This document is a comprehensive Project Manual Volume 1 for the FAA V-PAR (Vertical Takeoff and Landing Performance and Analysis Range) project located at the Mike Monroney Aeronautical Center in Oklahoma City, Oklahoma. The project manual includes detailed technical specifications for a single-story facility consisting of a 5,625 square foot hangar with structural steel or reinforced concrete construction and a 1,600 square foot administration/restroom space with light frame construction.
The geotechnical report accompanying the project manual provides critical site preparation recommendations, including subgrade improvement options to mitigate potential vertical soil movements. Key design parameters include foundation options such as conventional shallow foundations, monolithic slab/grade beam systems, or drilled pier foundations, with specific engineering specifications for soil bearing pressures, settlement expectations, and construction methodologies. The project is part of a federal solicitation (6973GH-26-R-00020) set aside for small businesses, with an estimated price range of $5-10 million, and proposals were due November 17th under the Federal Aviation Administration's procurement process.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Mike Monroney Aeronautical Center
Oklahoma City, OK
V-PAR
VTOL - Performance and Analysis Range
100% Type B Design Analysis
Contract No. 6973GH-21-D-00046
Work Order # 23-030509
September 18, 2025 October 15, 2025
100% IFC - Project Manual Volume 1
This page intentionally left blank
V-PAR, VTOL – PERFORMANCE AND ANALYSIS RANGE BUILDING OK70448-013
SEALS PAGE 00 01 07 - 1
15 October 2025
10/15/2025
SEALS PAGE 00 01 07 - 2
TABLE OF CONTENTS 00 01 10 - 1
SECTION 00 01 10
TABLE OF CONTENTS
SECTIONS PAGES
VOLUME 1
COVER & TABLE OF CONTENTS
00 00 00 - TYPE B PROJECT MANUAL COVER VOLUME 1
00 01 07 - SEALS PAGE
00 01 10 - TABLE OF CONTENTS
DIVISION 00 — PROCUREMENT AND CONTRACTING REQUIREMENTS
00 31 32 - GEOTECHNICAL DATA
00 31 32.1 - FAA Vertiport Facility - ECS Project No. 2033
DIVISION 01 — GENERAL REQUIREMENTS
01 01 00 - SUMMARY OF WORK
01 01 90 - CONTRACT CONSIDERATIONS
01 02 80 - MODIFICATION PROCEDURES
01 03 00 - OPTIONS
01 03 90 - COORDINATION AND MEETINGS
01 30 00 - SUBMITTALS
01 40 00 - QUALITY REQUIREMENTS
01 40 00.01 - STATEMENT OF SPECIAL INSPECTIONS (SSI) -2018
01 43 39 - MOCKUPS
01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
01 57 23 - STORMWATER POLLUTION PREVENTION
01 59 00 - FIELD OFFICES AND SHEDS
01 60 00 - MATERIAL AND EQUIPMENT
01 60 10 - SUBSTITUTION REQUEST FORM
01 65 00 - STARTING OF SYSTEMS
01 70 00 - CONTRACT CLOSEOUT
01 73 00 - OPERATION AND MAINTENANCE DATA
01 74 19 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL PART 1 - GENERAL
01 77 00 - CLOSEOUT PROCEDURES
DIVISION 03 — CONCRETE
03 10 00 - CONCRETE FORMING AND ACCESSORIES
03 20 00 - CONCRETE REINFORCING
03 30 00 - CAST-IN-PLACE CONCRETE
03 35 11 - CONCRETE FLOOR FINISHES
DIVISION 05 — METALS
05 12 00 - STRUCTURAL STEEL FRAMING
05 21 00 - STEEL JOIST FRAMING
05 31 00 - STEEL DECKING
05 40 00 - COLD-FORMED METAL FRAMING
05 50 00 - METAL FABRICATIONS AND MISCELLANEOUS METAL
DIVISION 06 — WOOD, PLASTICS, AND COMPOSITES
06 10 00 - ROUGH CARPENTRY
06 16 00 - SHEATHING
06 41 00 - ARCHITECTURAL WOOD CASEWORK
06 64 00 - PLASTIC PANELING
TABLE OF CONTENTS 00 01 10 - 2
DIVISION 07 — THERMAL AND MOISTURE PROTECTION
07 21 00 - THERMAL INSULATION
07 21 19 - FOAMED-IN-PLACE INSULATION
07 27 26 - FLUID-APPLIED MEMBRANE AIR BARRIERS
07 42 13.13 - FORMED METAL WALL PANELS
07 54 23 - THERMOPLASTIC-POLYOLEFIN (TPO) ROOFING
07 62 00 - SHEET METAL FLASHING AND TRIM
07 71 00 - MANUFACTURED ROOF SPECIALTIES
07 92 00 - JOINT SEALANTS
DIVISION 08 — OPENINGS
08 11 13 - HOLLOW METAL DOORS AND FRAMES
08 41 13 - ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS
08 71 00 - DOOR HARDWARE
08 80 00 - GLAZING
08 91 19 - FIXED LOUVERS
DIVISION 09 — FINISHES
09 22 16 - NON-STRUCTURAL METAL FRAMING
09 29 00 - GYPSUM BOARD
09 30 13 - CERAMIC TILING
09 51 13 - ACOUSTICAL PANEL CEILINGS
09 65 13 - RESILIENT BASE AND ACCESSORIES
09 65 19 - RESILIENT TILE FLOORING
09 91 13 - EXTERIOR PAINTING
09 91 23 - INTERIOR PAINTING
09 96 00 - HIGH-PERFORMANCE COATINGS
DIVISION 10 — SPECIALTIES
10 14 23 - ROOM-IDENTIFICATION PANEL SIGNAGE
10 14 23 -1 - FAA-MMAC DOOR SIGN CRITERIA
10 28 00 - TOILET ACCESSORIES
10 44 13 - FIRE PROTECTION CABINETS
10 44 16 - FIRE EXTINGUISHERS
10 73 16 - WEATHER SHELTER CANOPY
10 73 20 - CANTILEVER CANOPIES
DIVISION 11 — EQUIPMENT
11 30 13 - RESIDENTIAL APPLIANCES
DIVISION 12 — FURNISHINGS
12 24 13 - ROLLER WINDOW SHADES
12 36 61.10 - SOLID SURFACE COUNTERTOPS
DIVISION 22 — PLUMBING
22 05 00 - COMMON WORK RESULTS FOR PLUMBING
22 05 23 - GENERAL-DUTY VALVES FOR PLUMBING PIPING
22 05 29 - HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT
22 05 53 - IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT
22 07 19 - PLUMBING PIPING INSULATION
22 11 16 - DOMESTIC WATER PIPING
22 11 19 - DOMESTIC WATER PIPING SPECIALTIES
22 13 16 - SANITARY WASTE AND VENT PIPING
22 13 19 - SANITARY WASTE PIPING SPECIALTIES
22 13 19.13 - SANITARY DRAINS
22 14 14 - STORM DRAINAGE PIPING
22 14 23 - STORM DRAINAGE PIPING SPECIALTIES
TABLE OF CONTENTS 00 01 10 - 3
22 33 00 - ELECTRIC, DOMESTIC-WATER HEATERS
22 42 00 - COMMERCIAL PLUMBING FIXTURES
DIVISION 23 — HEATING VENTILATING AND AIR CONDITIONING
23 05 00 - COMMON WORK RESULTS FOR HVAC
23 05 48.13 - VIBRATION CONTROLS FOR HVAC
23 05 53 - IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT
23 05 93 - TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 13 - DUCT INSULATION
23 07 19 - HVAC PIPING INSULATION
23 23 00 - REFRIGERANT PIPING
23 31 13 - METAL DUCTS
23 33 00 - AIR DUCT ACCESSORIES
23 33 46 - FLEXIBLE DUCTS
23 34 00 - HVAC FANS
23 37 13.13 - AIR DIFFUSERS
23 37 13.23 - REGISTERS AND GRILLES
23 81 26 - SPLIT-SYSTEM AIR-CONDITIONERS
23 81 26.01 - MINI-SPLIT AIR-CONDITIONERS
VOLUME 2
DIVISION 26 — ELECTRICAL
26 00 10 - SUPPLEMENTAL REQUIREMENTS FOR ELECTRICAL
26 05 13 - MEDIUM-VOLTAGE CABLES
26 05 19 - LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
26 05 26 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
26 05 29 - HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
26 05 33.13 - CONDUITS FOR ELECTRICAL SYSTEMS
26 05 33.16 - BOXES AND COVERS FOR ELECTRICAL SYSTEMS
26 05 43 - UNDERGROUND DUCTS AND RACEWAYS FOR ELECTRICAL SYSTEMS
26 05 44 - SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING
26 05 53 - IDENTIFICATION FOR ELECTRICAL SYSTEMS
26 05 72 - OVERCURRENT PROTECTIVE DEVICE SHORT-CIRCUIT STUDY PART 1 - GENERAL
26 05 73 - OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY PART 1 - GENERAL
26 05 74 - OVERCURRENT PROTECTIVE DEVICE ARC-FLASH STUDY PART 1 - GENERAL
26 09 23 - LIGHTING CONTROL DEVICES
26 12 00 - VOLTAGE TRANSFORMERS
26 13 29 - VOLTAGE COMPARTMENTALIZED SWITCHGEAR
26 18 23 - MEDIUM VOLTAGE SURGE ARRESTERS
26 22 13 - LOW-VOLTAGE DISTRIBUTION TRANSFORMERS
26 24 16 - PANELBOARDS
26 27 13 - ELECTRIC METERS
26 27 26 - WIRING DEVICES
26 28 16 - ENCLOSED SWITCHES AND CIRCUIT BREAKERS
26 41 13 - LIGHTNING PROTECTION SYSTEMS
26 43 13 - SURGE PROTECTIVE DEVICES FOR LOW-VOLTAGE ELECTRICAL POWER CIRCUITS
26 50 00 - LIGHTING
DIVISION 27 — COMMUNICATIONS
27 00 00 - GENERAL PROVISION FOR TELECOMMUNICATIONS SPECIFICATIONS
CONSTRUCTION STANDARD
27 00 00.1 - TELECOMMUNICATIONS STANDARDS FOR THE MIKE MONRONEY AERONAUTICAL
CENTER
27 10 00 - STRUCTURED CABLING
TABLE OF CONTENTS 00 01 10 - 4
DIVISION 28 — ELECTRONIC SAFETY AND SECURITY
28 14 00 - ACCESS CONTROL SYSTEM HARDWARE
28 31 10 - FIRE ALARM SYSTEM, ADDRESSABLE, TONE TYPE
DIVISION 31 — EARTHWORK
200 - EARTHWORK (COKC)
300 - SURFACES (COKC)
31 31 16 - TERMITE CONTROL
400 - CONCRETE (COKC)
500 - WATER (COKC)
600 - SANITARY (COKC)
800 - INCIDENTAL CONSTRUCTION (COKC)
900 - MATERIALS (COKC)
C-102 TEMPORARY AIR AND WATER POLLUTION, SOIL EROSION, AND SILTRATION CONTROL
D-701 PIPE FOR STORM DRAINS AND CULVERTS
D-751 MANHOLES, CATCH BASINS, INLETS AND INSPECTION HOLES
L-107 AIRPORT WIND CONES
L-108 UNDERGROUND POWER CABLE FOR AIRPORTS
L-110 AIRPORT UNDERGROUND ELECTRICAL DUCT BANKS AND CONDUITS
L-115 ELECTRICAL JUNCTION STRUCTURES
L-125 INSTALLATION OF AIRPORT LIGHTING SYSTEMS
P-152 EXCAVATION, SUBGRADE, AND EMBANKMENT
P-156 CEMENT TREATED SUBGRADE
P-209 CRUSHED AGGREGATE BASE COURSE
P-501 CEMENT CONCRETE PAVEMENT
P-605 JOINT SEALANTS FOR PAVEMENTS
P-610 CONCRETE FOR MISCELLANEOUS STRUCTURES
P-620 RUNWAY AND TAXIWAY MARKING
T-904 SODDING
T-905 TOPSOIL
DIVISION 33 — UTILITIES
33 71 19 - ELECTRICAL UNDERGROUND DUCTS, DUCTBANKS, AND MANHOLES
GEOTECHNICAL DATA 00 31 32 - 1
DOCUMENT 00 31 32 - GEOTECHNICAL DATA
PART 1 - GENERAL
1.1 GEOTECHNICAL DATA
A. This Document, with its referenced attachments, is part of the Procurement and Contracting Requirements for the Project. They provide Owner's information for Bidders' convenience and are intended to supplement rather than serve in lieu of Bidders' own investigations. They are made available for Bidders' convenience and information. This Document and its attachments are not part of the Contract Documents.
B. Because subsurface conditions indicated by the soil borings are a sampling in relation to the entire construction area, and for other reasons, Owner, Architect, Architect's consultants, and the firm reporting the subsurface conditions do not warranty the conditions below the depths of the borings or that the strata logged from the borings are necessarily typical of the entire site.
Any party using the information described in the soil borings and geotechnical report accepts full responsibility for its use.
C. A Geotechnical Investigation Report for Project, prepared by ECS Southwest, LLP, dated February 21, 2025, is available for viewing as appended to this Project Manual.
1. The opinions expressed in this report are those of a geotechnical engineer and represent interpretations of subsoil conditions, tests, and results of analyses conducted by a geotechnical engineer. Owner is not responsible for interpretations or conclusions drawn from the data.
2. Any party using information described in the geotechnical report will make additional test borings and conduct other exploratory operations that may be required to determine the character of subsurface materials that may be encountered at no additional cost to the Owner.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF DOCUMENT 00 31 32
ECS Southwest, LLP Geotechnical Engineering Report FAA Vertiport Facility
McLucas Steet and Halaby Drive Oklahoma City, Oklahoma
ECS Project Number 58:2033
February 21, 2025
FAA Vertiport Facility February 21, 2025 ECS Project No. 58:2033 Page i
TABLE OF CONTENTS
EXECUTIVE SUMMARY
1.0 INTRODUCTION
2.0 PROJECT INFORMATION
2.1 Project Location/Current Site Use
2.2 Proposed Construction
3.0 FIELD EXPLORATION AND LABORATORY TESTING
3.1 Subsurface Characterization
3.2 Groundwater Observations
3.3 Laboratory Testing
4.0 DESIGN RECOMMENDATIONS
4.1 Potential Vertical Movements
4.2 Subgrade Improvements
4.3 Shallow Foundations
4.4 Drilled Piers
4.4.1 Lateral Considerations
4.4.2 Uplift Considerations
4.5 Building Slab
4.5.1 Structurally Suspended Slab
4.5.1 Slab on Grade
4.6 Building Perimeter Conditions
4.7 Seismic Design Considerations
4.8 Pavements
4.9 Site Retaining Walls
4.10 Corrosion Potential
5.0 SITE CONSTRUCTION RECOMMENDATIONS
5.1 Subgrade Preparation
5.1.1 Stripping and Grubbing
5.1.2 Proofrolling
5.2 Earthwork Operations
5.2.1 Fill Placement
5.2.2 Earthwork Testing
5.3 Material Specifications
5.3.1 Select Fill
5.3.2 Moisture Conditioning
5.3.3 Lime Stabilized On Site Clay
5.4 Foundation and Slab Observations
5.5 Utility Installations
6.0 CLOSING
ECS Project No. 58:2033 Page ii
APPENDICES
Appendix A – Drawings & Reports
• Site Location Diagram
• Boring Location Diagram
• Generalized Subsurface Soil Profile A-A’
• Clay Plug Detail at Trench
Appendix B – Field Operations
• Reference Notes for Boring Logs
• Subsurface Exploration Procedures: Standard Penetration Testing (SPT)
• Boring Logs B-01 to B-08
Appendix C – Laboratory Testing
• Laboratory Testing Summary
• Standard Proctor Curve Test Reports
• California Bearing Ratio (CBR) Test Reports
ECS Project No. 58:2033 Page 1
EXECUTIVE SUMMARY
This Executive Summary is intended as a very brief overview of the primary geotechnical conditions that are expected to affect design and construction. The following summarizes the main findings of the exploration, particularly those that may have a cost impact on the planned development.
Further, our principal foundation recommendations are summarized. Information gleaned from the executive summary should not be utilized in lieu of reading the entire geotechnical report.
• The planned project consists of the construction of an approximately 5,625 square feet, one-vehicular hangar consisting of structural steel or cast-in-place reinforced concrete construction with an approximately 1,600 square feet, single-story, administration/restroom space consisting of light frame construction and associated ground-based landing pad/apron and parking/drive areas. We have assumed the structures will be entirely above grade. We understand anticipated maximum structural loads are to be column loading of 200 kips and have assumed maximum wall loads of 6 kips/foot. We have assumed the structure will have a finished floor elevation at or near the existing grade.
• The planned structures may be supported on a shallow foundation system consisting of spread footings with conventional slab on grade, provided the subgrade is improved and prepared as outlined in this report. Should improving the subgrade in order to use conventional spread footings and slab on grade be cost prohibitive, a reinforced slab with grade beams (monolithic slab/BRAB) or post-tensioned slab on grade may be used on the existing soils. As an alternative, a drilled pier and grade beam foundation system could also be used. Drilled piers should extend into the underlying weathered shale and can be used with a conventional slab on grade, provided the subgrade is improved as recommended.
Alternatively, drilled piers could be used with a structurally suspended floor slab in which case subgrade improvements are not required.
• The soils encountered at the site are highly active. Therefore, subgrade improvements will be necessary to reduce the potential for vertical movements. Specific details on addressing these highly expansive clay soils are presented in the body of the report.
• Pavements should be supported directly on stabilized subgrades or a layer of aggregate base upon subgrades that are evaluated and prepared as outlined in this report.
• It is recommended that ECS conduct a geotechnical review of the project plans (prior to issuance for construction) to check to see that ECS’ geotechnical recommendations have been properly interpreted and implemented.
• To prevent misinterpretation of ECS recommendations, ECS should be retained to perform quality control testing and documentation during construction of the earthwork and foundations for the project.
ECS Project No. 58:2033 Page 2
1.0 INTRODUCTION
The purpose of this study was to provide geotechnical information for the design and construction of the foundations, floor slabs, retaining walls, and pavements for the planned FAA Vertiport Facility project located near McLucas Street and Halaby Drive within the Mike Monroney Aeronautical Center campus in Oklahoma City, Oklahoma. The recommendations developed for this report are based on project information provided by the client.
Our services were provided in accordance with our Proposal No. 58:3505-GP Revised, dated December 18, 2024, and authorized by the client by providing the subconsultant task order OK70448011-0820 on January 3, 2025
This report contains the procedures and results of our subsurface exploration and laboratory testing programs, review of existing site conditions, engineering analyses, and recommendations for the design and construction of the project.
The report includes the following items.
• A brief review and description of our field and laboratory test procedures and the results of testing conducted.
• A review of surface topographical features and site conditions.
• A review of area and site geologic conditions.
• A review of subsurface soil stratigraphy with pertinent available physical properties.
• A final copy of our soil test borings.
• Recommendations for site preparation and construction of compacted fills, including an evaluation of on-site soils for use as compacted fills.
• Recommended foundation types.
• General recommendations for pavement design.
• General recommendations for retaining wall design.
2.0 PROJECT INFORMATION
2.1 PROJECT LOCATION/CURRENT SITE USE
The project is located along the westbound side of McLucas Street and is approximately 1,000 feet west of Halaby Drive within the Mike Monroney Aeronautical Center campus in Oklahoma City, Oklahoma. The location is depicted in Figure 2.1.1 as shown below.
ECS Project No. 58:2033 Page 3
Figure 2.1.1. Site Location
ECS reviewed aerial photographs of the subject site dated 1990 to 2024. Since April 1990, the site has been an undeveloped, grassed property. At some time between February 1995 and October 1998, it appears McLucas Street and Halaby Drive were constructed in areas south and east of the site. Since that time, the site has remained relatively unchanged.
Currently the site is an undeveloped, grassed property. The topography of the site generally slopes down from southwest to northeast with maximum and minimum boring elevations of EL 1300 and EL 1294, respectively. The ground surface elevations noted in this report were obtained from the USGS National Map provided and have been rounded to the nearest foot.
2.2 PROPOSED CONSTRUCTION
The following information explains our understanding of the planned development including the proposed building and related infrastructure.
SUBJECT DESIGN INFORMATION / ASSUMPTIONS
Building Footprint Hangar: approx. 5,625 square feet
Administration/Restroom: approx. 1,600 square feet # of Stories Single-story above grade Usage Aviation/maintenance Framing Hangar: structural steel or cast-in-place reinforced concrete
Administration/Restroom: light framing Column Loads 200 kips (Full Dead and Live Load) maximum Wall Loads (assumed) 6 kips per linear foot (klf) maximum
ECS Project No. 58:2033 Page 4
SUBJECT DESIGN INFORMATION / ASSUMPTIONS
Lowest Finish Floor Elevation Unknown, assumed no more than 2 feet below or above existing grades
We also understand that associated parking/drive areas will be constructed. If ECS’ understanding of the project is not correct, especially if the structural loads are different, please contact ECS so that we may review these changes and revise our recommendations, as appropriate.
3.0 FIELD EXPLORATION AND LABORATORY TESTING
Our exploration procedures are explained in greater detail in Appendix B including the insert titled Subsurface Exploration Procedures. Our scope of work included drilling eight (8) borings. The boring locations were selected by ECS based on the site plan provided by the client and identified in the field by the drilling crew using boring GPS coordinates generated by ECS. Approximate as-drilled boring locations are shown on the Boring Location Diagram in Appendix A.
3.1 SUBSURFACE CHARACTERIZATION
The subsurface conditions encountered were generally consistent with published geological mapping. The following sections provide generalized characterizations of the soil strata encountered during our subsurface exploration. For specific subsurface information refer to the boring logs in Appendix B.
Approximate Depth of Bottom of Strata
Below Grade Elevation(1) (ft) Stratum Material Description Consistency /
Density
6 inches --- Cover Topsoil --
13 to 14 feet Elevation 1285 to 1282 I
(CL) LEAN CLAY, LEAN CLAY WITH
SAND, and (CH) FAT CLAY, various shades of red, brown, and gray Soft to Very Hard
19 feet(2) Elevation 1280 to 1277 II(3) (WR) WEATHERED SHALE, various shades of red Very Hard
Notes:
(1) Elevations are approximate.
(2) Depth to deepest boring termination depth.
(3) Stratum II was encountered in the building borings only.
Please refer to the attached boring logs and laboratory data summary for this field exploration for a more detailed description of the subsurface conditions encountered in the borings as the stratification descriptions above are generalized for presentation purposes.
3.2 GROUNDWATER OBSERVATIONS
Water levels were measured in our boring logs in Appendix B. Groundwater was not observed in the borings at the time of our exploration and is indicated on the boring logs as “dry”.
Variations in the long-term water table may occur as a result of changes in precipitation, evaporation, surface water runoff, construction activities, and other factors.
ECS Project No. 58:2033 Page 5
3.3 LABORATORY TESTING
The laboratory testing consisted of selected tests performed on samples obtained during our field exploration operations. Classification and index property tests were performed on representative soil samples. Testing performed include moisture content, Atterberg Limits, percent passing the No. 200 sieve, Standard Proctor, California Bearing Ratio (CBR), and corrosion testing which includes pH, resistivity, and total soluble sulfate.
Samples were visually classified based on texture and plasticity in accordance with ASTM D2488 Standard Practice for Description and Identification of Soils (Visual-Manual Procedures) and including USCS classification symbols, and ASTM D2487 Standard Practice for Classification for Engineering Purposes (Unified Soil Classification System (USCS). After classification, the samples were grouped in the major zones noted on the boring logs in Appendix B. The group symbols for each soil type are indicated in parentheses along with the soil descriptions. The stratification lines between strata on the logs are approximate; in situ, the transitions may be gradual.
4.0 DESIGN RECOMMENDATIONS
4.1 POTENTIAL VERTICAL MOVEMENTS
The intent of recommendations contained in this report are provided in order to reduce the potential risk associated with the shrink/swell tendencies of the on-site expansive soil, should a conventional shallow footing foundation and slab on grade be used.
The majority of clay soils encountered in the borings have a high expansion potential. Based on our Atterberg limits laboratory test results and experience with similar soils, we estimate potential vertical soil movements (PVM) of the highly expansive soils encountered in the borings of up to about 2 ½ inches, based on dry conditions. These potential movements reflect moisture changes in the soil that can occur over the life of the structure and after construction is complete. The actual movements could be greater if poor drainage, ponded water, and/or other unusual sources of moisture are allowed to saturate the soils beneath the structure after construction.
4.2 SUBGRADE IMPROVEMENTS
In order to reduce the risk associated with future movements due to expansion potential, we recommend the following general building pad subgrade improvements to reduce the PVM to approximately 1 inch. Please note, these recommendations are the minimum requirements to reduce potential movements due to expansion potential, should conventional spread footings and slab on grade be used. If a monolithic slab/BRAB slab or post-tensioned slab be used to support the structure, subgrade improvements are not required as those systems are design to withstand the potential vertical movements. Alternatively, drilled piers could be used with a structurally suspended floor slab in which case subgrade improvements are not required.
ECS Project No. 58:2033 Page 6
Options Depth of Select Fill (feet)
Depth of Moisture Conditioning (feet)
Total Depth of Improved Zone (feet)
Estimated
PVM
(inch)
Option 1 3 --- 3 1
Option 2 2 2 4 1
Option 3 --- 5 5 1
The subgrade improvements should extend at least 5 feet beyond the edge of the building pads and include any flatwork sensitive to movements such as sidewalks or pavements. Exterior perimeter footing/grade beam backfill should consist of moisture conditioned clay soil. Please refer to the “Material Specifications” section of this report for more details.
These design parameters assume that positive drainage will be provided away from the structures and with moderate irrigation of surrounding lawn and planter areas with no excessive wetting or drying of soils adjacent to the foundations. Greater potential movements could occur with extreme wetting or drying of the soils due to ponding of water, plumbing leaks or lack of irrigation. Recommendations for earthwork operations are found in the “Site Construction Recommendations” portion of this report.
4.3 SHALLOW FOUNDATIONS
Provided the subgrades are improved and structural fills are prepared as recommended in this report, the proposed structures can be supported by conventional shallow foundations including column footings and continuous wall footings. We recommend the foundation design use the following parameters:
Design Parameter Column Footing Wall Footing
Net Allowable Bearing Pressure(1) 3,000 psf 3,000 psf
Bearing Soil Material Improved Subgrade Improved Subgrade
Minimum Width 24 inches 18 inches
Minimum Footing/Grade Beam Embedment Depth (below slab or finished grade) (2) 24 inches 24 inches
Estimated Total Settlement (3) Less than 1- inch Less than 1- inch
Estimated Differential Settlement (4)
Less than ¾ inches between columns
Less than ¾ inches per 30 linear feet
Notes:
(1) Net allowable bearing pressure is the applied pressure in excess of the surrounding overburden soils above the base of the foundation.
(2) For bearing considerations and frost penetration requirements.
(3) Based on our assumed structural loads. If final loads are different, ECS must be contacted to update foundation recommendations and settlement calculations.
(4) Based on maximum loads and variability in borings. Differential settlement can be re-evaluated once the foundation plans are more complete.
ECS Project No. 58:2033 Page 7
Monolithic Slab/BRAB: Should improving the subgrade in order to use conventional shallow foundations and slab on grade be cost prohibitive, foundations consisting of a reinforced slab with grade beams (monolithic slab/BRAB) under load bearing walls could also be used to support the proposed structures.
The reinforced slab may be designed using a soil modulus of subgrade reaction of 125 pci and the grade beams or spread footings may be designed for a net allowable soil bearing pressure of 3,000 psf bearing on newly placed and compacted select fill or natural soils that were encountered in the borings.
If a monolithic slab is used this system may be designed with conventional reinforcing. The slab should be designed in accordance with WRI/CRSI “Design Slab-On-Ground Foundations”. The structure can be supported on a monolithic/waffle slab and grade beam foundation system designed in accordance with the following information:
Design Parameter BRAB/WRI Slab
Allowable Bearing Pressure 3,000 psf
Design PI 39
Climatic Rating (Cw) 20
Soil-Climate Support Index (1-C) 0.25
Post-Tensioned Slab: In lieu of a BRAB/WRI slab, a post-tensioned slab on grade could also be used on the existing soils without subgrade improvement. The following design parameters are recommended for the Post-Tensioning Institute's slab-on-grade design method (3rd Edition) should that method be chosen:
Center Lift Edge Lift em (feet) Ym (inches) em (feet) Ym (inches)
9.0 1.5 5.0 2.0
Potential Undercuts: Due to the presence of relatively soft soils, DCP testing of the bearing soils by ECS representatives should be incorporated during construction to verify their suitability for supporting shallow foundations. If soft or inadequate soils are observed at the footing bearing elevations, these soils should be undercut and removed. Any undercut should be backfilled with lean concrete (f’c ≥ 1,000 psi at 28 days) up to the original design bottom of footing elevation; the original footing shall be constructed on top of the hardened lean concrete.
4.4 DRILLED PIERS
A drilled straight shaft pier and grade beam system could also be used to support the structures.
We recommend the drilled pier design use the following parameters:
ECS Project No. 58:2033 Page 8
Design Parameter Drilled Pier
Bearing Material(1) (WR) WEATHERED SHALE that was encountered in the building borings at depths of approximately 13 to 14 feet below existing site grades
Minimum Embedment Depth 2 feet into approved bearing material
Net Allowable End Bearing Pressure(1) 30 ksf
Net Allowable Skin Friction Resistance(2) 2.5 ksf
Net Allowable Tension/Uplift Resistance 1 ksf
Minimum Pier Diameter(3) 18 inches
Minimum Pier Spacing between New and Existing Piers (center to center)
100% Capacity with min Center to Center Spacing Ratio of 3 pier diameters linearly reduced to 50%
Capacity at 2 pier diameters
Minimum Pier Length (from top of pier) Three times the pier diameter
Minimum Grade Beam Depth(4) 24 inches below finish grade
Estimated Total Settlement <1 inch
Estimated Differential Settlement 0.5 inches between piers
Notes:
(1) Drilled pier installation should be observed by ECS to verify that proper bearing material is encountered and minimum embedment is achieved.
(2) Skin friction resistance should be used for the portion of the pier that penetrates the approved bearing material only.
(3) Assumes the pier is designed with adequate reinforcing steel.
(4) Grade beams and piers should be structurally connected.
(5) Column loads should be supported by the drilled piers while wall loads can be carried by the grade beams.
Installation: The use of temporary casing is not expected to be necessary; however, this is contingent upon the groundwater conditions at the specific locations of the structures at the time of construction. This office should be contacted for additional recommendations if seepage cannot be controlled by conventional means (i.e. placement of concrete soon after the excavation is complete, use of sump pumps, use of temporary steel casing, etc.).
Installation (drill and final concrete placement) of individual shafts should be completed in one day.
This time limit does not only have design implications (reduction of side friction, excessive settlement due to the softening and saturation of bearing materials) but also has practical implications such as losing steel casing in the ground due to excessive soil squeeze and set up, losing shaft integrity due to instabilities or continuous seepage as well as loss of side friction resistance.
The concrete should have a slump between 5 and 7 inches and should be placed in a manner that prevents it from striking the reinforcing steel and sides of the excavation (such as using a tremie).
We recommend that all drilled shafts be observed by ECS personnel, to verify proper shaft installation. The concrete in the upper five feet of the shaft should be mechanically consolidated.
4.4.1 Lateral Considerations
Drilled Shafts may be subject to lateral loads. For the lateral design consideration of the drilled shafts bearing in weathered bedrock, we are providing the following information that can be used in ENSOFT’s LPILE 2013 computer program:
ECS Project No. 58:2033 Page 9
LPILE Design Parameters - Soil
LPILE Design Parameters - Rock
Soil Description LPILE Material
Description
Unit Weight
(pcf)
Uniaxial Compressive Strength, (psi)
Elastic Modulus, krm (psi)
RQD
E50
Weathered Shale
Weak Rock (Reese)
130 300 50,000 50 0.0005
4.4.2 Uplift Considerations
We recommend using an uplift of 1,000 psf over the shaft perimeter to a depth of 8 feet. This uplift may be reduced to 500 psf at depths where moisture conditioned soils are used and may be considered negligible at depths where select fill soils are used.
The drilled shafts should contain sufficient reinforcing steel throughout the shaft length (top of shaft to bottom of shaft) to resist uplift (tensile) forces due to post-construction heave of the clay soils. The magnitude of uplift is difficult to estimate and will vary with the in-situ moisture contents at the time of construction.
Widening the upper portion of the pier (or pier cap) will create the potential for high uplift pressures from the underlying clay soils, regardless of the subgrade improvement selected. This condition should be avoided, and if required, the piers should be designed for an uplift of 6 ksf acting on the entire surface of the bottom of the widened portion of the pier (or pier cap). Alternatively, the pier (or pier cap) may be underlain by nominal 6-inch void (PVR of 1 inch or less) or 12 inches of low volume change material or select fill.
4.5 BUILDING SLAB
Since the potential vertical movements (PVM) of the existing soil may be beyond normal design tolerances for interior slabs, the most positive method to reduce movements of slabs to very low levels would be to structurally suspend these slabs above the active clays. We are providing both a suspended slab supported by the drilled pier foundations and a slab on grade.
4.5.1 Structurally Suspended Slab
In lieu of providing any subgrade improvements, we believe that the lowest risk option of future movements and their impact on the building would be to structurally suspend the slab either using
Soil Description LPILE Material Desciption
Unit Weight, (pcf)
Undrained Shear strength, (psf)
Friction Angle, (degrees)
Subgrade Modulus, (pci) E50
Upper 3 feet Ignore Ignore Ignore Ignore - Ignore
Engineered Fill Sand (Reese) 120 - 33 90 -
Moisture Conditioned Soil Soft Clay 120 500 - - 0.01
Existing Clays Stiff Clay without Free Water 120 2,000 - - 0.05
ECS Project No. 58:2033 Page 10 a crawl space or void cartons. If void cartons are used, they should be at least 24 inches beneath the slab and all grade beams.
If a crawl space is provided below the floor slabs, adequate ventilation should also be provided.
Additionally, if a crawl space will be primarily below the level of existing grade, a vertical moisture barrier should be considered around the perimeter of the structures. Adequate drainage should be provided should standing water infiltrate underneath the slabs.
The ground surface beneath suspended floors should be shaped and drained to prevent the ponding of water. A permanent sump pit should be considered.
4.5.1 Slab on Grade
A conventional slab on grade may be used provided it is supported on subgrades improved as presented in this report.
The following graphic depicts our soil-supported slab recommendations:
1.
2.
3.
Concrete Slab Thickness: 4 inches minimum Concrete Slab Strength: 3,000 psi minimum Drainage Layer Thickness: 4 inches minimum
4. Drainage Layer Material: GRAVEL (GP, GW)
5. Subgrade compacted per the earthwork recommendations provided.
Subgrade Modulus: Provided subgrades are improved and prepared as discussed herein, the slab may be designed assuming a modulus of subgrade reaction, k1 of 125 pci (lbs/cu. inch).
Vapor Retarder: Before the placement of concrete, a vapor retarder may be placed on top of the granular drainage layer to provide additional protection against moisture penetration through the floor slab. When a vapor retarder is used, special attention should be given to surface curing of the slab to reduce the potential for uneven drying, curling and/or cracking of the slab. Depending on proposed flooring material types, the structural engineer and/or the architect may choose to eliminate the vapor retarder.
Slab Isolation: Soil-supported slabs should be isolated from the foundations and foundation-supported elements of the structure so that differential movement between the foundations and slab will not induce excessive shear and bending stresses in the floor slab. Where the structural configuration prevents the use of a free-floating slab such as in a drop-down footing/monolithic slab configuration, the slab should be designed with suitable reinforcement and load transfer devices to reduce the risk of overstressing of the slab.
Concrete Slab
Improved Subgrade (as recommended)
Vapor Retarder
Granular Base Layer
ECS Project No. 58:2033 Page 11
4.6 BUILDING PERIMETER CONDITIONS
Soils placed along the exterior of the foundations should consist of fine-grained soils encountered on site, placed and compacted in accordance with the “Fill Placement” section of this report. The purpose of this clay backfill is to reduce the opportunity for surface or subsurface water infiltration beneath the structure. Additionally, where lateral penetrations (for utilities) into or below the structure occur, a clay plug (or suitable synthetic alternative) should be placed at the building line to reduce the opportunity for infiltrating water, regardless of the backfill material. A clay plug detail is included in Appendix A.
Positive drainage away from the structure should also be provided. Additionally, irrigation of lawn and landscaped areas should be moderate, with no excessive wetting or drying of soils around the perimeter of the structures allowed. Trees and bushes/shrubs planted near the perimeter of the structures can withdraw large amounts of water from the soils and should be planted at least their anticipated mature height away from the building.
Where flatwork is placed against or near the structure, a positive seal must be installed and adequately maintained to limit water intrusion. Down spouts and gutters should be used to collect and distribute water at least 10 feet away from the structure.
Routine maintenance of the building perimeter condition is necessary so that the recommendations contained in this report are followed and maintained. Greater potential vertical movements could occur with extreme wetting or drying of the soils due to poor drainage, ponding of water, plumbing leaks, lack of irrigation, and/or lack of routine maintenance, etc.
4.7 SEISMIC DESIGN CONSIDERATIONS
Seismic Site Classification: The International Building Code (IBC) 2018 requires site classification for seismic design based on ASCE 7-16 and the upper 100 feet of a soil profile. At least two methods are utilized in classifying sites, namely the shear wave velocity (vs) method and the Standard Penetration Resistance (N-value) method. The Standard Penetration Resistance (N-value) method was used in classifying this site.
SEISMIC SITE CLASSIFICATION
Site
Class Soil Profile Name Shear Wave Velocity, Vs, (ft./s)
N value (bpf)
A Hard Rock Vs > 5,000 fps N/A
B Rock 2,500 < Vs ≤ 5,000 fps N/A
C Very dense soil and soft rock 1,200 < Vs ≤ 2,500 fps >50
D Stiff Soil Profile 600 ≤ Vs ≤ 1,200 fps 15 to 60
E Soft Soil Profile Vs < 600 fps <15
Based upon our interpretation of the subsurface conditions, the appropriate Seismic Site Classification is “C” as shown in the preceding table.
Ground Motion Parameters: In addition to the seismic site classification, ECS has determined the design spectral response acceleration parameters following the IBC/ASCE 7-16 methodology. The Mapped Reponses were estimated from the U.S. Seismic Design Maps website
ECS Project No. 58:2033 Page 12 https://seismicmaps.org/. The design responses for the short (0.2 sec, SDS) and 1-second period (SD1) are noted in bold at the far right end of the following table.
GROUND MOTION PARAMETERS [IBC 2015/2018 Method]
Period (sec)
Mapped Spectral Response
Accelerations (g)
Values of Site Coefficient for Site Class
Maximum Spectral Response Acceleration
Adjusted for Site Class (g)
Design Spectral Response
Acceleration (g)
Reference Figures 1613.3.1
(1) & (2)
Tables 1613.3.3
(1) & (2)
Eqs. 16-37 & 16-38
Eqs. 16-39 & 16-40
0.2 SS 0.342 Fa 1.3 SMS=FaSs 0.445 SDS=2/3
SMS
0.297
1.0 S1 0.084 Fv 1.5 SM1=FvS1 0.126 SD1=2/3
SM1
0.084
The Site Class definition should not be confused with the Seismic Design Category designation which the Structural Engineer typically assesses. If a higher site classification is beneficial to the project, we can provide additional testing methods that may yield more favorable results.
4.8 PAVEMENTS
Subgrade Characteristics: Based on the results of our borings, it appears that the pavement subgrades will consist of existing moderate to high plasticity soils. Based on the results of our laboratory tests and our experience with similar soils, a CBR value of 3 is recommended for this project site. The subgrade should be prepared in accordance with the recommendations in the Site Construction Recommendations section of this report.
We were not provided traffic loading information so we have assumed heavy duty pavements will experience a maximum traffic loading of 300,000 ESALs.
The preliminary pavement sections below are guidelines that may or may not comply with local jurisdictional minimums.
PROPOSED PAVEMENT SECTIONS
FLEXIBLE PAVEMENT RIGID PAVEMENT
MATERIAL Heavy Duty Light Duty Heavy Duty Light Duty Portland Cement Concrete(1) - - 6 in. 5 in.
Asphaltic Concrete Surface Course 2 in. 2 in. - -
Asphaltic Concrete Binder Course(2) 4 ½ in. 3 in. - -
Stabilized Subgrades(3,4) 8 in. 8 in. 8 in. 8 in.
Notes:
(1) Due to the excessive surface wear and subsequent deterioration of asphalt pavement caused by turning truck traffic, we recommend that any areas where trucks will be turning or backing up be constructed of Portland cement concrete only.
(2) ODOT Type A aggregate base material may be substituted for the asphalt binder using a substitute ratio of three inches of aggregate base for each inch of asphalt binder.
(3) Based on experience with similar soils, we estimate 5% to 6% Hydrated Lime will be required to stabilize the near surface soils at this site. The final amount and type of stabilizing agent https://seismicmaps.org/
ECS Project No. 58:2033 Page 13 should be determined at the time of construction based on the type(s) of material(s) at final grade.
(4) In lieu of stabilized subgrades, 8 inches of ODOT Type A aggregate base material may be used.
ECS should be allowed to review these recommendations and make appropriate revisions based upon the formulation of the final traffic design criteria for the project. It is important to note that the design sections do not account for construction traffic loading. It should also be noted that these design recommendations may not satisfy the local jurisdictional traffic guidelines. Any roadways constructed for public use and to be dedicated to the local or state jurisdiction for repair and maintenance must be designed in accordance with those jurisdictional requirements.
In general, heavy-duty sections are areas that will be subjected to trucks, buses, or other similar vehicles including main drive lanes of the development. Light duty sections are appropriate for vehicular traffic and parking areas.
An important consideration with the design and construction of pavements is surface and subsurface drainage. Where standing water develops, either on the pavement surface or within the base course layer, softening of the subgrade and other problems related to the deterioration of the pavement can be expected. Furthermore, good drainage should reduce the possibility of the subgrade materials becoming saturated during the normal service period of the pavement.
Large, front loading trash dumpsters frequently impose concentrated front wheel loads on pavements during loading. This type of loading typically results in rutting of asphalt pavement and ultimately pavement failures. For preliminary design purposes, we recommend that the pavement in trash pickup areas consist of an 8-inch-thick Portland Cement Concrete (PCC) pavement section.
Appropriate jointing should also be incorporated into the design of the PCC pavement. When traffic loading becomes available ECS, or the Civil Engineer can design the pavements.
Pavements should be specified, constructed and tested to meet the ODOT Standard Specifications for Highway Construction and the following requirements:
1. Reinforcing steel may consist of #3 reinforcing steel bars placed at 18 inches on center each way.
2. Hot Mix Asphaltic Concrete: In accordance with Oklahoma Department of
Transportation (ODOT) Standard Specifications.
3. Portland Cement Concrete: Minimum compressive strength of 3,500 psi (28 Days).
Concrete should be designed with 3 to 6 percent entrained air.
4. Crushed Limestone Base Material: ODOT Type A Aggregate Base. The material should be compacted to a minimum 95 percent of Standard Proctor maximum dry density (ASTM D 698) and within three percentage points of the material's optimum moisture.
4.9 SITE RETAINING WALLS
Unlike below grade walls, site retaining walls are free to rotate at the top (not restrained). For these walls the "Active" (ka) soil condition should be used along with a triangular distribution of earth pressures. In addition, site retaining walls should be designed to withstand lateral earth pressures exerted by the backfill and any surcharge loads within the “Critical Soil Zone”. The Critical
ECS Project No. 58:2033 Page 14
Zone is defined as the area between the back of the retaining wall footing and an imaginary line projected upward and rearward at a 45-degree angle (see figure below).
The lateral earth pressures developed behind site retaining walls are a function of the backfill soil type, backfill slope angle, and any surcharge loads. For the design of site retaining walls, we recommend the soil parameters provided below.
RETAINING WALL BACKFILL IN THE CRITICAL SOIL ZONE
Soil Parameter Estimated Value
Soil Classification LEAN CLAY (CL) or more granular
Fines Content (passing #200 Sieve) Max. 90%
Coefficient of Active Earth Pressure (Ka) 0.42 Retained Soil Moist Unit Weight (γ) 120 pcf Cohesion (C) 100 psf
Angle of Internal Friction (φ) 24°
Active Equivalent Fluid Pressure 51 psf/ft
FOUNDATION SOILS
Soil/Weathered Rock Parameter Estimated value
Allowable Soil Bearing Pressure Per Section 4.1
Minimum Wall Embedment Below Grade 24 inches
Coefficient of Passive Earth Pressure (Kp) 2.2
Soil Moist Unit Weight (γ) 120 pcf
Cohesion (C) 100 psf
Interface Friction Angle [Concrete on Soil / Weathered Rock] (φf) 18° / 26°
Sliding Friction Coefficient [Concrete on Soil / Weathered Rock] (μ) 0.32 / 0.4
Passive Equivalent Fluid Pressure 275 psf/ft
It is critical that the soils used for backfill of the retaining walls meet the soil parameters recommended above. If the soils available do not meet those parameters, then ECS should be contacted to provide revised values, and to confirm that only suitable soils will be used for wall backfill.
Care should be used to avoid the operation of heavy equipment to compact the wall backfill since it may overload and damage the wall. In addition, such loads are not typically considered in the design of site retaining walls, and are not provided for in our recommendations.
Wall Drainage: Retaining walls should be provided with a wall and foundation drainage system to relieve hydrostatic pressures which may develop behind the walls. This system should consist of weepholes through the wall and/or a 4-inch perforated, closed joint drain line located along the backside of the walls above the top of the footing. The drain line should be surrounded by a minimum of 6 inches of AASHTO #57 Stone wrapped with an approved non-woven geotextile, such as Mirafi 140-N or equivalent. Wall drains can consist of a 12-inch wide zone of free draining gravel, ECS Project No. 58:2033 Page 15 such as AASHTO #57 Stone, employed directly behind the wall and separated from the soils beyond with a non-woven geotextile. Alternatively, the wall drain can consist of a suitable geocomposite drainage board material. The wall drain should be hydraulically connected to the foundation drain.
4.10 CORROSION POTENTIAL
Total soluble sulfate, electrical resistivity, and pH tests were performed on one composite sample to provide an estimation of the materials’ corrosion potential. The test results are presented in the following table:
Sample Location / Depth Sulfate (mg/Kg)
Resistivity (ohms.cm) pH
Composite 1 B-01, B-04, B-05, B-06 0 to 5 ft. <200 13000 7.27
Sulfate test results indicate the soil sulfate exposure to concrete to be negligible. Type I Portland cement concrete may be used for this site. Resistivity test results indicate the onsite soils to be moderately corrosive to severely corrosive. Soil pH results indicate the soil to be mildly corrosive.
Cathodic protection or a polyethylene coating or wrap should be used to protect ferrous metal pipes and the manufacturer’s corrosion specifications should be followed. These test results should be used to determine the corrosion potential of on-site soils when in contact with various underground materials to be used in construction.
5.0 SITE CONSTRUCTION RECOMMENDATIONS
5.1 SUBGRADE PREPARATION
In a dry and undisturbed state, the upper 1-foot of the majority of the soil at the site should provide good subgrade support for fill placement and construction operations. However, when wet, this soil will degrade quickly with disturbance from contractor operations. Therefore, good site drainage should be maintained during earthwork operations, which should help maintain the integrity of the soil.
The surface of the site should be kept properly graded in order to enhance drainage of the surface water away from the proposed structures during the construction phase. We recommend that an attempt be made to enhance the natural drainage without interrupting its pattern, where possible.
The soils at the site are moisture and disturbance sensitive, and contain fines which are considered moderately erodible. Therefore, the contractor should carefully plan his operation to limit exposure of the subgrade to weather and construction equipment traffic, and provide and maintain good site drainage during earthwork operations. All erosion and sedimentation shall be controlled in accordance with sound engineering practice and current jurisdictional requirements.
5.1.1 Stripping and Grubbing
The subgrade preparation should consist of stripping all existing gravels/pavements, vegetation, topsoil, loose, poorly compacted or deleterious existing soils, existing fill (as defined in this report), and any soft or yielding materials from the 5-foot expanded building area, and any areas receiving new fill. Deeper topsoil or organic laden soils may be present in wet, low-lying, and poorly drained
ECS Project No. 58:2033 Page 16 areas. ECS should be retained to verify that topsoil and yielding surficial materials have been removed prior to the placement of structural fill or construction of structures.
5.1.2 Proofrolling
Prior to fill placement or other construction on subgrades, the subgrades should be evaluated by an ECS field technician. The exposed subgrade should be extensively proofrolled with construction equipment having a minimum axle load of 10 tons [e.g. fully loaded tandem-axle dump truck].
Proofrolling should be traversed in two perpendicular directions with overlapping passes of the vehicle under the observation of an ECS technician. This procedure is intended to assist in identifying any localized yielding materials.
Where proofrolling identifies areas that are yielding or “pumping” subgrade those areas should be repaired prior to the placement of any subsequent Structural Fill or other construction materials.
Methods of stabilization include undercutting, moisture conditioning, or chemical stabilization. The situation should be discussed with ECS to determine the appropriate procedure. Test pits may be excavated to explore the shallow subsurface materials to help in determining the cause of the observed yielding materials, and to assist in the evaluation of appropriate remedial actions to repair the subgrade.
5.2 EARTHWORK OPERATIONS
The…