This Scope of Work details a construction project for the FAA's eVTOL (electric Vertical Takeoff and Landing) Procedures and Analysis Range (VPAR) at the Mike Monroney Aeronautical Center in Oklahoma City, Oklahoma. The project involves constructing a new 5,364 square foot vehicle weather shelter, a 1,315 square foot support building, and 38,100 square foot taxi and touchdown/lift-off areas, with related site improvements. Construction work includes site demolition, grading, soil preparation, street extension, paving, electrical infrastructure, utilities, concrete foundations, structural steel, building envelope, doors, windows, interior finishes, equipment installation, signage, fire suppression, plumbing, HVAC systems, electrical power and lighting, fire alarm, telecom, and lightning protection systems.

The contract has a duration of 425 calendar days, with the contractor required to coordinate closely with the FAA Contracting Officer's Representative (COR) throughout the project. Key requirements include providing seven days' notice for submittals and system start-ups, maintaining on-site supervision, and adhering to environmental guidelines such as diverting a minimum of 50% of non-hazardous waste from landfills. The construction site is located on the north side of McLucas Street, east of Shaffer Street and west of Halaby Drive, within an operating environment that will require careful coordination to minimize disruptions to ongoing FAA operations.

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF WORK

23-030509 MMAC VPAR

PAGE

TABLE OF CONTENTS 1

1.0 GENERAL 2

1.1 DESCRIPTION OF FACILITY/WORK 2

1.2 CONSTRUCTION DURATION 2

1.3 CONTRACTOR USE OF PREMISES 2

1.4 COORDINATION AND ON-SITE SUPERVISION 2

1.5 FIELD ENGINEERING 3

1.6 CUTTING AND PATCHING 3

1.7 SUBMITTAL REQUIREMENTS 3

1.8 SHOP DRAWINGS 3

1.9 SAMPLES 3

1.10 CONSTRUCTION PROGRESS SCHEDULE 3

1.11 QUALITY ASSURANCE-CONTROL OF INSTALLATION 3

1.12 INSPECTION AND TESTING LABORATORY SERVICES 4

1.13 TEMPORARY FACILITIES 4

1.14 BARRIERS AND FENCING 4

1.15 PROTECTION OF NEW WORK 4

1.16 PROTECTION OF EXISTING EQUIPMENT AND BUILDING 4

1.17 CONDUCT OF WORK 4

1.18 SECURITY 4

1.19 WORK HOURS 4

1.20 STARTING SYSTEMS OR EQUIPMENT 4

1.21 FINAL CLEANING 4

1.22 PROJECT RECORD DOCUMENT 5

1.23 CODES AND PERMITS 5

2.0 PRODUCTS AND EXECUTION 5

2.1 PROJECT DRAWINGS AND SPECIFICATIONS 5

10/6/25

1.0 GENERAL

1.1 DESCRIPTION OF FACILITY/WORK

A. The scope of work for the MMAC eVTOL Procedures and Analysis Range (VPAR) at the Mike Monroney Aeronautical Center in Oklahoma City, OK includes:

1. Improve the site and construct a new eVTOL Procedures and Analysis Range. The project includes a new 5,364 gross square foot vehicle weather shelter, 1,315 gross square foot support building, 38,100 square foot taxi and touchdown and lift-off areas, and related site improvements. Work includes, but is not limited to: Site demolition, site grading, soil preparation, street extension, paving, medium voltage electrical, utilities, concrete foundations, structural steel, building envelope, doors, windows, interior finishes, equipment, signage, fire suppression, plumbing, HVAC system, electrical power & lighting, fire alarm, telecom, lightning protection system, and other items as noted on the drawings and specifications.

2. All work done must meet all the requirements indicated in the project drawings and specifications.

3. The project is located at: Mike Monroney Aeronautical Center (MMAC) 6500 S.

MacArthur Blvd., Oklahoma City, OK 73169. The construction site is located on the north side of McLucas Street, east of Shaffer Street and west of Halaby Drive.

1.2 CONSTRUCTION DURATION

A. The contract duration for this project is 425 calendar days. The contractor will be working in an operating environment.

B. Contractor must be adequately staffed to complete all construction during contract days allotted.

1.3 CONTRACTOR USE OF PREMISES

See project drawings and specifications.

1.4 COORDINATION AND ON-SITE SUPERVISION

A. The contractor must coordinate scheduling, submittals, and work of the various sections of the specifications to ensure efficient and orderly sequence of installation of independent construction elements. The contractor must have a designated supervisor on site during all phases of construction activities. This person must be responsible for ensuring that the provisions of the contract are followed by all contractors.

B. Utility Outages and Shutdown: Coordinate with the FAA COR. Outages affecting FAA Operations are required to be accomplished at night, or on Saturdays, Sundays, or designated government holidays. Prior to any outage or shutdown, fourteen (14) working days notification must be made to coordinate scheduling of any Work to be performed during any hours.

1.5 FIELD ENGINEERING

Establish elevations, lines and levels and verify the elevations and location of the work conform with Contract Documents or requirements.

1.6 CUTTING AND PATCHING

Employ skilled and experienced installers to perform cutting and patching new work;

restore work with new products except as noted.

1.7 SUBMITTAL REQUIREMENTS

A. See project drawings and specifications.

B. The FAA must have seven (7) working days to review the contractor submittals. Any delay as a result of submittal disapproval and required re-submittal must not be grounds for any contract adjustment. Receive submittal approval prior to starting the work. All materials installed in the work must match the approved submittals. After a submittal has been approved, no substitutions will be permitted without written approval by the COR.

1.8 SHOP DRAWINGS

1.9 SAMPLES

1.10 CONSTRUCTION PROGRESS SCHEDULE

1.11 QUALITY ASSURANCE-CONTROL OF INSTALLATION

B. Comply with specified standards as a minimum quality for the work except where more stringent tolerances, codes, or specific requirements indicate higher standards or more precise workmanship.

1.12 INSPECTION AND TESTING LABORATORY SERVICES

1.13 TEMPORARY FACILITIES

1.14 BARRIERS AND FENCING

1.15 PROTECTION OF NEW WORK

1.16 PROTECTION OF EXISTING BUILDINGS AND IMPROVEMENTS

1.17 CONDUCT OF WORK

1.18 SECURITY

Provide list of contractor’s key personnel who will require badged access to COR prior to the notice-to-proceed date. Keep list current during project work.

1.19 WORK HOURS

1.20 STARTING SYSTEMS OR EQUIPMENT

A. Provide seven (7) working days notification prior to the start-up of each item.

B. See project drawings and specifications.

1.21 FINAL CLEANING

B. Remove waste and surplus materials, rubbish, and construction facilities from the MMAC property. In accordance with EO 13514, FAA is required to divert from landfill or incineration facility disposal a minimum of 50% of non-hazardous waste generated as a result of its operations. In support of meeting this requirement and to minimize the environmental impact of maintenance activities, the Contractor must divert from landfill or incineration facility disposal a minimum of 50% of non-hazardous waste and 50% of construction and demolition material and debris generated as a result of the Contractor’s work, to the maximum extent feasible. The Contractor must report non-hazardous waste diversion rates on a regular basis. The Whole Building Design Guide (http://wbdg.org) outlines recommended practices for construction waste and debris removal.

1.22 PROJECT RECORD DOCUMENT

A. Maintain on site, one set of construction documents to be utilized for record drawings.

B. Record revisions to the work. Record information concurrent with construction progress.

C. Specifications: Legibly mark each item to record actual construction.

D. Record documents and shop drawings. Legibly mark each item to record actual construction.

E. Submit documents to the COR for approval prior to final inspection.

1.23 CODES AND PERMITS

2.0 PRODUCTS AND EXECUTION

Refer to project drawings and specifications regarding products and execution.