SOLICITATION #: 36C77624R0148
PROJECT NAME: VISN 8 Construction MATOC - Caribbean
TECHNICAL QUESTIONS AND VA RESPONSE TRACKING SHEET
| Item No. |
| MATOC |
| SEED PROJECT |
| QUESTION |
| GOVERNMENT RESPONSE |
| X |
| RFI Response Question 12: This response states that the AER Machines are not a part of the projects scope. Yet on Sheet AE-101B this calls for new AER Units. There is also details listed on sheet AE-405 showing these units. Please revise drawing set or confirm AER and associated work is not included with this projects scope. |
| AER(s) are VA provided, Contractor installed. |
| X |
| In addition to questions above. If New AER units are not required in this projects scope of work. Please confirm if new supply registers and return registers will be required. |
| GC to provide and install per sheet MH-401 |
| X |
| Please confirm if the RFU-37 is included in the scope of work for this project. |
| Not in Contract, disregard item RTU-37 |
| X |
| If so, please provide specifications for this unit as well as drawing with details showing installation. |
| NIC |
| X |
| Are temporary walls to be rated? If so please confirm rating. |
| No. Temporary walls must be certified for ICRA Class III/IV. |
| X |
| Please confirm partition types of new walls per plan. |
| Please refer to Sheet AE-600 Partition Types |
| X |
| RFI response Question 52: States we will not be able to utilize a vacant space for a field office. Please identify an area on site where contractor will be able to set up a jobsite trailer. |
| There is no area inside VA premises available for a field office. |
| X |
| Please confirm if contractor can use existing conduit and wiring to hook up new light fixtures. |
| Refer to Demolition Notes on Sheet EP-101. Existing Raceway and wiring are allowed to be reused. Provided they meet the specifications for the new system. |
| X |
| Please confirm if piping shown on PL-201 is existing or not. |
| All are new up to the point of connection. |
| X |
| Please |
| Question not clear. |
| X |
| Please confirm of any exit signs this space is to receive. Please show on plan where any exit signs are to be installed. |
| Exit Signs are existing to remain. Coordinate in the field if any needs to be relocated. |
| X |
| There seems to be glazing associated with the drying cabinets on sheet AE-405 detail 1. Please provide additional information on drying cabinets. |
| Drying Cabinet to be provided by VA. |
| X |
| Please consider extending the bid due date time to allow Prime and Subcontractors to adjust their bids accordingly upon receiving the unanswered RFI’s |
| The bid date was extended to 8-1-25 at 5PM ET via Amendment 0002 |