAS, showing in detail:
the estimated cost, percentage of completion, and value of completed performance for each of the construction categories stated in this contract. Use NAVFAC Form 4330/110 on NAVFAC contracts when a Monthly Estimate for Voucher is required.
c. Updated Project Schedule and reports required by the contract.
d. Contractor Safety Self Evaluation Checklist.
e. Other supporting documents as requested.
f. Updated copy of submittal register.
g. Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies.
h. Subcontractor and supplier payment certification.
i. Materials on Site.
1.5.2 Submission of Invoices
If DFARS Clause 252.232-7006 is included in the contract, the documents listed in paragraph CONTENT OF INVOICE above must be provided in their entirety as an attachment in Wide Area Work Flow (WAWF) for each invoice submitted. The maximum size of each WAWF attachment is two megabytes, but there are no limits on the number of attachments. If a document cannot be attached in WAWF due to system or size restriction it must be provided as instructed by the Contracting Officer. All other paper invoices must be forwarded with specific marking on the envelope. This marking must be in the front lower left hand corner, in large letters, "INVOICES - ENCLOSED."
Monthly invoices and supporting forms for work performed through the anniversary award date of the contract must be submitted to the Contracting Officer within 5 calendar days of the date of invoice. For example, contract award date is the 7th of the month, the date of each monthly invoice must be the 7th and the invoice must be submitted by the 12th of the month.
SECTION 01 20 00.05 20 Page 4
1.5.3 Final Invoice
a. A final invoice must be accompanied by the certification required by DFARS 252.247.7023 TRANSPORTATION OF SUPPLIES BY SEA, and the Contractor's Final Release. If the Contractor is incorporated, the Final Release must contain the corporate seal. An officer of the corporation must sign and the corporate secretary must certify the Final Release.
b. For final invoices being submitted via WAWF, the original Contractor's Final Release Form and required certification of Transportation of Supplies by Sea must be provided directly to the respective Contracting Officer prior to submission of the final invoice. Once receipt of the original Final Release Form and required certification of Transportation of Supplies by Sea has been confirmed by the Contracting Officer, the Contractor must then submit final invoice and attach a copy of the Final Release Form and required certification of Transportation of Supplies by Sea in WAWF.
c. Final invoices not accompanied by the Contractor's Final Release and required certification of Transportation of Supplies by Sea will be considered incomplete and will be returned to the Contractor.
1.6 PAYMENTS TO THE CONTRACTOR
Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section, and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.
1.6.1 Obligation of Government Payments
The obligation of the Government to make payments required under the provisions of this contract will, at the discretion of the Contracting Officer, be subject to reductions and/or suspensions permitted under the FAR and agency regulations including the following in accordance with "FAR 32.503-6:
a. Reasonable deductions due to defects in material or workmanship;
b. Claims which the Government may have against the Contractor under or in connection with this contract;
c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and
d. Failure to provide up to date record drawings not current as stated in Contract Clause "FAC 5252.236-9310, Record Drawings."
e. Failure to provide GIS Data per the Part 6 Standards and Requirements fee vector GIS Deliverables.
1.6.2 Payment for Onsite and Offsite Materials
Progress payments may be made to the contractor for materials delivered on the site, for materials stored off construction sites, or materials that are in transit to the construction sites under the following conditions:
a. FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.
SECTION 01 20 00.05 20 Page 5
b. Materials delivered on the site but not installed, including completed preparatory work, and off-site materials to be considered for progress payment must be major high cost, long lead, special order, or specialty items, not susceptible to deterioration or physical damage in storage or in transit to the construction site. Examples of materials acceptable for payment consideration include, but are not limited to, structural steel, non-magnetic steel, non-magnetic aggregate, equipment, machinery, large pipe and fittings, precast/prestressed concrete products, plastic lumber (e.g., fender piles/curbs) and high-voltage electrical cable. Materials not acceptable for payment include consumable materials such as nails, fasteners, conduits, gypsum board, glass, insulation, and wall coverings.
c. Materials to be considered for progress payment prior to installation must be specifically and separately identified in the Contractor's estimates of work submitted for the Contracting Officer's approval in accordance with Earned Value Report requirement of this contract.
Requests for progress payment consideration for such items must be supported by documents establishing their value and that the title requirements of the clause at FAR 52.232-5 have been met.
d. Materials are adequately insured and protected from theft and exposure.
e. Provide a written consent from the surety company with each payment request for offsite materials.
f. Materials to be considered for progress payments prior to installation must be stored in the Continental United States. Other locations are subject to written approval of the Contracting Officer.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 20 00.05 20 Page 6
SECTION 01 30 00.05 20
ADMINISTRATIVE REQUIREMENTS FOR DESIGN-BUILD
03/13
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29.05 20 SUSTAINABILITY REPORTING FOR DESIGN-BUILD. Submit the following in accordance with Section 01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES and 01 33 10.05 20
DESIGN SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Insurance
1.2 MINIMUM INSURANCE REQUIREMENTS
Procure and maintain during the entire period of performance under this contract the following minimum insurance coverage:
a. Comprehensive general liability: $500,000 per occurrence.
b. Automobile liability: $200,000 per person, $500,000 per occurrence for bodily injury, $20,000 per occurrence for property damage.
c. Workmen's compensation as required by Federal and State workers' compensation and occupational disease laws.
d. Employer's liability coverage of $100,000, except in States where workers compensation may not be written by private carriers.
e. Others as required by the State.
Refer to Section 01 33 00.05 20, CONSTRUCTION SUBMITTAL PROCEDURES for typical preconstruction submittals similar to insurance.
1.3 CONTRACTOR PERSONNEL REQUIREMENTS
1.3.1 Subcontractor Special Requirements
1.3.1.1 Asbestos Containing Material
All contract requirements of PART 4, F20 SELECTIVE BUILDING DEMOLITION, assigned to the Private Qualified Person (PQP) must be accomplished directly by a first tier subcontractor.
1.3.1.2 HVAC TAB
All contract requirements of TAB work required by PART 4 D30, HVAC, must be accomplished directly by a first tier subcontractor. No TAB work required by PART 4, D30, HVAC, is allowed to be accomplished by a second
SECTION 01 30 00.05 20 Page 1 tier subcontractor.
1.3.1.3 Qualified Testing Organization
All contract requirements of work required to be performed by a Qualified Testing Organization in PART 4, D50 ELECTRICAL and G40 SITE ELECTRICAL UTILITIES, must be accomplished directly by a first tier subcontractor.
No work to be performed by a Qualified Testing Organization, required by PART 4, D50 and G40 is allowed to be accomplished by a second tier subcontractor.
1.4 SUPERVISION
Have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours. In addition, the Quality Control (QC) representative must also have fluent English communication skills.
1.5 AVAILABILITY OF CAD DRAWING FILES
After award and upon request, the electronic "Computer-Aided Design (CAD)" drawing files will be made available to the Contractor for use in preparation of construction drawings and data related to the referenced contract subject to the following terms and conditions.
Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction drawings and data for the referenced project. Any other use or reuse is at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor must make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.
These electronic CAD drawing files are not construction documents.
Differences may exist between the CAD files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic CAD files, nor does it make representation to the compatibility of these files with the Contractors hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished CAD files, the signed and sealed construction documents govern. The Contractor is responsible for determining if any conflict exists. Use of these CAD files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project.
If the Contractor uses, duplicates or modifies these electronic CAD files for use in producing construction drawings and data related to this contract, all previous indicia of ownership (seals, logos, signatures, initials and dates) must be removed.
SECTION 01 30 00.05 20 Page 2
1.6 CLEANUP
Leave premises "broom clean." Clean interior and exterior glass surfaces exposed to view; remove temporary labels, stains and foreign substances;
polish transparent and glossy surfaces; vacuum carpeted and soft surfaces. Clean equipment and fixtures to a sanitary condition. Replace filters of operating equipment. Clean debris from roofs, gutters, downspouts and drainage systems. Sweep paved areas and rake clean landscaped areas. Remove waste and surplus materials, rubbish and construction facilities from the site.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 30 00.05 20 Page 3
THIS PAGE INTENTIONALLY LEFT BLANK
SECTION 01 30 00.05 20 Page 4
SECTION 01 31 19.05 20
POST AWARD MEETINGS
09/15
PART 1 GENERAL
1.1 SUMMARY
This document includes post-award requirements for project kickoff and subsequent design and preconstruction meetings.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29.05 20 SUSTAINABILITY REPORTING FOR DESIGN-BUILD. Submit the following in accordance with Section 01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES and 01 33 10.05 20
DESIGN SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Design Submittal Packaging Proposal; G
Project Schedule; G
Performance Assessment Plan (PAP); G
CDW Facilitator Experience Resume; G
CDW Preliminary Concept Design; G
CDW Cost Estimate; G
Concept Design Workshop Report; G
1.3 POST AWARD KICKOFF MEETING
The Post Award Kickoff (PAK) meeting is made up of Contract Administration, Concept Design Presentation/Design Development or Concept Design Workshop (CDW), Partnering, and Scheduling. If mutually beneficial to the Contractor and the Government, these four elements may be addressed in a single multi day meeting, but most often multiple scheduled meetings are required. Schedule a separate meeting or a separate day of the multiday PAK, to accomplish the Design Presentation/Design Development Meeting or Concept Design Workshop(CDW).
1.3.1 PAK Meeting Schedule and Location
Within 35 calendar days after contract award, and prior to commencing work, meet with the Contracting Officer for the PAK meeting(s). The meeting will be located at a specific time and place to be determined by the Contracting Officer.
SECTION 01 31 19.05 20 Page 1
1.3.2 PAK Meeting Outcomes
The meeting(s) outcomes are:
a. Integrate the Contractor and all client representatives into the project team.
b. Achieve consensus from the project team on any issues and concerns with the Contractor's technical proposal and the User's functional requirements. Confirm the design is within the project budget.
c. Establish and explain policies and procedures for completion of a successful project.
d. Establish clear lines of communication and points of contact for Government and Contractor team members.
e. Obtain an acceptable conceptual design including floor and site plans, signed by the client, Contractor and other key team members.
f. Establish project design schedule, design submittal packaging, and preliminary construction schedule in accordance with Section 01 32 17.0 0 20 COST-LOADED NETWORK ANALYSIS SCHEDULE (NAS). Discuss design milestones and events that will be included in the Quality Control Communication Plan.
g. Establish clear expectations and schedules for facility turnover, providing DD Form 1354 asset management records, eOMSI submittals, Guiding Principle Validation, Third Party Certification (if applicable), and training of Government maintenance personnel.
h. Establish procedure for design packages reviews, Contractor's resolution to comments, and Government's role in review of packages.
i. Establish clear expectations for the Concept Design Workshop.
j. Establish clear expectations for Design Model presentations for projects implementing Building Information Management/Modeling (BIM).
k. Provide sufficient time during the PAK meeting for the Designer of Record responsible for preparing the Request For Proposal to present his design rationale and describe reasoning by which the bridging documents were prepared.
1.3.3 PAK Meeting Contractor Attendees
The following Contractor key personnel must attend the PAK: Project Manager, Project Scheduler, Lead Designer-of-Record (DOR), Design Staff responsible for each architectural/engineering discipline when facility design is discussed, Superintendent, QC Manager, DQC Manager and the Commissioning Authority (CA). Optional attendees include: Principal, Assistant Project Manager, major subcontractors and specialized supplemental QC personnel.
1.3.4 Contract Administration
Contract administration roles and responsibilities will be addressed.
SECTION 01 31 19.05 20 Page 2
1.3.5 Concept Design Workshop (CDW)
Provide a CONCEPT DESIGN WORKSHOP that meets the following requirements;
1.3.5.1 CDW General Requirements
a. Methodology. Concept a CDW for this project. This effort will examine project functions and requirements, quality and life safety costs, analyze alternate design concepts, expose and resolve project issues, and develop the final conceptual design.
b. Facilitator. Provide a Facilitator who is experienced in conducting Concept Design Workshops. Submit a CDW Facilitator Experience Resume to the Contracting Officer describing his experience. He or she will be responsible for leading the team in a timely manner, making sure that issues are pursued and resolved to the maximum extent possible, documenting meetings, organizing the design concept documents for on-site approval, and providing the Concept Design Workshop Report.
c. Contractor's Design Team. The primary functions of the Design Team will be to investigate, develop and present alternate design solutions. The entire Design Team must participate in all phases of the Concept Design Workshop effort and provide assistance to the Facilitator in development of the Concept Design Workshop Report, including most of the required documentation. Contractor must retain the services of a Human Performance Center / Gymnasium equipment Subject Matter Expert (SME) to aid the design team for the equipment layout. SME must have a minimum of five year's experience in equipment layouts for similar size and type facilities. Responsibilities must include:
1. Equipment layouts reflecting an appropriate floor plan
2. 3D visualization of the facility
3. Electrical positioning for the equipment layout
4. TV placement for the best ergonomics, user comfort, and viewing
5. Placement of equipment for optimal workouts and traffic flow
6. Correct spacing around equipment for safe, effective use
d. Concept Design Workshop Report. Produced almost entirely on-site, the Concept Design Workshop Report must summarize the final conceptual design.
e. Award Amount. At each contract stage, the Contractor must verify that the concept is within the contract award amount.
f. It is the intent of the CDW that all issues related to the design of the facility must be resolved and approved prior to closing the meeting with no follow-on Requests for Information (RFI's).
1.3.5.2 CDW Procedures
a. Preliminary Work.
The Contractor's Design Team must complete the following prior to the on-site workshop:
(1) Review the contract documents and references explaining the project scope and history.
SECTION 01 31 19.05 20 Page 3
(2) At the Post Award Kickoff meeting, the User(s) makes a presentation of their functional requirements.
(3) Prepare and submit, at least 14 days in advance of the CDW, 15 copies of a CDW Preliminary Concept Design (Concept #1), a Basis of Design, and a statement that the concept provided is within the award amount.
(4) Make arrangements for and provide an appropriate conference room convenient to the project site and Users for use by the Design Team and government participants during the workshop.
(5) Incorporate government comments in a revised Concept #1 and produce at least 20 copies of the revised Concept #1 documents for distribution at the workshop.
(6) Facilitator conducts meeting with NAVFAC representatives before the CDW to review preparations, relationships, and the status of work to be accomplished.
b. On-Site Workshop.
The Design Team must accomplish the following items during the on-site phase of the CDW. (Typically conducted in four to six working days, minimizing breaks so as to maintain momentum. The Design Team should expect longer than normal workdays.)
(1) On the first day of the workshop, meet with the using activity, Station and other Government representatives. The Facilitator will describe the CDW process and review the workshop agenda. The user(s) will provide a functional presentation. This is to reiterate to all participants the User(s) needs and desires. The intent is to make the design solution and issue resolution function-oriented.
(2) Present the revised Concept #1 and respond to questions.
(3) Participate in a comment/creative session to generate ideas to improve this project in the areas of function, quality and total life cycle cost, issue resolution and sustainable design within the award amount. It is often helpful to request User comments in writing so they may be considered, responded to, and presented at subsequent presentations.
(4) Create a new concept design. Design concepts must include drawings, sketches, and other graphics as necessary to fully describe the concept. Prepare at least 20 copies for distribution at all presentations.
(5) Repeat applicable steps as necessary. Usually, three concepts are required. The final concept must be within the contract award amount.
(6) The final concept must include the following:
(a) Site Plan: Show the layout of the proposed facility in relation to major landmarks. Show all buildings, access roads, parking, pedestrian walkways, roads, sidewalks, landscaping, and major utilities. Indicate major dimensions and orientation.
SECTION 01 31 19.05 20 Page 4
Provide a building code analysis, relating the proposed building site, size, and construction type to maximum allowable limits of the International Building Code.
(b) Building Floor Plans: Provide floor plans depicting functional utilization of spaces and furniture and equipment layout. Show room sizes or dimensions. Provide a Life Safety Code analysis with the floor plan to identify required life safety and egress features.
(c) Perspective Sketches: Provide at least one sketch to show a perspective of major buildings. The sketch should not be elaborate but must show the proposed form and massing, colors to be used, and an indication of materials used.
(d) Mechanical Plans: Provide plans as necessary to show the essential work and intent of the design. Suggestions include equipment layouts, zones, etc.
(e) Electrical Plans: Provide plans as necessary to show the essential work and intent of the design. Suggestions include special light fixture types, locations, switching, power outlets and panelboard location. Provide electrical distribution single line diagram.
(f) Cost Estimate: Provide a CDW Cost Estimate and statement that the concept presented can be constructed within the award amount.
(g) Basis of Design: Describe the intent of the design by discipline. Address material quality, energy efficiency and life cycle costs.
(h) Sustainable Design: Demonstrate ability to achieve identified Guiding Principle sustainability goals and also Third Party Certification sustainability goals, if applicable. Provide Preliminary Sustainable Notebook, refer to Section 01 33 29.05 20 SUSTAINABILITY REPORTING FOR DESIGN-BUILD for requirements.
(i) System Safety Engineering
(7) Prepare 20 copies of the final concept (drawings, basis of design and statement that the concept is within the award amount) for distribution at the final presentation.
(8) Dependent upon the project, the Concept Design Workshop Report is provided by the Facilitator, includes all items included in the final concept design and the following:
(a) Endorsements: Include a copy of the signature/endorsement sheet.
(b) Comments: Include comments and resolutions concerning the final concept design.
(c) Executive Summary: Summarize the workshop, including how the various concepts differed and were improved during the workshop.
(d) Special Design Features: Identify and describe unique project needs and features, e.g., pile foundations, physical security, SECTION 01 31 19.05 20 Page 5 intrusion detection systems, access control, construction in humid climates, pollution abatement, tempest, HEMP, etc.
(e) Architectural Compatibility Statement: Identify architectural style, materials, and color scheme; and indicate their compatibility with installation planning and design concepts established in the Base Exterior Architectural Plan.
(f) Environmental Summary: Provide a summary of environmental issues, listing completed actions and items requiring further coordination, waivers or permits.
(g) Supporting Project Documentation: Include data to support the development of the concept design, layout, and special features.
Items should include: project scope discussion, minutes of meetings, function analysis work sheets, and economic and technical analyses if alternatives evaluated.
(9) Except for final comments, responses and endorsements, the final report should be completed (electronically) on site, before the final presentation. If requested by the NAVFAC Project Manager, be prepared to present up to 10 hard copies of the report at the conclusion of the workshop.
(10)Conduct a "front-to-back" comprehensive presentation of the final concept. Obtain user signatures on a conceptual design endorsement sheet, signifying approval of the concept design, subject to the final comments and their resolutions agreed to at the final presentation meeting.
1.3.5.3 Concept Design Workshop Report
Within 14 calendar days of completion of the on-site Concept Design Workshop, the Design Team must submit to the NAVFAC Project Manager an electronic copy of the Concept Design Workshop Report as one file in .PDF format.
1.3.5.4 CDW Meeting Attendees
The following Contractor key personnel must attend the CDW: Project Manager, Project Scheduler, Cost Estimator, Lead Designer of Record, Design Staff representing each architectural/engineering discipline and Major Subcontractors when facility design is discussed, Superintendent, QC Manager, and DQC.
1.3.6 Partnering
To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government, Contractor and its Subcontractors. Key Personnel from the Supported Command, End User (who will occupy the facility), NAVFAC (Echelon III and/or IV), Navy Region/Installation, Contractor and Subcontractors and the Designer of Record will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in an effort to achieve a project without any safety mishaps, conforming to the Contract, within budget and on schedule.
Information on the Partnering Process…