The file is a Base Offer Cost Breakdown template for a VA project (Project Number 675-23-151) located at the Viera VA Clinic. The spreadsheet provides a detailed construction cost breakdown across 34 standard construction divisions, including categories such as General Requirements, Concrete, Electrical, HVAC, and Utilities. While the template is currently unpopulated with actual costs, it includes placeholders for labor costs, material costs, overhead percentage, profit percentage, and bonding percentage. The document is associated with Solicitation Number 36C77624R0131 for the VISN 8 MATOC - Mainland contract, issued by the Department of Veterans Affairs Technology Acquisition Center Austin. A sample labor and materials section demonstrates how contractors would populate the detailed cost breakdown, with example entries showing labor rates, hours, and equipment rental costs.

View the file

Other files

File Type Posted
36C77624R0131 0006.docx DOCX document
Attachment 1 - REV1 Attachment 06a - 100 Percent Specifications.pdf PDF
Attachment 2 - REV1 Attachment 06a - 100 Percent Drawings.pdf PDF
36C77624R0131 0005.docx DOCX document
Attachment 1 - RFP 36C77624R0131 Tech Questions dated 9-29-25.xlsx XLSX spreadsheet
36C77624R0131 0004.docx DOCX document
Attachment 1 - RFP 36C77624R0131 Tech Questions dated 8-22-25.xlsx XLSX spreadsheet
Attachment 1 - RFP 36C77624R0131 Tech Questions dated 8-21-25.xlsx XLSX spreadsheet
Attachment 2 - Viera Sign Design Intent.pdf PDF
Attachment 1J - Orlando - VHA ICRA-PCRA-1.2 updated Dec 2024.pdf PDF
Attachment 1B - 52.209-7 Information Regarding Responsibility Matters.pdf PDF
Attachment 1A - 52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment.pdf PDF
Attachment 1E - Chiller Plant - 100 Drawings.pdf PDF
Attachment 1I - Panel CHB B228-1 Photo and Panel Schedule.pdf PDF
Attachment 1C - 52.209-13 Violation of Arms Control Treaties or Agreements-Certification.pdf PDF
36C77624R0131 0003.docx DOCX document
Attachment 1H - Underground Utilities Drawings.pdf PDF
Attachment 1K - VHA ICRA Update - Nov 2024.pptx PPTX presentation
Attachment 1G - Clinic Drawings.pdf PDF
Attachment 1F - Panel LCP-1 Photo and Panel Schedule.pdf PDF
Attachment 1D - 52.229-11 Tax on Certain Foreign Procurements—Notice and Representation.pdf PDF
36C77624R0131 0002.pdf PDF
Attachment 1 - Sign-In Sheet - VISN 8 MATOC Mainland 7-19-25.pdf PDF
Attachment 2 - Attachment 06 - 675-23-151 Seed Project Notice of Task Order Request for Proposal - Updated 7-21-25.docx DOCX document
Attachment 3 - Attachment 06f - Wage Determination FL20250196 Rev 4 7-4-25.pdf PDF
36C77624R0131 0001.docx DOCX document
Attachment 06b - Seed Project Price Schedule Sheet.docx DOCX document
Attachment 06a - Spec Supplement - Orlando VAHCS Physical Security Systems Tech Specs 06-06-2025.pdf PDF
Attachment 06a - 100 Percent Specifications.pdf PDF
Attachment 01 - Technical Question Form - VISN 8 MATOC - Mainland.xlsx XLSX spreadsheet
36C77624R0131_2.docx DOCX document
Attachment 06f - Wage Determination FL20250196 Rev 3 3-14-25.pdf PDF
Attachment 06e - PCRA-ILSM- ICRA- 675-23-151.pdf PDF
Attachment 06d - Site Visit Instructions - Seed Project VISN 8 MATOC Mainland.pdf PDF
Attachment 06a - 100 Percent Narrative.pdf PDF
Attachment 04 - Subcontractor Information and Consent Form.docx DOCX document
Attachment 03 - Project Information Sheet for Contractors.docx DOCX document
Attachment 02 - Limitations on Subcontracting.docx DOCX document
Attachment 6g - Brand Name Justification - Project 675-23-151- Address Viera Site Deficiencies -Redacted.pdf PDF
Attachment 06a - 100 Percent Drawings.pdf PDF
Attachment 05 - Past Performance Questionnaire.docx DOCX document
Attachment 06 - 675-23-151 Seed Project Notice of Task Order Request for Proposal.docx DOCX document
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Base Offer

Base Offer Cost Breakdown

Project Number: 675-23-151 Edward L Roy: VA assigned project #

Date:
Project TitleAddress Viera Site Deficiencies

Edward L Roy: VA assigned Project Title

Project LocationViera VA Clinic
Offeror Name
Offeror Street
Offeror CityStateZip

Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division

Material Cost
Edward L Roy: Enter all Material Costs by DivisionTotal Cost

Edward L Roy: This Column is the sum of the Division's Labor and Material Costs

Division 1General Requirements$ - 0$ - 0$ - 0
Division 2Existing Conditions- 0- 0- 0
Division 3Concrete- 0- 0- 0
Division 4Masonry- 0- 0- 0
Division 5Metals- 0- 0- 0
Division 6Wood and Plastic- 0- 0- 0
Division 7Thermal & Moisture Protect- 0- 0- 0
Division 8Doors and Windows- 0- 0- 0
Division 9Finishes- 0- 0- 0
Division 10Specialties- 0- 0- 0
Division 11Equipment- 0- 0- 0
Division 12Furnishings- 0- 0- 0
Division 13Special Construction- 0- 0- 0
Division 14Conveying Equipment- 0- 0- 0
Division 21Fire Suppression- 0- 0- 0
Division 22Plumbing- 0- 0- 0
Division 23HVAC- 0- 0- 0
Division 26Electrical- 0- 0- 0
Division 27Communications- 0- 0- 0
Division 28Electronic Safety & Security- 0- 0- 0
Division 31Earthwork- 0- 0- 0
Division 32Exterior Improvements- 0- 0- 0
Division 33Utilities- 0- 0- 0
Division 34Transportation Subtotal- 0- 0- 0
Division Subtotals :$ - 0$ - 0$ - 0

Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).

Edward L Roy: Date Offer Prepared/Submitted

- 0
Profit %0.00%
Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38).- 0
Bond %0.00%

Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).

Edward L Roy: Enter all Labor Costs by Division

- 0
Overhead/Profit Subtotals :$ - 0

Edward L Roy: Sum of Overhead, Profit and Bond %.

Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Base Offer Cost $ - 0 $ - 0 $ - 0

Labor Detail

Sample Example
DivisionLabor CategoryLabor RateHoursTotal
1Plumber$35.00123$4,305.00
1Laborer14.7570$1,032.50
$5,337.50

Materials and Equipment Details

Sample Example
DivisionItemRateUnitsTotal
1Pipe - 150'$1.50150$225.00
190 Degree Coupling$1.105$5.50
1Pump Rental - Hour$200.006$1,200.00
$1,430.50