This is a production schedule template (Attachment 10) for a 60' Dive Support Boat contract, showing the key milestones and delivery timeline for Boat 1 (CLIN 0001). The schedule tracks major events from contract award through delivery, including Design Maturity Review, ordering/receipt of major items, hull fabrication, engine installation, Technical Data Package (TDP) submission, Pre-Delivery Inspection Tests (PDITs), and final boat delivery.

The template specifies that delivery will occur at Groton, CT with a Government Notional Delivery of 545 Days After Contract Award (DAC). Major items are defined to include engines, generators, and raw material suppliers like aluminum. The Design Maturity Review is noted as a one-time event, and contractors must fill in their planned number of days after contract award for each milestone in the empty cells provided.

View the file

Other files for this federal contract opportunity

Other files attached to 60' Dive Support Boat, newest first.
File Type Posted
N6426725Q5016 - Amendment 3.pdf PDF
7_Attachment 19 - NAVSEACOMBATSYSENGSTA Report No. 6660-99 Rev A Procedures Manual for Stability Analysis of U.S. Navy Small Craft.PDF PDF
7_Attachment 23 - NSWCCD-23-TM-2009-61 RevA Boat Example Data Package.pdf PDF
7_Attachment 28 - NSWCCD-80-TR-2014-38 Weight Management Process Guidance.pdf PDF
7_Attachment 16 - NAVSEA 0900 LP 060 4010 Fabrication Welding and Inspection of Metal Boat and Craft Hulls.pdf PDF
7_Attachment 22 - NSWCCD-23-TM-2009-59 Rev B Ungrounded Electrical Systems Verification Test.pdf PDF
7_Attachment 24 - NSWCCD-23-TM-2009-64 RevC Small Craft Transportability Design and Certification Process Guidance.pdf PDF
7_Attachment 26 - NSWCCD-23-TM-2011-05 Boat Mechanical Practices.pdf PDF
N6426725Q5016 - Amendment 2.pdf PDF
7_Attachment 21 - NSWCCD-23-TM-2009-58 RevB Boat Electrical Practices.pdf PDF
7_Attachment 25 - NSWCCD-23-TM-2009-65 RevC Towing Fitting Design and Certification Process Guidance.pdf PDF
7_Attachment 13 - Pricing CLIN Chart.xlsx XLSX spreadsheet
Attachment 14 - Questions and Answers.pdf PDF
7_Attachment 20 - NSWCCD-23-TM-2009-33 RevB Hoisting System Design and Certification Process Guidance.pdf PDF
7_Attachment 27 - NSWCCD-23-TM-2011-38 RevA Mooring Fitting Design and Verification Process Guidance.pdf PDF
N6426725Q5016 - Amendment 1.pdf PDF
Attachment 1 - DS Boat Specification Rev.pdf PDF
Attachment 4 - Notional DS Boat Arrangement.pdf PDF
Attachment 8 -Notional Dive Boat AC Power - One-Line.pdf PDF
Attachment 2 - Specification Response Matrix.pdf PDF
Attachment 6 - Unique Item Identification.pdf PDF
Attachment 11 - Technical Data Rights Assertion.pdf PDF
Attachment 12 - Past Performance and Experience.pdf PDF
N6426725Q5016 - RFQ.pdf PDF
Attachment 5 - Electrical Load Analysis AC Distribution.pdf PDF
Attachment 7 - DS Boat Spare Parts List.pdf PDF
Attachment 9 - Warranty Terms.pdf PDF
Show all 27

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Design Maturity Review

Order Major Items

Receipt of Major Items

Start Hull Fabrication

Install Engines

Submit

TDP

Conduct PDITs

Deliver Boat

Delivery Location

Gov't Notional Delivery

Boat 1 (CLIN 0001) Groton, CT 545 DAC

Notes:

4. DAC – Days after contract award Add additional column(s) if needed

N6426725Q5016 Attachment 10

Production Schedule (Days After Contract Award (DAC) or Option Exercise (AOE))

1. Add the planned number of days after contract or option award for each of the events in the cells above.

2. Design Maturity Review is a one time event.

3. Major Items include engines, generators, and raw material suppliers (e.g. aluminum);