Attachment 2- SCMACC SOW (6 Apr 20).pdf

PDF 193 KB Posted

Attached to
Space Coast Multiple Award Construction Contract (SCMACC) Federal contract opportunity
Solicitation number
FA252120R0009
Issued by
Department of the Air Force Space Command

About this file

This document is a draft statement of work for a multiple award construction contract to provide maintenance, repair and minor military construction services at various facilities in Florida. Work will include furnishing all materials, equipment, transportation and personnel necessary to design up to 100%, manage and accomplish simultaneous projects for a broad range of maintenance, repair and minor construction work. Services will be provided at Cape Canaveral Air Force Station, Patrick Air Force Base, Kennedy Space Center and the Jonathan Dickinson Missile Tracking Annex in Florida for the 45th Space Wing, Naval Ordinance Test Unit, Air Force Technical Applications Center and National Aeronautics and Space Administration along with other tenant units. This contract will also be available for use by the 6th Contracting Squadron at MacDill Air Force Base to support natural disaster contingency response.

View the file

Other files for this federal contract opportunity

Other files attached to Space Coast Multiple Award Construction Contract (SCMACC), newest first.
File Type Posted
SF30 Amend 04 20R00090004.pdf PDF
Attachment 22- Badge Request 45 SFS Form V11.pdf PDF
SF30 Amend 03 20R00090003.pdf PDF
Attachment 20b (revised) SCMACC QA (29_ 34).pdf PDF
SF30 Amend 02 20R00090002.pdf PDF
Attachment 20b SCMACC QA (16-62).pdf PDF
Attachment 5 - SCMACC Section L (Rev).pdf PDF
Attachment 20a SCMACC QA (1-15).pdf PDF
SF30 Amend 01 20R00090001.pdf PDF
Attachment 13-Past_Performance_Questionnaire (Rev).pdf PDF
Attachment 5- SCMACC Section L.pdf PDF
Attachment 15a-MacDill Appendix and Forms.pdf PDF
Attachment 7a-Financial_Information_Request.pdf PDF
Attachment 21- Q_A Template.pdf PDF
Attachment 19-NAF General Provisions_Clauses.pdf PDF
Attachment 18a-KSC Project Deliverables.pdf PDF
Attachment 11-Fully-Burdened_Hourly_Labor_Ratesv2.pdf PDF
Attachment 9-Consent_Letter.pdf PDF
Solicitation - FA252120R0009.pdf PDF
Attachment 2- SCMACC SOW.pdf PDF
Attachment 4-Task_Order_Procedures.pdf PDF
Attachment 7-Financial_Information_Request_Auth.pdf PDF
Attachment 4a-On-Off_Ramping_Procedures Rv1.pdf PDF
Attachment 13-Past_Performance_Questionnaire.pdf PDF
Attachment 17-KSC Clauses.pdf PDF
Attachment 6- SCMACC Section M.pdf PDF
Attachment 12-Past_Performance_Information_Citations_-_Unique_Areas.pdf PDF
Attachment 14 RESERVED.pdf PDF
Attachment 1- 45 CES Specifications.pdf PDF
Presolicitation Notice.pdf PDF
Attachment 20- SCMACC QA.pdf PDF
Attachment 10-Sample_Client_Authorization_Letter.pdf PDF
Attachment 4a-On-Off_Ramping_Procedures.pdf PDF
Attachment 12-Past_Performance_Information_Citations_-_Unique_Areas.pdf PDF
Attachment 16-NFS Clauses.pdf PDF
Attachment 6- SCMACC Section M.pdf PDF
DRAFT Solicitation - FA252120R0009.pdf PDF
Attachment 3-Wage Rate Requirements (Brevard Co.) (21Feb 2020).pdf PDF
Attachment 1- 45 CES Specifications.pdf PDF
Attachment 13-Past_Performance_Questionnaire.pdf PDF
Attachment 7-Financial_Information_Request_Contractor.pdf PDF
Attachment 17-KSC Clauses.pdf PDF
Attachment 8a-Bonding_Information_Request_Surety.pdf PDF
Attachment 5- SCMACC Section L.pdf PDF
Attachment 15- MacDill Design Guide (2019).pdf PDF
Attachment 4-Task_Order_Procedures.pdf PDF
Attachment 9-Consent_Letter.pdf PDF
Attachment 18-KSC Project Specific Requirements.pdf PDF
Attachment 8-Bonding_Information_Request_Contractor.pdf PDF
Attachment 11-Fully-Burdened_Hourly_Labor_Rates.pdf PDF
Show all 50

Space Coast Multiple Award Construction Contract (SCMACC) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA2521-20-R-0009

Attachment 1

6 Apr 20

BASIC CONTRACT

STATEMENT OF WORK

for

SPACE COAST MULTIPLE AWARD CONSTRUCTION CONTRACT (SCMACC)

SOLICITATION NUMBER: FA2521-20-R-0009

TABLE OF CONTENTS

1.0 SCOPE

2.0 APPLICABLE DOCUMENTS

3.0 GOVERNMENT PROPERTY INCLUDING GOVERNMENT FURNISHED INFORMATION,

EQUIPMENT, AND PROPERTY (GFI, GFE, GFP)

4.0 MANAGEMENT, PLANNING, AND REPORTING REQUIREMENTS

4.1 SCHEDULE AND PLANNING REQUIREMENTS

4.1.1 Project Planning Chart (PPC) and/or Construction Planning Chart (CPC)

4.1.2 Integrated Master Schedule (IMS)

4.2 MEETING AND CONFERENCE REQUIREMENTS

4.2.1 Meeting/Teleconference Support

4.2.2 Red Zone Meeting

4.3 CONTRACTOR DOCUMENTATION

4.4 NOTIFICATION REQUIREMENTS

4.5 PERMITS

4.6 PHOTO DOCUMENTATION

4.7 REMOTE AND/OR AUSTERE SITES

4.8 SITE ACCESS BADGES

4.9 WORKSITE ACTIVITIES AND COORDINATION

4.9.1 Project Superintendent……………………………………………………………………………………… …9

4.9.2 Coordination of Activities Related to Safety

4.9.3 Radiological Waste, Hazardous Material and Hazardous Waste Permitting and Reporting

4.9.4 Recycable Waste Diversion Reports

4.10 PROJECT DATA/PROJECT DELIVERABLES

4.10.1 Protecting Unclassified DoD Data

4.10.2 Security Breach Notification

4.10.3 Data Collaboration Site

4.11 HEALTH AND SAFETY PLAN (HSP)

4.12 QUALITY SYSTEM PLAN (QSP)

4.13 TECHNICAL PLANS AND REPORTS

4.13.1 Construction Work Plan

4.13.2 Technical Reports

5.0 EXECUTING THE WORK

5.1 SITE WORK

5.1.1 Conservation

5.1.2 Site Preparation

5.1.3 Demolition

5.2 CONSTRUCTION OPERATION SERVICES

5.2.1 Construction

5.2.2 Inspections

5.2.2.1 Pre-Final Inspection

5.2.2.2 Final Inspection

5.2.3 Delivery and Warranty

5.3 DEMOBILIZATION

5.4 EMERGENCY RESPONSE

6.0 FACILITY CONSTRUCTION TASK ORDER DELIVERY METHODS

6.1 DESIGN BUILD (D-B)

6.1.1 Designers of Record (DOR)/Design Project Manager (PM)

6.1.2 Contractor Design Requirements after Award

6.1.3 User Requirements Design Meeting

6.1.4 Geotechnical/Hazardous Material Survey Requirements and Responsibilities

6.1.5 General Design Requirements

6.1.5.1 Furniture, Fixtures & Equipment (FF&E) Requirements

6.1.5.1.1 CID/SID and FF&E Interim and Final Design Submittals

6.1.5.1.1.1 Submittal Development

6.1.5.1.1.2 Submittal Format and Timing

6.1.5.1.1.3 Presentation Color Boards

6.1.6 Design Review

6.2 DESIGN-BID-BUILD (D-B-B)

7.0 ADDITIONAL REQUIREMENTS

7.1 TYPES OF PROJECTS/WORK

7.1.1 Asbestos and Hazardous Metal Management/Abatement

7.1.2 Utilities

7.1.3 Waste Water Treatment Plant Systems

7.1.4 Pavement Systems (Airfield and Non-airfield)

7.1.5 Renovations (including historic buildings)

7.1.6 Construction of Classified or Highly Secure Facilities

7.1.7 Mold/Mildew Rememdiation and Cleanup

7.1.8 Historic Preservation and Artficact Restoration

7.1.9 Coast and Shore Front Facilities

7.1.10 Other Civil Engineering Work

7.2 AS-BUILT DOCUMENTATION

8.0 POINTS OF CONTACT (POCS)

1.0 SCOPE

This Basic Contract Statement of Work (SOW) defines the scope of a full range of design, construction and engineering activities necessary to meet Air Force and other customer requirements for the Space Coast Multiple Award Construction Contract (SCMACC). This basic contract SOW will be tailored to identify specific requirements at the Task Order (TO) level.

SOWs or Statements of Requirements (SOR) may be used under this contract at the TO level.

Projects will be located at Patrick Space Force Base, Cape Canaveral Space Force Station, Kennedy Space Center, and other 45 SW Geographically Separated Units (GSU) in Florida that support these locations.

Prior to issuing any task order under this SOW, the Government will develop Statement of Objectives (SOO) either through Government in-house resources or through private consultants.

The Statement of Objectives will clearly define the project requirements in terms of performance, appearance, criteria and/or specification with sufficient detail that permits a contractor to provide a proposal with reasonable performance, cost and schedule.

This SOW is organized and developed to provide maximum flexibility in the use of this contract vehicle. Basic requirements described here are further refined through the use of individual project Task Orders (TO). TOs will be issued for projects at various stages of development.

General performance requirements for construction activities are described throughout this SOW. Depending on the project development stage and level of design required, TOs will be issued for Design-Build (D-B) or Design-Bid-Build (D-B-B) Construction as determined by the Government. Each method is separately described in Section 6.0 of this SOW.

This SOW encompasses the full range of methods, technologies, and supporting activities necessary to conduct project construction at Air Force installations and other locations within the United States in accordance with (IAW) technical and regulatory requirements. Stand-alone design is not included in the scope of this contract. All new permanent facilities and major renovations/repairs of existing facilities designed using D-B procedures shall comply with Whole Building Design Guide criteria.

The contractor shall function as an integral team member in support of the Air Force and other customer missions, to include sharing information with other contractors and cooperation with communities and other Government entities.

Requirements include efficient management of TOs including, but not limited to, the submission of accurate, on-time, quality contract deliverables and timely identification and solution of impediments to successful project execution. Technical requirements include, but are not limited to the development of the most cost-effective and technically sound approach or solution. The Government will rely on the contractor’s expertise in recognizing and addressing problematic issues and successful execution of each TO. The contractor shall perform all work IAW federal, state, and local statutes and regulations.

2.0 APPLICABLE DOCUMENTS

The Contractor shall identify and comply with all applicable federal, state, and local laws;

statutes; Executive Orders; Department of Defense/Air Force manuals, handbooks, regulations, guidance, and policies. The contractor shall comply with the National Institute of Building Sciences, Whole Building Design Guide Construction Criteria Base (CCB), Unified Facility Criteria (UFC) and all of the related libraries. The primary criteria are the Air Force Criteria from the Documents Library, but other agency criteria may be directed for use, depending on the customer agency for a particular TO. The Unified Facilities Guide Specifications (UFGS) is the mandatory starting point for all specifications, and shall not be deleted, materially modified, or made less stringent without Government approval. It is the contractor’s responsibility to identify and comply with all applicable requirements. It shall be the contractor’s responsibility as the Designer of Record (DOR) to identify any design/construction criteria waivers that are warranted for the TO and to accomplish all necessary coordination activities necessary to obtain approval of these proposed waivers through the Contracting Officer (CO), and/or Project Manager (PM).

In addition, the contractor shall refer to and comply with the current versions of the Department of Defense Policy and Guidelines for Acquisitions Involving Environmental Sampling or Testing and The United States Air Force Construction Management Implementation Guide as well as the latest version of The USAF Project Manager’s Guide to Design and Construction. Agency-specific documents shall be identified in each TO.

3.0 GOVERNMENT PROPERTY INCLUDING GOVERNMENT FURNISHED

INFORMATION, EQUIPMENT, AND PROPERTY (GFI, GFE, GFP)

GFI, GFE, GFP requirements will be specified in each TO, to include delivery, management, accountability and disposition. FAR 52.245-1 defines Government Property and the procedures for accounting for and disposition of property. Defense Contract Management Agency (DCMA) instructions for reporting of and including in the Plant Clearance Automated Reutilization Screening System (PCARSS) will be followed for any Government Property remaining at the end of the project.

To the extent it is available, the Government will provide information in the form of available conceptual design plans, reports, maps, drawings, and as-built drawings as necessary to facilitate accomplishment of the work required in the task order SOW. However, these GFIs are to be utilized by the SCMACC contractor as guidance to facilitate a complete, technically adequate design and are not warranted to show conditions as they actually exist. The designer shall verify (by field investigation and through design development) information shown on all GFIs (relevant to the project) for accuracy to ensure technical adequacy of the design.

4.0 MANAGEMENT, PLANNING, AND REPORTING REQUIREMENTS

The contractor shall implement a full range of design, construction and engineering activities as specified in each TO and IAW all applicable compliance documents. The contractor shall supply all labor, equipment, and materials necessary to accomplish the work assigned unless otherwise specified in each TO. The contractor shall perform management and planning functions, including performance measurement and status reporting to effectively secure and monitor prime and sub-contract work, as required in each TO.

4.1 Schedule and Planning Requirements

The contractor shall provide schedules for tracking work progress. The SOW for each TO will identify which of the following schedules is required. Generally, the Government will require Project Planning Charts (PPCs) and/or Construction Planning Charts (CPCs) for less complex projects and Integrated Master Schedules (IMS) for more complex projects.

4.1.1 Project Planning Chart (PPC) and/or Construction Planning Chart (CPC)

The contractor shall prepare and submit a PPC and/or CPC in addition to the AF Form 3064 weekly for approval unless CO approves otherwise. The PPC/CPC shall detail the project schedule and status through the use of Gantt charts, which shall depict percent complete for each task. The project schedule shall be reported using the approved work-based schedule.

4.1.2 Integrated Master Schedule (IMS)

The contractor shall submit the Initial IMS and AF Forms 3064/3065 for approval within 30 calendar days after award or as otherwise directed by the CO for Government review, evaluation, and approval on an AF Form 3000. The Initial IMS shall be prepared and submitted in Primavera P6 and .pdf formats and shall be based on the schedule presented in the contractor’s accepted proposal. Compliance with SECTION 01 32 01.00 10 PROJECT SCHEDULE is required. The Initial IMS shall be cost loaded according to contract award most current Construction Specification Institute (CSI) Divisions and include major cost/schedule drivers such as, major material submittals and/or long lead-time items, work plans, and project close-out. The Initial IMS shall include an advanced level of detail and include all necessary activities, tasks, and subtasks to reflect all remaining construction activities. The schedule shall also allow for 10

– 14 days for closeout. The schedule must provide 10 business days for review and approval of construction material submittals. The Initial IMS shall be provided by the contractor and approved by the Government before a full Notice to Proceed (NTP) will be issued by the CO.

The approved IMS shall not be re-baselined by the contractor without approval by the CO. In the event of a contract change the contractor shall provide a re-baselined schedule, showing any new activities created by the change. Also, with the new schedule a narrative must be provided, detailing how any tasks in the previous schedule were altered in the new, updated schedule.

The Government shall use the IMS to measure the progress of the work based on earned value and aid in evaluating all progress payments. The contractor shall progress the schedule monthly unless otherwise directed by the CO. At a minimum, the AF Form 3064/3065 shall be derived from the IMS and be structured by major CSI divisions and assigned appropriate value in relationship to overall work and contract value. The contractor shall submit the updated progressed IMS (in native format and .pdf), and AF Forms 3064 every month. AF Form 3065s shall be submitted weekly for review/approval by the CO every Monday, unless otherwise directed by the CO. Upon acknowledgement of the NTP and continuing throughout the contract, the contractor shall record on the daily report, the occurrence of adverse weather (Phase I and Phase II lightning warning times), launch critical day impacts, and result impact to normally scheduled work.

4.2 Meeting and Conference Requirements

4.2.1 Meeting/Teleconference Support

The contractor shall attend meetings necessary to support design coordination, design review, construction activities, etc. The contractor also shall attend and support periodic meetings and/or teleconferences through the construction phase of the contract. Frequency of periodic meetings will be specified in the TO. The contractor shall prepare and maintain the periodic meeting agenda report which shall include the record of new and old discussion of technical issues, periodic earned value progress showing percent complete actual versus planned, tabular report of late tasks derived from the updated PPC/CPC or IMS, a three week look ahead, and tabular report for Requests for Information (RFIs) and submittals (open and upcoming). The contractor shall prepare, and submit for review, presentation materials for meetings and an agenda. The contractor shall prepare minutes for meetings attended, including teleconferences, design reviews, and “Red Zone Meetings”, and distribute minutes to attendees within three (3) working days.

4.2.2 Red Zone Meeting

The contractor shall support “Red Zone Meetings” as part of the closeout of the project if indicated in TO. The “Red Zone” shall commence at 80-percent of construction completion. At this meeting, the contractor and the project stakeholders shall discuss, define, and achieve consensus on actions necessary to complete construction, support user occupancy, and project closeout.

4.3 Contractor Documentation

The contractor shall create and maintain a Master Document List (MDL) that includes all documents, whether the document is a deliverable or not, which are prepared during the course of the TO. This includes, but is not limited to correspondence, requests for information, material submittals, schedule submittals, status reports, schedule updates, etc. The MDL will include the dispatch/receipt date, any suspense for each document, and the final disposition of those suspense’s. The MDL and its documents shall be maintained in Data Collaboration Site (4.12.3) and be readily available for submittal to the Government. All Material Submittals shall be accomplished IAW the instructions pertaining to AF Form 3000 (or other agency specific forms), Material Approval Submittal.

4.4 Notification Requirements

The contractor is required to notify the CO and PM of anything the contractor feels is outside their scope of work and/or beyond their control that could impact cost, schedule, or quality.

Additionally, the contractor is required to notify the CO and PM of critical issues that may affect the contract performance and/or human health and the environment. These types of issues that require notification include, but are not limited to, health risks, spills, changes in critical or key personnel, and finding unexploded ordnance (UXO). As an example, if unanticipated UXO were discovered during field activities, the contractor will immediately stop work, report the discovery to the facility Point of Contact (POC) (designated at the TO level), CO, and PM, and implement the appropriate safety precautions. Field activities shall not continue until clearance is received from the CO. On critical issues, verbal notification should be made immediately, followed by written notification within 2 business days.

4.5 Permits

The contractor shall develop, coordinate, and, apply for and obtain all applicable permits, access (including off-base easements and leases), agreements, licenses, and certificates required to perform and complete effort as specified under each TO. The contractor shall maintain a library of these documents at the contractor’s site office as well, the corporate facility handling each TO and in the Data Collaboration Site (4.10.3) to be readily available to the Government. The contractor shall comply with all applicable permit conditions, and shall keep all permits “current” until construction is 100% complete. The contractor may be required to provide the permits to the Government as required.

4.6 Photo Documentation

The contractor shall prepare digital photo documentation, including site(s) and building(s) under construction, field activities, and sample locations if applicable. Digital photos will be submitted using a minimum five (5) mega pixel photograph in JPEG format. The contractor shall provide an index for each set of photographs submitted, identifying the base or facility, TO number, project number, contractor, and a brief description. Photography of any kind must be coordinated through the installation, customer, or facility POC. Photo documentation shall be loaded to the Data Collaboration Site (4.10.3) as specified at the task order level, as requested by the base POC or directed by the CO and/or PM.

4.7 Remote and/or Austere Sites

The contractor may be requested to perform work as specified at remote and/or austere locations at one of the GSUs located in the state of Florida. The contractor shall be responsible for all personnel, security, supplies, equipment, and infrastructure (including, but not limited to, potable water, utility systems, etc.) when these facilities and services are not available. This shall include providing these facilities and services to a limited number of Government personnel or other contractor personnel (such as personnel under contract to perform Title II A-E services) present or visiting to oversee or assess the work.

4.8 Site Access Badges

The contractor shall obtain and monitor assigned security badges or passes (used by both contractor and subcontractor personnel) for the duration of this contract. All security badges or passes shall be returned to the base POC upon expiration of the badge, upon completion of the project, or when possession of the badge is no longer necessary (e.g., upon removal of contractor personnel from specific projects). Requirements for Common Access Cards (CACs) will be specified at the TO level.

4.9 Worksite Activities and Coordination

4.9.1 Project Superintendent

The project Superintendent must maintain a physical presence at the site at all times construction is taking place and is responsible for all construction and related activities at the site. The project Superintendent should be from the Prime Contractor, unless otherwise specified at the task order level. The project Superintendent must have the authority to commit and bind the Prime Contractor in exercising his superintendence. It is not acceptable for the Site Superintendent to have to request approval to make decisions on site. The project Superintendent must be appointed in writing prior to any work being performed on-site.

4.9.2 Coordination of Activities Related to Safety

The contractor shall be responsible for protecting the lives and health of employees and other persons on the work site; preventing damage to property, materials, supplies, and equipment, avoiding work interruptions and complying with Occupational Safety and Health Administration (OSHA) safety and local safety office requirements. The contractor shall perform all operations in a prudent, conscientious, safe and professional manner and conform to the safety requirements contained in the contract for all activities related to the accomplishment of the work. The contractor shall maintain documentation supporting training records on site and have written Health and Safety Plans on site and available for workers and/or regulatory review. The contractor shall provide the CO copies of any OSHA report(s), regarding a project site, submitted during the duration of the TO. For areas not covered by OSHA, the contractor shall comply with regulations regarding safety and health and the current edition of the U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1.

The contractor shall record and report promptly (within 1 hour) by telephone, email or other direct means to the CO, PM, the base POC, and to the military installation’s Safety Office, all available facts relating to each instance of damage to Government property or third party property or injury to either contractor, Government, or third party personnel. In the event of an accident/mishap, take reasonable and prudent action to establish control of the accident/mishap scene, prevent further damage to persons or property, preserve evidence until released by the accident/mishap investigative authority through the CO, and immediately report the incident to Emergency Services using the most expedient communication means (e.g., dialing 911 in the United States). If the Government elects to conduct an investigation of the accident/mishap, the contractor shall cooperate fully and assist Government personnel in conducting the investigation until it is completed.

The contractor agrees that all personnel and equipment are subject to safety inspections by Government personnel while on federal property.

4.9.3 Hazardous Material and Hazardous Waste Permitting and Reporting

The contractor shall sample, provide analysis from certified lab to Base Environmental Office and handle all hazardous materials and waste that is a requirement for construction of the project IAW applicable federal, state, and local requirements. The contractor shall provide Department of Transportation (DOT) approved containers and labels for hazardous, non- regulated and polychlorinated biphenyls (PCB) wastes during generation and storage. The contractor shall provide all hazardous materials use and hazardous waste disposal documentation to the Base Environmental Office or Installation Hazardous Waste Program Manager, and shall register with the Hazardous Materials Pharmacy program (if available) at the installation to ensure appropriate and efficient tracking of the contractor’s hazardous material purchases, inventories, use, and releases such as required by the Emergency Planning and Community Right-to-Know Act (EPCRA), Executive Orders, or any installation reporting requirements. The contractor shall submit hazardous waste manifest to the Installation Hazardous Waste Program Manager for review, approval and signature prior to any hazardous waste removed from installation. All hazardous Waste generated on the installation will be disposed of under the installation EPA ID number.

The contractor shall also comply with federal, state, and local requirements for any task involving the transportation of hazardous wastes and/or contaminated materials to off-site treatment, storage and/or disposal facilities. The contractor is responsible for the disposition of all Hazardous Material and Waste produced by activities directly involved in the construction related operations. This includes 40 CFR 260 - 280, 49 CFR 172, 173, 178, 179 and all other applicable local, state, and federal transportation regulations. The contractor shall ensure that all personnel involved in handling and packaging the hazardous waste be trained for the level of expertise required for the proper performance of the task and, in particular, in the areas of chemical incompatibility, general first aid procedures and spills. Hazardous waste training will provided for contractor by the Installation Hazardous Waste Program Manager. The contractor shall provide handling and personnel protective equipment to ensure safe handling of the hazardous/asbestos waste. The contractor agrees that all personnel and equipment are subject to safety inspections by Government personnel while on federal property.

4.9.4 Recyclable Waste Diversion Reports

The contractor shall provide monthly weight tickets of recyclable material diverted from landfills from TO. Tickets shall be in spreadsheet or pdf format and weight must be measured in tons.

4.10 Project Data/Project Deliverables

Project data and deliverables, as specified in each TO shall be provided to personnel by the contractor to support multiple projects with real-time or near real-time access. Deliverables may include, but are not limited to, a submittal tracker or register, a Request for Information (RFI) tracker, a change order tracker, a photographic log, status reports and project schedule(s).

4.10.1 Protecting Unclassified DoD and Government Data

All DoD and Government data that is shared, stored or created on non-DoD information systems must be protected and any breach or loss of that data must be reported. The contractor shall comply with the security requirements defined in DoD Instruction 8582.01.

4.10.2 Security Breach Notification

Contractor agrees to comply with all applicable laws that require the notification of individuals in the event of unauthorized release of personally identifiable information or other event requiring notification. In the event of a breach of any of contractor’s security obligations, or other event requiring notification under applicable law, contractor agrees to:

a. Notify CO by telephone and e-mail of such an event within 24 hours of discovery, and

b. Notify the US-CERT of such an event within 24 hours of discovery, and

c. Assume responsibility for informing all such individuals IAW applicable law, and

d. Indemnify, hold harmless and defend the United States, its trustees, officers, enlisted, and employees from and against any claims, damages, or other harm related to such event.

4.10.3 Data Collaboration Site

The contractor shall establish a Data Collaboration with real-time worldwide access available to persons authorized by the CO. DoD’s standard for this application is Oracle’s Primevera Submittal Exchange Cloud Service and for NASA is it Microsoft SharePoint. The site may include, but not be limited to, the submittal register, submittals, a Request for Information (RFI) tracker, a change order tracker, a photo log, project IMS record, quality control reports, daily reports with complete record of activities and on-site personnel, and other relevant project correspondence. The site must be demonstrated to the Government and approved by the CO prior to any submittals being submitted. The site shall be tailored to the individual projects and close-out documentation shall include an electronic copy of the site documentation, provided in electronic format – digital video disc (DVD) for historical information. Data Collaboration Site data shall be IAW 4.10.1 Protecting Unclassified DoD Data.

4.11 Health and Safety Plan (HSP)

The contractor shall provide a Health and Safety Plan (HSP) IAW EM385-1-1.

4.12 Quality System Plan (QSP)

The contractor shall prepare, for Government review and acceptance, a site-specific QSP that consists of plans, procedures, and organization necessary to produce an end product which complies with the contract requirements. The QSP shall cover all definable features of work (construction operations, both onsite and offsite) and be keyed to the construction sequence.

4.13 Technical Plans and Reports

The contractor shall provide technical plans, specifications, and reports as defined below and implemented at the TO level. Some of these may include, but are not limited to, the following:

4.13.1 Construction Work Plan

The contractor shall prepare a construction work plan that may include, but is not limited to, any or all of the following subsections as identified in each TO.

A. Work Sequencing B. Design Analysis C. Security D. Site Analysis E. Site Preparation F. Excavation G. Spill and Discharge Control H. Explosive Safety I. Health/Safety Plan J. Hazardous Materials Management K. Asbestos Abatement L. Surface Water Management M. Ground Water Management N. Erosion Control O. Emissions Control P. Material and Equipment Control and Storage Q. Transportation R. Startup Testing and Commissioning Plans

S. Warranty Call Out Program T. Draft DD Form(s) 1354 U. Demobilization V. Final DD Form(s) 1354 W. O&M Training Manuals X. Site Specific Safety Plans

4.13.2 Technical Reports

The contractor shall prepare and submit the following technical reports as identified in each TO.

All of the following technical reports may not be required at the TO level. Those that are required will be specified as such in each individual TO.

A. Miscellaneous Technical Report B. Construction Cost Estimates C. Site/Project Summary D. Daily Technical/Field Reports (Status Reports)

(As a part of the daily technical/field reports, all tasks shall be identified by Construction Activity Identification Number (CAIN) and correspond with the approved baseline schedule and the WBS.)

E. Hazardous Materials Survey Report F. Hazardous Material and/or Hazardous Waste Disposal Report G. Design Drawings H. Shop Drawings and/or As-built Drawings I. Design Specifications J. Geographical Information Systems Updates K. Computer Aided Design Drawings L. Survey Reports M. Quality Assurance/Quality Control Surveillance Plan N. O&M Training Manuals O. Startup and Commissioning Report P. Warranties Q. Call-Out Procedures R. Pre-Final Inspection Report S. Final Inspection Report

5.0 EXECUTING THE WORK

5.1 Site Work

The contractor shall perform site preparation, incidental characterization and field investigation, conservation, and demolition of sites as required in each TO.

5.1.1 Conservation

Activities shall be planned and implemented in a manner that protects existing site utilities, structures, surface features, service operations, monitoring and other types of wells, and the general site environment. This includes the protection of trees, shrubs and other vegetation not in the affected zone from dust damage, soil compaction, and physical contact with machines and equipment. If appropriate, the contractor shall conserve uncontaminated topsoil by removal, storage, or redistribution. All reasonable measures shall be taken to minimize and suppress fugitive emissions of dust, vapors, and other site materials during site work. All fill materials shall be non-contaminated. The contractor shall conduct all operations and activities with the intent of reducing the amount of pollution generated. Specific areas to be focused on are generation of solid waste, use of hazardous materials, use of ozone depleting chemicals, generation of hazardous waste, and use of energy and water. During site work the contractor shall plan, construct, operate, maintain, optimize, and decommission systems necessary to control storm water run-on and run-off; and transport surface water drainage to a treatment plant, discharge location, or any other appropriate destination for discharge IAW local environmental regulations.

5.1.2 Site Preparation

The contractor shall perform site work as necessary to prepare sites for construction activities.

Security and access controls shall be implemented to prevent unauthorized entry to sites and to protect wildlife from site exposure. The contractor shall survey existing utilities to determine adequacy and need for modifications to support site activities. The contractor shall obtain appropriate approvals and shall construct connections or new systems for electrical power, water, sewer, gas distribution, telephone, and other utilities, as required, to accomplish the activities specified in each TO.

5.1.3 Demolition

The contractor shall demolish facilities, systems, and other improvements as necessary to prepare sites for future construction activities. Demolition activities can be ancillary to other requirements or a stand-alone project. The contractor shall conduct demolition efforts in conjunction with such activities as new construction or renovation, removal of outdated facilities, and site clearing from natural disasters. The contractor shall perform surveys as part of demolition efforts to identify conditions and hazardous materials or Asbestos related hazards for mitigation. Demolition efforts shall include validation of existing utilities for active conditions, evaluate potential environmental concerns, and support all AF Real Property considerations at the TO Level.

5.2 Construction Operation Services

The contractor shall perform a full range of activities to meet all customers engineering and other construction requirements as described in each TO. Requirements may include construction, completion of conceptual design and construction, demolition, decommissioning, and emergency response for traditional engineering and construction needs. All completed designs shall be signed and sealed IAW all applicable requirements.

The contractor shall execute traditional engineering and construction projects. The contractor shall plan, develop cost estimates, install, construct, test, and decommission any site IAW each

TO.

The contractor shall perform incidental support such as designing, planning, programming, scoping, studying, investigating, evaluating, and consulting on traditional engineering and construction efforts. The contractor shall also provide training and operational support to Government and other contractor personnel regarding the operations and maintenance of equipment, systems, and facilities. The contractor shall provide operation and maintenance of equipment and systems during the commissioning period prior to acceptance by the Government.

5.2.1 Construction

Upon issuance of the Notice to Proceed (NTP) by the CO, the contractor may commence on-site construction activities. The contractor shall provide the manpower, equipment, material, services, and transportation necessary to review, plan, develop and implement quality control and oversight services during the construction phase of each TO. Key personnel for the prime contractor, to include the Site Superintendent and Health & Safety Manager (which can be the same individual) or their CO approved designated replacement. The key personnel will be onsite 100% of the time during all construction activities for the performance period of the contract.

The Quality Control manager or their CO approved designated replacement will be onsite 25% of the time during all construction activities for the performance period of the contract. The Project Manager shall be responsible for ensuring that practical and effective systems are developed to complete the task order and is expected to maintain a frequent on-site presence unless otherwise specified at task order level. In the event of brief absences by the primary, the contractor’s management plan shall include provisions for coverage of key positions by equally qualified personnel for the duration of those brief absences. Details regarding construction management requirements, inspection and testing, construction facilities and temporary controls, environmental protection, quality control system, construction quality control, and project closeout will be provided in the Statement of Objectives (SOO) for each TO.

5.2.2 Inspections

In all work performed it is the contractor’s responsibility to perform proper quality control (QC) inspections throughout the project to ensure a quality product. The Government inspector is responsible for adequate Quality Assurance (QA) for the work accomplished. It is not the role of the Government to perform the contractor’s QC for the project, especially during inspections.

The contractor shall comply with the standard three phase Contractor Quality Control (CQC) inspection process, referring to the standard UFGS 01 45 00.00 10.

5.2.2.1 Pre-Final Inspection

The contractor shall conduct a pre-final walkthrough or multiple inspections prior to Beneficial Occupancy Date (BOD) and publish each of the pre-final inspection findings in a pre-final inspection report. The contractor shall certify that 100% of the contractor’s QC punch list is completed prior to requests for a Government pre-final inspection, with their completed QC punch list attached. The contractor shall conduct a pre-final walk through inspection with a Government representative and publish the inspection findings in a Government pre-final inspection report. UFGS 01 45 00.00 20 1.41 commissioning needs to be completed prior to the pre-final inspection taking place. Contractor shall comply with all applicable provisions listed in UFGS 01 45 00.00 20 1.15. Pre-final inspection report(s) shall include a list of contractor warranty and manufacturer warranty books/certificates from newly installed equipment and materials. At the pre-final inspection(s), the contractor shall present an interim DD Form 1354, Transfer and Acceptance of Real Property to the Base Civil Engineer (BCE) or other appropriate organization for review. Details will be provided in each TO.

5.2.2.2 Final Inspection

The contractor shall certify that 100% of the pre-final punch list is completed prior to requests for a Government final inspection. The contractor shall conduct a final inspection and publish the findings in a final inspection report (Punch List) IAW the format specified in the SOW. The inspection shall concentrate on the items identified at the pre-final inspection and recorded in the pre-final report. The final inspection report shall (1) certify that all items of the design have been implemented and that the construction is complete; (2) include a record of as-built drawings and specifications verifying that all development standards have been met; (3) schedule to complete the punch list; (4) One year contractor warranty and manufacturer warranty books/certificates from newly installed equipment and materials. At the final inspection, the contractor shall present a completed DD Form 1354, Transfer and Acceptance of Real Property to the Base Civil Engineer (BCE) or other appropriate organization for signature and acceptance. Details will be provided in each TO. Contractor shall comply with all applicable provisions listed in UFGS 01 45 00.00 20 1.15.

5.2.3 Delivery and Warranty

The contractor shall complete all inspection and commissioning requirements prior to the pre-final inspection. The warranty shall be issued IAW FAR 52.246-21. Extended warranties offered by the contractor and its subcontractors or suppliers may be accepted at the Government’s discretion. The contractor shall provide system O&M manuals and parts list to the Government, and train maintenance personnel in system operations prior to delivery and Government acceptance, as well as manufacturers’ point of contacts (POCs) for troubleshooting, repair and consulting questions.

5.3 Demobilization

The contractor shall decontaminate equipment and facilities, decommission facilities as necessary, and restore the site back to its pre-project condition or as directed in the TO. The contractor shall remove any temporary facilities and implement erosion control measures such as seeding, mulch, sodding, and erosion control fabrics; restore roads, structures and utilities; and plant trees, shrubbery, grasses and other vegetation. The contractor shall document and report on activities and train Government personnel to perform required maintenance, as requested in each

TO.

The contractor shall abide by FAR 52.245-1 Government Property and Defense Contract Management Agency (DCMA) instructions pertaining to disposal of Government Property and reporting through the Plant Clearance Automated Reutilization Screening System (PCARSS) in the removal and disposition of any Government Property during the Demobilization from the project site.

5.4 Emergency Response

The contractor may be required to perform emergency response services. The contractor may be required to perform emergency repairs to facilities, systems, improvements, or utilities in the course of executing TO requirements or as stand-alone activities. The contractor may be required to perform emergency response to situations arising from natural disasters, project activities or actions from others.

6.0 FACILITY CONSTRUCTION TASK ORDER DELIVERY METHODS

The contractor shall perform a full range of activities to meet all customers’ construction requirements as designed and specified. Requirements may include construction, demolition, repair, and emergency response tasks.

6.1 Design Build (D-B)

From USC Title 10 Section 2305A and UFC 1-300-07A, design-build approach may be used to perform the design and construction of a public building, facility, or work. The SCMACC contractor shall manage and perform D-B construction work as defined in the TO. The information contained in this section applies to design submission procedures after award.

The contractor is the Designer of Record (DOR) as well as the Constructor of Record for D-B projects. As the DOR the contractor accepts specific responsibilities as described in Section 6.1.1.

6.1.1 Designers of Record (DOR)/Design Project Manager (PM)

The D-B contractor shall identify, for Government Acceptance, the DOR for each area of work.

One DOR may be responsible for no more than two disciplines. All DORs shall be registered Professional Engineers or Architects as required.

The DOR shall stamp, sign, and date each design drawing under their responsible discipline for Certified Final design documentation stage. The DOR shall be a prime contractor employee, be contracted directly by the prime contractor, or be an employee of a design firm that is contracted directly by the prime contractor.

In addition to these requirements, the prime contractor shall have a Design Project Manager (PM). This individual is responsible for overall integration of the contractor’s team DORs’ work.

All design professionals as specified in the TO requirements will need to comply with all applicable federal, state, local, and DoD (i.e., Unified Facilities Criteria (UFC)) licensure requirements.

6.1.2 Contractor Design Requirements after Award

The contractor must submit for Government acceptance, a Design Quality Control Plan as required, before design may proceed. The Design Quality Control Plan must indicate the designer’s integral role throughout design and construction. Resumes of each DOR shall be included to demonstrate compliance with the RFP requirements. A list of designers, checkers, and independent reviewers must be included to demonstrate professional registration and three separate individuals working per discipline. The Design Quality Control Plan must address how drawings will be coordinated and finalized through as-built submission. The Design Quality Control Plan shall include the design configuration management addressing authorities, symbols/abbreviations, legends, naming, drawing revision controls and process, record file maintenance, and QC checklists.

The contractor shall design and detail a complete and usable facility before construction begins.

If fast track design and construction is approved for a project, it will be indicated in the TO requirements. In order to expedite the construction schedule, fast-tracking is the authorization for the contractor to begin construction operations before final design has been approved.

However, the contractor shall note that no construction activity will be allowed to commence on any fast-tracked item or aspect of work until all comprehensive data (100% documentation), containing the appropriate signed and sealed drawings and specifications relating to this item or aspect of work are received and approved by the Government. It may include mobilization, site work, ordering long-lead materials, and building foundations.

The design shall consist of the submittals, as described in the TO requirements.

The Certified Final Design shall be submitted only when ALL review comments have been addressed, incorporated into the design, and the final design has been accepted, and is ready for construction. It shall include signatures on each sheet and professional stamps from each DOR.

The design submittals shall include specifications; drawings; design analysis; Furniture, Fixtures and Equipment (FF&E); Comprehensive Interior Design (CID); Structural Interior Design (SID);

permit applications; confirmation notices and submittal registers. The Government will assist the contractor in finalizing the draft DD1354 or NASA form 1046; however, it is the contractor’s responsibility to provide the form.

The design shall be completed IAW the applicable criteria as specified at the task order level.

6.1.3 User Requirements Design Meeting

The DORs are required to hold and document individual meetings with the Users on their respective areas of responsibility. The Architect and Interior Designer shall hold a furniture meeting with the Users. They shall discuss each room and the furniture requirements involved.

The discussions from this meeting shall be reflected in the FF&E and SID submittals. Meeting records will be provided to the entire project delivery team. The Communication/Electrical Designer is required to hold a separate meeting with the Users and personnel from base. They shall discuss the IT requirements of the project. The discussions from this meeting shall be reflected in the Interim Design Submittal. Meeting minutes will be provided to the entire project delivery team. Any design issues which arise that are outside the scope of the contract at the TO level shall be identified by the Design PM. A response will be furnished by the CO, and if necessary, a change order will be issued.

The Design PM is responsible for preparing and distributing meeting minutes for all meetings and conference calls during design.

6.1.4 Geotechnical/Hazardous Material Survey Requirements and Responsibilities

The contractor’s team shall include a licensed professional geotechnical engineer to interpret the subsurface conditions and develop earthwork, foundation, and design parameters. Subsequent to award, the contractor is required to perform and provide a complete geotechnical exploration of the proposed site to develop the final design. A Geotechnical Report shall be generated and submitted for review. Report must include soil’s permeability, California Bearing Ratio (CBR) test, site preparation requirements and/or foundation requirements, and a test analysis.

The Geotechnical report and exploration shall be performed under the direction of a licensed professional engineer with at least 10 years’ experience specializing in geotechnical engineering.

This exploration shall be the full responsibility of the contractor. It is the responsibility of the contractor to conduct a meeting with the PM subsequent to completion and evaluation of the site specific geotechnical exploration to enumerate any differences encountered that are not consistent with the information provided by the Government at the TO level and identify any required changes in the foundation type, structure, pavement and earthwork requirements from the provided Government information. The contractor is responsible for field verifying all information given. The contractor is also responsible for obtaining all information necessary to properly design and install all work. The contractor is responsible for surveys/testing to verify existing features/accuracy of as-built drawings, to include the existence, location, size, depth, capacity, flow, inverts, and condition of existing utilities. Information gathering during design shall be coordinated through the CO and the PM. The contractor shall validate design compatibility with Government furnished and Government installed (GFGI) items at the task order level. Contractor is responsible for documenting due diligence during design development to ensure technical adequacy of design.

Hazardous Material Survey Report and Permitting: The contractor shall complete a hazardous material survey (i.e. asbestos and lead based paint) IAW applicable federal, state, and local requirements. It is the responsibility of the contractor to conduct a meeting with the PM subsequent to completion and evaluation of the site specific hazardous material conditions to enumerate any differences encountered that are not consistent with the information provided by the Government at the TO level and identify any required changes in the demolition, removal, abatement, disposal, and worker protection requirements from the provided Government information.

6.1.5 General Design Requirements

The contractor is required to independently prepare and submit for Government acceptance a complete design. The contractor’s Design Professionals shall independently confirm and be responsible for the technical accuracy and adequacy of all aspects of the project design. The contractor shall provide key contract deliverables consisting of contract drawings, technical specifications, schedule, table of values tied to schedule, cost estimate, color boards, renderings, and design analysis. General and detail drawings shall have a well-defined and clear cut to/cut from convention for referencing all details.

a. The level of detail shall clearly show sufficient adequacy of design and demonstrate conformance of the design with the intent of the project as set forth in the instructions. NOTE: While the Government will entertain contractor requests for partial NTP, the contractor shall note that no mobilization, construction or demolition activity will be allowed to commence on any item or aspect of work that the contractor wants to pursue partial NTP on until all comprehensive data (100% documentation) containing the appropriate signed and sealed drawings and specifications relating to this item or aspect of work are received and approved by the Government.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .