Attachment 6 Experience Information Sheet.pdf

PDF 161 KB Posted

Attached to
Y1DA--FY23: NRM-Tier 1 (PROJ: 548-23-122) D/B Install Additional Pump on OR Chilled Water Loop
Solicitation number
36C24823R0051_1
Issued by

About this file

This document contains an experience information sheet template and details of a related federal contract opportunity for installation services. The opportunity is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses to install an additional pump on an existing OR chilled water loop at a Veterans Affairs medical center within 120 days of award. The contractor will match existing pumps and valves, install a new parallel pump and Eaton VFD, rewire existing power feeds, and integrate new DDC controls and devices into the BAS system. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 8 is the awarding agency.

View the file

Other files

File Type Posted
Award Announcement 36C24823C0052_1.pdf PDF
548-23-122 QAs.pdf PDF
16-104 18-5-18 RECORD PDF PACKAGE CH1-2.pdf PDF
Doors - Windows.Wood Doors.Ash.jpg JPG image
03 30 53.pdf PDF
Brooks controls - approved by Moses lr.pdf PDF
h-max-installation-manual-mn04008005e.pdf PDF
IOM1206 - Daikin Trailblazer (AGZ).pdf PDF
36C24823R0051 0003.pdf PDF
19010 Electrical - SandS.pdf PDF
WPB-VA_S-SHEETS.txt TXT text file
h-max-application-manual-mn04008006e.pdf PDF
A100 - SS.pdf PDF
19010 Mechical - SandS.pdf PDF
Grundfosliterature-5104627.pdf PDF
h-max-quick-start-guide-mn04008004e.pdf PDF
Structural.pdf PDF
A210 - SS.pdf PDF
36C24823R0051 0002.pdf PDF
S06 36C24823R0051 0001.pdf PDF
Attachment 3 548-23-122 01321615 Spec.docx DOCX document
Attachment 1 548-23-122 010000 Spec.docx DOCX document
Attachment 14 Site Plan.pdf PDF
Attachment 11 548-23-122 AE Instructions DB.docx DOCX document
Attachment 4 548-23-122 013323 Spec.docx DOCX document
Attachment 13 Location Plan.pdf PDF
Attachment 9 Combatting COVID 19.pdf PDF
Attachment 2 548-23-122 014219 Spec.docx DOCX document
Attachment 12 Design Manual Index.pdf PDF
Attachment 10 548-23-122 001121 SpecSOW.docx DOCX document
Attachment 8 WD FL20220220 09.30.2022.pdf PDF
S02 36C24823R0051 for SAM.docx DOCX document
Attachment 5 Project Price Breakdown.xlsx XLSX spreadsheet
Attachment 7 VA Info and Info System Security.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXPERIENCE INFORMATION SHEET

36C24822R0002

PROJECT NO. [ ] Page 1 Must have a total of four (4) projects, more than 4 will not be evaluated; less than 4 may result in a lower rating.

a. Contractor Information of Awarded Contract (Firm Name, Address, DUNS Number, Phone number, POC Name, POC e‐mail, Company e‐mail)

b. Contract and/or Task Order Number and Award Date (mm/dd/yyyy)

c. Project Title/Name and Location

d. Work Performed as: Prime Contractor or Subcontractor

e. Percent (%) of project work performed by your company.

f. If you work as subcontractor, who was the prime?

(Firm Name, Address, DUNS Number and Cage Code, Phone number, POC Name, POC email, Company email)

g. Government Agency/Company which awarded contract to offeror, and Contact Information, such Contracting Officer/Procurement Official/Point of Contract (Name, Title, Email, Phone Number).

PROJECT NO. [ ] Page 2

h. Description of project’s scope of work and the offeror’s specific roles and responsibilities in the project:

Describe work performed in sufficient detail to permit evaluation of project relevancy to this procurement. Detail how work performed is relevant to the effort required by the solicitation? Use continuation page for additional information, if necessary.

PROJECT NO. [ ] Page 3

i. Describe any difficulties and/or obstacles encountered during project performance; steps taken toward resolution

j. Describe differing site condition(s) occurrence(s) and how each were resolved.

k. Performance Period, including contract start date (mm/dd/yyyy), and original completion date, if not completed, projected date (mm/dd/yyyy)

Contract start date (mm/dd/yyyy): Original completion date (mm/dd/yyyy):

l. Actual Completion Date (mm/dd/yyyy), and if not completed, why?

Actual Completion Date:

m. Attesting the example project is 100% complete? YES [ ]

n. The Offerors shall indicate if any of the example project provided was terminated and the type and reasons for the termination.

o. Original Contract Price (Award Amount), Final Contract Price (to include all modifications, if applicable), Explain Differences.

Original Contract Price: Final Contract Price:

Explain Differences:

PROJECT NO. [ ] Page 4