Att 4 Mobile Targets DO 1 - Logistics Plan.pdf
PDF 107 KB Posted
- Attached to
- Mobile Targets IDIQ Federal contract opportunity
- Solicitation number
- FA282325R0005
About this file
This is a Logistics Support Plan for Delivery Order #1 under the RNRT Mobile Target IDIQ contract at Eglin AFB, Florida, with a delivery date of 1 August 2024. The document outlines requirements for contractors to develop and deliver a logistics support plan for managing mobile target assets used in test and training operations by the 96th Range Support Squadron Target Systems Flight.
The plan requires contractors to detail procurement methods, oversight, and management processes tailored to their capabilities under the Mobile Target IDIQ contract. Key deliverables include one copy of the Mobile Target Logistics Support Plan to both Technical Project Manager and Program Manager, with completion required within 21 days ARO. The document specifies Distribution Statement D restrictions limiting distribution to DoD and U.S. DoD contractors only. Additional requirements include designation of a Project Manager within 7 days of delivery order issuance and strict controls on information release requiring Contracting Officer approval.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFIs 23 Jan 25.pdf | ||
| RFIs 21 Jan 25.pdf | ||
| RFIs 15 Jan 25.pdf | ||
| Att 11 Example Project 3.pdf | ||
| Att 7 App B Past Perf Ques.docx | DOCX document | |
| Att 12 Pricing Worksheet.xlsx | XLSX spreadsheet | |
| Att 8 Subcontractor Consent.docx | DOCX document | |
| Att 6 App A Past Perf Info.docx | DOCX document | |
| Att 3 Draft Solicitation FA282325R0005.pdf | ||
| Att 10 Example Project 2.pdf | ||
| Att 9 Example Project 1.pdf | ||
| Att 5 App C Financial Resp Ques.docx | DOCX document | |
| Att 2 Mobile Targets Ordering Procedures 06.14.24.pdf | ||
| Att 1 Mobile Targets SOO 4.4.24.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Mobile Target IDIQ Logistics Support Plan – Delivery Order #1
1 August 2024
1. Introduction
The 96th Range Support Squadron Target Systems Flight (RNRT) is responsible for the daily operation and management of foreign and domestic target assets used in test and training at Eglin AFB Florida.
2. Purpose
The purpose of this delivery order is to provide a logistics support plan for the implementation of a delivery order under the RNRT Mobile Target Indefinite Delivery/Indefinite Quantity (IDIQ) contract to show regular processes for procurement methods, oversight, and management processes.
3. Scope
The Contractor shall provide a logistics support plan tailored to the Statement of Objectives (SOO) that is inherent to each Contractor’s capability related to the Mobile Target IDIQ contract.
The plan shall (although not limited to) provide details of procurement methods, oversight and management methods that will be used to execute the Mobile Target IDIQ contract.
4. Technical Requirements
The Contractor shall develop and deliver a logistics support plan for the Mobile Target IDIQ contract that, at a minimum, considers the following processes and demonstrates the author’s understanding and ability to manage procurement and logistics to point of delivery.
4.1. Procurement Methods – Contractor shall define
5. Deliverables
5.1. Mobile Target Logistics Support Plan
TITLE: Mobile Target Logistics Support Plan DISTRIBUTION: One copy each to Technical Project Manager and Program Manager REMARKS: Electronic delivery by email is acceptable
5.2. Delivery Schedule - Estimated completion in twenty-one (21) days ARO
5.3. Document Marking - All documents containing technical information shall be marked as follows unless approved for public release:
Distribution Statement D: Distribution authorized to Department of Defense and U.S.
DoD contractors only (Critical Technology, 21 Sept 2023). Other requests for this document shall be referred to: US Air Force 96 RANSS/RNRT, Eglin AFB FL (850) 883-7949
6. General Information
6.1. Project Management - The Contractor shall designate a Project Manager who shall be responsible for the control and coordination of all work performed on this delivery order. The Contractor shall provide the Project Manager’s name, in writing, to the PCO within 7 days after issuance of delivery order.
6.2. Release of Information - The Contractor shall not release any information to any person, Government agency, or Contractor concerning the delivery order without the approval of the Contracting Officer.