This is a Temporary Facilities and Controls specification document for the New Hampshire Department of Military Affairs and Veterans Services (DMAVS) NHARNG Center Strafford Building 12 Interior Renovation project. The document establishes contractor requirements for managing temporary construction infrastructure during the interior renovation of Building 12 at the NH Army National Guard Training Site in Strafford County. The specification addresses eighteen categories of temporary facilities and controls, including electricity, lighting, heating, cooling, ventilation, water service, sanitary facilities, field offices, parking, waste removal, barriers, security measures, dust control, and pollution prevention. The contractor is responsible for providing flexible power cords, main service disconnect, branch wiring with distribution boxes, temporary lighting for work and security purposes, temporary fan units for ventilation, portable sanitary facilities, and temporary field offices or storage sheds if needed. A non-mandatory bidder's conference and site walk-through is scheduled for February 19, 2025, at 10:00 AM, with sealed bids due February 28, 2025, at 12:00 PM EST. Work is scheduled to occur between 7:00 AM and 3:30 PM, with the contract term running from Governor and Council approval through November 28, 2025.

The specification requires the contractor to maintain the construction site in a clean and orderly manner, removing debris and waste weekly and disposing of materials off-site. The Department will pay for temporary electricity and water consumption, though contractors must exercise energy conservation measures. Contractors are prohibited from using the internal state/federal phone system and must coordinate field office locations with the Department prior to placement due to limited available space. All temporary utilities, equipment, facilities, and materials must be removed prior to final payment, with existing facilities restored to original condition. Security measures include restricted site access limited to authorized personnel with proper identification, maintenance of worker and visitor logs, personnel accreditation lists, and coordination with Department security forces. The contractor must implement dust control measures, prevent unauthorized entry through barriers and temporary partitions, and establish rodent control methods. Contractors and subcontractors are required to park only in Department-designated spaces, maintain approach walks free of mud and water, and ensure the building's elevator—the only one in the facility—remains clean during construction operations.

View the file

Other files

File Type Posted
Addendum_2_RFB DMAVS 2025-01.pdf PDF
Addendum_3_RFB DMAVS 2025-01.pdf PDF
Addendum_1_RFB DMAVS 2025-01.pdf PDF
attachment_2_RFB DMAVS 2025-01.pdf PDF
attachment_1_RFB DMAVS 2025-01.pdf PDF
attachment_4_RFB DMAVS 2025-01.pdf PDF
attachment_10_RFB DMAVS 2025-01.pdf PDF
attachment_5_RFB DMAVS 2025-01.pdf PDF
RFB DMAVS 2025-01.pdf PDF
attachment_7_RFB DMAVS 2025-01.pdf PDF
attachment_8_RFB DMAVS 2025-01.pdf PDF
attachment_12_RFB DMAVS 2025-01.pdf PDF
attachment_9_RFB DMAVS 2025-01.pdf PDF
attachment_11_RFB DMAVS 2025-01.pdf PDF
attachment_3_RFB DMAVS 2025-01.pdf PDF
attachment_6_RFB DMAVS 2025-01.pdf PDF
addendum-1-rfb-dmavs-2025-01.pdf PDF
attachment-8-rfb-dmavs-2025-01.pdf PDF
addendum-4-rfb-dmavs-2025-01.pdf PDF
attachment-2-rfb-dmavs-2025-01.pdf PDF
attachment-11-rfb-dmavs-2025-01.pdf PDF
attachment-1-rfb-dmavs-2025-01.pdf PDF
attachment-10-rfb-dmavs-2025-01.pdf PDF
rfb-dmavs-2025-01.pdf PDF
attachment-5-rfb-dmavs-2025-01.pdf PDF
attachment-4-rfb-dmavs-2025-01.pdf PDF
addendum-3-rfb-dmavs-2025-01.pdf PDF
attachment-9-rfb-dmavs-2025-01.pdf PDF
attachment-3-rfb-dmavs-2025-01.pdf PDF
attachment-6-rfb-dmavs-2025-01.pdf PDF
addendum-2-rfb-dmavs-2025-01.pdf PDF
attachment-12-rfb-dmavs-2025-01.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TEMPORARY FACILITIES AND CONTROLS

1. TEMPORARY ELECTRICITY

A. The Department will pay cost of energy used. Exercise measures to conserve energy.

B. Provide flexible power cords as required for portable construction tools and equipment.

C. Provide main service disconnect and over-current protection at convenient location.

D. Permanent convenience receptacles may be utilized during construction.

2. TEMPORARY LIGHTING FOR CONSTRUCTION PURPOSES

A. Provide and maintain lighting for construction operations.

B. Provide and maintain lighting to interior work areas after dark for security purposes.

C. Provide branch wiring from power source to distribution boxes with lighting conductors, pigtails, and lamps for specified lighting levels.

D. Maintain lighting and provide routine repairs, E. Permanent building lighting may be utilized during construction.

3. TEMPORARY HEATING

A. Existing building heating system may be used during construction. Exercise measures to conserve energy.

4. TEMPORARY COOLING

A. Existing building cooling system may be used during construction. Exercise measures to conserve energy.

5. TEMPORARY VENTILATION

A. Ventilate enclosed areas to achieve curing of materials, to dissipate humidity, and to prevent accumulation of dust, fumes, vapors, or gases.

B. Provide temporary fan units as required to maintain clean air for construction operations.

6. TELEPHONE SERVICE

A. Contractor may not use internal state/federal phone system.

7. WATER SERVICE

A. The Department will pay cost of temporary water used. Exercise measures to conserve energy. Utilize Department’s existing water system, extend and supplement with temporary devices as needed to maintain specified conditions for construction operations.

8. TEMPORARY SANITARY FACILITIES

A. Provide and maintain required facilities and enclosures. Existing facility use is not permitted. Provide facilities at time of project mobilization.

9. FIELD OFFICES AND SHEDS

A. If the contractor decides to have a field office the location shall be coordinated with the department prior to placement. There is limited space available in the construction area for storage or a field office.

B. Provide Portable or mobile buildings, or buildings constructed with floors raised above ground, securely fixed to foundations with steps and landings at entrance doors. Maintain during progress of Work; remove at completion of Work.

C. Storage Areas And Sheds: Size to storage requirements fill products of individual Sections, allowing for access and orderly provision for maintenance and for inspection of products.

D. Maintenance and Cleaning: Maintain approach walks free of mud, water, and snow.

E. Removal: At completion of Work remove buildings, foundations, utility services, and debris. Restore areas.

10. PARKING

A. Contractor and subcontractors to park in department directed spaces only.

11. PROGRESS CLEANING AND WASTE REMOVAL

A. Maintain areas free of waste materials, debris, and rubbish. Maintain site in clean and orderly condition.

B. Remove debris and rubbish from pipe chases, plenums, attics, crawl spaces, and other closed or remote spaces, prior to enclosing spaces.

C. Broom and vacuum clean interior areas prior to start of surface finishing and continue cleaning to eliminate dust.

D. Collect and remove waste materials, debris, and rubbish from site weekly and dispose off-site.

E. Elevator may be used for removal of construction waste. Contractor is responsible for maintaining cleanliness of said elevator as it is the only one in the building.

12. BARRIERS

A. Provide barriers to prevent unauthorized entry to construction areas to allow for the

Department‘s use of the site and facility, and to protect existing facilities and adjacent properties from damage from construction operations and demolition.

B. Protect non-owned vehicular traffic, stored materials, site and structures from damage.

13. ENCLOSURES AND FENCING

A. Interior Enclosures:

i. Provide temporary partitions and ceilings as indicated on Drawings to separate work areas from Department occupied areas, to prevent penetration of dust and moisture into Department occupied areas, and to prevent damage to existing materials and equipment.

ii. Construction: Framing with reinforced polyethylene and plywood sheet materials with closed joints and scaled edges at intersections with existing surfaces.

14. SECURITY

A. Security Program:

i. Protect new Work and existing premises from theft, vandalism, and unauthorized entry.

B. Entry Control.

i. Restrict entrance of persons and vehicles into Project site and existing facilities,

ii. Allow entrance only to authorized persons with proper identification.

iii. Maintain log of workers and visitors, make available to Department on request.

iv. Coordinate access of Department personnel to site in coordination with

Department security forces.

C. Personnel Identification

i. Maintain list of accredited persons, submit copy to Department on request.

ii. A driver's license or other acceptable positive identification will be required.

iii. DMAVS reserves the right to conduct State Police background checks.

15. DUST CONTROL

A. Execute Work by methods to minimize raising dust from construction operations.

B. Provide positive means to prevent air-borne dust from dispersing into atmosphere.

C. After completion of work, clean all interior work surfaces.

16. POLLUTION CONTROL

A. Provide methods, means, and facilities to prevent contamination of soil, water, and atmosphere from discharge of noxious, toxic substances, and pollutants produced by construction operations.

B. Comply with pollution and environmental control requirements of authorities having jurisdiction.

17. RODENT CONTROL

A. Provide methods, means, and facilities to prevent rodents from accessing or invading premises.

18. REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS

A. Remove temporary utilities, equipment, facilities, materials, prior to Final

Application for Payment.

B. Clean and repair damage caused by installation or use of temporary work.

C. Restore existing facilities used during construction to original condition.

END OF SECTION