APPENDIX 3

TIME ALLOWED FOR COM AND MAJOR REPAIR

The time allowed for COM and major repair shall be computed by using Calendar days (weekends count in calculations). Allowable downtime elements are as follows:

a. COM unit (maintenance only)2 days
b. COM cleaning1 day
c. Major paint over 200 sq. ft. (including interior and exterior)2 days
d. floor replacement over 200 sq. ft.2 days
e. Texturing walls/ceilings & texture removal2 days
f. Ceramic tile installation (all sq. ft.)2 days
g. Countertop and splash back replacement1 day
h. Add icemaker water line for refrigerator1 day
i. Carpet repair/cleaning (all sq. ft.)1 day
j. Refinish cabinets (more than 100 sq. ft.)1 day
k. Replace/reface cabinets4 days
l. Patch excessive number of holes in walls (COR discretion)1 day
m. SOQ (437, 1078, 1017, 1065)1 day
n. Stand-alone unit GOQ/SOQ (1070, 1080, 1081)2 days

An example of total allowable downtime is:

COM2 days
Paint (over 200 SF) Clean

Carpet Cleaning

2 days 1 day 1 day 6 days

Vinyl Tile replacement Total downtime allowed

2 days 8 days