Attachment 13 Renovation Project Sustainment and Restoration 23 Oct 20.pdf

PDF 970 KB Posted

Attached to
Maintenance & Repair (M&R) IDIQ, Luke AFB, AZ
Solicitation number
FA488721R0014
Issued by

View the file

Other files

File Type Posted
FA488721R0014 Consolidated RFI Responses.xlsx XLSX spreadsheet
Attachment 8 Luke AFB Disc Submittal Guidelines.pdf PDF
Attachment 9 LUKE Design and Construction Standards.pdf PDF
Attachment 16 NAF Construction Clauses Definitions.pdf PDF
Attachment 2 Wage Determination AZ20210031 Maricopa County 26 Feb 2021.pdf PDF
Attachment 5 Ordering Procedures 26 Feb 2021.pdf PDF
Attachment 17 Joint Venture Teaming Partner Consent Letter 17 Dec 20.pdf PDF
Attachment 1 M and R SOW 5 Mar 2021.pdf PDF
Attachment 12 Luke Specification for Fire Protection and Life Safety 6 Jun 15.pdf PDF
Attachment 3 Wage Determination AZ20210030 Coconio County 26 Feb 2021.pdf PDF
Attachment 14 Basic Project Design Requirements 23 Oct 20.pdf PDF
Attachment 11 Fire System Criteria 10 Dec 18.pdf PDF
Attachment 4 PPQ and Cover Letter 17 Dec 2020.pdf PDF
Attachment 6 Luke Master Specifications 9 Sep2020.pdf PDF
Pre- Proposal Conference.pptx PPTX presentation
Attachment 18 Sections L and M Instructions to Offerors and Evaluation Factors 9 Mar 2021.pdf PDF
Solicitation - FA488721R0014.pdf PDF
Attachment 19 Price Evaluation Worksheet 8 Mar 2021.xlsx XLSX spreadsheet
Attachment 10 AETC First 400 Feet Standard Guidance with Luke Supplemental 5 May15 v4.pdf PDF
Attachment 7 AFI 33-118 Electromagnetic Spectrum Management.pdf PDF
Attachment 15 NAF Standard Clauses.pdf PDF
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 13 – FA488721R0014 Renovation Projects – Sustainment and Restoration

23 October 2020

RENOVATION PROJECTS

Sustainment and Restoration……. UFC 3-600-01

1-3.2.4.1 When any portion of a building is modified from its current use to that of a mission essential building for one year or more, the building must meet the requirements for new construction.

Facilities in which alteration, modernization, rehabilitation, and renovation work is less than 50% of the replacement value of the building, the building must comply with the criteria in this UFC for new construction, to the maximum extent practical. All new work accomplished as part of alteration, modernization, modification, rehabilitation, and renovation actions/projects must meet the requirements for new construction.

Renovation to Existing Systems.

Existing Control Panels

Replace existing non-addressable fire alarm panels with a new analog/addressable panel when a project includes fire alarm work.

5-5.1.1 New devices and circuits must be addressable.

5-5.1.2 The existing devices can remain, but must be connected to the new panel via a monitor addressable module or control module.

Complete Replacement

If the existing system is to be completely replaced all conductors must be replaced with new.

Partial Renovation

If the work involves only partial renovation of a facility and is providing a new fire alarm control panel for the renovated areas, demolish the existing FACP. The existing circuits in the areas of the building that is not being renovated may be retained, if not replaced, and connected to the new fire alarm control panel via monitor modules or control modules.

Manual Pull Station

Provide addressable double action type manual pull stations with mechanical reset features. If the manual alarm station requires a key for reset, it must be the same key as required for the fire alarm control panel. 5-6.3

Attachment 21 – FA488721R0003 Renovation Projects – Sustainment and Restoration

23 October 2020

2-1.20…Major Project

A project that includes any one of the following:

a. Addition to an existing Facility.

b. Renovation, Reconstruction or Alteration of 50 percent or more of the total floor area of an existing Facility.

c. Design or construction of a new Facility.

d. New installation or Modification of an area of construction greater than 5,000 ft2 of floor area that involves existing or new fire barriers or fire-rated construction; Life Safety Systems; fire alarm or detection systems; fire suppression systems.

Note: Modification of 20 or more existing sprinklers is considered a Major Project.

New installation or Modification of existing HVAC systems that remove or install the ductwork passing through fire-rated or smoke partitions/barriers or interconnected plenum areas serving an area greater than 5,000 ft2 of floor area.