Attachment 1- 45 CES Specifications.pdf
PDF 8 MB Posted
- Attached to
- Space Coast Multiple Award Construction Contract (SCMACC) Federal contract opportunity
- Solicitation number
- FA252120R0009
About this file
This is a draft solicitation for an indefinite delivery, indefinite quantity multiple award construction contract to provide maintenance, repair, and minor construction services at Cape Canaveral Air Force Station, Patrick Air Force Base, Kennedy Space Center, and the Jonathan Dickinson Missile Tracking Annex in Florida. Work will include furnishing materials, equipment, transportation, and personnel to design, manage, and accomplish simultaneous projects for a broad range of real property maintenance, repair, and construction. The contract will also be available to support natural disaster response at MacDill Air Force Base. Services will be provided for the 45th Space Wing, Naval Ordinance Test Unit, Air Force Technical Applications Center, National Aeronautics and Space Administration, and other tenant units located at the listed bases. The solicitation does not specify pricing terms, response dates, or other contract details.
View the file
Other files for this federal contract opportunity
Show all 50
Space Coast Multiple Award Construction Contract (SCMACC) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CCAFS and PAFB Standard Specs
Section 01 11 00.00 30 Page 1 3/2/2020
SECTION 01 11 00.00 30
SUMMARY OF WORK
10/14
PART 1 GENERAL
1.1 SUMMARY
The work to be performed under this project is located at Cape Canaveral Air Force Station. Cape Canaveral Air Force Station is located at the end of State Road 401, north of Port Canaveral.
The work to be performed under this project is located at Patrick Air Force Base. Patrick Air Force Base is located approximately three miles south of Cocoa Beach on State Road A1A.
The work to be performed under this project consists of providing the labor, equipment and materials to [_____].
1.2 PROJECT DESCRIPTION
1.2.1 Civil/Site
1.2.2 Structural
1.2.3 Architectural
1.2.4 Mechanical
1.2.5 Electrical
[1.2.6 Telecommunications
[1.2.7 Special Construction
]1.3 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
Section 01 11 00.00 30 Page 2
45TH SPACE WING (SWI)
45 SWI 31-1 Integrated Defense Plan
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 101 (2015; ERTA 2015) Life Safety Code
U.S. AIR FORCE (USAF)
AFI 33-580 (2013) Spectrum Management
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910 Occupational Safety and Health Standards
29 CFR 1926 Safety and Health Regulations for
Construction
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control information only. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES in sufficient detail to show full compliance with the specification:
SD-01 Preconstruction Submittals
Submit the following items to the Contracting Officer:
[Lifting Operation Plan;G]
[Utility Outage Requests;G]
[Connection Requests;G]
[Air Force Form 3952 (AF 3952), Chemical/Hazardous Material Request Authorization;G (including all paint)]
[SOLID WASTE DISPOSAL DIVERSION TRACKING;G]
[Premises/Access Plan;G]
[Storage Area Request;G]
[Contractor Survey Record Drawings;G]
[Superintendent Contact and Qualifications;G]
1.5 CONTRACT DRAWINGS
Section 01 11 00.00 30 Page 3
See Drawing Index for list of project drawings.
Contract drawings, maps, and specifications will be furnished to the Contractor either hard copy or electronic at the Government's discretion.
Reference publications will not be furnished.
Contractor shall immediately check furnished drawings and notify the Contracting Officer of any discrepancies.
The drawings indicate the general location and arrangement of existing conditions. Field measurements may be necessary to determine the size and quantity of materials. Conditions which are obvious/visible or which should be reasonably anticipated by the Contractor on inspection will not be considered under the Differing Site Conditions clause of this contract.
1.5.1 Layout of Work and Elevations
Dimensions and elevations indicated in the layout of work shall be verified by the Contractor. Discrepancies between the drawings, specifications and/or existing conditions shall be referred to the Contracting Officer in writing, for review, before the affected work is performed. Failure to make notification shall place the responsibility upon the Contractor to carry out the work in a satisfactory and workmanlike manner.
1.6 WORK SCHEDULING
Work Schedules for all on-site activities must be reviewed and approved by the Contracting Officer prior to start of the project; and all activities coordinated with the Contracting Officer once work has begun. Due to the critical nature of the work location, all work pertaining to this contract shall be completed [without disrupting] [with minimal disruption to] the operation of [_____].
Contractor shall allow for non-access days where construction activity is prohibited due to hazardous operations or launch activity. When possible, the Government will provide 24 hour notification each time the restrictions are invoked.
1.6.1 Requirements
Working hours will normally range between the hours of 7:30 AM and 4:00 PM (0730-1600) excluding Saturdays, Sundays and Federal Holidays. If work must be done during periods other than above, additional Government inspection and Range Support personnel may be required. Notification must be given to the Contracting Officer five working days in advance of intention to work during other periods to allow assignment of additional inspection forces when the Contracting Officer determines that they are reasonably available.
If such support is reasonably available, the Contracting Officer may authorize work to be performed during periods other than normal duty hours/days. Work beyond normal hours/days may be required for major utility outages. It is to the government's discretion to request copies of contractor inspection records for periods worked on holidays and weekends (FAR 52.246-12 Inspection of Construction).
No construction work shall take place over the Christmas/New Year holiday period. This period will start one full work day before the Federal Christmas holiday and end the first work day after the Federal New Year
Section 01 11 00.00 30 Page 4
Holiday. The Contractor may request to work during this time at the discretion of the Contracting Officer, however no base support will be available.
1.7 OCCUPANCY OF PREMISES/ACCESS REQUIREMENTS
Building(s) [will] [will not] be occupied during performance of work under this Contract. Occupancy notifications will be posted in a prominent location in the work area. [Contractor shall post warning signs in accordance with OSHA requirements].
Before work is started, the Contractor shall submit a Premises/Access Plan to the Contracting Officer or Representative for approval. The plan shall include a sequence of procedures, means of access, space plan for storage of materials and equipment, and use of approaches, corridors, and stairways.
This plan must comply with NFPA 101 requirements that all exits and exit access must be maintained at all times. Base Fire Department is required to approve any deviations which affect the exiting or exit access from the building.
1.7.1 Facility Contents
1.7.1.1 Responsibilities
The schedule of work shall be closely coordinated with the Contracting Officer. Unless otherwise stated, remove all furniture, equipment, curtains, drapes, pictures, blackboards, etc., as required to perform the work. Any movable or fixed furniture, equipment, carpet, etc., remaining in the work area shall be covered and protected from damage. All relocated items shall also be protected from damage throughout the construction period. After completion of work and prior to final acceptance, replace removed items in their original location.
[The entire area will not be available to the Contractor at one time. The following phases of work and procedures are required:
a. [_____]
b. [_____]]
[Demolition of critical facility systems [mechanical, electrical, etc.] shall not be started until replacement equipment is on site.]
1.7.1.2 Maintain Clean Work Areas
All work areas shall be kept clean at all times. Contractor shall prevent introduction of dirt or dust into areas adjacent to the work areas. All materials, tools and equipment shall be thoroughly cleaned prior to being brought into the work areas or adjacent areas.
1.7.1.3 Damage to Existing Equipment
Any damage must be reported to the Contracting Officer immediately. Damage to existing materials, equipments, systems, or properties occurring from Contractor activities or neglect, shall, at the sole discretion of the
Section 01 11 00.00 30 Page 5
Contracting Officer, be repaired or replaced by the Contractor at no cost to the Federal Government.
1.7.1.4 New Material and Construction Equipment
Only material and construction equipment designated for performance of contract work may be stored at the construction site or located in Government-controlled warehouses or shop facilities.
1.7.2 Construction Area Access and Control
1.7.2.1 Access and Control Requirements
Exclusive use or control of any area will not be allowed as the Government must have access to all areas at all times. All work must be scheduled around operational constraints.
1.7.3 Vehicle Parking
1.7.3.1 Requirements
Job and support vehicles for workers will be parked in designated parking areas within reasonable access to the worksite. All vehicle operators must comply with all traffic laws including mandatory seat belt usage, speed limits and hauling restrictions. Contractor shall be responsible for repairing or replacing any facility/grounds damaged areas.
1.8 STORAGE, TRANSPORTATION AND PROTECTION
1.8.1 Storage
At Government discretion, Contractor may be assigned a storage area upon submitting written Storage Area Request to the Contracting Officer.
Contractor's Storage Area Request shall indicate dimensions of trailer, size of storage area, and utilities required. All trailers shall be in good and safe condition. Storage space is normally co-located with construction site, at the Contracting Officer's discretion. Storage areas may require fence and screening as required by Government. Contractor shall secure storage areas during inclement weather situation.
[Contractor is to submit a Work Order Management System (WOMS) through 45 SW Civil Engineering Squadron (45 CES) to request a telephone number and line for their office trailer. Commercial Internet service is available through local Internet service provider at contractor cost. ]
[Office trailers and long term (longer than one year) storage trailers shall be painted to match the base approved color", as noted in the base Facilities Sustainment guide. Trailers located on site for short term storage, less than one year, will not need to meet this requirement. In addition, all office trailers and long term storage trailers shall be skirted along the entire perimeter with a wood lattice material. This skirting shall be painted to match the same trailer color as described above. Contractor shall be responsible for the storage and protection of all of their materials and equipment, whether incorporated into the job or not.]
Section 01 11 00.00 30 Page 6
1.8.2 Protection
Store and protect products in accordance with manufacturer's instructions.
Store products with seals, labels intact and legible. Store sensitive products in weather tight, climate controlled, enclosures in an environment favorable to the product. Products acceptable for exterior storage shall be on sloped supports above ground. Contractor shall not use swales, drainage ditches, or any other storm water permitted area to store materials or equipment. If swales, drainage ditches or any other storm water permitted areas must be used for storage, Contractor must get special permission from Contracting Officer.
1.8.3 Transportation
Transport and handle products in accordance with manufacturer's instructions. Promptly inspect shipments to ensure the products comply with requirements, quantities are correct, and products are undamaged. Protect products subject to deterioration with impervious sheet covering. Provide ventilation to prevent condensation and degradation of products. Store loose granular materials on solid flat surfaces in a well drained area.
Prevent mixing with foreign materials.
1.8.4 Hazardous Materials
Submit an Air Force Form 3952 (AF 3952), Chemical/Hazardous Material Request Authorization if hazardous materials & petroleum product will used on site.
Hazardous Materials & petroleum product containers shall be stored on an impervious surface with containment. Incompatible materials shall be segregated and have separate containment systems. Additional HAZMAT requirements are provided in Section 01 57 19 TEMPORARY ENVIRONMENTAL
CONTROLS.
1.8.5 Site Protection Plan
Structures, utilities, sidewalks, pavements, and other facilities immediately adjacent to excavations shall be protected against damage.
Contractor shall comply with "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements" and is required to protect areas adjacent to the construction site.
1.9 GOVERNMENT-FURNISHED EQUIPMENT [- NONE]
[Government will furnish to the Contractor the following property to be incorporated or installed in the work, or used in its performance.
Maintain and protect Government furnished property once it is on the construction site.
ITEM DESCRIPTION QUANTITY LOCATION FOR PICK-UP POINT
Quantities indicated for the above-listed items marked with an asterisk are estimates. It is the intention of the Government to furnish all quantities of the asterisk items required to complete the work as specified.
Section 01 11 00.00 30 Page 7
Quantities stated for the above items not marked with an asterisk are all that will be furnished by the Government. Contractor shall furnish any additional quantities required.]
1.10 ON-SITE PERMITS
1.10.1 Utility Outage Requests and Connection Requests
Work shall be scheduled to hold outages to a minimum.
Utility outages and Connection Requests required during the execution of work that affect existing systems shall be arranged at the convenience of the Government, which may require scheduling outside of the regular working hours or on weekends, at no additional cost to the Government.
Each Utility Outage and Connection Requests shall state the system involved, area involved, approximate duration of outage, and the nature of work involved.
1.10.1.1 Requirements
A written request for a utilities outage (electricity, communication, water, compressed air, gas, steam, air conditioning, fire detection and suppression systems, etc.) must be submitted to the Contracting Officer at least [14][30] calendar days in advance of the desired outage. Approval is required prior to scheduling any outage. All limitations noted on the approved outage authorization shall be carefully observed. A utilities outage without prior approval and coordination is prohibited.
Utility outages affecting fire alarm, fire detection, fire suppression, fire pumps and water supplies to fire protection systems greater than 4 hours will require a fire watch.
Since many systems are critical to facility operations, the number and duration of utility outages shall be kept to an absolute minimum. All work effort shall be coordinated and sufficient manpower, materials, and equipment shall be provided to complete the work within the authorized outage window.
Existing utility services may be interrupted only when approved by the Contracting Officer. The interruption shall be scheduled at a time of minimum demand on the utility, convenient to the Government. Outages on weekends, holidays, or evenings shall be performed at no additional cost to the Government.
Contractor shall make all necessary arrangements to schedule and provide connections to existing utilities and to cause minimum interruption to system operation. All temporary utility hook-ups and disconnects shall be made by the Contractor.
If the Contractor fails to comply with a scheduled outage, the cost to reschedule the outage will be deducted from the final contract payment.
1.10.2 Protection of Work
All construction work requires a Work Clearance Request, AF Form 103. This permit is processed by the Government and provided to the Contractor. It is
Section 01 11 00.00 30 Page 8 required prior to the start of any construction at the project site and must be posted in a conspicuous location on site during all construction activities.
Contractor shall obtain (from technical representative), prepare, and properly complete "Base Civil Engineering Work Clearance Request" AF Form
103. Prior to submitting Form 103 for review and approval, contractor shall mark in white paint all locations requiring utility locates and a commercial utility locate ticket number must be obtained by calling SUNSHINE at 1-800-432-4770. Contractor shall provide coordination for location of buried structures and utility lines before beginning any work involving digging/excavation. Contact the Government Technical Representative to schedule locates prior to any excavation. The Technical representative shall be the first and the last to coordinate on the AF Form 103.
After excavation permit has been obtained and prior to any excavating, verify with Cape Support (853-5211) that there are no "Critical Days" that would prevent excavation.
Contractor shall temporarily halt any machine excavation work or other surface penetration when approaching within 5 feet of the existing utility line until the Contractor has exposed the utility line by hand excavation to fix its location.
1.10.3 Burn Permits
Burn permits are required for any spark,flame, or welding activity. Burn Permits shall be obtained thru Cape Support (853-5211)PAFB Fire Department (494-7642).
Permits shall be posted at a conspicuous location in the construction area.
Burning of trash or rubbish is not permitted on any USAF facility.
1.11 SALVAGE AND DISPOSAL OF MATERIAL AND EQUIPMENT
1.11.1 Removal
Remove and/or relocate only those materials or items of equipment specifically indicated in the drawings and specifications. Removal operations shall be performed in such a manner that adjacent areas, installed equipment, or existing utilities are not damaged. Repair all openings that occur due to removal or demolition operations to match adjacent, existing surfaces. Any damage incurred during removal operations shall be repaired at no additional cost to the Government.
1.11.2 Housekeeping
Sufficient personnel and equipment shall be provided to ensure compliance with all housekeeping requirements. Work will not be allowed in those areas that do not comply with the requirements of Section 14.C of EM 385-1-1. Job sites are to be kept clean on an ongoing, daily basis. All areas are to be thoroughly cleaned prior to leaving the jobsite at completion of project work.
1.11.3 Salvage of Material and Equipment
Section 01 11 00.00 30 Page 9
All salvageable materials or items to be removed shall remain the property of the Federal Government. Salvageable items are listed below in the paragraph entitled, "Salvage Items". Salvageable items shall be transported to and deposited at the Defense Logistics Agency Office - Disposition Services (DLA) at Cape Canaveral Air Force Station at the contractor's expense.
Salvageable material must be segregated and separated into categories before transport. Material shall be palletized and secured onto pallets or moveable by forklift (maximum 10,000 lbs). For material that is not palletized, it will be the responsibility of the Contractor to provide labor support for material removal.
Deliveries to DLA shall be scheduled through the Contracting Officer a minimum of 72 hours in advance. All salvageable items delivered to DLA shall be accompanied by a properly prepared DD Form 1348. This form will be furnished by the Contracting Officer. A signed copy by DLA reflecting the turn in materials shall be furnished to the Contracting Officer.
Contractor shall maintain property control records for material or equipment designated as salvage. Contractor's system of property control may be used if approved by the Contracting Officer. Contractor shall be responsible for storage and protection of salvaged materials and equipment until disposition by the Contracting Officer.
Material to be salvaged and reinstalled by the Contractor shall be protected during removal and stored to prevent damage.
For reference purposes salvageable is defined as: items, material, equipment which can be refitted, reworked, and restored and put to use or sold. The Contracting Officer shall have sole discretion as to determining whether any particular item is salvageable.
1.11.3.1 Salvage Items [- None]
[The following equipment and materials shall be salvaged for the Government:
a. [_____]
b. [_____]
c. [_____]
Any additional items shall be inspected by the Contracting Officer to determine whether salvageable or debris. All salvageable materials shall be delivered to the DLA facility within Cape Canaveral Air Force Station at Contractor's expense. Salvageable material delivery shall also be accompanied by a properly prepared DD Form 1348.]
1.11.4 Waste Disposal
Non-salvageable material and debris shall be removed from work areas and disposed of daily. Contractor shall dispose of Construction and Demolition (C&D) material at a State approved disposal site.
Refer to Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS for further waste disposal and record keeping requirements.
Section 01 11 00.00 30 Page 10
1.11.5 Cleanup
[All waste materials, except indicated salvaged items, generated by the construction shall be hauled off U.S. Government property at the end of each work day and deposited at a disposal site selected by the Contractor.
Disposal shall be in accordance with federal, state, county and city ordinances and at the expense of the Contractor.]
Upon completion of the construction each day, the Contractor shall leave the work premises in a clean, neat and workmanlike condition, satisfactory to the Contracting Officer.
1.11.6 Salvage and Disposal Record Keeping
Contractor shall maintain and submit quarterly and at the completion of the project the SOLID WASTE DISPOSAL DIVERSION TRACKING form to the Contracting Officer of all materials removed from the job site. This inventory shall include waste materials disposed in landfills and materials reused on the job, sold for salvage and recycled.
1.12 RADIO FREQUENCY MANAGEMENT PROCEDURES
The following procedures shall be followed in obtaining radio frequency authorization:
The policy and procedures contained in AFI 33-580 shall be followed to obtain frequency allocation approval of electronic devices and USAF Radio Frequency Assignment.
1.13 COMMUNICATION SECURITY (COMSEC)
Government telecommunications networks are continually subject to interception by hostile/unfriendly intelligent organizations. Therefore, the DOD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls from, or terminating at, DOD organizations.
Contractor shall assume the responsibility for ensuring frequent dissemination of this information to all employees dealing with official DOD information.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.1 ACCESS REQUIREMENTS
3.1.1 Construction Site Requirement
[All on-site project work is confined to non-restricted areas. That is, no restricted area badge shall be necessary to accomplish the on-site work.
However, normal access requirements into Cape Canaveral Air Force Station (CCAFS)Patrick Air Force Base (PAFB) must still be accomplished.]
Section 01 11 00.00 30 Page 11 3/2/2020
[The on-site project work is located within a restricted area. The restricted area requirement must be accomplished in order to access the construction site.]
[The project will require the Contractor to work inside restricted area Facility No. [_____]]. [The project will require the Contractor to work inside the restricted area perimeter fence of Facility No. [_____] but outside the actual facility]. [The project will require the Contractor to work both inside the restricted area perimeter fence of and inside restricted area Facility No. [_____]].
3.1.2 Air Force Restricted Area Requirements (Black & Blue Restricted Unescorted Badge)
Access to construction sites located in restricted areas requires a Black & Blue Restricted Area Unescorted Badge. Contractor is responsible for satisfying the prerequisites for unescorted entry and/or providing escorted entry to a restricted area for all their personnel and subcontractor personnel. Escort services will not be provided by the Government. It is the Contractor's responsibility to determine the minimum number of personnel needed and obtain the required badges with escort authority in order to meet the contract requirements. Failure to do so could result in denied access to the construction site, interruption of performance and negatively impact timely contract completion.
Individuals meeting the 45 SWI 31-1 security requirements will be allowed to acquire restricted area badges. If the Contractor has proper clearance in JPAS, the Contractor may complete an AF Form 2586 "Unescorted Entry Authorization Certificate" (signed by the CE Security Manage in signature block #2) and transmit it to the Facility Manager of the restricted area for signature. After obtaining signatures, the individual must make an appointment with Visitor Control Center (321-853-5261) to obtain a Restricted Area Badge.
In order for Contractor personnel to enter restricted areas, a Restricted Area Badge for the area is required. Those individuals not in possession of a Restricted Area Badge (RAB) must remain under the surveillance of the escorts at all times while working in the restricted area. Escorts are subject to having their base access privileges revoked if it is found that they are not in visual contact with the employees they are escorting. The required responsibilities and duties of an escort shall be adhered to by all Contractor and subcontractor personnel. 45 SWI 31-1 and Restricted Area Badge Processing Guide outline the requirements and procedures in obtaining a restricted area badge.
Contingent upon the location and nature of the work, a construction site "Free Zone" may be established by the Commander of the restricted area site.
If the area is designated as a construction site "Free Zone", only normal access requirements will apply.
3.2 CCAFS VEHICLE INSPECTION
The Oversized Vehicle Search Area is located on State Road 401 near the Visitor Control Center. Manned Operating hours are scheduled from 0600- 1700. For after hours access, call CCAFS Security Forces at (321) 853-2121 to coordinate entry. Mandatory inspection is required for all: Commercial Vehicles, Tractor Trailers, Trailers, RVs and Boats. Allow ample time for
Section 01 11 00.00 30 Page 12 inspections, especially for the critical delivery period of mixed concrete.
The government will not be responsible for rejected batches, caused by Contractor delays. Advance coordination is highly recommended.
3.3 PAFB VEHICLE INSPECTION
The Oversized Vehicle Search Area is located on State Road A1A approximately 1 mile north of Pineda Causeway. Manned Operating hours are scheduled from 0600-1700. For after hours access, call PAFB Security Forces at (321) 494- 2000 to co-ordinate entry. Mandatory inspection is required for all:
Commercial Vehicles, Tractor Trailers, Trailers, RVs and Boats. All other passenger vehicles will be turned away from this gate and are required to enter at either the Main Gate or South Gate. Allow ample time for inspections, especially for the critical delivery period of mixed concrete.
The government will not be responsible for rejected batches, caused by Contractor delays. Advance coordination is highly recommended.
3.4 CCAFSPAFB DELIVERIES
3.4.1 Non-Hazardous Deliveries
All deliveries of construction material and equipment to job sites (including cement trucks) shall use the CCAFS South Gate for access. To the maximum extent possible, deliveries shall be scheduled between 1000 and 1500 hours to avoid the peak traffic volume times. PAFB Oversized Vehicle Search Area (located on State Road A1A approximately 1 mile north of Pineda Causeway) for access. The operating hours for the Oversized Vehicle Search Area are 0600-1700. After hours access shall be through the South Gate.
The driver of each delivery vehicle and their passengers must have the following:
a. A valid photo ID; and
b. A valid bill of lading; and
c. A known delivery point on CCAFSPAFB; and
d. An on-base or local phone number and POC to vouch for delivery
Only deliveries that can be verified will be allowed to proceed. Special deliveries, deliveries after normal business hours, or deliveries that cannot negotiate through the barricades must be coordinated in advance.
All delivery vehicles shall be inspected by Security Forces personnel prior to being allowed to proceed onto the installation.
3.4.2 Hazardous Deliveries
Deliveries of fuel, large volume of chemicals, or other hazardous materials shall comply with this section. All hazardous deliveries shall enter through the same gates as non-hazardous delivers and have the information required for non-hazardous deliveries (see subpart entitled "Non-Hazardous Deliveries" of this section). Only deliveries that can be verified will be allowed to proceed. In addition, hazardous deliveries must be scheduled a minimum of 48 hours in advance for escort by Security Forces to and from job site. Contractors shall contact the CCAFS Security at 321-853-2121PAFB Security Forces at 321-494-2000 to arrange for hazardous delivery escorts.
Section 01 11 00.00 30 Page 13
Deliveries that have not arranged in advance for Security Forces escorts will be turned away and must be re-scheduled.
3.5 RESPONSIBILITIES
The Government reserves the right to revoke badging authority, escort authority and/or base access privileges for any person, at any time and for any reason. Contractor understands that the Government has made every attempt to identify potential delays associated with background checks and badging requirements and those delays have been considered in the construction schedule. Delays resulting from the Contractor's failure to follow the badging guidelines above shall not be considered grounds for contract extension or compensation.
3.6 EXCAVATION
3.6.1 Dig/Utility Locate Permit Requirements
Excavation shall be accomplished only after the Dig permit is received and utility locates accomplished and then with extreme caution to prevent damage to the existing buried utilities in the area. All open trenches must comply with OSHA regulations. All excavation must be further approved by daily contact with Cape Support (321-853-5211).
3.6.1.1 Location of Buried Structures and Utility Lines
Accurately locate and stake structures and utility lines indicated by the Government provided Utility Locators on CCAFS. Accurately locate and paint structures and utility lines indicated by the Government provided Utility Locators on PAFB. If unidentified underground utilities are encountered during excavation, notify the Contracting Officer and cease operations until they are properly identified.
3.6.1.2 Excavation, Trenching, and Backfilling
Open only those trenches for which material is ready to be placed. As soon as approved by the Technical Representative, trenches shall be backfilled and tamped as required by the drawings and specifications. As a minimum, the topsoil shall be replaced and the disturbed area shall be grassed by seeding, watered and maintained for a minimum of 60 calendar days. All excavation shall be in compliance with OSHA regulations. Mark or barricade construction work which may present a hazard.
3.6.1.3 Cutting of Roads, Streets, Driveways, and Paved Areas
Repair roads, streets, and paved parking areas which require surface cutting under this project within 10 calendar days after initial cutting. The topping shall be a minimum of 2 inches of asphalt and match existing (concrete topping on asphalt areas is not allowed). Mark, barricade, and illuminate construction work on or near roads or streets which may present a traffic hazard per OSHA 29 CFR 1910. Contractor shall provide signaling, lighting, and barricades in the construction area conforming to the Manual on Uniform Traffic Control Devices, OSHA 29 CFR 1926.201 and 1926.202.
Closures of Streets, parking lots, and other traffic areas will not be permitted unless approved by the Contracting Officer after written request 14 calendar days before the scheduled closure.
Section 01 11 00.00 30 Page 14
3.6.2 Restrictions
[All excavation at the work site must be accomplished by hand only.
Excavating machinery is prohibited.]
[Excavation at the work site may be accomplished with machinery only after underground utilities have been identified and with approval by Contracting Officer.]
Hand digging is required within five feet of located underground utilities.
3.6.3 Temporary Shoring, Bracing And Supports
All new excavation and trenching work shall be securely and safely supported during installation with temporary, but substantial, shoring, bracing, hangers and other supports as required by OSHA regulations. After new work is completed and completely cured (if required) and all permanent fasteners, anchors and supports are properly installed, the temporary supports shall be removed.
3.6.4 Barricades
Guardrails, fences or other suitable barricades and warning lights shall be placed at all open excavations/trenches which are adjacent to paths, walkways, sidewalks, vehicle parking areas, and other pedestrian or vehicle thoroughfares. Coordinate with 45 CE Environmental prior to placing warning lights.
[3.7 LAND SURVEYING REQUIREMENTS
Land surveying, to include all projections and datum points, shall be required for all modifications affecting civil site plans (e.g., utilities, additions, new construction or storm water modifications). The survey shall be performed by a State of Florida Professional Licensed Surveyor (PLS) and shall be submitted by the Contractor in digital and hard copy format.
3.7.1 Contractor Provided Survey Support
Record drawings shall reflect all civil site developments such as new facility and/or land modifications, external structural changes to aboveground structures, and changes to underground structures and utilities external to facilities located on lands owned by or held in leasehold interest of the federal government.
Information in record drawings shall include, but not be limited to:
Location of all new lines, conduits, valves, fittings, fire hydrants, meters, terminal points using at least two ties to permanent points (manholes, power poles, curbs, or storm water inlets), [or GPS coordinates with accuracy to 1 foot or better unless more stringent accuracy requirements are specified in other sections of this contract.] Locate manhole, catch basin, and storm water control structures noting top of rim, inverts, weirs, dimensions and conduit sizes and material entering the structure. An acceptable station and offset system may be used for service lines and fittings only.
Section 01 11 00.00 30 Page 15
Location of new lines from property easement lines or edges of pavement at intervals of 300 feet.
All utility routing and interface changes shall be reflected on the drawings to scale and defined with sufficient dimensions.
Locate with elevation all improvements constructed or modified including but not limited to pavement, striping, curbs, sidewalks, signs, gutters, walls, fences, buildings, pads, open stormwater conveyance systems, stormwater retention/detention ponds, etc.
Elevation information should be adequate to illustrate flow patterns, retention capacity and overflow levels. Ground contours at intervals of 1 foot in elevation shall be shown on unpaved areas of the site on the sketch of survey
Contractor shall facilitate the receipt of surveyed coordinates for facility footprint corners coordinates and underground structures and utilities external to facilities by submitting digital data using the spatial reference identified below to 45 CES through the Contracting Officer within five (5) working days of foundation construction, or open excavation.
Record drawing prints will be drawn at a minimum scale of 1 inch = 100 feet. Areas requiring additional detail shall be enlarged as necessary.
Record drawings shall be provided in digital format. [Geospatially referenced files shall be in [ESRI GIS Geodatabase,] [ESRI GIS Shapefile,] or [AutoCAD DWG] format.] Information should be provided in separate layers/levels as specified by GIS and in at least the same degree of separation as the design drawings that were provided.
Designation for naming of layers/levels shall adhere to current DOD, A/E/C CAD Standards with strict adherence to layer format.
https://cadbim.usace.army.mil/. New like items shall be contained in the same levels to permit easy conversion to GIS layers.
All lines, letters, and details shall be sharp, clean, and fully legible.
[5 (Five) reproducible print and one digital copy in an electronic storage media of the Contractor Survey Record Drawings are required for submittal. ][10 (Ten) reproducible print signed and sealed by a PLS for Agency Submittal and one digital copy in an electronic storage media of the Contractor Survey Record Drawings are required for submittal.]
3.7.1.1 Horizontal Reference Datum
All surveys shall be referenced to Florida State Plane Coordinate System, East Zone, North American Datum 1983/2011 adjustment based on Second order Class II horizontal control monument.
3.7.1.2 Vertical Reference Datum
All surveys shall be referenced to North American Vertical Datum (NAVD) 1988. The survey shall include a description of the reference benchmarks from which the NAVD has been determined.
https://cadbim.usace.army.mil/
Section 01 11 00.00 30 Page 16
]3.8 HOISTING AND LIFTING
3.8.1 Lifting Operation Plan
Contractor shall have a Lifting Operation Plan and procedure that is fully in accordance with the requirements of OSHA regulations, and shall include drawings/sketches of lifting slings, lifting equipment, and tag lines. The plan shall show weights, center of gravity, and clearances of load over entire lift. Plans shall have details showing any structural mounting of hoisting equipment on sheaves or structural steel, and shall show loading calculations on any such structural mounting showing forces, weights, turning moments, etc. A procedure shall accompany the drawings describing all lifting operations. Use spreader bars wherever necessary to prevent hoisting cables from contacting equipment/material.
3.9 QUALITY CONTROL
It is the Contractor's responsibility to provide, inspect and document the level of quality that has been established by all applicable standards, codes and guidelines. The Contractor shall use skilled workers, an adequate number of which are thoroughly trained and have a minimum of 3 years experience in the necessary crafts and who are completely familiar with the specified requirements and the methods needed for the proper performance of the work in each section of these specifications. Contractor shall submit Superintendent Contact and Qualifications to the Contracting Officer.
3.9.1 Licenses
Contractor or their subcontractors shall be licensed by the State of Florida or have an equivalent out-of-state license in all areas applicable to this contract or as otherwise stated elsewhere in this contract. Copies of licenses and certificates shall be provided to the Contracting Officer.
Asbestos Abatement Contractor shall be licensed by the State of Florida.
[3.9.2 Quality Control Manager
The Quality Control Manager shall direct the execution of the Contractor's approved Quality Control Plan with exclusive responsibility for administration of the plan and inspections of work. The Quality Control Manager shall be available during normal duty within thirty (30) minutes after notification to meet with the Contracting Officer, or designated representative. The Quality Control Manager shall be a different individual than the project superintendent.]
3.9.3 Government Inspection/Approval
When the Contractor considers that the work is acceptable to the Government and is complete, he/she shall inform the Contracting Officer, or designated representative, and the Government Project Manager that the work is complete and ready for inspections. In the event that the work is not acceptable, the Contractor shall record a list of items noted by the Government Project Manager, A subsequent inspection may take place in order to review the corrected items. The Government is not required to inspect all work.
3.9.4 Inspection Files
Section 01 11 00.00 30 Page 17
The Contractor shall be responsible for keeping inspection files for all projects. Files shall include on site records of all inspections conducted by the Contractor and the necessary corrective actions taken. Daily Reports shall be kept and made available to the Government throughout the contract performance period and for the period after completion until final settlement of any claims made under this contract.
3.10 SUPERINTENDENT
Provide name and qualifications and past experience for review. Designate a competent superintendent who shall have full authority to act for the Contractor and who shall be the primary contact with the Government until acceptance. Contractor's superintendent shall be at the job site at all times when work is taking place and shall have full authority to act for the Contractor.
3.11 CONSTRUCTION SCHEDULING REQUIREMENTS
3.11.1 Contractor Coordination Meetings
Contractor shall attend weekly project meetings, not to exceed 3 hours, scheduled by the Government. [Contractor's Superintendent shall attend the scheduled coordination meetings.] Subcontractor representatives shall attend as required.
Discussion shall address the progress schedule, potential factors of delay, deficiencies, material delivery schedules, submittals, and safety issues.
3.11.2 On-Site Construction Sequence
The required work shall be performed in a sequence to minimize the time when [potable water, air conditioning, panelboards, transformers, power supply, etc.] are [inoperative or out-of-service.] [Remove a single item of equipment, install the new replacement item, tie in required utilities, test, and restore the new item of equipment to fully operational status before removing subsequent equipment.]
-- End of Section --
Section 01 33 00 Page 1 3/9/2020
SECTION 01 33 00
SUBMITTAL PROCEDURES
08/18
PART 1 GENERAL
1.1 SUMMARY
1.1.1 Submittal Information
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
1.1.2 Project Type
The Contractor's Quality Control (CQC) System Manager are to check and approve all items before submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves;
test reports; test cylinders; samples; O&M manuals (including parts list);
certifications; warranties; and other such required submittals.
The Contractor and the Designer of Record (DOR), if applicable, are to check and approve all items before submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves;
test reports; test cylinders; samples; O&M manuals (including parts list);
certifications; warranties; and other such required submittals.
1.1.3 Submission of Submittals
Schedule and provide submittals requiring Government approval before acquiring the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Safety Data Sheets (SDS) and in compliance with existing laws and regulations.
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
Submittal requirements are specified in the technical sections. Examples and descriptions of submittals identified by the Submittal Description (SD) numbers and titles follow:
Section 01 33 00 Page 2
Submittals that are required prior to or commencing with the start of work on site. Submittals that are required prior to or at the start of construction (work) or the next major phase of the construction on a multiphase contract.
Preconstruction Submittals include schedules and a tabular list of locations, features, and other pertinent information regarding products, materials, equipment, or components to be used in the work.
Certificates Of Insurance
Surety Bonds
List Of Proposed Subcontractors
List Of Proposed Products
Baseline Network Analysis Schedule (NAS)
Submittal Register
Schedule Of Prices Or Earned Value Report
Accident Prevention PlanHealth And Safety Plan
Work Plan
Quality Control (QC) plan
Environmental Protection Plan
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-04 Samples
Section 01 33 00 Page 3
Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.
Field samples and mock-ups constructed on the project site establish standards ensuring work can be judged. Includes assemblies or portions of assemblies that are to be incorporated into the project and those that will be removed at conclusion of the work.
SD-05 Design Data
Design calculations, mix designs, analyses or other data pertaining to a part of work.
Design submittals, design substantiation submittals and extensions of design submittals.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.
Report that includes findings of a test required to be performed on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report that includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports
Daily logs and checklists
Final acceptance test and operational test procedure
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.
Confined space entry permits
Text of posted operating instructions
Section 01 33 00 Page 4
SD-08 Manufacturer's Instructions
Preprinted material describing installation of a product, system or material, including special notices and (SDS)concerning impedances, hazards and safety precautions.
SD-09 Manufacturer's Field Reports
Documentation of the testing and verification actions taken by manufacturer's representative at the job site, in the vicinity of the job site, or on a sample taken from the job site, on a portion of the work, during or after installation, to confirm compliance with manufacturer's standards or instructions. The documentation must be signed by an authorized official of a testing laboratory or agency and state the test results; and indicate whether the material, product, or system has passed or failed the test.
Factory test reports.
SD-10 Operation and Maintenance Data
Data provided by the manufacturer, or the system provider, including manufacturer's help and product line documentation, necessary to maintain and install equipment, for operating and maintenance use by facility personnel.
Data required by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.
Data incorporated in an operations and maintenance manual or control system.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Submittals required for Guiding Principle Validation (GPV) or Third Party Certification (TPC).
Special requirements necessary to properly close out a construction contract.
For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.
1.2.2 Approving Authority
Office or designated person authorized to approve the submittal.
1.2.3 Work
As used in this section, on-site and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction. In exception, excludes work to produce SD-01 submittals.
1.3 SUBMITTALS
Section 01 33 00 Page 5
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor QC approval.][for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for…