This is a Contract Data Requirements List (CDRL) DD Form 1423-1 for COE Task Order 2, which specifies two key deliverables: a Project Plan (CDRL B001) and Project Final Report (CDRL B004). Both deliverables fall under contract line item 0002 and are categorized as R&D items.

The Project Plan is required once, while the Final Project Report is required quarterly. Both deliverables must follow the Navy ManTech template under ManTech Guidance documentation and are subject to Distribution Statement D, limiting distribution to Department of Defense and U.S. DoD contractors only (Critical Technology). The requiring office is N00014 (Office of Naval Research), and both items use Data Item Description DI-MISC-81612B, which will be finalized with the ONR program officer upon contract award. The submission dates align with the FY planning cycle per ONR Navy ManTech Office requirements. The contractor and contract number are listed as TBD (To Be Determined), indicating this is part of a pre-award package.

View the file

Other files

File Type Posted
Attachment 27 Cost Information 2.xlsx XLSX spreadsheet
Questions for EOC 4 24 Feb 2025.xlsx XLSX spreadsheet
EOC RFP 28 Feb 2025 Amemndment 1.pdf PDF
EOC RFP 28 Feb 2025 Amemndment 2.pdf PDF
Attachment 1 EOC 4 SOW_2-25-2025.pdf PDF
Questions for EOC 4 24 Feb 2025 2.xlsx XLSX spreadsheet
Attachment 27 Cost Information 2.docx DOCX document
Attachment 26 Cost Proposal Cost Plus Fixed Fee.xlsx XLSX spreadsheet
Solicitation - N0001425R7001 Page 1.pdf PDF
Attachment 27 Cost Information.docx DOCX document
Attachment 21 Technology Transition Plan Guidance.pdf PDF
Attachment 15 Project Quad Chart Guidance.pdf PDF
Attachment 6 Benefits and ROI Guidance.pdf PDF
Attachment 1 EOC 4 SOW.pdf PDF
Attachment 12 Navy ManTech Code 33 Monthly Report Guidance.pdf PDF
Attachment 3 Navy ManTech Program Annual Data Call.pdf PDF
Attachment 8 Final Report Guidance.pdf PDF
Attachment 24 A COE CDRLS.pdf PDF
EOC RFP 13 Feb 2025.pdf PDF
Attachment 22 Trip Report Guidance.pdf PDF
Attachment 20 Success Story Guidance.pdf PDF
Attachment 18 Quarterly Report Guidance.pdf PDF
Attachment 19 Rapid Response and Special Projects Guidance.pdf PDF
Attachment 23 CDRL Instructions for Distribution.pdf PDF
Attachment 9 Funding Allocation Spreadsheet Guidance.pdf PDF
Attachment 5 Instructions to Complete Review Forms.pdf PDF
Attachment 4 Annual Review Project Briefing Template.pdf PDF
Attachment 10 Implementation Risk Assessment Guidance.pdf PDF
Attachment 7 COE Transition Implementaion Guidance.pdf PDF
Attachment 13 Project Book Guidance.pdf PDF
Attachment 14 Project Briefing Guidance.pdf PDF
Attachment 16 Proposal Pipeline and ONR Contratracts Action Spreadsheet Guidance.pdf PDF
Attachment 17 Public Release Tool Guidance.pdf PDF
Attachment 2 Affordability Assessment Guidance.pdf PDF
Attachment 11 Key Personnel.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

Form Approved

OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services and Communications Directorate (0704-1088). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. Listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP_____ TM ______ OTHER: R&D

D. SYSTEM/ITEM

TBD

E. CONTRACT/PR NO.

TBD

F. CONTRACTOR

TBD

1. DATA ITEM NO.

B001

2. TITLE OF DATA ITEM

Project Plan

3. SUBTITLE

COE Task Order 2

4. AUTHORITY (Data Acquisition Document No.)

DI-MISC-81612B

5. CONTRACT REFERENCE

Statement of Work

6. REQUIRING OFFICE

N00014

7. DD 250 REQ

N/A

9. DIST STATEMENT

REQUIRED

# Dist. D

10. FREQUENCY

Once

12. DATE OF FIRST SUBMISSION

** Block 16

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

N/A

11. AS OF DATE

13. DATE OF SUBSEQUENT

SUBMISSION

Once

Draft Final

Reg Repro

16. Remarks:

The contractor shall submit Project Plan in accordance with SOW and current Navy ManTech template under the ManTech Guidance documentation.

# Block 9: DISTRIBUTION STATEMENT D. Distribution authorized to the Department of Defense and U.S. DoD contractors only (Critical Technology) (date of determination). Other requests shall be referred to the Office of Naval Research, Code 332, COR noted in the contract.

** Blocks 11 and 12: The Project Plan for each planned project will be due in accordance to FY planning cycle in accordance to the ONR Navy ManTech Office.

Use of DI-MISC-81612B will be discussed with ONR program officer upon contract award to finalize content according to ManTech Guidance.

See Enclosure 1

15. TOTAL

G. PREPARED BY

William Crespo

H. DATE

01/06/2025

I. APPROVED BY:

William Crespo

J. DATE

01/06/2025

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 1 of 6 Pages

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 2 of 6 Pages

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 3 of 6 Pages

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

Form Approved

OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services and Communications Directorate (0704-1088). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. Listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP_____ TM ______ OTHER: R&D

D. SYSTEM/ITEM

TBD

E. CONTRACT/PR NO.

TBD

F. CONTRACTOR

TBD

1. DATA ITEM NO.

B004

2. TITLE OF DATA ITEM

Project Final Report

3. SUBTITLE

COE Task Order 2

4. AUTHORITY (Data Acquisition Document No.)

DI-MISC-81612B

5. CONTRACT REFERENCE

Statement of Work

6. REQUIRING OFFICE

N00014

7. DD 250 REQ

N/A

9. DIST STATEMENT

REQUIRED

# Dist. D

10. FREQUENCY

Quarterly

12. DATE OF FIRST SUBMISSION

See Block 16

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

N/A

11. AS OF DATE

13. DATE OF SUBSEQUENT

SUBMISSION

Once

Draft Final

Reg Repro

16. Remarks:

The contractor shall submit Final Project Report in accordance with SOW and current Navy ManTech template under the ManTech Guidance documentation.

# Block 9: DISTRIBUTION STATEMENT D. Distribution authorized to the Department of Defense and U.S. DoD contractors only (Critical Technology) (date of determination). Other requests shall be referred to the Office of Naval Research, Code 332, COR noted in the contract.

** Blocks 11 and 12: The Project Plan for each planned project will be due in accordance to FY planning cycle in accordance to the ONR Navy ManTech Office.

Use of DI-MISC-81612B will be discussed with ONR program officer upon contract award to finalize content according to ManTech Guidance.

See Enclosure 1

15. TOTAL

G. PREPARED BY

William Crespo

H. DATE

01/06/2025

I. APPROVED BY

William Crespo

J. DATE

01/06/2025

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 4 of 6 Pages

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 5 of 6 Pages

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 6 of 6 Pages r

File details come from the government source that posted it. Updated .