Atch 6A - B26 PWS.pdf

PDF 268 KB Posted

Attached to
FY26 Flooring Installation Services IDIQ, MacDill AFB/Avon Park Range
Solicitation number
FA481426Q0014
Issued by

About this file

This is a Statement of Work (SOW) for carpet tile installation at Avon Park Air Force Reserve, Building 26 (Auditorium), dated 17 April 2026.

The contractor shall remove existing wall base and transitions, and furnish and install 24"x24" pressure-sensitive adhesive carpet tiles with 6-inch rubber base and transitions throughout the 2,427 square foot auditorium space (with a 108 square foot stage area excluded from the main installation zone). Work includes demolition of existing transitions and wall base, inspection and repair of existing VCT flooring to ensure proper bonding, floor preparation including stripping wax and finish and leveling with Portland-based compound as needed, and daily site cleanup with proper disposal of all debris off the Air Force Reserve. The contractor is responsible for furniture movement necessary for installation. Work must commence within 30 days of purchase order award and be completed within 60 days. If asbestos-containing materials are encountered, work must cease immediately and the Contracting Officer Representative (COR) must be notified. The contractor shall protect adjacent areas from dust and debris and maintain daily cleanup standards. The contractor must immediately notify the COR of any delays caused by carpet goods suppliers.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 6A

STATEMENT OF WORK

Avon Park AFR, BLDG #26 Carpet Tile

17 April 2026

1. SCOPE OF WORK

The work will include providing all necessary labor, equipment, transportation, materials, and support accessories, to remove existing, wall base and transitions. Contractor will be responsible for lifting or moving any furniture required for proper removal and installation of carpet. Furnish and install selected 24”x24” carpet tiles with “Pressure-sensitive” adhesive, 6-inch rubber base and transitions to match existing.

Contractor must complete work within 1 month from start date.

2. DEMOLITION

The contractor shall demo all existing transitions, and wall base in designated areas. The existing VCT to remain and encapsulated must be inspected for loose tiles to ensure existing VCT is well-bonded to the subfloor. Any loose, broken, or "popping" tiles shall be removed and the resulting gaps filled with a cement-based patching compound approved by the new flooring manufacturer. All building material shall be disposed of off Avon Park AFR.

3. FLOOR PREPARATION

If the VCT floor has significant height differences or wide grout lines, use a flooring Manufacture approved Portland-based leveling compound to create a smooth substrate. strip all wax and floor finish before installation from the existing VCT, as “Pressure-sensitive” adhesive will not bond to a waxed surface. The surface must be completely free of dirt, oil, grease, and dust. Any additional floor preparation that may be required as a result of unforeseen conditions shall be brought to the attention to the Contracting Officer Representative (COR).

4. ASBESTOS ABATEMENT

No asbestos has been recorded in this facility. Should the Contractor encounter Asbestos Containing Material (ACM) which must be disturbed, the Contractor shall cease all work that would disturb the ACM and shall immediately notify the COR.

5. SITE MAINTENANCE AND CLEANUP

a. SITE MAINTENANCE – The Contractor shall protect adjacent property, building, and their contents from dust, dirt, or other materials.

b. CLEANUP – Daily, the Contractor shall collect all trash, debris, refuse, garbage, etc., which is generated and place it in the appropriate containers with lids or approved covers.

6. LOCATION OF WORK

Work is located at building 26

7. PERIOD OF PERFORMANCE

Attachment 6A

All work is to be started within 30 days and completed within 60 days of purchase order award.

Contractor will immediately notify COR of delays due to mandated carpet goods suppliers.

Building 26: Auditorium Existing flooring VCT

Total SQ Ft.:

2,427 SQ Ft.

Stage:

108 SQ Ft. (16x6)

File details come from the government source that posted it. Updated .