This document is a detailed specification (Attachment 06a) for a VA construction project to provide a High Level Disinfection Room for the Sterile Processing (SPS) department at the VA Caribbean Healthcare System in San Juan, Puerto Rico. The project (VA Project #672-22-810) involves creating a specialized room with specific technical requirements for construction, including detailed specifications for materials, installation methods, and performance standards across multiple divisions such as concrete, metals, wood, thermal protection, doors, finishes, and specialized equipment installation.

The specification covers comprehensive requirements for the project, including precise instructions for surface preparation, installation of metal framing, gypsum board, acoustical ceilings, resinous flooring with integral cove base, and other critical components. The project involves specific performance criteria for materials, such as fire resistance, sound transmission, and environmental controls. The solicitation is issued by the VA Network Contracting Office 8 (NCO-8), with the project consultant being RGD Engineers, and is scheduled for a 100% Construction Document (CD) phase as of 04/22/2024. The contract number is 36C24822C0087, and the project will require careful coordination of multiple construction disciplines to meet the specialized requirements of a high-level disinfection room.

View the file

Other files

File Type Posted
Attachment 1 _ RFP 36C77624R0149 Tech Questions _ dated 7-30-25.docx DOCX document
36C77624R0149 0005.docx DOCX document
Attachment 1 _ RFP 36C77624R0149 Tech Questions _ dated 7-29-25.docx DOCX document
36C77624R0149 0004.docx DOCX document
36C77624R0149 0003.docx DOCX document
Attachment 1 _ RFP 36C77624R0149 Tech Questions _ dated 7-25-25.docx DOCX document
Attachment 2 - SOW Provide High Level Disinfection Room at SPS - 7-21-25.docx DOCX document
36C77624R0149 0002.docx DOCX document
Attachment 1 _ RFP 36C77624R0149 Tech Questions _ dated 7-24-25.docx DOCX document
36C77624R0149 0001.docx DOCX document
Attachment 1 - Sign-In Sheet - VISN 8 MATOC Caribbean - 7-9-25.pdf PDF
Attachment 06a - Drawings 100CD-Plumbing.pdf PDF
Attachment 04 - Subcontractor Information and Consent Form.docx DOCX document
Attachment 03 - Project Information Sheet for Contractors.docx DOCX document
Attachment 06e - PCRA 672-22-810.pdf PDF
Attachment 06a - Drawings 100CD-Architect.pdf PDF
Attachment 05 - Past Performance Questionnaire.docx DOCX document
36C77624R0149_2.docx DOCX document
Attachment 06d - Site Visit Instructions - Seed Project VISN 8 MATOC Caribbean.docx DOCX document
Attachment 06a - Drawings 100CD-Mechanical.pdf PDF
Attachment 06 - 672-22-810 Seed Project Notice of Task Order Request for Proposal.docx DOCX document
Attachment 02 - Limitations on Subcontracting.docx DOCX document
Attachment 01 - Technical Question Form - VISN 8 MATOC - Caribbean.xlsx XLSX spreadsheet
Attachment 06c - Base Offer Cost Breakdown.xlsx XLSX spreadsheet
Attachment 06b - Seed Project Price Schedule Sheet.docx DOCX document
Attachment 06a - Drawings 100CD-Electrical.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIFICATIONS CD(100%CD-IFB) SUBMITTAL

04/22/2024

Contract No. 36C24822C0087 VA Design Services Project: 672-22-810

“Provide High Level Disinfection Room for SPS”

VA Caribbean Healthcare System, San Juan, PR, 00921

Project Location: VA Caribbean Healthcare System #10 Calle Casia

San Juan, PR 00921

Issuing Office:

Department of Veterans Affairs

Network Contracting Office 8 (NCO-8) VA Caribbean HCS

Point of Contact: Ana G. Alvarado, VA Contracting Officer email address: ana.alvarado@va.gov

Project Consultant:

121 South Orange Ave., Unit 1230 Orlando, FL 32801

Point of Contact: Amy W. Davenport, President email address: amy.davenport@rgdengineers.com mailto:ana.alvarado@va.gov mailto:amy.davenport@rgdengineers.com

VA CARIBBEAN HEALTHCARE SYSTEM, SAN JUAN, PR

“PROVIDE HIGH LEVEL DISINFECTION ROOM FOR SPS"

VA PROJECT#: 672-22-810

CD(100%CD-IFB) – 04/22/2024

11/07/2022 11/07/2022

TABLE OF CONTENTS 00 01 10 - 1/3

SECTION 00 01 10

TABLE OF CONTENTS

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 10 Table of Contents 05-20 00 01 15 List of Drawing Sheets 05-20

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 11-21 01 32 16 Project Schedules 03-20 01 33 23 Shop Drawings, Product Data, and Samples 06-21 01 35 26 Safety Requirements 11-21 01 42 19 Reference Standards 11-20 01 45 00 Quality Control 02-21 01 45 29 Testing Laboratory Services 11-18 01 57 19 Temporary Environmental Controls 01-21 01 58 16 Temporary Interior Signage 07-15 01 74 19 Construction Waste Management 11-21 01 81 13 Sustainable Construction Requirements 10-17 01 91 00 General Commissioning Requirements 10-15

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17

DIVISION 03 – CONCRETE

03 30 53 Cast-in-Place Concrete 01-21

DIVISION 05 – METALS

05 50 00 Metal Fabrications 08-18

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 10-17

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 84 00 Firestopping 01-21 07 92 00 Joint Sealants 10-17

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 01-21 08 14 00 Interior Wood Doors 01-21 08 31 13 Access Doors and Frames 01-21 08 71 00 Door Hardware 01-21 08 80 00 Glazing 01-21

VA PROJECT#: 672-22-810

CD(100%CD-IFB) – 04/22/2024

11/07/2022 11/07/2022

TABLE OF CONTENTS 00 01 10 - 2/3

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 01-21 09 06 00 Schedule for Finishes 01-21 09 22 16 Non-Structural Metal Framing 06-18 09 29 00 Gypsum Board 04-20 09 51 00 Acoustical Ceilings 12-18 09 67 24 Resinous Poured-in-Place Resilient Flooring (RES-4) 01-21 09 91 00 Painting 01-21

DIVISION 10 – SPECIALTIES

10 26 00 Wall and Door Protection 01-21

DIVISION 11 – EQUIPMENT

11 05 12 General Motor Requirements for Equipment 01-21 11 71 01 Medical Washing and Sterilizing Equipment 01-21

DIVISION 12 – FURNISHINGS

12 34 00 Manufactured Plastic Casework 01-21 12 36 00 Countertops 12-18

DIVISION 13 - SPECIAL CONSTRUCTION

13 05 41 Seismic Restraints Requirements 01-21

DIVISION 21- FIRE SUPPRESSION

21 13 13 Wet-Pipe Sprinkler Systems 06-15

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 09-20 22 11 00 Facility Water Distribution 05-21 22 13 00 Facility Sanitary and Vent Piping 09-20 22 40 00 Plumbing Fixtures 09-15

VA PROJECT#: 672-22-810

CD(100%CD-IFB) – 04/22/2024

11/07/2022 11/07/2022

TABLE OF CONTENTS 00 01 10 - 3/3

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 02-20 23 05 93 Testing, Adjusting, and Balancing for HVAC 02-20 23 07 11 HVAC Insulation 02-20 23 08 00 Commissioning of HVAC Systems 02-20 23 31 00 HVAC Ducts and Casings 02-20 23 37 00 Air Outlets and Inlets 02-20

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16 26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17 26 05 26 Grounding and Bonding for Electrical Systems 01-17 26 05 33 Raceway and Boxes for Electrical Systems 01-18 26 05 36 Wireways for radiology equipment 01-18 26 05 73 Overcurrent Protective Device Coordination Study 01-18 26 08 00 Commissioning of Electrical Systems 11-16 26 09 23 Lighting Controls 01-18 26 24 16 Panelboards 01-18 26 27 26 Wiring Devices 01-18 26 29 21 Enclosed Switches and Circuit Breakers 01-17 26 51 00 Interior Lighting 01-18

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 09-19

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 31 00 Fire Detection and Alarm 10-11

VA PROJECT#: 672-22-810

CD(100%CD-IFB) – 04/22/2024

11/07/2022 11/07/2022

LIST OF DRAWINGS 00 01 15 - 1/2

SECTION 00 01 15

LIST OF DRAWINGS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

GENERAL

GI-001 COVER SHEET

GI-002

SHEET INDEX, GENERAL NOTES, SYMBOLS AND ABBREVIATIONS

LS-001

LIFE SAFETY PLAN

LS-002

PROPOSED DEBRIS REMOVAL

ARCHITECTURAL

AE-101A DEMO PLAN

AE-101B

PROPOSED FLOOR PLAN

AE-112A

REFLECTED CEILING PLAN

AE-405

INTERIOR ELEVATIONS AND DETAILS

AE-600

PARTITION TYPES, DOOR SCHEDULE AND DETAILS

PLUMBING

PL-001

PLUMBING COVER SHEET

PL-101

FIRE PROTECTION PLANS

PL-201

PLUMBING PLANS

PL-501

PLUMBING DETAILS AND SCHEDULES

MECHANICAL

MH-001

MECHANICAL COVER SHEET

MD-101

MECHANICAL DEMOLITION PLAN

MD-102

MECHANICAL PHASING PLAN

MH-101

MECHANICAL FLOOR PLAN

MH-401

MECHANICAL SCHEDULES

MH-501

MECHANICAL DETAILS

VA PROJECT#: 672-22-810

CD(100%CD-IFB) – 04/22/2024

11/07/2022 11/07/2022

LIST OF DRAWINGS 00 01 15 - 2/2

ELECTRICAL

E-001

ELECTRICAL COVER SHEET

EP-101

ELECTRICAL FLOOR PLANS

E-501

ELECTRICAL DETAILS

E-601

PANEL SCHEDULES

- - - E N D - - -

VA PROJECT#: 672-22-810

CD(100%CD-IFB) – 04/22/2024

11/07/2022 11/07/2022

GENERAL REQUIREMENTS 01 00 00 - 1/24

SECTION 01 00 00

GENERAL REQUIREMENTS

1.1 SAFETY REQUIREMENTS

Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall furnish labor and materials and perform site preparation work for the VA CARIBBEAN HEALTHCARE SYSTEM project in SAN

JUAN, PR, as required by contract documents (drawings and specifications) for a fully operational new HIGH LEVEL DISINFECTION

(HLD)ROOM. The contractor shall coordinate with the Cantel Medical

Company to completely prepare the site for the placement of the new

EQUIPMENT (AER) and associated infrastructure. Contractor shall provide all connections between the new AER(s)and required associated infrastructure.

B. Visits to the site by Bidders will be organized by the Medical Center

Engineering Office Contracting Owner’s Representative (COR) as outlined in the solicitation.

C. Offices of RGD CONSULTING ENGINEERS, LLC, as Architect-Engineers (A/E) design team, will render certain technical services during construction. Such services shall be considered as advisory to the

Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting

Officer (CO) or it’s duly authorized representative (COR).

D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the Resident Engineer COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the Resident Engineer COR.

E. All employees of the Contractor and sub-contractors shall comply with

VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

VA PROJECT#: 672-22-810

CD(100%CD-IFB) – 04/22/2024

11/07/2022 11/07/2022

GENERAL REQUIREMENTS 01 00 00 - 2/24

1.3 STATEMENT OF BID ITEM(S)

A. ITEM I, GENERAL CONSTRUCTION: Interior Work: Work includes general construction, alterations, necessary removal of existing structures and construction and certain other items.

ITEM II, Electrical Work: Work includes all labor, material, equipment and supervision to perform the required electrical construction work on this project including Fire-Alarm and Telecom.

ITEM III, Mechanical Work: (HVAC, Plumbing, and Fire Sprinkler): Work includes all labor, material, equipment and supervision to perform the required Mechanical construction work on this project.

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without permission of the

Contracting Officer. No pictures of staff or patients are allowed.

4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the

VA PROJECT#: 672-22-810

CD(100%CD-IFB) – 04/22/2024

11/07/2022 11/07/2022

GENERAL REQUIREMENTS 01 00 00 - 3/24

event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

C. Guards:

1. The General Contractor shall provide unarmed guards at the project site after construction hours.

2. The Contractor shall provide the guards and VA police with communication devices as directed.

3. The general Contractor shall install equipment for recording guard rounds to ensure systematic checking of the premises.

D. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR)

Resident Engineer for the purpose of security inspections of every area of project including toolboxes and parked machines and take any emergency action.

2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation.

E. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of

“sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.

Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting

Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

VA PROJECT#: 672-22-810

CD(100%CD-IFB) – 04/22/2024

11/07/2022 11/07/2022

GENERAL REQUIREMENTS 01 00 00 - 4/24

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document

Management Software (EDMS). Example software programs include

PROCORE, Submittal Exchange, or approved equal. Characteristics of

EDMS include: a controlled document repository, audit history, revision control, workflow automation of change management, real-time and secure collaboration, engineering transmittal database, and an automated process for document distribution, review, and approval.

a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the

EDMS system.

b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

F. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

2. A limited number of (2 to 5) permits shall be issued for General

Contractor and its employees for parking in designated areas only.

G. Prohibited Tobacco Products and Use

1. Smoking and Vaping is strictly prohibited on the entire VAMC campus.

Smoking shall include the inhaling, exhaling, burning and breathing of any lighted/heated cigarette, cigar, pipe, electronic cigarette or other similar lighted/heated tobacco or plant product intended for inhalation, including hookahs and marijuana, whether natural or synthetic, in any manner or in any form. “Smoking” also includes the use of an electronic smoking device which creates an aerosol or vapor, in any manner or in any form.

1.6 OPERATIONS AND STORAGE AREAS

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the

VA PROJECT#: 672-22-810

CD(100%CD-IFB) – 04/22/2024

11/07/2022 11/07/2022

GENERAL REQUIREMENTS 01 00 00 - 5/24

Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the

Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the

Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting

Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the Contracting

Officer, use only established roadways as authorized by the Contracting

Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The

Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

1. Working space and space available for storing materials shall be as determined by the Resident Engineer COR.

D. Workers are subject to rules of Medical Center applicable to their conduct.

E. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by Resident Engineer COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of

Veterans Affairs in quantities sufficient for not more than two work

VA PROJECT#: 672-22-810

CD(100%CD-IFB) – 04/22/2024

11/07/2022 11/07/2022

GENERAL REQUIREMENTS 01 00 00 - 6/24

days. Provide unobstructed access to Medical Center areas required to remain in operation.

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

F. Phasing:

The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.

It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:

To ensure such executions, Contractor shall furnish the Resident

Engineer COR with a schedule of approximate phasing dates on which the

Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the

Resident Engineer COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to Medical Center

Director, COR and Contractor, as follows:

Phase I:

Upon the receipt of the Notice to Proceed and Prior to the start of

Phase II, the Contractor shall start the completion of all contractual work per contact documents, except for setting RTU-37 (otherwise known as Phase II) Phase I shall be as follows:

1. Provide Infection Control Partitions as required to comply with

Infection Control Risk Assessment (ICRA). ICRA partitions shall be designed as 1-hour barriers with 45-minute doors where applicable. In the case that existing walls are used as the ICRA barrier, contractor to confirm those walls and doors meet the same fire-rating requirements. Walls shall extend to the underside of structure above with 1-hour rated details. Where walls do not meet the requirement, contractor to bring existing walls up to code or install a temporary ICRA partition to

VA PROJECT#: 672-22-810

CD(100%CD-IFB) – 04/22/2024

11/07/2022 11/07/2022

GENERAL REQUIREMENTS 01 00 00 - 7/24

separate the Phase under construction from the areas surrounding

it. Areas under construction shall be maintained under a negative pressure (-) differential relative to adjacent occupancies. ICRA to be Class IV Walls and Doors. Temporary barriers may be an anti-static fire-retardant plastic barrier meeting local fire codes. Temporary ICRA walls shall not impede the means of egress travel as required by code. Path shall remain clear and free of obstruction. COR to approve compliance to requirements at beginning and end of each phase.

2. Provide all required infrastructure to temporary connect the existing RTU-37 to the new ductwork-thru-roof, CHW and HW piping, HVAC controls to the BAS / ECC until such time when new RTU 37 is delivered to the site and is ready to replace the existing RTU(see

Phase II)

Phase II:

Upon the completion of Phase I, the Contractor shall start the completion of Phase II:

1. Upon the arrival of the new RTU-37, RTU-37 will be delivered by the manufacturer as a “bare” unit with sections, casings, coils, fans and motors.

2. The Contractor shall field install all HVAC Controls components including sensors, dampers, actuators, valves.

3. Remove and safely dispose of existing RTU-37.

4. Install new rooftop mounting curb.

5. Connect the new RTU-37 to existing; ductwork-thru-roof, CHW and

HW piping, HVAC controls to the BAS / ECC.

6. Commission new RTU-37.

G. Building No. 1 will be occupied during performance of work; but immediate areas of alterations will be vacated. See above Phasing for times when areas will be occupied and when they will be vacated.

1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of

Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated

VA PROJECT#: 672-22-810

CD(100%CD-IFB) – 04/22/2024

11/07/2022 11/07/2022

GENERAL REQUIREMENTS 01 00 00 - 8/24

from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access.

Coordinate alteration work in areas occupied by Department of Veterans Affairs so that Medical Center operations will continue during the construction period.

I. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.

2. Contractor shall maintain the existing fire protection and fire alarm equipment in active operating condition. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.

J. Utilities Services: Maintain existing utility services for Medical

Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.

Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by Resident Engineer COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of Resident Engineer COR.

Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification

Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS for additional requirements.

2. Contractor shall submit a request to interrupt any such services to

Resident Engineer COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least

VA PROJECT#: 672-22-810

CD(100%CD-IFB) – 04/22/2024

11/07/2022 11/07/2022

GENERAL REQUIREMENTS 01 00 00 - 9/24

inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the Resident Engineer COR.

5. In case of a contract construction emergency, service will be interrupted on approval of Resident Engineer COR. Such approval will be confirmed in writing as soon as practical.

K. Abandoned Lines: Abandoned-in-place equipment and related appurtenances is not permitted. All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, not being used shall be demolished and removed. Existing lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

L. To minimize interference of construction activities with flow of

Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.

K. Allocate a minimum of five (5) business days for relocation of furniture by the VA. Coordinate with the VA COR.

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the Resident Engineer COR of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting

Officer. This report shall list by rooms and spaces:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

VA PROJECT#: 672-22-810

CD(100%CD-IFB) – 04/22/2024

11/07/2022 11/07/2022

GENERAL REQUIREMENTS 01 00 00 - 10/24

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and Resident Engineer

COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of

Resident Engineer COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by

Contractor with new items in accordance with specifications which will be furnished by Government.

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and Resident Engineer COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of

Contractor to restore damage caused by Contractor's workers in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

2. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

VA PROJECT#: 672-22-810

CD(100%CD-IFB) – 04/22/2024

11/07/2022 11/07/2022

GENERAL REQUIREMENTS 01 00 00 - 11/24

1. Reserved items which are to remain property of the Government are identified by attached tags as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed the COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

1.9 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the

Resident Engineer COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the Resident

Engineer COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged.

Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

VA PROJECT#: 672-22-810

CD(100%CD-IFB) – 04/22/2024

11/07/2022 11/07/2022

GENERAL REQUIREMENTS 01 00 00 - 12/24

1.10 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the Resident Engineer's COR review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the Resident

Engineer COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

1.11 WARRANTY MANAGEMENT

A. Warranty Management Plan: Develop a warranty management plan at least

30 days before the planned pre-warranty conference, submit four sets of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract.

The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the

Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the

Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4-month and 9-month warranty inspection will be conducted, measured from time of acceptance, by the

Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:

1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.

VA PROJECT#: 672-22-810

CD(100%CD-IFB) – 04/22/2024

11/07/2022 11/07/2022

GENERAL REQUIREMENTS 01 00 00 - 13/24

2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.

3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.

4. A list for each warranted equipment item, feature of construction or system indicating:

a. Name of item.

b. Model and serial numbers.

c. Location where installed.

d. Name and phone numbers of manufacturers and suppliers.

e. Name and phone numbers of manufacturers or suppliers.

f. Names, addresses and phone numbers of sources of spare parts.

g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.

h. Starting point and duration of warranty period.

i. Summary of maintenance procedures required to continue the warranty in force.

j. Cross-reference to specific pertinent Operation and Maintenance manuals.

k. Organizations, names and phone numbers of persons to call for warranty service.

l. Typical response time and repair time expected for various warranted equipment.

5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.

6. Procedure and status of tagging of all equipment covered by extended warranties.

7. Two copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.

B. Performance Bond: The Performance Bond must remain effective throughout the construction period.

VA PROJECT#: 672-22-810

CD(100%CD-IFB) – 04/22/2024

11/07/2022 11/07/2022

GENERAL REQUIREMENTS 01 00 00 - 14/24

1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.

2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.

3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.

C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for

Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for

Contractor response, and other details deemed necessary by the

Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor.

This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.

D. Contractor’s Response to Construction Warranty Service Requirements:

Following oral or written notification by the Contracting Officer, the

Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty Service Priority List”

VA PROJECT#: 672-22-810

CD(100%CD-IFB) – 04/22/2024

11/07/2022 11/07/2022

GENERAL REQUIREMENTS 01 00 00 - 15/24

and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period.

Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the

Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.

1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.

2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.

3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.

4. The “Construction Warranty Service Priority List” is as follows:

Code 1-Life Safety Systems

a. Fire suppression systems.

b. Fire alarm system(s).

Code 1-Air Conditioning Systems

a. Air conditioning leak in part of the building, if causing damage.

b. Air conditioning system not cooling properly.

Code 1 Doors

a. Interior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.

Code 3-Doors

a. Interior personnel doors or hardware not functioning properly.

Code 1-Electrical

a. Power failure (entire area or any building operational after 1600 hours).

b. Security lights.

c. Smoke detectors.

Code 2-Electrical

a. Power failure (no power to a room or part of building).

b. Receptacles and lights not operational (in a room or part of building).

Code 3-Electrical

VA PROJECT#: 672-22-810

CD(100%CD-IFB) – 04/22/2024

11/07/2022 11/07/2022

GENERAL REQUIREMENTS 01 00 00 - 16/24

Code 1-Gas

a. Leaks and pipeline breaks.

Code 1-Heat

a. Power failure affecting heat.

Code 1-Plumbing

a. Hot water heater failure.

b. Leaking water supply pipes.

Code 2-Plumbing

a. Flush valves not operating properly

b. Fixture drain, supply line or any water pipe leaking.

c. Toilet leaking at base.

Code 3- Plumbing

a. Leaky faucets.

Code 3-Interior

a. Floors damaged.

b. Paint chipping or peeling.

c. Casework damaged.

Code 2-Water (Hot)

a. No hot water in portion of building listed.

Code 3

a. All work not listed above.

E. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting

Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.

VA PROJECT#: 672-22-810

CD(100%CD-IFB) – 04/22/2024

11/07/2022 11/07/2022

GENERAL REQUIREMENTS 01 00 00 - 17/24

1.12 USE OF ROADWAYS

A. For hauling, use only established public roads and roads on Medical

Center property. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.

1.13 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:

1. Permission to use each unit or system must be given by Resident

Engineer COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the Resident Engineer COR will withdraw permission for use of the equipment.

2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their

VA PROJECT#: 672-22-810

CD(100%CD-IFB) – 04/22/2024

11/07/2022 11/07/2022

GENERAL REQUIREMENTS 01 00 00 - 18/24

overload elements shall be properly sized, coordinated and adjusted.

Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014

Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.

3. Units shall be properly lubricated, balanced, and aligned.

Vibrations must be eliminated.

4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.

5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.

6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.

Boilers, pumps, feedwater heaters and auxiliary equipment must be operated as a complete system and be fully maintained by operating personnel. Boiler water must be given complete and continuous chemical treatment.

B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.

C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.

D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.

VA PROJECT#: 672-22-810

CD(100%CD-IFB) – 04/22/2024

11/07/2022 11/07/2022

GENERAL REQUIREMENTS 01 00 00 - 19/24

1.14 TEMPORARY USE OF EXISTING ELEVATORS

A. Use of existing elevator for handling building materials and

Contractor's personnel will be permitted subject to following provisions:

1. Contractor makes all arrangements with the COR for use of elevators. The COR will ascertain that elevators are in proper condition. Contractor may use elevators designated by the COR for daily use between the hours designated by the COR and for special nonrecurring time intervals when permission is granted. Personnel for operating elevators will not be provided by the Department of Veterans Affairs.

2. Contractor covers and provides maximum protection of following elevator components:

a) Entrance jambs, heads soffits and threshold plates.

b) Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.

c) Finish flooring.

3. Government will accept hoisting ropes of elevator and rope of each speed governor if they are worn under normal operation.

However, if these ropes are damaged by action of foreign matter such as sand, lime, grit, stones, etc., during temporary use, they shall be removed and replaced by new hoisting ropes at the contractor’s expense.

1.15 TEMPORARY TOILETS

A. Contractor may have for use of Contractor's workers; such toilet accommodations as may be assigned to Contractor by Medical Center.

Contractor shall keep such places clean and be responsible for any damage done thereto by Contractor's workers. Failure to maintain satisfactory condition in toilets will deprive Contractor of the privilege to use such toilets.

1.16 AVAILABILITY AND USE OF UTILITY SERVICES

A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for

VA PROJECT#: 672-22-810

CD(100%CD-IFB) – 04/22/2024

11/07/2022 11/07/2022

GENERAL REQUIREMENTS 01 00 00 - 20/24

chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.

B. Electricity (for Construction and Testing): Furnish all temporary electric services.

1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.

C. Water (for Construction and Testing): Furnish temporary water service.

1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the

Contractor.

2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at Resident Engineer's COR discretion) of use of water from Medical Center's system.

1.17 TESTS

A. As per specification section 23 05 93 the contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The contractor shall document the results of the approved plan and submit for approval with the as built documentation.

B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.

C. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer.

Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.

VA PROJECT#: 672-22-810

CD(100%CD-IFB) – 04/22/2024

11/07/2022 11/07/2022

GENERAL REQUIREMENTS 01 00 00 - 21/24

D. Mechanical and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire system which must be coordinated to work together during normal operation to produce results for which the system is designed. For example, air conditioning supply air is only one part of entire system which provides comfort conditions for a building. Other related components are return air, exhaust air, steam, chilled water, refrigerant, hot water, controls and electricity, etc. Another example of a system which involves several components of different disciplines is a boiler installation. Efficient and acceptable boiler operation depends upon the coordination and proper operation of fuel, combustion air, controls, steam, feedwater, condensate and other related components.

E. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonably period of time during which operating and environmental conditions remain reasonably constant and are typical of the design conditions.

F. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.

1.19 INSTRUCTIONS

A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.

B. Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the Resident Engineer COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, VA PROJECT#: 672-22-810

CD(100%CD-IFB) – 04/22/2024

11/07/2022 11/07/2022