Cost Proposal Breakdown Revised 7-30-20.pdf

PDF 147 KB Posted

Attached to
Y1PC--Massachusetts National Cemetery Phase 4 Expansion
Solicitation number
36C10F20R0042
Issued by

About this file

This document contains a cost proposal breakdown for a construction project to expand a national cemetery in Massachusetts. The cost proposal includes line item costs for a base bid and seven add alternates to complete site work and construct new burial sections, crypts, storage bins, roadways, and irrigation and electrical upgrades. The base bid and add alternates cover site demolition and preparation, concrete, masonry, metals work, utilities installation and other construction divisions. The total proposed cost is included. The related federal contract opportunity is to develop approximately 20 acres at the Massachusetts National Cemetery to include around 12,000 new gravesites under a tiered evaluation process.

View the file

Other files

File Type Posted
Pre-Proposal Inquiry (PPI) Form-- VA Responses dated 7-30-20.pdf PDF
36C10F20R0042 0005.pdf PDF
Geotechnical Engineering Report MNC BOURNE MA dated July 12 2019.pdf PDF
Pre-Proposal Inquiry (PPI) Form--VA Responses dated 7-29-20.pdf PDF
36C10F20R0042 0004.pdf PDF
36C10F20R0042 0003.pdf PDF
Pre-Proposal Inquiry (PPI) Form--VA Responses dated 7-27-20 Amendment 0003.pdf PDF
36C10F20R0042 0002.pdf PDF
Pre-Proposal Inquiry (PPI) Form--VA Responses dated 7-27-2020.pdf PDF
MASSACHUSETTS NATIONAL CEMETERY ITINERARY.pdf PDF
36C10F20R0042 0001.pdf PDF
Attachment 7 818PC2032-MNC_BD_PLANS_Part4.pdf PDF
Attachment 1 Wage Determination MA20200008 03-13-2020.pdf PDF
Attachment 8 818PC2032-MNC_BD_PLANS_Part5.pdf PDF
Attachment 4 818PC2032-MNC_BD_PLANS_Part1.pdf PDF
Attachment 13 Cost Proposal Breakdown.pdf PDF
Attachment 2 818PC2032-MNC_BD_SPEC_VOL1.pdf PDF
Attachment 5 818PC2032-MNC_BD_PLANS_Part2.pdf PDF
Attachment 3 818PC2032-MNC_BD_SPEC_VOL2.pdf PDF
Attachment 12 Pre-Proposal Inquiry (PPI) Form.pdf PDF
36C10F20R0042.docx DOCX document
Attachment 6 818PC2032-MNC_BD_PLANS_Part3.pdf PDF
Attachment 11 Contractor Safety and Environmental Record Evaluation Form.pdf PDF
Attachment 9 818PC2032-MNC_BD_PLANS_Part6.pdf PDF
Attachment 10 Past Performance Questionnaire.pdf PDF
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Revised 7/30/20

Offeror: Solicitation No.:

Cost Proposal Breakdown

CLIN/

Division Description Cost Totals

CLIN 001 – Base Bid

01A Insurance & Bonding 01B Overhead & Profit 01C Taxes & Permits 01D Demolition 01E Clearing and Grubbing 01F General Conditions

02A Temporary Facilities Including Trailers & Other Resident Engineer Provisions

02B Restoration of Temporary Facilities 03 Concrete

04 Masonry and Stone

05 Metals

06 Wood, Plastics, And Composites

07 Thermal & Moisture Protection

08 Openings – including doors and windows

09 Finishes

10 Specialties

11 Equipment 22 Plumbing

23 HVAC

26 Electrical

27 Communications

28 Electronic Safety and Security

31 Earthwork & Site Development

31 Crypt Installation 32 Irrigation 32 Landscaping 32 Roadways & Paving

32 Exterior Improvements Including Signage and Site Furnishings

33 Utilities

Sub-Total – CLIN 001

CLIN 002 – Cost of Crypts (not including placement)

03 Concrete Crypts

Subtotal – CLIN 002

Division Description Cost Totals

CLIN 003 – Add Alternate #1 – Replacement of Concrete Caps with Bluestone Caps 01 General Requirements 02 Demolition 04 Masonry

05 Metals 06 Wood, Plastics, and Composites 07 Thermal & Moisture Protection 09 Finishes 10 Specialties

Subtotal – CLIN 003 ______________________

CLIN/

Division Description Cost Totals

CLIN 004 – Add Alt #2 – Material Storage Bin (3- Bin) 01 General Requirements 02 Demolition 03 Concrete

04 Masonry 05 Metals 06 Wood, Plastics, and Composites 07 Thermal & Moisture Protection 09 Finishes

31 Earthwork

Subtotal – CLIN 004

CLIN 005 – Add Alternate #3 – Roadway 1

01 General Requirements 02 Demolition 32 Roadways and Paving

Sub-Total – CLIN 005

CLIN 006 – Add Alternate #4 – Maintenance Building - Restrooms

03 Concrete 05 Metals 06 Wood, Plastic and Composites 07 Thermal and Moisture Protection 08 Openings 09 Finishes 10 Specialties 22 Plumbing

23 HVAC

26 Electrical

27 Communications Sub-Total – CLIN 006

CLIN 007 – Add Alternate #5 – Metal Roof Replacement

05 Metal 07 Thermal and Moisture Protection

Sub-Total – CLIN 006

CLIN 008 – Add Alternate #6 – Upgrade Irrigation Controllers

32 Irrigation

Sub-Total – CLIN 008

CLIN 009 – Add Alternate #7 Hardwire Solar Irrigation Controllers

01 General Conditions

26 Irrigation

32 Electrical

Sub-Total – CLIN 009

GRAND TOTAL CLINs 1-9

File details come from the government source that posted it. Updated .