This solicitation is for the Massachusetts National Cemetery Phase 4 Expansion project in Bourne, MA. The project will develop approximately 20 acres of land and include approximately 12,000 gravesites for both casket and cremation burials in new sections. The Department of Veterans Affairs Office of Construction and Facilities Management is the contracting agency. The solicitation uses a tiered evaluation method and requests responses by a certain date, though specific dates are not provided in this document.

View the file

Other files

File Type Posted
Pre-Proposal Inquiry (PPI) Form-- VA Responses dated 7-30-20.pdf PDF
36C10F20R0042 0005.pdf PDF
Cost Proposal Breakdown Revised 7-30-20.pdf PDF
Geotechnical Engineering Report MNC BOURNE MA dated July 12 2019.pdf PDF
Pre-Proposal Inquiry (PPI) Form--VA Responses dated 7-29-20.pdf PDF
36C10F20R0042 0004.pdf PDF
36C10F20R0042 0003.pdf PDF
Pre-Proposal Inquiry (PPI) Form--VA Responses dated 7-27-20 Amendment 0003.pdf PDF
36C10F20R0042 0002.pdf PDF
Pre-Proposal Inquiry (PPI) Form--VA Responses dated 7-27-2020.pdf PDF
MASSACHUSETTS NATIONAL CEMETERY ITINERARY.pdf PDF
36C10F20R0042 0001.pdf PDF
Attachment 7 818PC2032-MNC_BD_PLANS_Part4.pdf PDF
Attachment 1 Wage Determination MA20200008 03-13-2020.pdf PDF
Attachment 8 818PC2032-MNC_BD_PLANS_Part5.pdf PDF
Attachment 4 818PC2032-MNC_BD_PLANS_Part1.pdf PDF
Attachment 13 Cost Proposal Breakdown.pdf PDF
Attachment 2 818PC2032-MNC_BD_SPEC_VOL1.pdf PDF
Attachment 5 818PC2032-MNC_BD_PLANS_Part2.pdf PDF
Attachment 12 Pre-Proposal Inquiry (PPI) Form.pdf PDF
36C10F20R0042.docx DOCX document
Attachment 6 818PC2032-MNC_BD_PLANS_Part3.pdf PDF
Attachment 11 Contractor Safety and Environmental Record Evaluation Form.pdf PDF
Attachment 9 818PC2032-MNC_BD_PLANS_Part6.pdf PDF
Attachment 10 Past Performance Questionnaire.pdf PDF
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NCA MASTER

SPECIFICATIONS

MASSACHUSETTS NATIONAL

CEMETERY

BOURNE TOWNSHIP

BARNSTABLE COUNTY, MASSACHUSETTS

PROJECT NO. 818-PPC-2032

PHASE IV DEVELOPMENT

BID DOCUMENTS

Prepared for:

United States Department of Veterans Affairs

March 13, 2020 Volume 2

MASSACHUSETTS NATIONAL CEMETERY PROJECT NO. 818-032

PHASE 4 DEVELOPMENT JANUARY 2020

TABLE OF CONTENTS

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

NCA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

VOLUME 1

DIVISION 00 - SPECIAL SECTIONS DATE

00 01 10 Table of Contents 03-18 00 01 15 List of Drawing Sheets 05-10

DIVISION 01 - GENERAL REQUIREMENTS

01 00 01 General Requirements (Major NCA Projects) 06-14 01 32 16.13 Network Analysis Schedules 06-19 01 33 23 Shop Drawings, Product Data, and Samples 06-14 01 42 19 Reference Standards 06-14 01 45 00 Quality Control 03-19 01 45 29 Testing Laboratory Services 06-14 01 57 19 Temporary Environmental Controls 06-14 01 74 19 Construction Waste Management 06-14 01 81 13 Sustainable Construction Requirements 08-16 01 91 00 General Commissioning Requirements 12-15

DIVISION 02 – EXISTING CONDITIONS

02 41 10 Demolition and Site Clearing 06-14 02 41 10.1 Demolition and Site Clearing for Irrigation Tank 06-14

DIVISION 03 – CONCRETE

03 08 00 Commissioning Of Pre-Cast Crypts 06-14 03 30 53 Cast-in-Place Concrete 06-14 03 48 21 Precast Concrete Burial Crypts (Double Depth Lawn Crypt) 06-13 03 48 24 Precast Concrete Columbarium Units 06-13

DIVISION 04 – MASONRY

04 05 13 Masonry Mortaring 06-14 04 05 16 Masonry Grouting 06-14 04 05 31 Masonry Tuck Pointing 06-14 04 30 00 Cap Replacements 04 40 10 Cut Stone Assemblies 04 41 00 Dry Stone Wall Systems 04 72 00 Cast Stone Masonry (Simulated) 02-15

MASSACHUSETTS NATIONAL CEMETERY PROJECT NO. 818-032

TABLE OF CONTENTS

00 01 10-2

04 73 00 Columbarium Niche Covers 06-14

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 06-14 05 21 00 Steel Joist Framing 06-14 05 40 00 Cold-Formed Metal Framing 06-14 05 50 00 Metal Fabrication 06-14

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 12-15 06 20 00 Finish Carpentry 06-14

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 08 00 Facility Exterior Closure Commissioning 12 15 07 12 00 Built-Up Bituminous Waterproofing 06-14 07 21 13 Thermal Insulation 12-15 07 40 00 Roofing and Siding Panels 06-14 07 41 13 Standing Seam Metal Roofing 06-14 07 60 00 Flashing and Sheet Metal 06-14 07 92 00 Joint Sealants 06-14

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 06-14 08 33 00 Coiling Doors and Grilles 06-14 08 71 00 Door Hardware 06-14 08 90 00 Louver and Vents 06-14

DIVISION 09 – FINISHES

09 06 00 Schedule for Finishes 06-14 09 22 16 Non-Structural Metal Framing 06-14 09 29 00 Gypsum Board 06-14 09 30 13 Tiling 06-14 09 51 00 Acoustic Ceiling 06-14 09 91 00 Painting 06-14

DIVISION 10 – SPECIALTIES

10 14 00 Exterior Signage 06-14 10 21 13 Toilet Compartments 06-14 10 28 00 Toilet and Bath Accessories 06-14 10 51 13 Metal Lockers 06-14 10 73 43 Transportation Stop Shelter

MASSACHUSETTS NATIONAL CEMETERY PROJECT NO. 818-032

TABLE OF CONTENTS

00 01 10-3

DIVISION 11 - EQUIPMENT

11 08 00 Commissioning oF GNSS, GPS, and GIS systems 05-16

11 83 00 Global Navigation Satellite System (GNSS) Reference System 01-20 11 83 02 GNSS & GIS Mapping and Geodata 01-20

DIVISION 13– SPECIAL CONSTRUCTION

13 34 23 Fabricated Control Booths 06-14

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 11-16 22 05 23 General-Duty Valves for Plumbing Piping 11-16 22 07 11 Plumbing Insulation 11-16 22 08 00 Commissioning Of Plumbing Systems 11-16 22 11 00 Facility Water Distribution 11-16 22 13 00 Facility Sanitary Sewerage 11-16 22 14 00 Facility Storm Drainage 11-16 22 40 00 Plumbing Fixtures 11-16

VOLUME 2

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 11-16 23 05 12 General Motor Requirements for HVAC Equipment 11-16 23 05 41 Noise and Vibration Control for HVAC Piping and Equipment 11-16 23 05 93 Testing, Adjusting, and Balancing for HVAC 11-16 23 07 11 HVAC Insulation 11-16 23 08 00 Commissioning of HVAC Systems 12-15 23 11 23 Facility Natural-Gas Piping 11-16 23 34 00 HVAC Fans 11-16 23 55 23 Gas-Fired Radiant Heaters 11-16 23 82 39 Unit Heaters 11-16

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 07-17 26 05 19 Low-Voltage Electrical Power Conductors and Cables 07-17 26 05 26 Grounding and Bonding for Electrical Systems 07-17 26 05 33 Raceway and Boxes for Electrical Systems 07-17 26 05 41 Underground Electrical Construction 07-17 26 08 00 Commissioning of Electrical Systems 12-15 26 22 00 Low-Voltage Transformers 07-17 26 24 16 Panelboards 07-17 26 27 26 Wiring Devices 07-17

MASSACHUSETTS NATIONAL CEMETERY PROJECT NO. 818-032

TABLE OF CONTENTS

00 01 10-4

26 29 11 Motor Controllers 07-17 26 29 21 Enclosed Switches and Circuit Breakers 07-17 26 41 00 Facility Lightning Protection 07-17 26 51 00 Interior Lighting 07-17 26 56 00 Exterior Lighting 07-17

DIVISION 27 – COMMUNICATIONS

27 05 00 Common Work Results for Communications 11-16 27 05 26 Grounding and Bonding for Communications Systems 11-16 27 05 33 Conduits and Backboxes for Communications Systems 11-16 27 11 00 Communications Equipment Room Fittings 11-16

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 08 00 Commissioning of Electronic Safety and Security Systems 12-15 28 10 00 Access Control 11-16 28 20 00 Video Surveillance 11-16 28 31 00 Intrusion Detection 11-16 28 46 00 Fire Detection and Alarm 11-16

DIVISION 31 – EARTHWORK

31 20 00 Earthwork 11-16 31 23 19 Dewatering 11-16

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23 Cement and Concrete for Exterior Improvements 11-16 32 08 00 Commissioning Of Irrigation Systems 12-15 32 12 16 Asphalt Paving 11-16 32 17 23 Pavement Markings 11-16 32 31 13 Chain Link Fences and Gates 11-16 32 33 00 Site Furnishings 01-17 32 84 00 Planting Irrigation 01-17 32 90 00 Planting 11-16

DIVISION 33 – UTILITIES

33 10 10 Well and Testing 33 10 20 Well Pump 33 10 30 SCADA Programmable Automation Controllers 33 10 40 SCADA Instrumentation and Control 33 10 50 SCADA Adjustable Frequency Drives 33 40 00 Storm Sewer Utilities 11-16

MASSACHUSETTS NATIONAL CEMETERY PROJECT NO. 818-032

PHASE 4 DEVELOPMENT JANUARY 2020

COMMON WORK RESULTS FOR HVAC

23 05 11 - 1

SECTION 23 05 11

COMMON WORK RESULTS FOR HVAC

PART 1 - GENERAL

1.1 DESCRIPTION

A. The requirements of this Section apply to all sections of Division 23.

B. Definitions:

1. Exposed: Piping, ductwork, and equipment exposed to view in finished rooms.

C. Abbreviations/Acronyms:

1. ABS: Acrylonitrile Butadiene Styrene

2. AC: Alternating Current

3. ACR: Air Conditioning and Refrigeration

4. AI: Analog Input

5. AISI: American Iron and Steel Institute

6. AO: Analog Output

7. AWG: American Wire Gage

8. BACnet: Building Automation and Control Network

9. BAg: Silver-Copper-Zinc Brazing Alloy

10. BAS: Building Automation System

11. BCuP: Silver-Copper-Phosphorus Brazing Alloy

12. BSG: Borosilicate Glass Pipe

13. BTU: British Thermal Unit

14. BTUH: British Thermal Unit Per Hour

15. CDA: Copper Development Association

16. C: Celsius

17. CD: Compact Disk

18. CFM: Cubic Foot Per Minute

19. CLR: Color

20. CO: Carbon Monoxide

21. COR: Contracting Officer’s Representative

22. CPVC: Chlorinated Polyvinyl Chloride

23. CRS: Corrosion Resistant Steel

24. CWP: Cold Working Pressure

25. CxA: Commissioning Agent

26. db(A): Decibels (A weighted)

27. DDC: Direct Digital Control

28. DI: Digital Input

29. DO: Digital Output

MASSACHUSETTS NATIONAL CEMETERY PROJECT NO. 818-032

PHASE 4 DEVELOPMENT JANUARY 2020

COMMON WORK RESULTS FOR HVAC

23 05 11 - 2

30. DVD: Digital Video Disc

31. DN: Diameter Nominal

32. DWV: Drainage, Waste and Vent

33. ECC: Engineering Control Center

34. EPDM: Ethylene Propylene Diene Monomer

35. EPT: Ethylene Propylene Terpolymer

36. ETO: Ethylene Oxide

37. F: Fahrenheit

38. FAR: Federal Acquisition Regulations

39. FD: Floor Drain

40. FED: Federal

41. FG: Fiberglass

42. FNPT: Female National Pipe Thread

43. GPM: Gallons Per Minute

44. HDPE: High Density Polyethylene

45. Hg: Mercury

46. HOA: Hands-Off-Automatic

47. hp: Horsepower

48. ID: Inside Diameter

49. in. wc: Inches of Water Column

50. IPS: Iron Pipe Size

51. Kg: Kilogram

52. kPa: Kilopascal

53. lb: Pound

54. lb/hr: Pounds Per Hour

55. L/s: Liters Per Second

56. L/min: Liters Per Minute

57. MAWP: Maximum Allowable Working Pressure

58. MAX: Maximum

59. MBH: 1000 BTUH

60. MBTU: 1000 BTU

61. MED: Medical

62. m: Meter

63. MFG: Manufacturer

64. mg: Milligram

65. mg/L: Milligrams Per Liter

66. ml: Milliliter

MASSACHUSETTS NATIONAL CEMETERY PROJECT NO. 818-032

PHASE 4 DEVELOPMENT JANUARY 2020

COMMON WORK RESULTS FOR HVAC

23 05 11 - 3

67. mm: Millimeter

68. MIN: Minimum

69. NC: Normally Closed

70. NF: Oil Free Dry (Nitrogen)

71. NO: Normally Open

72. NPTF: National Pipe Thread Female

73. NPS: Nominal Pipe Size

74. NPT: Nominal Pipe Thread

75. OD: Outside Diameter

76. OSD: Open Sight Drain

77. OS&Y: Outside Stem and Yoke

78. PLC: Programmable Logic Controllers

79. PP: Polypropylene

80. PPM: Parts Per Million

81. PSIA: Pounds Per Square Inch Absolute

82. PSIG: Pounds Per Square Inch Gage

83. PTFE: Polytetrafluoroethylene

84. PVC: Polyvinyl Chloride

85. PVDF: Polyvinylidene Fluoride

86. RAD: Radians

87. RO: Reverse Osmosis

88. RPM: Revolutions Per Minute

89. RTRP: Reinforced Thermosetting Resin Pipe

90. SCFM: Standard Cubic Feet Per Minute

91. SPEC: Specification

92. SPS: Sterile Processing Services

93. STD: Standard

94. SDR: Standard Dimension Ratio

95. SUS: Saybolt Universal Second

96. SWP: Steam Working Pressure

97. TAB: Testing, Adjusting, and Balancing

98. TDH: Total Dynamic Head

99. TEFC: Totally Enclosed Fan-Cooled

100. TFE: Tetrafluoroethylene

101. THERM: 100,000 BTU

102. THHN: Thermoplastic High-Heat Resistant Nylon Coated Wire

103. THWN: Thermoplastic Heat & Water-Resistant Nylon Coated Wire

MASSACHUSETTS NATIONAL CEMETERY PROJECT NO. 818-032

PHASE 4 DEVELOPMENT JANUARY 2020

COMMON WORK RESULTS FOR HVAC

23 05 11 - 4

104. T/P: Temperature and Pressure

105. USDA: U.S. Department of Agriculture

106. V: Volt

107. VAC: Vacuum

108. VA: Veterans Administration

109. VAMC: Veterans Administration Medical Center

110. VAC: Voltage in Alternating Current

111. WOG: Water, Oil, Gas

1.2 RELATED WORK

A. Section 01 00 01, GENERAL REQUIREMENTS (Major NCA Projects).

B. Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.

C. Section 01 42 19, REFERENCE STANDARDS.

D. Section 01 81 13, SUSTAINABLE DESIGN REQUIREMENTS.

E. Section 01 91 00, GENERAL COMMISSIONING REQUIREMENTS.

F. Section 05 31 00, STEEL DECKING.

G. Section 05 50 00, METAL FABRICATIONS.

H. Section 07 60 00, FLASHING AND SHEET METAL: Flashing for Wall and Roof Penetrations.

I. Section 07 92 00, JOINT SEALANTS.

J. Section 09 91 00, PAINTING.

K. Section 23 05 12, GENERAL MOTOR REQUIREMENTS FOR HVAC EQUIPMENT.

L. Section 23 05 41, NOISE AND VIBRATION CONTROL FOR HVAC PIPING AND EQUIPMENT.

M. Section 23 05 93, TESTING, ADJUSTING, AND BALANCING FOR HVAC.

N. Section 23 07 11, HVAC INSULATION.

O. Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.

P. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS.

Q. Section 26 05 21, LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES (600

VOLTS AND BELOW).

R. Section 26 29 11, MOTOR STARTERS.

S. Section 31 20 00, EARTH MOVING: Excavation and Backfill.

1.3 APPLICABLE PUBLICATIONS

A. The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.

B. Air Movement and Control Association (AMCA):

410-1996 .................................. Recommended Safety Practices for Users and Installers of Industrial and Commercial Fans

MASSACHUSETTS NATIONAL CEMETERY PROJECT NO. 818-032

PHASE 4 DEVELOPMENT JANUARY 2020

COMMON WORK RESULTS FOR HVAC

23 05 11 - 5

C. American Society of Mechanical Engineers (ASME):

ASME Boiler and Pressure Vessel Code -

BPVC Section IX-2015 .............. Welding, Brazing, and Fusing Qualifications

D. American Society for Testing and Materials (ASTM):

A36/A36M-2014 ........................ Standard Specification for Carbon Structural Steel

A575-1996(2013) e1 ................. Standard Specification for Steel Bars, Carbon, Merchant Quality, M-Grades

E. Manufacturers Standardization Society (MSS) of the Valve and Fittings Industry, Inc.:

SP-58-2009............................... Pipe Hangers and Supports - Materials, Design, Manufacture, Selection, Application, and Installation

SP-127-2014a ........................... Bracing for Piping Systems: Seismic–Wind–Dynamic Design, Selection, and Application F. National Electrical Manufacturers Association (NEMA):

MG 1-2014 ................................ Motors and Generators

G. National Fire Protection Association (NFPA):

70-2018 .................................... National Electrical Code (NEC)

1.4 SUBMITTALS

A. Submittals, including number of required copies, shall be submitted in accordance with Section

01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES, and with requirements in the individual specification sections.

B. Submit welder certificates.

C. Make all necessary field measurements and investigations to ensure that the equipment and assemblies will meet contract requirements.

D. If equipment is submitted which differs in arrangement from that shown, provide drawings that show the rearrangement of all associated systems. Approval will be given only if all features of the equipment and associated systems, including accessibility, are equivalent to that required by the contract.

E. Prior to submitting shop drawings for approval, certify in writing that manufacturers of all major items of equipment have each reviewed drawings and specifications, and have jointly coordinated and properly integrated their equipment and controls as to provide a complete and efficient installation.

F. Coordination Drawings: Indicate the proposed locations of equipment, ductwork, piping, and materials by preparing floor plans, elevations, and details to indicate penetrations in floors, walls, and ceilings and their relationship to other penetrations and installations. The sheet metal drawing shall be the Base Sheet. Other drawings produced shall be coordination drawing overlays, so interferences can be detected. Prepare coordination drawings to a scale of 1/4" =

1'-0" or larger clearly indicating the following:

MASSACHUSETTS NATIONAL CEMETERY PROJECT NO. 818-032

PHASE 4 DEVELOPMENT JANUARY 2020

COMMON WORK RESULTS FOR HVAC

23 05 11 - 6

1. Clearances for servicing and maintaining equipment, including tube removal, filter removal, and space for equipment disassembly required for periodic maintenance.

2. Clearances for installing and maintaining insulation.

3. Clearances for installing and maintaining valves, dampers, and their actuators.

4. Equipment connections and support details.

5. Exterior wall and foundation penetrations.

6. Fire-rated wall and floor penetrations.

7. Sizes and location of required concrete pads and bases.

8. Indicate locations where space is limited for installation and maintenance.

9. Indicate scheduling, sequencing, movement, and positioning of large equipment into the building during construction.

10. Indicate location of existing utilities, ducts, piping and equipment that are to remain.

11. Prepare reflected ceiling plans to coordinate and integrate installations, air outlets and inlets, light fixtures, communication systems components, sprinklers, and other ceiling-mounted items.

G. Upon request by COR, provide lists of previous installations for selected items of equipment.

Include contact persons who will serve as references, with telephone numbers and e-mail addresses.

H. Submittals and shop drawings for interdependent items, containing applicable descriptive information, shall be furnished together and complete in a group. Coordinate and properly integrate materials and equipment in each group as to provide a completely compatible and efficient installation. Final review and approvals will be made only by groups.

I. Manufacturer's Literature and Data: Submit under the pertinent section rather than under this section.

1. Belt drive with the driven equipment.

2. Electric motor data and variable speed drive data with the driven equipment.

3. Equipment and materials identification.

4. Fire-stopping materials.

5. Hangers, inserts, supports, and bracing.

6. Wall, floor, and ceiling plates.

J. HVAC Maintenance Data and Operating Instructions: Maintenance and operating manuals in accordance with Section 01 00 01, GENERAL REQUIREMENTS (Major NCA Projects), paragraph, INSTRUCTIONS, for systems and equipment.

K. Provide copies of approved HVAC equipment submittals to the testing, adjusting, and balancing subcontractor.

MASSACHUSETTS NATIONAL CEMETERY PROJECT NO. 818-032

PHASE 4 DEVELOPMENT JANUARY 2020

COMMON WORK RESULTS FOR HVAC

23 05 11 - 7

1.5 QUALITY ASSURANCE

A. Mechanical, electrical, and associated systems shall be safe, reliable, efficient, durable, easily and safely operable and maintainable, easily and safely accessible, and in compliance with applicable codes as specified. The systems shall be comprised of high quality institutional-class and industrial-class products, of manufacturers that are experienced specialists in the required product lines. All construction firms and personnel shall be experienced and qualified specialists in institutional HVAC construction.

B. Contractor to ensure the flow rate tolerance for HVAC equipment is consistent with Section 23 05

93, TESTING, ADJUSTING, AND BALANCING FOR HVAC.

C. Equipment Vibration Tolerance:

1. Refer to Section 23 05 41, NOISE AND VIBRATION CONTROL FOR HVAC PIPING AND

EQUIPMENT. Equipment shall be factory-balanced to this tolerance and be re-balanced on site, as necessary.

2. After HVAC air balance work is completed and permanent drive sheaves are in place, perform field mechanical balancing and adjustments required to meet the specified vibration tolerance.

D. Products Criteria:

1. Standard Products: Material and equipment shall be the standard products of a manufacturer regularly engaged in the manufacture of the products for at least 3 years. The design, model, and size of each item shall have been in satisfactory and efficient operation on at least three installations for at least three years. However, digital electronics devices, software, and systems such as controls, instruments, and computer work stations shall be the current generation of technology and basic design that has a proven satisfactory service record of at least three years. See other specification sections for any exceptions.

2. All items furnished shall be free from defects that would adversely affect the performance, maintainability, and appearance of individual components and overall assembly.

3. Conform to codes and standards as required by the specifications. Conform to local codes, if required by local authorities such as the natural gas supplier, if the local codes are more stringent than those specified. Refer any conflicts to the COR.

4. Multiple Units: When two or more units of materials or equipment of the same type or class are required, these units shall be products of one manufacturer.

5. Assembled Units: Ensure manufacturers of equipment assemblies, which use components made by others, that the manufacturer will assume complete responsibility for the final assembled unit.

6. Nameplates: Nameplate bearing manufacturer's name or identifiable trademark shall be securely affixed in a conspicuous place on equipment, or name or trademark cast integrally with equipment, stamped or otherwise permanently marked on each item of equipment.

MASSACHUSETTS NATIONAL CEMETERY PROJECT NO. 818-032

PHASE 4 DEVELOPMENT JANUARY 2020

COMMON WORK RESULTS FOR HVAC

23 05 11 - 8

7. Do not use asbestos containing products, equipment, or materials.

E. HVAC Equipment Service Organizations: Products and systems shall be supported by service organizations that maintain a complete inventory of repair parts and are located reasonably close to the site.

F. HVAC Mechanical Systems Welding: Before any welding is performed, submit a certificate certifying that welders comply with the following requirements:

1. Qualify welding processes and operators for piping according to ASME BPVX Section IX.

2. Certify that each welder has passed American Welding Society (AWS) qualification tests for the welding processes involved, and that certification is current.

G. Execution (Installation, Construction) Quality:

1. Apply and install all items in accordance with manufacturer's written instructions. Refer conflicts between the manufacturer's instructions and the contract drawings and specifications to the COR for resolution. Provide written hard copies or computer files of manufacturer’s installation instructions to the COR at least two weeks prior to commencing installation of any item. Installation of the item will not be allowed to proceed until the recommendations are received. Failure to furnish these recommendations is a cause for rejection of the material.

2. All items that require access, such as for operating, cleaning, servicing, maintenance, and calibration, shall be easily and safely accessible by persons standing at floor level, or standing on permanent platforms, without the use of portable ladders. Examples of these items include, but are not limited to, all types of valves, filters and strainers, transmitters, and control devices. Prior to commencing installation work, refer conflicts between this requirement and contract drawings to the COR for resolution.

3. Provide complete layout drawings required by Paragraph, SUBMITTALS. Do not commence construction work on any system until the layout drawings have been approved.

1.6 DELIVERY, STORAGE AND HANDLING

A. Protection of Equipment:

1. Equipment and material placed on the job site shall remain in the custody of the Contractor until phased acceptance, whether or not the Government has reimbursed the Contractor for the equipment and material. The Contractor is solely responsible for the protection of such equipment and material against any damage.

2. Place damaged equipment in new operating condition; or, replace same as determined and directed by the COR. Such repair or replacement shall be at no additional cost to the

Government.

3. Protect interiors of new equipment and piping systems against entry of foreign matter. Clean both inside and outside before painting or placing equipment in operation.

MASSACHUSETTS NATIONAL CEMETERY PROJECT NO. 818-032

PHASE 4 DEVELOPMENT JANUARY 2020

COMMON WORK RESULTS FOR HVAC

23 05 11 - 9

4. Existing equipment and piping being worked on by the Contractor shall be under the custody and responsibility of the Contractor and shall be protected as required for new work.

B. Cleanliness of Piping and Equipment Systems:

1. Exercise care in storage and handling of equipment and piping material to be incorporated in the work. Remove debris arising from cutting, threading, and welding of piping.

2. Piping systems shall be flushed, blown, or pigged as necessary to deliver clean systems.

3. Clean interior of all tanks prior to delivery for beneficial use by the Government.

4. Contractor is fully responsible for all costs, damage, and delay arising from failure to provide clean systems.

PART 2 - PRODUCTS

2.1 FACTORY-ASSEMBLED PRODUCTS

A. Provide maximum standardization of components.

B. Ensure manufacturers of equipment assemblies, which use components made by others, that the manufacturer assumes complete responsibility for the final assembled unit.

1. All components of an assembled unit need not be products of same manufacturer.

2. Constituent parts that are alike shall be products of a single manufacturer.

3. Components shall be compatible with each other and with the total assembly for intended service.

4. Guarantee performance of assemblies of components, and repair or replace elements of the assemblies as required to deliver specified performance of the complete assembly.

C. Components of equipment shall bear manufacturer's name and trademark, model number, serial number, and performance data on a name plate securely affixed in a conspicuous place, or cast integral with, stamped, or otherwise permanently marked upon the components of the equipment.

D. Major items of equipment, which serve the same function, shall be the same make and model.

Exceptions will be permitted only with the approval of the COR and if performance requirements are met.

2.2 COMPATIBILITY OF RELATED EQUIPMENT

A. Equipment and materials installed shall be compatible with other items being furnished and with existing items so that the result will be a complete and fully operational plant that conforms to contract requirements.

2.3 BELT DRIVES

A. Drive Types:

1. Provide adjustable-pitch or fixed-pitch drive as follows:

a. Fan speeds up to 1800 RPM: 10 horsepower and smaller.

b. Fan speeds over 1800 RPM: 3 horsepower and smaller.

2. Provide fixed-pitch drives for drives larger than those listed above.

MASSACHUSETTS NATIONAL CEMETERY PROJECT NO. 818-032

PHASE 4 DEVELOPMENT JANUARY 2020

COMMON WORK RESULTS FOR HVAC

23 05 11 - 10

3. The final fan speeds required to meet the system CFM and pressure requirements, without throttling, shall be determined by adjustment of a temporary adjustable-pitch motor sheave, or by fan law calculation if a fixed-pitch drive is used initially.

2.4 DRIVE GUARDS

A. For machinery and equipment, provide guards as shown in AMCA 410 for belts, chains, couplings, pulleys, sheaves, shafts, gears, and other moving parts regardless of height above the floor as to prevent damage to equipment and injury to personnel. Drive guards may be excluded where motors and drives are inside factory-fabricated air handling unit casings.

B. Pump shafts and couplings shall be fully guarded by a sheet steel guard, covering coupling and shaft but not bearings. Material shall be minimum 16 gage sheet steel; ends shall be braked and drilled and attached to pump base with minimum of four 1/4 inch bolts. Reinforce guard as necessary to prevent side play forcing guard onto couplings.

2.5 LIFTING ATTACHMENTS

A. Provide equipment with suitable lifting attachments to enable equipment to be lifted in its normal position. Lifting attachments shall withstand any handling conditions that might be encountered, without bending or distortion of shape, such as rapid lowering and braking of load.

2.6 ELECTRIC MOTORS

A. All material and equipment furnished and installation methods shall conform to the requirements of Section 23 05 12, GENERAL MOTOR REQUIREMENTS FOR HVAC EQUIPMENT; Section

26 29 11, MOTOR STARTERS; and, Section 26 05 21, LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES (600 VOLTS AND BELOW). Provide all electrical wiring, conduit, and devices necessary for the proper connection, protection, and operation of the systems.

Provide special energy efficient motors as scheduled. Unless otherwise specified for a particular application, use electric motors with the following requirements.

B. Single-phase Motors: Capacitor-start type for hard starting applications. Motors for centrifugal fans and pumps may be permanent split capacitor (PSC).

C. Poly-phase Motors: NEMA Design B, Squirrel cage, induction type.

D. Electronically Commutated Motors: Brushless DC motors. Provide with equipment where indicated on drawings.

E. Rating: Continuous duty at 100 percent capacity in an ambient temperature of 104 degrees F and sea level; minimum horsepower as shown on drawings; when operating maximum horsepower, not to exceed nameplate rating without service factor.

F. Special Requirements:

1. Where motor power requirements of equipment furnished deviate from power shown on plans, provide electrical service designed under the requirements of NFPA 70 without additional time or cost to the Government.

MASSACHUSETTS NATIONAL CEMETERY PROJECT NO. 818-032

PHASE 4 DEVELOPMENT JANUARY 2020

COMMON WORK RESULTS FOR HVAC

23 05 11 - 11

2. Assemblies of motors, starters, controls, and interlocks on factory assembled and wired devices shall be in accordance with the requirements of this specification.

3. Wire and cable materials specified in the electrical division of the specifications shall be modified as follows:

a. Provide shielded conductors or wiring in separate conduits for all instrumentation and control systems where recommended by manufacturer of equipment.

4. Select motor sizes so that the motors do not operate into the service factor, at maximum required loads, on the driven equipment. Motors on pumps and fans shall be sized for non-overloading at all points on the pump and fan performance curves.

5. Motors utilized with variable frequency drives shall be rated “inverter-ready” per NEMA MG 1.

Provide motor shaft grounding apparatus that will protect bearings from damage from stray currents.

G. Motor Efficiency and Power Factor: All motors, when specified as “high efficiency” by the project specifications on driven equipment, shall conform to efficiency and power factor requirements in

Section 23 05 12, GENERAL MOTOR REQUIREMENTS FOR HVAC EQUIPMENT, with no consideration of annual service hours. Motor manufacturers generally define these efficiency requirements as “NEMA premium efficient” and the requirements generally exceed those of the

Energy Policy Act of 1992 (EPACT). Motors not specified as “high efficiency” shall comply with

EPACT.

H. Insulation Resistance: Not less than one-half meg-ohm between stator conductors and frame, to be determined at the time of final inspection.

2.7 VARIABLE SPEED MOTOR CONTROLLERS

A. Refer to Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS and Section

26 29 11, MOTOR STARTERS for specifications.

B. The combination of controller and motor shall be provided by the manufacturer of the driven equipment, such as pumps and fans, and shall be rated for 100 percent output performance.

Multiple units of the same class of equipment, i.e. air handlers, fans, pumps, shall be the products of a single manufacturer.

C. Motors shall be energy efficient type and be approved by the motor controller manufacturer. The controller-motor combination shall be guaranteed to provide full motor nameplate horsepower in variable frequency operation. Both driving and driven motor/fan sheaves shall be fixed pitch.

D. Controller shall not add any current or voltage transients to the input AC power distribution system, DDC controls, etc., nor shall be affected from other devices on the AC power system.

2.8 EQUIPMENT AND MATERIALS IDENTIFICATION

A. Use symbols, nomenclature, and equipment numbers specified, shown on the drawings, and shown in the maintenance manuals. Identification for piping is specified in Section 09 91 00, PAINTING.

MASSACHUSETTS NATIONAL CEMETERY PROJECT NO. 818-032

PHASE 4 DEVELOPMENT JANUARY 2020

COMMON WORK RESULTS FOR HVAC

23 05 11 - 12

B. Use symbols, nomenclature, and equipment numbers specified, shown on the drawings, and shown in the maintenance manuals. In addition, provide bar code identification nameplate for all equipment which will allow the equipment identification code to be scanned into the system for maintenance and inventory tracking. Identification for piping is specified in Section 09 91 00, PAINTING.

C. Interior (Indoor) Equipment: Engraved nameplates, with letters not less than 1-7/8 inches high of brass with black-filled letters, or rigid black plastic with white letters as specified in Section 09 91

00, PAINTING permanently fastened to the equipment. Identify unit components such as coils, filters, fans, etc.

D. Exterior (Outdoor) Equipment: Brass nameplates, with engraved black filled letters, not less than

1-7/8 inches high, riveted or bolted to the equipment.

E. Control Items: Label all temperature and humidity sensors, controllers, and control dampers.

Identify and label each item as they appear on the control diagrams.

F. Valve Tags and Lists:

1. Valve tags: Engraved black-filled numbers and letters not less than 1/2-inch high for number designation, and not less than 1/4 inch for service designation on 19 gage 1-1/2 inches round brass disc, attached with brass "S" hook or brass chain.

2. Valve lists: Typed or printed plastic-coated card(s), sized 8-1/2 inches by 11 inches showing tag number, valve function, and area of control for each service or system. Punch sheets for a 3-ring notebook.

2.9 GALVANIZED REPAIR COMPOUND

A. Green Seal Standard GC-03, paint form.

2.10 HVAC PIPE AND EQUIPMENT SUPPORTS AND RESTRAINTS

A. Vibration Isolators: Refer to Section 23 05 41, NOISE AND VIBRATION CONTROL FOR HVAC

PIPING AND EQUIPMENT.

B. Supports for Roof Mounted Items:

1. Equipment: Equipment rails shall be galvanized steel, minimum 18 gage, with integral baseplate, continuous welded corner seams, factory installed 2 inch by 4 inch treated wood nailer, 18 gage galvanized steel counter flashing cap with screws, built-in cant strip (except for gypsum or tectum deck), with minimum height 11 inches. For surface insulated roof deck, provide raised cant strip starting at the upper surface of the insulation.

2. Pipe/duct pedestals: Provide a galvanized Unistrut channel welded to U-shaped mounting brackets which are secured to side of rail with galvanized lag bolts.

C. Pipe Supports: Comply with MSS SP-58. Type numbers specified refer to this standard. For selection and application, comply with MSS SP-58. Refer to Section 05 50 00, METAL FABRICATIONS, for miscellaneous metal support materials and prime coat painting requirements.

MASSACHUSETTS NATIONAL CEMETERY PROJECT NO. 818-032

PHASE 4 DEVELOPMENT JANUARY 2020

COMMON WORK RESULTS FOR HVAC

23 05 11 - 13

D. Attachment to Concrete Building Construction:

1. Concrete insert: MSS SP-58, Type 18.

2. Self-drilling expansion shields and machine bolt expansion anchors: Permitted in concrete not less than 4 inches thick, when approved by the COR for each job condition.

3. Power-driven fasteners: Permitted in existing concrete or masonry not less than 4 inches thick, when approved by the COR for each job condition.

E. Attachment to Steel Building Construction:

1. Welded attachment: MSS SP-58, Type 22.

2. Beam clamps: MSS SP-58, Types 20, 21, 28 or 29. Type 23 C-clamp may be used for individual copper tubing up to 7/8 inch outside diameter.

F. Attachment to Metal Pan or Deck: As required for materials specified in Section 05 31 00, STEEL

DECKING.

G. Attachment to Wood Construction: Wood screws or lag bolts.

H. Hanger Rods: Hot-rolled steel, ASTM A36/36M or ASTM A575 for allowable load listed in MSS

SP-58. For piping, provide adjustment means for controlling level or slope. Types 13 or 15 turn-buckles shall provide 1-1/2 inches minimum of adjustment and incorporate locknuts. All-thread rods are acceptable.

I. Hangers Supporting Multiple Pipes (Trapeze Hangers): Galvanized, cold formed, lipped steel channel horizontal member, not less than 1-5/8 inches by 1-5/8 inches, 12 gage, designed to accept special spring held, hardened steel nuts.

1. Allowable hanger load: Manufacturers rating less 200 pounds.

2. Guide individual pipes on the horizontal member of every other trapeze hanger with 1/4-inch

U-bolt fabricated from steel rod. Provide Type 40 insulation shield, secured by two 1/2-inch galvanized steel bands, or pre-insulated calcium silicate shield for insulated piping at each hanger.

J. Supports for Piping Systems: Select hangers sized to encircle insulation on insulated piping.

Refer to Section 23 07 11, HVAC INSULATION, for insulation thickness. To protect insulation, provide Type 39 saddles for roller type supports or pre-insulated calcium silicate shields. Provide

Type 40 insulation shield or pre-insulated calcium silicate shield at all other types of supports and hangers, including those for pre-insulated piping.

2.11 PIPE PENETRATIONS

A. Install sleeves during construction.

B. Penetrations are prohibited through beams or ribs but may be installed in concrete beam flanges.

Any deviation from these requirements shall be made only after receipt of prior approval from the

COR.

C. Sheet Metal, Plastic, or Moisture Resistant Fiber Sleeves: Provide for pipe passing through floors, interior walls, and partitions, unless brass or steel pipe sleeves are specifically called for below.

MASSACHUSETTS NATIONAL CEMETERY PROJECT NO. 818-032

PHASE 4 DEVELOPMENT JANUARY 2020

COMMON WORK RESULTS FOR HVAC

23 05 11 - 14

D. Cast Iron or Zinc-Coated Pipe Sleeves: Provide for pipe passing through exterior walls below grade. Make space between sleeve and pipe watertight with a modular or link rubber seal. Seal shall be applied at both ends of sleeve.

E. Galvanized Steel or an Alternate Black Iron Pipe with Asphalt Coating Sleeves: Provide for pipe passing through concrete beam flanges, except where brass pipe sleeves are called for.

F. Brass Pipe Sleeves: Provide for pipe passing through quarry tile, terrazzo, or ceramic tile floors.

Connect sleeve with floor plate.

G. Sleeves are not required for wall hydrants for fire department connections or in drywall construction.

H. Sleeve Clearance: Sleeve through floors, walls, partitions, and beam flanges shall be one inch greater in diameter than external diameter of pipe. Sleeve for pipe with insulation shall be large enough to accommodate the insulation. Interior openings shall be caulked tight with fire stopping material and sealant to prevent the spread of fire, smoke, and gases.

I. Sealant and Adhesives: Shall be as specified in Section 07 92 00, JOINT SEALANTS.

2.12 SPECIAL TOOLS AND LUBRICANTS

A. Furnish, and turn over to the COR, special tools not readily available commercially, that are required for disassembly or adjustment of equipment and machinery furnished.

2.13 WALL, FLOOR AND CEILING PLATES

A. Material and Type: Chrome-plated brass or chrome-plated steel, one piece or split type with concealed hinge, with set screw for fastening to pipe or sleeve. Use plates that fit tight around pipes, cover openings around pipes, and cover the entire pipe sleeve projection.

B. Thickness: Not less than 3/32 inch for floor plates. For wall and ceiling plates, not less than 0.025 inch for up to 3-inch pipe, 0.035 inch for larger pipe.

C. Locations: Use where pipe penetrates floors, walls, and ceilings in exposed locations, in finished areas only. Use also where insulation ends on exposed water supply pipe drop from overhead.

Provide a watertight joint in spaces where brass or steel pipe sleeves are specified.

2.14 ASBESTOS

A. Materials containing asbestos are prohibited.

PART 3 - EXECUTION

3.1 INSTALLATION

A. If an installation is unsatisfactory to the COR, the Contractor shall correct the installation at no additional cost or time to the Government.

3.2 ARRANGEMENT AND INSTALLATION OF EQUIPMENT AND PIPING

A. Coordinate location of piping, sleeves, inserts, hangers, ductwork, and equipment. Locate piping, sleeves, inserts, hangers, ductwork, and equipment clear of windows, doors, openings, light outlets, and other services and utilities. Prepare equipment layout drawings to coordinate proper

MASSACHUSETTS NATIONAL CEMETERY PROJECT NO. 818-032

PHASE 4 DEVELOPMENT JANUARY 2020

COMMON WORK RESULTS FOR HVAC

23 05 11 - 15 location and personnel access to all facilities. Submit the drawings for review as required by Part

1. Follow manufacturer's published recommendations for installation methods not otherwise specified.

B. Operating Personnel Access and Observation Provisions: Select and arrange all equipment and systems to provide clear view and easy access, without use of portable ladders, for maintenance and operation of all devices including, but not limited to, all equipment items, valves, filters, strainers, transmitters, sensors, and control devices. All gages and indicators shall be clearly visible by personnel standing on the floor or on permanent platforms. Do not reduce or change maintenance and operating space and access provisions that are shown on the drawings.

C. Equipment and Piping Support: Coordinate structural systems necessary for pipe and equipment support with pipe and equipment locations to permit proper installation.

D. Location of pipe sleeves, trenches, and chases shall be accurately coordinated with equipment and piping locations.

E. Cutting Holes:

1. Cut holes through concrete and masonry by rotary core drill. Pneumatic hammer, impact electric, and hand or manual hammer type drill is prohibited, except as permitted by the COR where working area space is limited.

2. Locate holes to avoid interference with structural members such as beams or grade beams.

Holes shall be laid out in advance and drilling done only after approval by COR. If the

Contractor considers it necessary to drill through structural members, refer to the COR for approval.

3. Do not penetrate membrane waterproofing.

F. Interconnection of Instrumentation or Control Devices: Generally, electrical and pneumatic interconnections are not shown but shall be provided.

G. Minor Piping: Generally, small diameter pipe runs from drips and drains, water cooling, and other service are not shown but shall be provided.

H. Electrical Interconnection of Controls and Instruments: Generally, not shown but shall be provided. This includes interconnections of sensors, transmitters, transducers, control devices, control and instrumentation panels, instruments, and computer workstations. Comply with NFPA

70.

I. Protection and Cleaning:

1. Equipment and materials shall be carefully handled, properly stored, and adequately protected to prevent damage before and during installation, in accordance with the manufacturer's recommendations, and as approved by the COR. Damaged or defective items, in the opinion of the COR, shall be replaced.

2. Protect all finished parts of equipment, such as shafts and bearings, where accessible, from rust prior to operation by means of protective grease coating and wrapping. Close pipe

MASSACHUSETTS NATIONAL CEMETERY PROJECT NO. 818-032

PHASE 4 DEVELOPMENT JANUARY 2020

COMMON WORK RESULTS FOR HVAC

23 05 11 - 16 openings with caps or plugs during installation. Tightly cover and protect fixtures and equipment against dirt, water chemical, or mechanical injury. At completion of all work, thoroughly clean fixtures, exposed materials, and equipment.

J. Concrete and Grout: Use concrete and shrink compensating grout 3000 psig minimum.

K. Install gages, thermometers, valves, and other devices with due regard for ease in reading or operating and maintaining devices. Locate and position thermometers and gages to be easily read by operator or staff standing on floor or on walkway provided. Servicing shall not require dismantling adjacent equipment or pipe work.

L. Work in Existing Building:

1. Perform as specified in paragraphs, OPERATIONS AND STORAGE AREAS, ALTERATIONS, and RESTORATION of //Section 01 00 01, GENERAL REQUIREMENTS

(Major NCA Projects), for relocation of existing equipment, alterations and restoration of existing building(s).

2. As specified in paragraph, OPERATIONS AND STORAGE AREAS of //Section 01 00 01, GENERAL REQUIREMENTS (Major NCA Projects), make alterations to existing service piping at times that will least interfere with normal operation of the facility.

3. Cut required openings through existing masonry and reinforced concrete using diamond core drills. Use of pneumatic hammer type drills, impact type electric drills, and hand or manual hammer type drills will be permitted only with approval of the RCOR. Locate openings that will least effect structural slabs, columns, ribs, or beams. Refer to the COR for determination of proper design for openings through structural sections and for opening layouts approval prior to cutting or drilling into structures. After COR approval, carefully cut opening through construction no larger than necessary for the required installation.

M. Switchgear Drip Protection: Every effort shall be made to eliminate the installation of pipe above electrical and telephone switchgear. If this is not possible, encase pipe in a second pipe with a minimum of joints.

N. Inaccessible Equipment:

1. Where the Government determines that the Contractor has installed equipment not conveniently accessible for operation and maintenance, equipment shall be removed and reinstalled or remedial action performed as directed at no additional cost to the Government.

2. The term "conveniently accessible" is defined as capable of being reached without the use of ladders, or without climbing or crawling under or over obstacles such as motors, fans, pumps, belt guards, transformers, high voltage lines, piping, and ductwork.

3.3 TEMPORARY PIPING AND EQUIPMENT

A. Continuity of operation of existing facilities will generally require temporary installation or relocation of equipment and piping.

MASSACHUSETTS NATIONAL CEMETERY PROJECT NO. 818-032

PHASE 4 DEVELOPMENT JANUARY 2020

COMMON WORK RESULTS FOR HVAC

23 05 11 - 17

B. Provide all required facilities in accordance with the requirements of phased construction and maintenance of service. All piping and equipment shall be properly supported, sloped to drain, operate without excessive stress, and shall be insulated where injury can occur to personnel by contact with operating facilities. The requirements of paragraph, ARRANGEMENT AND INSTALLATION OF EQUIPMENT AND PIPING apply.

3.4 RIGGING

A. Alternative methods of equipment delivery may be offered by Contractor and will be considered by Government if allowed under specified restrictions of phasing and maintenance of service as well as structural integrity of the building.

B. Close all openings in the building when not required for rigging operations, to maintain proper environment in the facility for Government operation, and maintenance of service.

C. Provide all facilities required to deliver specified equipment, and place on foundations.

Attachments to structures for rigging purposes and support of equipment on structures shall be

Contractor's responsibility. Upon request, the Government will check structure adequacy and advise Contractor of recommended restrictions.

D. Check all clearances, weight limitations, and provide a rigging plan designed by a Registered

Professional Engineer. All modifications to structures, including reinforcement, shall be at

Contractor's cost, time, and responsibility.

E. Rigging plan and methods shall be referred to COR for evaluation prior to actual work.

F. Restore building to original condition upon completion of rigging work.

3.5 PIPE AND EQUIPMENT SUPPORTS

A. Where hanger spacing does not correspond with joist or rib spacing, use structural steel channels secured directly to joist and rib structure that will correspond to the required hanger spacing, and then suspend the equipment and piping from the channels. Drill or burn holes in structural steel only with the prior approval of the COR.

B. Use of chain, wire, or strap hangers; wood for blocking, stays, and bracing; or, hangers suspended from piping above is prohibited. Replace or thoroughly clean rusty products and paint with zinc primer.

C. Use hanger rods that are straight and vertical. Turnbuckles for vertical adjustments may be omitted where limited space prevents use. Provide a minimum of 1/2 inch clearance between pipe or piping covering and adjacent work.

D. HVAC Horizontal Pipe Support Spacing: Refer to MSS SP-58. Provide additional supports at valves, strainers, in-line pumps, and other heavy components. Provide a support within one foot of each elbow.

E. Overhead Supports:

1. The basic structural system of the building is designed to sustain the loads imposed by equipment and piping to be supported overhead.

MASSACHUSETTS NATIONAL CEMETERY PROJECT NO. 818-032

PHASE 4 DEVELOPMENT JANUARY 2020

COMMON WORK RESULTS FOR HVAC

23 05 11 - 18

2. Provide steel structural members, in addition to those shown, of adequate capability to support the imposed loads, located in accordance with the final approved layout of equipment and piping.

F. Floor Supports:

1. Provide concrete bases, concrete anchor blocks and pedestals, and structural steel systems for support of equipment and piping. Anchor and dowel concrete bases and structural systems to resist forces under operating and seismic conditions without excessive displacement or structural failure.

2. Do not locate or install bases and supports until equipment mounted thereon has been approved. Size bases to match equipment mounted thereon plus 50 mm (2 inch) excess on all edges. Refer to structural drawings. Bases shall be neatly finished and smoothed, shall have chamfered edges at the top, and shall be suitable for painting.

3. All equipment shall be shimmed, leveled, firmly anchored, and grouted with epoxy grout.

Anchor bolts shall be placed in sleeves, anchored to the bases. Fill the annular space between sleeves and bolts with a granular material to permit alignment and realignment.

3.6 MECHANICAL DEMOLITION

A. In an occupied building, maintain the operation, cleanliness, and safety. Government personnel will be carrying on their normal duties or normal duties of operating, cleaning, maintaining equipment, and building operation. Confine the work to the immediate area concerned; maintain cleanliness and wet down demolished materials to eliminate dust. Allowing debris to accumulate in the area to the detriment of operations is prohibited. Perform all flame cutting to maintain the fire safety integrity of the building and occupants. Adequate fire extinguishing facilities shall be available at all times. Perform all work in accordance with recognized fire protection standards.

Inspection will be made by personnel of the VA and Contractor shall follow all directives of the

COR with regard to rigging, safety, fire safety, and maintenance of operations.

B. Completely remove all piping, wiring, conduit, and other devices associated with the equipment not to be re-used in the new work. This includes all pipe, valves, fittings, insulation, and all hangers including the top connection and any fastenings to building structural systems. Seal all openings, after removal of equipment, pipes, ducts, and other penetrations in roof, walls, and floors in an approved manner and in accordance with plans and specifications where specifically covered. Structural integrity of the building system shall be maintained.