Appendix F - Deliverables Schedule Project Initiation Phase.docx

DOCX document 23 KB Posted

Attached to
T2904- WIC System – Web-Based Electronic Data Processing System
Solicitation number
25DPP01188
Issued by
New Jersey

About this file

This document is a deliverables schedule for the New Jersey Department of Health's Women, Infants, and Children (WIC) System cloud migration and modernization project (Bid T2904). The schedule outlines comprehensive deliverables across six project phases: Project Initiation, Project Execution (Design, Development, and Integration Testing), Cloud Migration, User Acceptance Testing (UAT), Transition, and System Operations and Maintenance. During the Project Initiation Phase, the contractor must submit a kickoff meeting within 15 calendar days of contractor engagement start (CES), followed by the Project Work Plan, Contract Schedule, and Risk Management Plan within 45 calendar days. The Project Execution Phase requires the contractor to develop business requirement documents, functional and detailed design documents, interface control documents, system test plans and cases, and monthly and weekly status reporting, with all items subject to mutual agreement and approval by the State Contract Manager (SCM). The Cloud Migration Phase, with deliverables due within 90 calendar days of CES, includes cloud infrastructure, security, network, capacity, and disaster recovery plans; data migration plans; system architecture diagrams; and weekly and monthly status reporting, culminating in a Cloud Migration Validation Result at least three weeks before phase completion and a Cloud Migration Completion Certificate at least two weeks prior to phase end.

The UAT Phase requires the contractor to develop training plans, readiness certificates, release notes, and production implementation plans, with manuals and training materials transferred from the incumbent contractor and delivered 20-30 calendar days before UAT commencement. The Transition Phase deliverables, due within 45 calendar days of CES, include transition and staffing plans, with operations manuals and handoff certificates delivered 90 and 20 calendar days respectively before phase completion. The System Operations and Maintenance Phase requires ongoing monthly status reports, maintenance plans, daily end-of-day process reports, quarterly resource utilization reports, weekly operations meetings, and continuous system issue tracking, with transition planning for contract closeout beginning 300 calendar days before contract end and finalized 240 calendar days prior to expiration. The file does not contain pricing information, set-asides, incumbent vendor details, or funding amounts; these specifications are referenced in the broader bid solicitation T2904 for a five-year base contract with potential five-year extensions.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

The following deliverables are scheduled for the project initiation phase.

ID #
Deliverable Name
Due Date/ Frequency
1.
Kickoff meeting
15 Calendar Days after Contractor Engagement Start (CES)
To be scheduled.
2.
Project Work Plan – Final
45 Calendar Days after CES
To be created and maintained by new contractor
3.
Contract Schedule – Final
45 Calendar Days after CES
To be created and maintained by new contractor
4.
Risk Management Plan
45 Calendar Days after CES
To be created by new contractor
5.
Risk Register
45 Calendar Days after CES
To be created and maintained by new contractor
6.
Project Issue Log
45 Calendar Days after CES
To be created and maintained by new contractor

The following deliverables are scheduled for the project execution phase, including Design, Development and Integration Testing.

ID #
Deliverable Name
Due Date/ Frequency
1.
Business Requirement Document (BRD)
Mutually agreed by the SCM and the Contractor, and approved by the SCM.
To be created by new contractor
2.
Requirements Traceability Matrix (RTM)
Mutually agreed by the SCM and the Contractor, and approved by the SCM.
To be created and maintained by new contractor
3.
Detailed Functional Design Document (DFDD)
Mutually agreed by the SCM and the Contractor, and approved by the SCM.
To be created by new contractor
4.
Detailed Design Document (DDD)
Mutually agreed by the SCM and the Contractor, and approved by the SCM.
To be created by new contractor
5.
Interface Control Document (ICD)
Mutually agreed by the SCM and the Contractor, and approved by the SCM.
To be created and maintained by new contractor
6.
System Test Plan
Mutually agreed by the SCM and the Contractor, and approved by the SCM.
To be created by new contractor
7.
System Test Case and Test Data
Mutually agreed by the SCM and the Contractor, and approved by the SCM.
To be created by new contractor
8.
System Test Summary
Upon system test completion
To be created by new contractor
9.
Monthly Project Status Report
Monthly
To be created by new contractor
10.
Project Weekly Meeting
Weekly
To be created by new contractor
11.
Project Weekly Status Report
Weekly
To be created by new contractor
12.
Project Monthly Status Summary
Monthly
To be created by new contractor

The following deliverables are scheduled for the cloud migration phase.

ID #
Deliverable Name
Due Date/ Frequency
1.
Cloud Infrastructure Plan – Final
90 Calendar Days after CES
To be created by new contractor if not available at the time of contract award
2.
Cloud Security Plan - Final
90 Calendar Days after CES
To be created by new contractor if not available at the time of contract award
3.
Cloud Network Plan – Final
90 Calendar Days after CES
To be created by new contractor if not available at the time of contract award
4.
Cloud Capacity Plan – Final
90 Calendar Days after CES
To be created by new contractor if not available at the time of contract award
5.
Cloud System Cutoff Plan – Final
90 Calendar Days after CES
To be created by new contractor if not available at the time of contract award
6.
Cloud Risk Management Plan – Final
90 Calendar Days after CES
To be created by new contractor if not available at the time of contract award
7.
Cloud Disaster Recovery Plan – Final
90 Calendar Days after CES
To be created by new contractor if not available at the time of contract award
8.
Data Migration Plan
90 Calendar Days after CES
To be created by new contractor
9.
System Logical Architecture Diagram
90 Calendar Days after CES
To be transferred from incumbent contractor to new contractor and maintained by new contractor
10.
System Physical Architecture Diagram
90 Calendar Days after CES
To be transferred from incumbent contractor to new contractor and maintained by new contractor
11.
Cloud Migration Weekly Status Report
Weekly
To be created by new contractor
12.
Cloud Migration Monthly Status Summary
Monthly
To be created by new contractor
13.
Cloud Migration Weekly Meeting
Weekly
To be created by new contractor
14.
Cloud Platform Operations Manual/Helpdesk Guide
210 Calendar Days after CES
To be created by new contractor if not available at the time of contract award
15.
Cloud Migration Validation Result
At least three (3) weeks before the end of the cloud migration phase.
To be created by new contractor
16.
Cloud Migration Completion Certificate
At least two (2) weeks before the end of the cloud migration phase.
To be created by new contractor

The following deliverables are scheduled for the UAT phase.

ID #
Deliverable Name
Due Date/ Frequency
1.
Report Manual
20 Calendar Days before the start of UAT.
To be transferred from incumbent contractor to new contractor and maintained by new contractor
2.
User Manual
20 Calendar Days before the start of UAT.
To be transferred from incumbent contractor to new contractor and maintained by new contractor
3.
Training Plan
30 Calendar Days before the start of UAT.
To be created by new contractor
4.
UAT Readiness Certificate
At least 3 Calendar Days before the start of UAT release.
To be created by new contractor
5.
Production Readiness Certificate
At least one (1) week before the start of production release.
To be created by new contractor
6.
Release Notes (for UAT, and Production only)
One (1) week before the deployment of changes to UAT or production.
To be created by new contractor
7.
Production Implementation Plan
20 Calendar Days before the deployment of changes to production.
To be created by new contractor
8.
Project Monthly Status Report
Monthly
To be created by new contractor
9.
Project Weekly Meeting
Weekly
To be created by new contractor
10.
Project Weekly Status Report
Weekly
To be created by new contractor
11.
UAT Issue Log
Daily
To be created by new contractor

The following deliverables are scheduled for the transition phase.

ID #
Deliverable Name
Due Date/ Frequency
1.
Transition Plan (Incoming) - Final
45 Calendar Days after CES
To be created by new contractor
2.
Staffing Plan – Final
45 Calendar Days after CES
To be created by new contractor
3.
Business Continuity Plan – Final
45 Calendar Days after CES
To be transferred from incumbent contractor to new contractor and maintained by new contractor
4.
Operations Manual/ Helpdesk Guide
At least 90 Calendar Days before the end of the transition phase.
To be transferred from incumbent contractor to new contractor and maintained by new contractor
5.
System Handoff Certificate
At least 20 Calendar Days before the end of the transition phase.
To be created by new contractor
6.
Monthly System Operations Status Report
Monthly
To be created by new contractor

The following deliverables are scheduled for the system operations and maintenance phase.

ID #
Deliverable Name
Due Date/ Frequency
1.
Monthly System Operations Status Report
Monthly
To be created by new contractor
2.
Monthly Maintenance Plan
Monthly
To be created by new contractor
3.
End-of-Day (EOD) Processes Report
Daily
To be created by new contractor
4.
Quarterly Resource Utilization Report
Quarterly
To be created by new contractor
5.
Weekly Operations Meeting
Weekly
To be created by new contractor
6.
System Issue Tracker
Ongoing
To be created and maintained by new contractor
7.
Transition Plan (Outgoing) – Draft
300 Calendar Days before the Contract ends
To be created by new contractor
8.
Transition Plan (Outgoing) – Final
240 Calendar Days before the Contract ends.
To be created by new contractor