Att 7 App B Past Perf Ques.docx

DOCX document 44 KB Posted

Attached to
Mobile Targets IDIQ Federal contract opportunity
Solicitation number
FA282325R0005
Issued by
Department of the Air Force Materiel Command Test Center

About this file

This is a Past Performance Questionnaire template for a Mobile Target program being conducted by the Air Force Test Center at Eglin AFB. The questionnaire is designed to collect performance information from references about contractors who have provided mobile land targets such as Main Battle Tanks, Tracked and Wheeled Armored Personnel Carriers, Radar Systems, Trucks, and fabricated targets.

The questionnaire consists of four sections: Contract Identification, Customer/Agency Identification, Respondent Identification, and Performance Information. The performance rating scale ranges from Exceptional to Unsatisfactory, with evaluators asked to rate contractors on 14 performance areas including technical capability, personnel management, quality control, problem resolution, delivery schedule compliance, and small business goal achievement. The questionnaire also includes specific questions about cure notices, willingness to award future contracts, and compliance with small business subcontracting requirements under FAR 52.219-8 and 52.219-9. Completed questionnaires become part of the official source selection records.

View the file

Other files for this federal contract opportunity

Other files attached to Mobile Targets IDIQ, newest first.
File Type Posted
RFIs 23 Jan 25.pdf PDF
RFIs 21 Jan 25.pdf PDF
RFIs 15 Jan 25.pdf PDF
Att 4 Mobile Targets DO 1 - Logistics Plan.pdf PDF
Att 11 Example Project 3.pdf PDF
Att 12 Pricing Worksheet.xlsx XLSX spreadsheet
Att 8 Subcontractor Consent.docx DOCX document
Att 6 App A Past Perf Info.docx DOCX document
Att 3 Draft Solicitation FA282325R0005.pdf PDF
Att 10 Example Project 2.pdf PDF
Att 9 Example Project 1.pdf PDF
Att 5 App C Financial Resp Ques.docx DOCX document
Att 2 Mobile Targets Ordering Procedures 06.14.24.pdf PDF
Att 1 Mobile Targets SOO 4.4.24.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Controlled Unclassified Information When completed, this document is Source Selection Information IAW FAR 2.101 and 3.104.

Appendix B: Past Performance Questionnaire The Air Force Test Center (OL- Eglin) [Air Force Materiel Command] is in the process of competitively selecting a source for a Mobile Target program. The Awardee will be providing mobile land targets such as Main Battle Tanks, Tracked and Wheeled Armored Personnel Carriers, Radar Systems, Trucks, and fabricated targets under this effort.

One of the considerations in proposal evaluation is the verification of the offerors' past performance on contracts or other work efforts which reflect the offeror's ability to perform on the proposed effort. We depend on information received from organizations such as yours, which have had first-hand experience with the offeror, for the evaluation of the offeror's performance on those contracts or work efforts.

Our areas of interest regarding the offeror are summarized in the enclosed questionnaire. In order to meet the acquisition milestones, we request your written response no later than [insert number of days] calendar days after your receipt of this letter [or change to specify a date, e.g., “no later than 30 Jun 15”]. This schedule will allow us sufficient time to analyze the data prior to the start of negotiations.

Please fill out the questionnaire electronically and e-mail to kristina.brannon.1@us.af.mil. Your completed questionnaire will become a part of the official source selection records.

Your assistance is greatly appreciated and your prompt response will be one of the keys to the successful and timely completion of this Source Selection.

Signature

1 Atch Past Performance Questionnaire

Section 1: Contract Identification

A. Contractor (Company/Division):

B. Contractor Cage Code:

C. Contract Number:

D. Contract Type (e.g., FFP, FPIF, CPIF, CPFF, etc.):

E. Program Title:

F. Brief Program Description:

G. Program Phase (e.g., Engineering & Manufacturing Development (EMD)):

H. Period of Performance

1. Original Schedule (assuming all options exercised):

Beginning Date _________ through ____________

2. Current Schedule (assuming all options exercised):

Beginning Date _________ through ____________

3. Reason for difference (if applicable):

I. Contract Dollar Value

1. Original maximum contract dollar value (assuming all options exercised): $

2. Current maximum contract dollar value (assuming all options exercised): $

3. Reasons for difference between original and current contract dollar value (if applicable):

J. Description of work performed:

K. Was this a competitively awarded contract? ☐ Yes ☐ No

L. Contractor’s Role: ☐ Prime Contractor ☐ Subcontractor ☐ Key Personnel

Note: If offeror holds or has held other contracts with your agency/organization in the last three (3) years, please complete separate Past Performance Questionnaire forms for those contracts as well.

Section 2: Customer or Agency Identification

A. Customer or agency name:

B. Customer or agency description (if applicable):

C. Geographic description of work performed under this contract (i.e., local, nationwide, worldwide, other Commands):

Section 3: Respondent Identification

A. Respondent’s name:

B. Respondent’s title:

C. Respondent’s phone/fax number/e-mail address:

D. Length of time (number of years/months) respondent worked on subject contract and description of responsibility/position/role:

E. Other suggested points of contact:

Section 4: Performance Information

In the table below, indicate your rating for the contractor’s performance by placing an “X” in the appropriate block to the right of each question. Provide supporting information for each response in the space provided. Attach additional pages if more space is needed. The performance rating scale is defined as follows:

Code Performance Rating

E EXCEPTIONAL – Performance meets contractual requirements and exceeds many requirements to the Government’s benefit. The contractual performance being assessed was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.

V VERY GOOD – Performance meets contractual requirements and exceeds some requirements to the Government’s benefit. The contractual performance being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

S SATISFACTORY – Performance meets contractual requirements. The contractual performance being assessed contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

M MARGINAL – Performance does not meet some contractual requirements. The contractual performance being assessed reflects a serious problem for which the contractor has not yet identified corrective actions or the contractor’s proposed actions appear only marginally effective or were not fully implemented.

U UNSATISFACTORY – Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance being assessed contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective.

N/A NOT APPLICABLE – Unable to provide a rating. Contract did not include performance for this aspect, performance was not observed, or information was not available. Do not know.

Note: The following are SAMPLE questions. Past Performance evaluation teams MUST construct a simple and concise Past Performance Questionnaire, tailored to seek out key information tied to the significant aspects of the planned acquisition. Avoid questions that can be answered with a “yes” or “no” but instead include probing and direct questions to draw out the required information desired.

The Contractor:
E
V
S
M
U
N/A

1. Provided experienced managers and supervisors with the technical and administrative abilities needed to meet contract requirements.

SUPPORTING INFORMATION:

2. Demonstrated the ability to hire, maintain, and replace, if necessary, qualified personnel during the contract period.

3. Delegated authority to project managers and supervisors commensurate with contract requirements.

4. Home office participated in solving significant local problems.

5. Provided effective quality control and/or inspection procedures to meet contract requirements.

6. Promptly executed contingency strategies for unexpected delays.

7. Provided timely resolution of contract discrepancies.

8. Identified problems as they occurred.

9. Displayed initiative to solve problems.

10. Had the required knowledge of exporting goods from foreign countries.

11. Met established delivery schedule(s)

12. Cooperated with Government personnel after award.

13. Met or exceeded small business and small disadvantaged business goals set forth in the approved subcontracting plan.

14. How would you rate the contractor's overall performance on this contract?

15. Was the contractor ever issued a cure or show cause notice under the referenced contract? If yes, explain.

EXPLANATION:

☐ Yes ☐ No

16. Would you award another contract to this contractor? If not, explain.

EXPLANATION:

☐ Yes ☐ No

IF THIS WAS A GOVERNMENT CONTRACT:

Did this contract include FAR 52.219-9, Small Business Subcontracting Plan?

☐ Yes ☐ No

If yes, did the contractor comply with the clause? Please explain.

Did this contract include FAR 52.219-8, Utilization of Small Business Concerns?

☐ Yes ☐ No

If yes, did the contractor comply with the clause? Please explain.

Additional remarks:

[click and pick the date]

Respondent’s Signature Date

Controlled Unclassified Information Page 8 of 8

File details come from the government source that posted it. Updated .