This file is a template for a Fire Protection Method of Procedure (MOP) and Fire Watch Log used by the GSA Public Buildings Service Rocky Mountain Region. The template provides a structured format for documenting fire protection work procedures and associated fire watch activities in federal buildings.
The MOP template includes sections for work description, project contacts, step-by-step activities, systems affected, floor plans, safety requirements, protection requirements, tool identification, contingency plans, and signature approvals. The Fire Watch Log portion contains detailed requirements for implementing and documenting fire watch activities when fire protection systems are offline, including hourly patrol requirements, documentation procedures, and a standardized patrol log sheet. The template requires documentation of out-of-service systems, emergency contacts, and posting of appropriate signage. Additionally, it specifies that fire watch records must be retained on-site for 2 years and made available to the Chief Fire Official upon request.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. General Service Administration, Public Building Service, Rocky Mountain Region
CC: Page 1 of 10 Print Date: 3/15/16
Fire Protection
Method of Procedure (MOP)
Insert Type of Work
Insert Location of Work Performance
(WORK ANTICIPATED FOR)
Insert Dates:
*FINAL MOP REVIEWERS
Company/ Name Signature Date Comments
*Contractor*
Name (Print):
GSA Facility Manager
Name (Print):
*Fire Protection Engineer
Name (Print):
* Contractor Sub*
Name (Print):
*O&M Contractor:
Name (Print):
*GSA Senior Property Manager*
Name (Print):
GSA Regional Fire Protection Eng.
Name (Print):
CC: Page 2 of 10 Print Date: 3/15/16
METHOD OF PROCEDURE AUTHORIZATION
Step 1: MOP Description
MOP Title: Date Approved:
Name of (Sub) Contractor Performing Work: ________________________________________________
Phone Number:
Name of Person Submitting MOP: Date Submitted:
Tentative Start Date:
Tentative Time Frame:
Actual Outage/Loss of Service Time/Duration:
Step 2: Project Contact List
Medical Emergencies Dial: 911
Name Company Position Phone/Cell/Pager
CC: Page 3 of 10 Print Date: 3/15/16
Step 3: General Description of Work (Describe general overview of your procedure) Details to be described in Step 6:
Step 4:Systems affected by work:
Step 5: Detailed Floor Plans and Description of Temporary Containment:
CC: Page 4 of 10 Print Date: 3/15/16
[Insert Floor Plans].
Step 6: STEP-BY-STEP Activities (Describe each step in detail as follows, including activities time-lines):
Step Date Time Description Action By: Completed
1 .
End of MOP
Detailed Testing Procedures:
Step Date Time Description Action By: Completed
End of Testing
CC: Page 5 of 10 Print Date: 3/15/16
Step 6: Hoisting / Hauling / Storage Include detailed information for the following:
1) Identify routing to space.
[Insert if required]
2) Identify protection of walls/floors.
[Insert if required]
3) Identify weights.
[Insert if required]
4) Identify capacity of elevator if applicable.
[Insert if required]
5) If building structural system is utilized to support object, identify structural component, capacity of structural component, and method of support.
Step 7: Protection Requirements (Include detail information for the following):
1) Telecommunication Equipment / Computer / Cable / Fire Alarm.
a. Specifically detail protection when work occurs over telecommunications equipment/computer/cable including plywood enclosures and rubber mats. Attach sketch.
2) Protection of Personnel/Tenants: All PPE will be worn during work operations. Gloves, safety glasses, work shoes, hard hats, reflective vest, and proper clothing.
3) Electrical/Mechanical Equipment:
4) Miscellaneous Equipment: [Insert if required]
5) Fire Alarm Status: .
6) Lock Out/ Tag Out/ Check Out Program:
7) GSA Approved Hot Work Procedures:
Step 8: Tool Identification
1) Identify types of tools that would result in excessive noise, cause vibration in areas outside of the containment, create excessive loading on the floor, or create a condition to control water.
[Insert if required]
2) Include specifics regarding methods of cutting. (Include a detailed description for WET cutting)
3) Include specifics regarding welding/soldering (complete hot work permit).
CC: Page 6 of 10 Print Date: 3/15/16
Step 9: Safety Requirements
1) Fire Protection: [Insert if required]
2) Fire Watch: Required, Meridian Provided
3) Dust Protection: [Insert if required]
4) Asbestos Containment: [Insert if required]
5) Smoke Containment: [Insert if required]
6) Noise Containment: [Insert if required]
7) Water Containment: [Insert if required]
8) Mold Protection: [Insert if required]
9) Daily GSA Approved
Hot Work Permit:[Insert if required]
Step 10: Weather Protection
Include specific regarding protection from weather. In particular, address water protection, humidity protection, and temperature stability.
[Insert if required]
Step 11: Special Tenant Needs / Requirements
This section to be completed by User Group / Tenant as applicable.
Not applicable for this MOP
Step 12: Building Security
CC: Page 7 of 10 Print Date: 3/15/16
Step 13: Contingency Plans
This is an extremely important section, which must be completed in detail. In the event of an unforeseen problem associated with any aspect of the MOP, a contingency plan is to be developed. Identify potential problems which may arise. Include safe stop points. Include back out procedures. Spare parts, materials, etc. shall be identified for contingency plans.
Potential Problem:
[Insert if required]
Contingency Plans:
Backout:
Step 14: M.O.P Signature Sheet
1) If work procedure does not affect party identified, signature is not required. If you are required or need to be contacted if contingencies are implemented, mark the yes/ no box below accordingly.
2) Procedure for obtaining signatures shall be as follows:
a. Signatures shall be in the order indicated.
b. Email processing shall be an acceptable method of confirmation of concurrence of the MOP
c. Originator of the MOP shall indicate N/A adjacent to individuals who are not involved and/or affected by the MOP.
NAME Emergency
Contact
Emergency
Phone #
Date Signature
CC: Page 8 of 10 Print Date: 3/15/16
EMERGENCY CONTACT LIST
(EMERGENCY CALLS FLOWCHART)
In the event that the Insert the Building Name or Insert the Contractors Name needs to contact
Insert the Prime Contractor�s Name the following conditions shall be considered and steps implemented.
Normal Working Hours and Off Time Hours
1st Attempt � Contact * Insert* Project office at:
000-000-0000
The staff members at the office will notify
Name:
2nd Attempt � Contact * Insert Sub Contractor Name*
Name at cell phone no.
000-000-0000
CC: Page 9 of 10 Print Date: 3/15/16
3rd Attempt- Contact *Insert Sub Contractor�s Name*
Name at cell phone no.
000-000-0000
CC: Page 10 of 10 Print Date: 3/15/16
Comments:
Other:
***END OF MOP***
FIRE WATCH LOG SHEET
In the event that any of the following fire protection systems are off-line, a FIRE WATCH is to be implemented IMMEDIATELY – Fire Alarm System, Sprinkler System, Standpipe System, Fire Pump, Emergency Power System, Specialized Fire Suppression System, other specialized building systems.
Persons assigned to Fire Watch duties shall follow the requirements listed on the Fire Watch Duties sheet and shall patrol all unprotected areas of the building every hour to check for signs of fire or smoke conditions. All patrols are to be recorded on this Fire Watch Log Sheet immediately following each round. Records of Fire Watch shall be retained on site for 2 years after they are made, and shall be made available upon request to the Chief Fire Official.
NOTE: Start a new Fire Watch Log Sheet for each new day of Fire Watch
If fire or smoke conditions are discovered, alert all building occupants by sounding a portable air horn, whistle or another device approved by the Chief Fire Official.
Date: ________ Time: _______
Date: ________ Time: _______
_____________________________System OUT OF SERVICE
System Out of Service
System Out of Service Date: ________ Time: _______
Date: ________ Time: _______
Date: ________ Time: _______
____________________________System BACK IN SERVICE
System Back in Service
System Back in Service Date: ________ Time: _______
NAMES & POSITIONS OF PERSONS CONDUCTING FIRE WATCH: INITIALS
1.
2.
3.
4.
See Reverse for Fire Watch Patrol Log Sheet
FIRE WATCH PATROL LOG SHEET
NOTE: Start a new Fire Watch Log Sheet for each new day of Fire Watch
Fire Watch Duties Conducted By: ___________________________________________________ (print name & position)
Fire Watch Commenced: Date: _________________ Time: _______________
ROUNDS
DATE
(m/d/y)
START TIME
(circle a.m./p.m.)
FINISH TIME
(circle a.m./p.m.)
AREAS PATROLLED &
COMMENTS
INITIALS
1. / / a.m.
p.m.
a.m.
p.m.
2. / / a.m.
p.m.
a.m.
p.m.
3. / / a.m.
p.m.
a.m.
p.m.
4. / / a.m.
p.m.
a.m.
p.m.
5. / / a.m.
p.m.
a.m.
p.m.
6. / / a.m.
p.m.
a.m.
p.m.
7. / / a.m.
p.m.
a.m.
p.m.
8. / / a.m.
p.m.
a.m.
p.m.
9. / / a.m.
p.m.
a.m.
p.m.
10. / / a.m.
p.m.
a.m.
p.m.
11. / / a.m.
p.m.
a.m.
p.m.
12. / / a.m.
p.m.
a.m.
p.m.
13. / / a.m.
p.m.
a.m.
p.m.
14. / / a.m.
p.m.
a.m.
p.m.
15. / / a.m.
p.m.
a.m.
p.m.
16. / / a.m.
p.m.
a.m.
p.m.
17. / / a.m.
p.m.
a.m.
p.m.
18. / / a.m.
p.m.
a.m.
p.m.
OUT OF SERVICE SIGNAGE
INSTRUCTIONS: Note what fire protection system is out of service and post copies of this sign at main entrance and on all floor areas
(fire protection system out of service)
OUT OF SERVICE
A FIRE WATCH IS PATROLLING THE
AFFECTED AREAS OF THE BUILDING
IN CASE OF FIRE
CALL 911
FOLLOW POSTED
EMERGENCY
PROCEDURES
| Fire Protection Method Of Proceedure Region 8 2016 (1) |
| EMERGENCY CONTACT LIST |
Copy of R8 Fire-Watch-Log-Sheet
File details come from the government source that posted it. Updated .