Appendix 3 - Time Allowed for COM and Major Repair.docx
DOCX document 18 KB Posted
- Attached to
- Military Family Housing, Osan AB, ROK
- Solicitation number
- W91QVN-22-R-0001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W91QVN-22-R-0001-0003.pdf | ||
| Appendix 13 - CCTV (Revision 1).pdf | ||
| Amendment 0002 PWS (Revision 1).pdf | ||
| W91QVN-22-R-0001-0002.pdf | ||
| W91QVN-22-R-0001-0001.pdf | ||
| Appendix 2 - Service Call Categories.docx | DOCX document | |
| Appendix 6 - Facilities List.docx | DOCX document | |
| Performance Work Statement.docx | DOCX document | |
| Appendix 9 - Cleaning Frequency and Standards.docx | DOCX document | |
| Appendix 4 - COM Service Call and Recuring Items.docx | DOCX document | |
| Appendix 13 - CCTV.xlsx | XLSX spreadsheet | |
| Appendix 5 - Preventive Maintenance (PM) Requirements.docx | DOCX document | |
| Appendix 12 - HVAC Preventive Maintenance Checklist.docx | DOCX document | |
| W91QVN-22-R-0001.pdf | ||
| Appendix 11 - Change of Occupancy Maintenance (COM) Checklist.docx | DOCX document | |
| Appendix 1 - Historical Workload Data (Oct 2016 thru Apr 2021).xlsx | XLSX spreadsheet | |
| Appendix 7 - Standard Definitions.docx | DOCX document | |
| Appendix 10 - Contract Data Requirement List (CDRL).docx | DOCX document |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
APPENDIX 3
TIME ALLOWED FOR COM AND MAJOR REPAIR
The time allowed for COM and major repair shall be computed by using Calendar days (weekends count in calculations). Allowable downtime elements are as follows:
| a. COM unit (maintenance only) | 2 days | |
| b. COM cleaning | 1 day | |
| c. Major paint over 200 sq. ft. (including interior and exterior) | 2 days | |
| d. floor replacement over 200 sq. ft. | 2 days | |
| e. Texturing walls/ceilings & texture removal | 2 days | |
| f. Ceramic tile installation (all sq. ft.) | 2 days | |
| g. Countertop and splash back replacement | 1 day | |
| h. Add icemaker water line for refrigerator | 1 day | |
| i. Carpet repair/cleaning (all sq. ft.) | 1 day | |
| j. Refinish cabinets (more than 100 sq. ft.) | 1 day | |
| k. Replace/reface cabinets | 4 days | |
| l. Patch excessive number of holes in walls (COR discretion) | 1 day | |
| m. SOQ (437, 1078, 1017, 1065) | 1 day | |
| n. Stand-alone unit GOQ/SOQ (1070, 1080, 1081) | 2 days |
An example of total allowable downtime is:
| COM | 2 days | |
| Paint (over 200 SF) Clean |
Carpet Cleaning
2 days 1 day 1 day 6 days
Vinyl Tile replacement Total downtime allowed
2 days 8 days