This Statement of Work (SOW) details roof repair requirements for four buildings at the U.S. Bureau of Reclamation's Yuma Area Office (YAO) in Yuma, Arizona. The project involves comprehensive roof repairs across multiple buildings, including the YAO Admin Office, Desalting Building, YDP Admin Office, and Switchyard Control building. Specific work includes single-ply membrane roof overlay, replacing roof curbs, flashing, penetration points, vents, drains, sealant, expansion joints, installing roof walkways and permanent anchor points, and debris removal. The total project scope covers approximately 141,600 square feet of roofing across the four buildings.
The contract requires a 180-calendar day performance period, with strict safety and quality control requirements. The project is a 100% small business set-aside under NAICS code 238160 (Roofing Contractors) with a small business size standard of $19M. The estimated project magnitude is between $1,000,000 and $5,000,000, to be awarded as a firm fixed-price contract. Contractors must submit comprehensive documentation including a construction plan, safety program, detailed schedules, and material specifications. The YDP property must remain fully operational throughout the contract period, with an emphasis on maintaining safety and minimizing operational disruptions.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Yuma Area Office
Statement of Work
YDP Roof Repairs
PART I – GENERAL INFORMATION
A. BACKGROUND
The mission of U.S. Bureau of Reclamation (Reclamation) is to manage, develop, and protect water and related resources in an environmentally and economically sound manner in the interest of the American public. Reclamation’s Yuma Area Office (YAO) admin building’s roof is equipped with a thermoplastic polyolefin (TPO) membrane roof. The TPO roofing installation was completed in April 2011. Repairs were made to the roof in February 2020 under the 10-year warranty. The TPO membrane roof has weathered further and is no longer waterproof. During rain events, the water passes through the roof, down the structural beams, onto ceiling tiles in different areas, and eventually makes it into several office spaces. In August 2023, the remnants of Hurricane Hilary brought strong winds and rain making matters worse. Reclamation staff has been making observations of which areas are affected during rain events and noticed three additional buildings with leaking roofs within the Yuma Desalting Plant (YDP) property. The additional buildings are the Desalting Building (processing area), YDP admin office, and the switchyard control building where leaks and damaged ceiling tiles have been observed. The
Desalting Building is equipped with a built up roof (BUR), YDP admin office with an acrylic coated single-ply roof, and the switchyard control building with an acrylic coated spray polyurethane foam (SPF) roof.
B. LOCATION
Reclamation’s YAO complex along with the YDP is located at 7301 Calle Agua Salada, Yuma, Arizona. The YDP is a 60-acre plant located approximately 4.5 miles west of the City of Yuma.
The property is gated and requires Government supervision for entry. The contractor may access one roof at a time. Refer to the Vicinity and Location Maps included in the Appendix B.
C. SITE CONDITION
The weather in Yuma County is typical of the desert southwest. Annual highs and lows range from about 120 to 30 degrees Fahrenheit, with intraday variations of up to 50 degrees. Late fall and winter temperatures are generally mild with a slight possibility of freezing during the late winter months. Strong winds and dust storms are possible throughout the year but are generally experienced during the spring months. Thunderstorms and flash floods are also possible during the “monsoon” season which generally occurs during the late summer months (August and
September). Rain is also possible during the late winter and early spring months. Average yearly rainfall for the Yuma area is approximately 3 inches.
The YDP is an industrial facility, with active equipment and chemicals present. As such, all workers or visitors to the site need employ safe practices suitable for hazardous site conditions.
PART II – OBJECTIVE
A. SUMMARY
The contract objective is to make necessary repairs on four buildings including, but not limited to, single-ply membrane roof overlay, roof curbs, curb flashing, penetration flashings, vents through roof (VTR), drains, sealant, expansion joints, roof walkway, insulation, coating restoration, skylight cages, permanent anchor points, debris removal, and debris disposal. The
YDP property shall remain fully operational during the contract’s performance period. Ensuring the safety of all employees involved is paramount.
B. PERFORMANCE PERIOD
The performance period for the YDP Roof Repairs project will be 180 calendar days from the date of notice to proceed to the Contractor.
PART III – REQUIREMENT
A. DEFINITIONS
Debris: vegetation or dirt that has accumulated on the roof.
Hazardous air pollutants (HAPs): pollutants that are known or suspected to cause cancer or other serious health effects, such as reproductive effects or birth defects, or adverse environmental effects.
Hazardous Material (HazMat): a hazardous material is any substance or chemical which is a health hazard or physical hazard.
Legal Disposal: disposition of debris hauled off site to an approved disposal (landfill) area in accordance with Local, County, State, and Federal regulations.
National Emission Standards for Hazardous Air Pollutants (NESHAP): stationary source standards for hazardous air pollutants.
B. PROJECT DESCRIPTION
The project includes, but is not limited to the following:
1. Preparatory work. Submitting a comprehensive Construction Plan and Safety Program to be approved before notice to proceed (NTP) is issued and commencing onsite work.
2. Mobilization/demobilization. Mobilize all personnel and equipment necessary to perform roof repairs and replacements. When the work is completed, the Contractor shall fully vacate the site removing all equipment and materials used in or resulting from the work.
Legally dispose of demolished materials or resulting from the work in accordance with state, county, federal statutes.
3. Safety of personnel. Providing all safety equipment necessary for roof repairs such as, but not limited to, ladders, temporary skylight cages, safety harness, temporary roof anchors, fall protection, PPE, etc.
4. Roof Repairs and Replacements. Furnish materials, equipment, and labor necessary to make roof repairs on four buildings as described in YAO Roof Leak Inspection Report and Statement of Work.
5. Roof Anchors. Furnish materials, equipment, and labor necessary to install permanent
OSHA compliant roof anchors. Ensure existing roof conditions are adequate for roof anchor installation.
6. Skylight Screens. Furnish materials, equipment, and labor necessary to install permanent
OSHA compliant skylight screens.
7. Protect Property. If damage to government or personal property is caused by construction activities, the contractor shall return property to existing conditions or better. Corrective actions or replacements are to be made without cost to the Government.
8. Contractor Work Schedule. Work schedule shall not include federal holidays, weekends, and nighttime work. Changes to the work schedule shall be reviewed and approved by the
COR/CO prior to implementing any changes.
C. ROOF REPAIR DESCRIPTIONS
There are four buildings encompassing the work area:
1. Building 1: The YAO Admin Office is equipped with approximately 33,000 Square Feet
(SF) of existing TPO membrane roofing. Overlay existing roof with an all-new 80 mil single-ply membrane roof system e.g. TPO or PVC, fully adhered membrane, seam welded, total roof system R-value of 25 minimum, mechanically fastened coverboard and insulation, Cool Roof Rating Council (CRRC) compliant, Solar Reflectance Index (SRI) of 97 minimum, 30-year warranty coverage for 100 miles per hour winds minimum, and
FM approved. The SRI for the roof shall be 88 or higher at 3 years. Provide all manufacturer required materials and features so that roof can be warrantied for 30 years.
Construct new roof in a manner that all the interior features of the building are protected at all times. Replace all roof drain flashings, penetration flashings, curb flashings, expansion joints, and any other feature associated with single-ply membrane overlay installation. Raise all curbs, expansions joints, and flashings to 8” minimum above the new expected water line. Accommodate electrical and water components that may require adjustments for new curb and overlay elevations. Accommodate transition between expansion joint elevation differences of Building 1 and Building 2. Salvage and reuse existing vents and drains. Install new joint sealants at existing HVAC metal hoods/flashings. Remove existing walkway and install new OSHA compliant gray 150 mil walkway. Walkway shall give access to fixtures and metal walkway. Install two new
OSHA compliant permanent harness anchor points, approximate locations indicated in
Appendix A.1.
A metal 6 inch diameter waterline is connected to a high density polyethylene 8 inch diameter waterline which crosses over Building 1, and is expected to be in the way of the new roof overlay. In the case that any modifications to the waterline are required, the
Contractor shall coordinate with Reclamation’s maintenance personnel to schedule an outage during cool weather months as the waterline is a vital piece of the cooling/chiller air condition system for Building 1. During the outage, the waterline may be safely raised or relocated by the Contractor. The Contractor shall provide certified labor, materials, and equipment necessary for reassembly, flushing, and testing. All costs related to the waterline are to be included in CLIN 1003.
2. Building 2: The Desalting Building (processing area) is equipped with approximately
103,800 SF of BUR overlain by gravel. Replace all curb flashings, wall flashings, expansion joints. Install OSHA compliant skylight screens and OSHA compliant permanent harness anchor points. BUR roof is not being repaired in its entirety within this contract. Make repairs where insulation is exposed or damaged as shown on
Appendix A.1. Install four permanent OSHA compliant roof anchors, approximate locations indicated in Appendix A.1.
3. Building 3: The YDP Admin Office is equipped with approximately 3,000 SF of single-ply roof overlain by acrylic coating. Install fabric tape and flashing grade acrylic sealant at HVAC curbs and roof penetrations. Replace incorrect roof exhaust vent with exhaust vent type appropriate for flat roofs. Repair punctures and recoat entire roof with acrylic
1coating providing 10 year warranty. Install one permanent OSHA compliant roof anchor on the center of the roof.
4. Building 4: The Switchyard Control is equipped with approximately 1,800 SF closed-cell spray foam roof overlain by acrylic coating. Replace roof drains, repair punctures, and recoat entire roof with acrylic coating providing 10 year warranty. Install one permanent
OSHA compliant roof anchor on the center of the roof.
Table 1 - List of Estimated Quantities
Basis of Estimate Category
Building
Building
Building
Building
4 Total Unit
Bonding & Insurance 1 LS
Preparatory Work 1 LS
Mobilization and
Demobilization 1 LS
Complete Building 1
Single-Ply Membrane Roof
Overlay 33000 33000 SF
Replace Roof Penetration
Flashings 45 45 EA
Replace Curb Flashings 360 635 995 LF
Replace Expansion Joints 425 650 1075 LF
Replace Wall Flashings 1282 1282 LF
Replace Joint Sealant at
HVAC metal hoods. 21 21 EA
OSHA Roof Walkway 1300 1300 LF
OSHA Roof Anchor Points 2 4 1 1 8 EA
OSHA Skylight Screens 121 121 EA
Repair Exposed Insulation
Areas 9 9 SF
Repair Skylight Curb
Flashing 3752 3752 LF
Acrylic Coating 3000 1800 4800 SF
Replace Roof Drains 4 4 EA
Remove and Dispose of
Debris 1 1 2 Ton
Detail Roof Penetration
Flashings 4 4 EA
Detail HVAC Curbs 44 44 LF
Replace 4" Low Slope
Exhaust Vent 1 1 EA
Repair Roof Punctures 3 3 5 11 EA
QUALITY CONTROL
The Contractor’s Quality Control Plan must include at a minimum the following:
1. Documentation of Contractor’s daily reports, sign-in sheets, weekly safety meetings.
2. Reports of any incidents, accidents, or near misses that occur on the property.
D. QUALITY ASSURANCE
Government oversight of the project includes informing contractor of appropriate work practice at the YAO property, observing conformance to it, and notifying contractor if otherwise. The
Government also will ensure technical and safety requirements are met as per the Statement of
Work, Occupational Safety and Health Regulations (OSHA), and Reclamation Safety and Health
Standards (RSHS). Government must be informed of changes to construction schedule, work schedule, any accidents, etc. Quality assurance will be provided throughout the contract duration either by the COR and/or designees of the COR.
E. CONTRACTOR RESPONSIBILITIES
The Contractor shall exercise management and operational control of work areas and retain full responsibility for performance and quality of the work set forth in the Statement of Work.
1. The Contractor shall be qualified and experienced with installing single-ply membrane roof systems, including the product submitted for installation. The Contractor shall perform work in accordance with all manufacturer’s recommendations.
2. The Contractor shall develop and submit for approval all items listed in Table 2 – List of
Submittals.
3. The Contractor shall furnish all the labor, materials, equipment, and incidentals necessary to perform the tasks within this SOW.
4. The Contractor shall coordinate, schedule, and lead weekly progress meetings to discuss project updates, i.e. schedule updates, submittals, RFIs, safety, etc. An agenda, three-week look ahead schedule, and meeting minutes will be provided by the Contractor after each progress meeting. Monthly, the Contractor will include time in the agenda for a monthly safety meeting with Reclamation.
5. In the event the Contractor fails or refuses to promptly comply with all Federal, State, and Local safety and health laws, regulation, codes and standards, the Contract Officer
(CO) may issue an order to suspend all or any part of the work. When satisfactory corrective action is taken, an order to resume work will be issued. The Contractor shall not be entitled to any extension of time, or to any claim for damage or additional costs due to either the directive or the suspension order. Failure of the CO or COR to order discontinuance of any or all the Contractor’s operations shall not relieve the Contractor of the responsibility for the safety of personnel and property.
6. The Contractor shall adhere to all applicable rules, regulations, and laws relating to safety and health, including environmental quality control (i.e., dust control, hazardous materials, etc.). This applies to all aspects of the Contractor’s operations including mobilization, roof inspection activities, and project clean-up.
7. The Contractor shall not require any employee to work in surroundings or working conditions that are unsanitary, hazardous, or dangerous to their health and safety. The
Contractor shall furnish or require employees to obtain personal safety apparel and equipment needed for the specified work and as required by the Department of Labor, OSHA as published in 29 CFR, and RSHS, whichever is more stringent.
8. The Contractor shall comply with RSHS’s and OSHA’s safety regulations (in the instances of differences in requirements; the most stringent would prevail). Such responsibilities shall apply to the Contractor’s operations as well as any subcontractor operations. The Contractor shall immediately correct any safety or health violations and notify the CO in writing of any noted violation and the proposed corrective action. When safety or health violations are called to the Contractor’s attention by the CO or authorized representative, the Contractor shall immediately correct the condition. Such notice, either orally or in writing, when served on the Contractor or the Contractor’s designated on-site representative will be deemed sufficient. Oral notices will be confirmed to the Contractor in writing by the CO within 7 calendar days.
9. Materials or wastes defined as hazardous by 40 CFR 261.3 and Federal Standard 313, as amended; or by other Federal, State, and local laws and regulations and used by the
Contractor shall be disposed of in accordance with the applicable Federal, State, and local laws and regulations. Waste materials known or found to be hazardous shall be disposed of in an approved treatment or disposal facility. A copy of all hazardous waste and non-hazardous waste manifests shall be given to the COR within 7 days of hauling materials to their respective approved facility.
10. Contractor shall designate an employee as the Contractor’s Onsite Safety Representative prior to start of construction activities, with the following qualifications:
a. Competent supervisory employee with current safety and health related training, experience, and duties on at least two projects of similar nature, size, complexity, and work to be performed as the current project.
b. Current first aid CPR certification.
c. OSHA 30-Hour certification.
11. Contractor’s Onsite Safety Representative authorities, duties, and responsibilities will consist of, but not limited to:
a. Responsible for effectively implementing the Contractor’s Safety Program.
b. The Safety Representative shall coordinate all emergency response activities.
c. Recommend controls for observed hazards or predicted hazards.
d. Full authorization to correct unsafe acts on the spot, including the authority to stop work to correct safety and health problems.
e. Lead weekly safety meetings at the jobsite.
f. Remain onsite, during all roof construction activities.
g. Assemble, review, and sign each Job Hazard Analysis (JHA).
h. Review of JHA with employees.
i. Verify the correct use of personal protective equipment.
j. Provide direct oversight and assemble a detailed report of all incident reviews, near-misses, accidents, and emergency response or rescue actions.
k. The Onsite Safety Representative may have other non-safety duties.
F. TEMPORARY UTILITIES
Provide an office with approximately 100 square feet of useful floor area. Provide a weathertight structure with adequate heating and cooling, toilet facilities, lighting, ventilation, a standard size office desk and chair, computer station, and working communications facilities. Provide a door with a cylinder lock and windows with locking hardware. Make utility connections. Locate as directed. File quality control records in the office and make available at all times to the
Government. After completion of the work, remove the entire structure from the site. Cost incurred by this shall be included within the associated Contract Line Item Number (CLIN).
The Contractor may provide temporary utilities or convey from nearest available power (110V) or water source. Coordination with property operations personnel may be necessary.
G. PERMITS AND APPLICABLE PUBLICATIONS
General
The Contractor shall obtain all permits, licenses, and approvals that may be required by, but not limited to, Federal, State, County, Local regulations. Cost incurred by this shall be included within the associated CLIN.
Safety and Health Requirements
The Contractor shall develop and submit a comprehensive written safety program covering all aspects of the onsite and applicable offsite operations and activities associated with the contract in compliance with the RSHS, OSHA, and any other applicable regulations, to be implemented for the proposed construction. The proposed safety program shall be submitted and accepted per the requirements of Table 2 (List of Submittals). The safety program shall identify, evaluate, and control safety and health hazards for inspection operations. The Contractor’s submitted safety program shall be reviewed and accepted by the Government, prior to start of any onsite work. All site workers shall be familiar with the safety program and shall be given training on its contents.
The Contractor shall document all training of all site workers in an appendix. Standards of approval will be determined by compliance with RSHS and OSHA regulations. Refer to RSHS
Section 1.03.
Environmental Requirements
The Contractor shall fill out Hazardous Materials Authorization (HMA) forms, as needed, for any hazardous materials being brought to the site. Contractor shall comply with Arizona
NESHAP regulations. Contractor must recycle materials when possible.
H. SUBMITTALS
General
The Contractor shall submit, for review and approval, a comprehensive Construction Plan with a sequence of work activities and a Safety Program prior to the start of any onsite work.
The Contractor shall furnish all materials and perform all work required for furnishing submittals to the government, in accordance with this paragraph, Table 2 (List of Submittals) and the requirements in the provisions, clauses, and paragraphs of the Statement of Work.
No later than 14 days after notice of award and prior to beginning work at the site the contractor shall submit a list of key personnel including their responsibilities and training certifications.
Contractor shall submit details of all equipment and certifications for the equipment that will be on site.
Within 7 days of hauling materials to an approved off-site waste disposal (landfill) site, the contractor shall submit record copies of the waste disposal manifests for both hazardous and non-hazardous waste materials.
The contractor shall not include Reclamation’s logos. The contractor shall send all submittals via email.
Table 2 - List of Submittals
RSN
Provision, clause or paragraph
Submittals Required
No. of sets to be sent to: Due date/delivery time
CO COR
I-1 1452.228-70 Certificate of Liability
Insurance 1 0
30 days after Award. Before
NTP.
I-2 52.236-15 Schedules for Contracts 1 0 30 days after Award. Before
NTP.
I-3 Construction
Plan
Personnel, equipment list-specs-conditions, record of baseline conditions, work schedule, roof repair methods, sequence of events.
1 1
Delivery of draft 30 days after the award. Must be reviewed, and accepted prior to commencing onsite work.
I-4 Construction
Schedule
Construction project schedule.
1 1
Delivery of draft 30 days after the award. Must be reviewed, and accepted prior to commencing onsite work. Project schedule to be updated every two months.
I-5 Progress
Meetings
Progress meeting agenda, three-week look ahead schedule, and meeting minutes.
1 1
Delivery of agenda, three-week look ahead, and meeting minutes within two days after each progress meeting.
I-6 Quality
Control
Daily reports, sign-in sheets, and safety meeting.
1 1
Delivery of daily reports, sign-in sheets, and safety meeting the following
Tuesday.
I-7
Safety and
Health (WBR
1452.223-81)
Safety Program site specific for the project, including OSHA, first aid, CPR certifications.
1 1
Delivery of draft 30 days after the award. Must be reviewed, and accepted prior to commencing onsite work, see section 1.03 of RSHS. Before NTP.
I-8
Safety and
Health (WBR
1452.223-81)
Job Hazard Analysis
(JHA) List, including details of risks faced during work on entire work site.
1 1
Delivery of draft 30 days after the award.
Submitted, reviewed, and accepted before commencing onsite work.
RSN
Provision, clause or paragraph
Submittals Required
No. of sets to be sent to: Due date/delivery time
CO COR
I-9
Sustainability and
Environmental
Management
System
(SEMS)
Waste Management Plan 1 1
Delivery of draft 30 days after the award.
Submitted, reviewed, and accepted before commencing onsite work.
I-10
Safety and
Health (WBR
1452.223-81)
Weekly accident summary report 1 1
Every Tuesday reporting prior week through Friday.
See paragraph 1.03 of RSHS.
I-11 Detail Sheets
Manufacturer’s technical detail sheets showing cross sections of Building
1 roof system to be installed.
1 1
Delivery of draft 30 days after the award.
Submitted, reviewed, and accepted before commencing onsite work.
I-12 Materials Adhesives 1 1
Hazardous materials authorization form, technical data sheet, and safety data sheet submitted, reviewed, and accepted before bringing onsite.
I-13 Materials Acrylic Coating 1 1
Hazardous materials authorization form, technical data sheet, and safety data sheet submitted, reviewed, and accepted before bringing onsite.
I-14 Materials Sealants 1 1
Hazardous materials authorization form, technical data sheet, and safety data sheet submitted, reviewed, and accepted before bringing onsite.
PART IV – REFERENCES
Reclamation Safety and Health Standards https://www.usbr.gov/safety/rshs/index.html.
APPENDIX
A. YAO Roof Leak Inspection Report (with Attachments A.1-A.5)
B. 1292-303-60221 Vicinity and Location Maps
C. 2010 YDP Seismic Strengthening Roof Drawings Set (For Information Only)
D. Floor Plan Drawings (For Information Only)
E. Asbestos and Lead Inspection Report https://www.usbr.gov/safety/rshs/index.html