This is an instruction document for completing the Navy ManTech Program Annual Portfolio Review forms, dated January 2024. The document provides guidance for reviewing and rating ManTech implementation projects across three key risk assessment categories: Transition Planning, Technical Progress, and Business Case Benefit.
The review form requires evaluators to rate projects using a green/yellow/red scoring system based on specific criteria. Projects are evaluated on scientific merit, innovation potential, technical progress, business case benefits, and adherence to schedule. The form includes sections for detailed comments and implementation planning information. If a project receives red ratings in two consecutive reviews, a risk mitigation plan must be developed. Completed review forms must be submitted via email to Gabriel Puente Lay at the provided Navy email address. The document was approved for public release (Distribution A) on March 1, 2017 through the Office of Naval Research Science & Technology program.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DISTRIBUTION A. Approved for public release. Distribution is Unlimited. Approved 1 March 2017
Navy ManTech Program Annual Portfolio Review
Instructions to Complete Review Forms
Jan 2024
Annual Portfolio Review Form
Add as much input as possible, particularly the Comments column. Charts provided should clearly address the column headers and key questions.
Use the drop-down menu to rate green, yellow, or red per next slide
Complete with your information
Annual Portfolio Review Form
• Use the below definitions to provide a green, yellow, or red rating in columns E, F, and G.
• These definitions are also located in the review form.
• The three categories are part of the ManTech implementation risk assessment.
• If a red rating is given two reviews in a row, a risk mitigation plan must be developed.
Completed Forms
• At the end of the review, email completed forms to Gabriel Puente Lay at gabriel.r.puentelay.ctr@us.navy.mil