Attachment 5 YON 285 6B1 MILESTONE DSRA.xlsx
XLSX spreadsheet 19 KB Posted
- Attached to
- YON-285 Outfit
- Solicitation number
- N6264926R0013
About this file
This file is a Milestone & Key Event List for the YON-285 vessel availability management schedule, documenting critical project phases and completion dates anticipated between October 2025 and March 2027. The milestone schedule establishes a comprehensive timeline for the Sasebo Availability (SA00) commencing September 30, 2026, with key phases including prefabrication work, dry docking operations (October 15, 2026), tank closeout (January 6, 2027), undocking (January 13, 2027), and work completion (January 28, 2027). Major milestones encompass engineering testing of main and auxiliary machinery, combat systems light-off, CANES software implementation, crew movement ashore and aboard, dock trials, fast cruise, and sea trials, culminating in the end guarantee period on March 25, 2027.
The schedule correlates with the YON-285 Outfit solicitation (N6264926R0013), a Firm-Fixed-Price contract for repair and continuous maintenance of the YON-285 Craft being performed at Commander, Fleet Activities Sasebo (CFAS) on Sasebo Naval Base. The milestone document references the Sasebo Availability Management Manual as the governing directive and indicates percentage completion targets for major phases including fuel off-load (25% complete), ammunition off-load (50% complete), and LAN migration (75% complete). The Navy contract specialist for inquiries is Jason Rankin (jason.m.rankin6.civ@us.navy.mil).
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| As of | 4/17/26 | |||||||
| YON-285 7B1 Milestone & Key Event List | ||||||||
| Milestone & Key Event Item | Milestone | Key Event | Date | A+ | ||||
| Planning Start | - | PS00 | 10/5/2025,AM | -360 | ||||
| Start PREFAB Work | - | PF00 | Conferences | Expected | Days | Actual | ||
| Commence Fuel Off Load to Support SA00 | FM15 | - | 9/21/2026,AM | -10 | 25% | 10/31/2026,AM | ||
| AMMO Off Load to Support SA00 | AM15 | - | N/A | 50% | 12/1/2026,PM | |||
| LAN Migration | - | - | N/A | 75% | 1/1/2027,PM | |||
| Start Availability | - | SA00 | 9/30/2026,AM | 0 | ||||
| Crew Move Ashore | - | CM00 | N/A | |||||
| Complete Work to Support Dry Docking | DD42 | - | 10/14/2026,AM | 14 | ||||
| Commence Docking | - | DD00 | 10/15/2026,AM | 15 | ||||
| Assessments Complete 20% Avail Duration | - | AT00 | 11/2/2026,AM | 33 | ||||
| Complete Work to Support Tank Closeout | TK42 | 1/5/2027,AM | 97 | |||||
| Tank Closeout | TK00 | 1/6/2027,AM | 98 | |||||
| Complete Work to Support Undocking | UD42 | - | 1/6/2027,AM | 98 | ||||
| Commence Undocking | - | UD00 | 1/13/2027,AM | 105 | PW00 | 1/27/2027,AM | ||
| Complete All Work & Test to Support Engineering PCD | PW42 | - | 1/20/2027,AM | 112 | Engineering Test | |||
| Main/Auxiliary Machinery Space PCD | - | PW00 | 1/27/2027,AM | 119 | LOA | |||
| Complete Work and Test to Support FX00 | FX42 | - | N/A | |||||
| Combat Systems Light-Off | - | FX00 | N/A | |||||
| CANES LIGHT-OFF | - | - | N/A | CANES Software Lightoff | N/A | |||
| Complete Work and Test to Support HB00 | HB42 | - | N/A | |||||
| Crew Move Aboard | - | HB00 | N/A | |||||
| Complete All Work to Support WC00 | WC42 | 1/27/2027,AM | 119 | |||||
| Work Complete | - | WC00 | 1/28/2027,AM | 120 | ||||
| Complete Work to Support DT00 | DT42 | - | N/A | |||||
| Commence Dock Traials | - | DT00 | N/A | Wind Birds And Other Ship to Shop Antennae | ||||
| Complete Work to Support of FC00 | FC42 | - | N/A | Start Date | End Date | Days | Content | |
| Start Fast Cruise | - | FC00 | N/A | Overhaul of Wind Direction & Speed Indicator System | ||||
| Complete All Production Work to Support Sea Trials | ST42 | - | N/A | Shipping | ||||
| Commence Sea Trials | - | ST00 | N/A | Alignment & instatllation of Wind Birds | ||||
| Complete Availability | - | CA00 | 2/2/2027,AM | 125 | ||||
| Work Complete to Support EG00 | EG42 | - | 3/18/2027,AM | 44 | ||||
| End Guarantee Period | - | EG00 | 3/25/2027,AM | 51 |
These milestone & key events are referred to Sasebo Availability Management Manual.