This document is a section of a Request for Proposals (RFP) for a Design/Build project to install 20kW Cummins generators at buildings B810 and B845 at Beale Air Force Base.
The solicitation is seeking proposals for the design, permitting, construction, and installation of the generator systems, including removal and disposal of the existing systems. Proposals must be submitted by July 26, 2024 at 1:00 PM PST. The contract will be awarded based on a best value determination considering the offeror's technical approach, cost/price, and qualifications/experience. The technical proposal must detail the contractor's work plan, schedule, and compliance with DoD regulations. The cost proposal will be evaluated for reasonableness. Offerors must demonstrate relevant experience installing 20kW generators, especially Cummins models, on military installations. The magnitude of the contract is estimated between $500K to $1M. A mandatory site visit is scheduled for July 22, 2024.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA468624R0025 – Cummins Generator Installation (B810 & B845), Beale AFB
1. SECTION L - INSTRUCTIONS TO OFFERORS
L.1 Introduction
1. Purpose: This section provides instructions, conditions, and notices to offerors for the design and construction of 20kW Cummins generators to be installed at buildings B810, and B845. The solicitation is structured to emphasize the "Best Value" approach, ensuring a comprehensive evaluation that goes beyond cost considerations alone.
2. Overview: The Contractor shall submit one (1) proposal. The proposal shall be prepared in accordance with the following instructions, outlining the approach, methodology, and qualifications for the successful completion of the bid-build project. The proposal shall be clear, concise, and shall include sufficient detail for effective evaluation and for substantiating the validity of stated claims. The proposal should not simply rephrase or restate the Government's requirements but, rather, shall provide convincing rationale to address how the Offeror intends to meet these requirements. Offerors shall assume that the Government has no prior knowledge of their facilities or experience and will base its evaluation on the information presented in the Offeror's proposal.
L.2 Proposal Submission
1. Format: The proposal shall be submitted electronically via email to the contract administrator and contracting officer and prepared in accordance with the instructions provided in this solicitation and include the following sections:
a. Technical Proposal: Details of the proposed design, permitting, and construction/installation, ensuring compliance with DoD regulations.
b. Cost Proposal: A detailed breakdown of the costs associated with each phase of the Design/Build project.
2. Submission Deadline: Proposals must be submitted no later than 26 July 2024 at 1300 (1:00 pm) PST (Pacific Standard Time).
L.3 Technical Proposal Requirements.
1. Construction/Installation: The contractor is responsible for obtaining all necessary permits ensuring compliance with DoD regulations and other applicable laws and regulations. The Technical Proposal should be specific and complete. Legibility, clarity, and coherence are very important. Contractor responses will be evaluated against the Technical subfactors defined in this document. The Contractor is expected to provide as specifically as possible, the actual methodology that they intend to would use for accomplishing/satisfying these subfactors. Contractors will address their technical solution for meeting or exceeding the government’s minimum performance or capability requirements of each technical subfactor. All the requirements specified in the solicitation are mandatory. By submitting a proposal, the Contractor is representing that their firm will perform all of the requirements specified in the solicitation. The Contractor shall not merely reiterate the objectives or reformulate the requirements specified in the solicitation.
L.4 Evaluation Criteria/Factors Overview: Proposals will be evaluated based on the following criteria:
a. Technical Approach and Methodology
b. Cost Proposal/Price
c. Qualifications and Experience
1. FACTOR 1: Technical Approach and Methodology
a. Sub-Factor 1.1 – Statement of Work (SOW): The contractor’s SOW clearly details how work will be accomplished and meets/addresses the Government’s SON. The contractors SOW shall provide a written plan describing in detail all phases of equipment installation, address work sequencing, site preparation, equipment installation, and reporting.
b. Sub-Factor 1.2 – Schedule: The contractor’s proposal provides a progress schedule (design/construction) with a reasonable period of performance. This will be submitted on an AF 3064. The project schedule that the Contractor submits must include, at minimum, the Purchase Order (TO) award date, period of performance of the TO, and description of each task in a project schedule.
2. FACTOR 2: Cost Proposal/Price:
a. The cost proposal will be evaluated based on the total proposed cost for the entire Design/Build project.
1. All proposals shall be accompanied by a Bid-Schedule in order to be considered for evaluation.
3. FACTOR 3: Qualifications and Experience
a. Offerors will be evaluated based on their relevant experience in the removal & disposal of diesel generator systems, along with relevant experience in the installation of 20kW generator systems – to include compatible Bypass ATS’. Offeror shall highlight key projects, expertise with these disciplines, and any experience on military installations or compliance with DoD regulations.
1. Offeror shall provide information on certifications, and qualifications related to projects for the installation of 20kW generators, with specialization in Cummins generators.
2. Offeror is required to furnish documentation demonstrating successful completion of relevant contracts.
L.5 Basis of Award
1. This is a Design/Build project, and offerors are expected to provide comprehensive proposals that address all aspects of the Design/Build process, to include compliance with DoD regulations.
2. Award will be made in accordance with the procedures specified, and on the basis of the lowest priced proposal meeting the acceptability standards for non-price factors. An order may be awarded to the contractor who is deemed responsible IAW FAR 9.1, as supplemented, whose proposal conforms to the requirements (to include all stated terms, conditions, representations, certifications, and all other information required by the instructions) and is judged, based on the evaluation factors and subfactors, to represent the technically acceptable proposal with the lowest complete and reasonable price.
3. The Government will review Offeror Bid Schedules and arrange all proposals from lowest-priced to highest-priced. Bid Schedules must be complete, in order to be further considered. The Government will then evaluate offeror technical proposals and rate as either acceptable or unacceptable for each subfactor. An acceptable subfactor clearly meets the minimum requirements of the solicitation. Unacceptable technical proposals may not be further evaluated; however, the Government may conduct interchanges, as determined by the CO. The Government will then evaluate offerors’ price proposals and rate as Fair and Reasonable or Not Fair and Reasonable. Not Fair and Reasonable proposals may not be further evaluated; however, the Government may conduct interchanges as determined by the CO. Fair and Reasonableness will be determined by comparison to the Independent Government Estimate, other prices proposed, historical prices paid, or any other price analysis technique identified in FAR 15.404-1(b)(2). Price comparison using one or more of these techniques may identify unreasonable pricing (too low or too high). Unreasonable pricing may result in the Offerors’ proposal being not awardable.
L.6 Submission Instructions All proposals shall be submitted electronically to SrA James Buyag at james_bryan.buyag@us.af.mil.