Attachment 3. BAEY 240021 - AF 66.xls

XLS spreadsheet 55 KB Posted

Attached to
Cummins Generator Installation (B810 & B845)
Solicitation number
FA4686R0025
Issued by

About this file

This document is an attachment related to a federal contract opportunity for the replacement of a 20kW generator and associated equipment at Facility B810 on Beale Air Force Base. The key details are:

The solicitation number is FA4686R0025 and the opportunity is for the Cummins Generator Installation (B810 & B845) project. The government is seeking proposals for the removal and disposal of the existing standby diesel generator system and Automatic Transfer Switch (ATS), and the installation of a new Cummins 20kW generator system, fuel tank, and Cummins Diesel compatible Bypass ATS. The work must be performed in accordance with UFC 3-540-01, NFPA 70, and NFPA 110 requirements. The magnitude of the contract is between $500k and $1M. The site visit is scheduled for July 22, 2024, the RFI deadline is July 23, 2024, and the proposal deadline is July 26, 2024. The contracting agency is the Department of the Air Force Air Combat Command.

View the file

Other files

File Type Posted
Solicitation Amendment FA468624R00250004 SF 30.pdf PDF
Solicitation Amendment - FA468624R00250004.pdf PDF
Attachment 7.docx DOCX document
Solicitation Amendment - FA468624R00250003.pdf PDF
Solicitation Amendment FA468624R00250003 SF 30.pdf PDF
Solicitation Amendment - FA468624R00250001.pdf PDF
Attachment 5. FA468624R0025 Section M (25Jul24).docx DOCX document
Attachment 7. Resp_RFIs for Cummins Generator Installation (B810, B845) Version 2.pdf PDF
Solicitation Amendment FA468624R00250002 SF 30.pdf PDF
Attachment 4. FA468624R0025 Section L (25Jul24).docx DOCX document
Solicitation Amendment FA468624R00250001 SF 30.pdf PDF
Solicitation Amendment - FA468624R00250001.pdf PDF
Attachment 7. Responses_RFIs for Cummins Generator Installation (B810 B845).pdf PDF
Attachment 1. FA468624R0025 - B810 and B845 SON Version 2 (24 July 24).pdf PDF
Attachment 2. BAEY 240021 - Site Plan Version 2 (24Jul24).pdf PDF
Attachment 8. B845 - Site Pictures, Combined.pdf PDF
Attachment 5. FA468624R0025 Section M.docx DOCX document
Attachment 6. AF 3064 Progress Schedule.xlsx XLSX spreadsheet
Solicitation - FA468624R0025.pdf PDF
Attachment 1. FA468624R0025 - B810 and B845 SON.docx DOCX document
Attachment 4. FA468624R0025 Section L.docx DOCX document
Attachment 2. BAEY 240021 - Site Plan.pdf PDF
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submittal 1

SCHEDULE OF MATERIAL SUBMITTALSPROJECT NUMBERPROJECT NAMESOLICITATION /CONTRACT NUMBER
BAEY 240021B810 – Replace 20 kW Generator and Associated EquipmentFA4686-24-D-000X-00XX ; TBD
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACT ADMINISTRATOR
LINE NUMBERNote: 3 copies required per submittal. Government will retain all submittals. Provide an electronic copy for each submittal.CERTIF. OF COMPLIANCESHOP DRAWINGSCOLOR SELECTIONMANUFATURUR'S RECOMMENDATIONCATALOG DATAO&M RECOMMENDATIONSCALCULATIONSWARRANTYDRAWINGSREPORTTEST RESULTSREQUIRED SUBMISSION DATEDATE TO CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSAPPROVEDDISAPPROVEDCONTRACTOR SUBMITTALFINAL APPROVAL
GENERAL
Project Specific Form 66XNTP + 3
Construction ScheduleXNTP + 7
TCN Schedule (electronic required, hard copy optional)XNTP + 7
Contractor's Health, Safety, and Environment PlanXNTP + 7
Contractor's QA/QC PlanXNTP + 7
Copy of Engineering License(s) of person or consultancy responsible for designXDesign
DESIGN
All submissions to be provided in hard copy and electronically unless noted otherwise. 65%, 95%, and 100% Design Documents to include:XNTP + 21 (65%) NTP + 35 (95%) NTP + 45 (100%)
Roof Drain Storm Sewer Tie InXNTP+45
Wind Loading Diagrams for RoofXXNTP+45PE STAMP REQ'D
Structural Connection Details for Shear WallsXXNTP+45PE STAMP REQ'D
Structural Connection Details for FramingXXNTP+45PE STAMP REQ'D
Structural Connection Details for Blast Resistant Doors & WindowsXXNTP+45PE STAMP REQ'D
HVAC CalculationsXXNTP+45
Sprinkler LayoutXNTP+45FPE or NICET Tech stamp req'd
Fire Alarm LayoutXNTP+45FPE or NICET Tech stamp req'd
Communications LayoutXNTP+45
Technical SpecificationsXNTP+45PE STAMP REQ'D, NO HARD COPY
DEMOLITION/ASBESTOS
Demolition PlanXXXNTP+45
Asbestoes PlanXXXNTP+45
CIVIL
Soil Gradations for each type of soil usedXXInstall -7
Moisture-Density curve for each type of soil usedXInstall -7
Nuclear Densometer CalibrationXInstall -7
Soil Compaction Test Results for Utilities, Facilities & PavementXXInstall+7
Storm PipeXDesign+14
ARCHITECTURAL
Blast Resistant Doors and FramesXXXNTP+45
Door HardwareXXNTP+45Hardware Schedule
Gypsum Board-Type XXXNTP+45
Gypsum Board-Type X-Mold ResistantXXNTP+45
Wood PanelingXXXNTP+45
Wood Chair RailsXXXNTP+45
Wood Ceiling CloudXXXNTP+45
Sheet Vinyl FlooringXXXNTP+45
Rubber BaseXXXNTP+45
Ceiling TilesXXXNTP+45
Blast Resistant WindowXXXXXXXNTP+45
GlazingXXXNTP+45
Solid Surface CountertopsXXXXNTP+45
Kitchen CabinetsXXXXXNTP+45
Garbage DisposalXXNTP+45
Interior PaintXXXNTP+45
Exterior PaintXXXNTP+45
Roofing SystemXXXXXNTP+45
Roofing InsulationXXXXXXNTP+45
Roof DrainsXXXXXNTP+45
ScuppersXXNTP+45
CopingXXNTP+45
FlashingXXNTP+45
STRUCTURAL
Reinforcing Steel DrawingsXNTP+45
Concrete Mix DesignXXNTP+45
Concrete Curing Compounds, Admixtures, Joint Sealants, Expansion JointsXXXXXNTP+45
Concrete Field Test ResultsXNTP+45
Reinforcing Steel Mill CertificationsXXNTP+45
Slump Test results & Concrete Truck Tickets (per truck)XTest + 3
7-Day Concrete Compressive Strength TestXXTest + 3
28-Day Concrete Compressive Strength TestXXTest + 3
Blast Resistant Window AttachmentXXDesign + 14
MECHANICAL
HVAC BalancingXDesign+14
RegistersXXDesign+14
DampersXXDesign+14
DuctworkXDesign+14
Sprinkler HeadsXXNTP+14
Ductwork Pressure Drops Before RemovalXXNTP+14
Ductwork Pressure Drops After InstallationXXNTP+14
DuctworkXXNTP+14
ControlsXXDesign+14
PipingXDesign+14
HeatersXXDesign+14
ValvesXXDesign+14
PumpsXXDesign+14
Thermal InsulationXXDesign+14
InstrumentationXXDesign+14
PLUMBING
Plumbing FixturesXXXXXNTP+45
Piping for WaterXXNTP+45
Garbage DisposalXXNTP+45
Waste and VentXXXXNTP+45
INTERIOR ELECTRICAL
Cables(electrical,comm,fire alarm)XXXXXXXXNTP+45
SwitchesXXXXXXXXNTP+45
ReceptaclesXXXXXXXXNTP+45
PanelsXXXXXXXXNTP+45
BreakersXXXXXXXXNTP+45
ConduitsXXXXXXXXNTP+45
Lighting FixturesXXXXXXXXNTP+45
Lighting UPS units (if req'd)XXXXXXXNTP+45
Communication System Outlets(incl jacks)XXXXXXXXNTP+45
Communications patch panelsXXXXXXXNTP+45
PA SpeakersXXXXXXXNTP+45
Fire Alarm Devices (All)XXXXXXXXXXNTP+45
Occupancy SensorsXXXXXXXXNTP+45
Power PacksXXXXXXXNTP+45
EXTERIOR ELECTRICAL
ConduitsXXNTP+14
TransformerXXXXXXNTP+14
MeterXXXXXNTP+14
Cables(med & low voltage)XXXXNTP+14
SwitchesXXNTP+14
ContactorsXXXNTP+14
PanelsXXNTP+14
BreakersXXNTP+14
ControllerXXXNTP+14
Junction CabinetXXXXXNTP+14
Heating MatXXXXXXXXNTP+14
CLOSEOUT
O&M maint data and maint manuals & Manufacturer's Warranty for Communications EquipmentXXXInstall + 4
Factory and Field Test Certificates, Logs and Test ResultsXBefore Acceptance
Inspection LogbookXBefore Acceptance
As Builts (electronic in AutoCAD and hard copies on Mylar)XFinal + 7

File details come from the government source that posted it. Updated .