Attachment 10 - Delivery Schedule.pdf
PDF 681 KB Posted
- Attached to
- 60' Dive Support Boat Federal contract opportunity
- Solicitation number
- N6426725Q5016
About this file
This is a production schedule template (Attachment 10) for a 60' Dive Support Boat contract, showing the key milestones and delivery timeline for Boat 1 (CLIN 0001). The schedule tracks major events from contract award through delivery, including Design Maturity Review, ordering/receipt of major items, hull fabrication, engine installation, Technical Data Package (TDP) submission, Pre-Delivery Inspection Tests (PDITs), and final boat delivery.
The template specifies that delivery will occur at Groton, CT with a Government Notional Delivery of 545 Days After Contract Award (DAC). Major items are defined to include engines, generators, and raw material suppliers like aluminum. The Design Maturity Review is noted as a one-time event, and contractors must fill in their planned number of days after contract award for each milestone in the empty cells provided.
View the file
Other files for this federal contract opportunity
Show all 27
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Design Maturity Review
Order Major Items
Receipt of Major Items
Start Hull Fabrication
Install Engines
Submit
TDP
Conduct PDITs
Deliver Boat
Delivery Location
Gov't Notional Delivery
Boat 1 (CLIN 0001) Groton, CT 545 DAC
Notes:
4. DAC – Days after contract award Add additional column(s) if needed
N6426725Q5016 Attachment 10
Production Schedule (Days After Contract Award (DAC) or Option Exercise (AOE))
1. Add the planned number of days after contract or option award for each of the events in the cells above.
2. Design Maturity Review is a one time event.
3. Major Items include engines, generators, and raw material suppliers (e.g. aluminum);
File details come from the government source that posted it. Updated .