PN-020_Pre-Bid Conf_01-27-10
3 MB Posted
- Solicitation number
- AG-3K15-S-10-0005
About this file
Pre-Proposal Minutes - List of Attendees
Text of this file
5005 SW Meadows Road, Suite 100
Lake Oswego, OR 97035
1.503.624.3000 1.503.624.3134 Fax Project Note
Project Note 020
| -CLIENT |
| U.S. Dept. of Agriculture |
| NOTE NO. |
| PN020 |
| PROJECT |
| Recovery – Major Renovations, Phases 3 thru 6, WRRC |
| PROJECT NO. |
| 25KT8810 |
| Confirmation of |
| x |
| MEETINGS |
| Date Held |
| January 27, 2010 |
telecon
| Date issued |
| February 01, 2010 |
| OTHER |
| Recorded by |
| Paul Verbout |
| Place |
| USDA, WRRC, Albany, CA |
| Subject |
| Pre-Proposal Conference |
Participants: (* via phone) -
USDA
Ronda Ford
Tom Moreno
Rebecca Haussmann
Clarice Dixson Howard Zhang (part-time)
Jacobs
Greg Owen
Paul Verbout
Anthony DeSimone
John Westwood
Prospective Bidders
See attached list
ADDITIONAL DISTRIBUTION:
USDA
Ken Cook
Dr. Bill Orts
Dr. Hammond
Bob Matteri
Tara McHugh James Pan
Stanley Green
Jeff VanHouten Carolyn Williams
Sara Hake
Jerry Mayer
David Orong Lone Santacera
Fred Brown
Steve Douglass
Sam Gadzik Jacobs
Bob Patterson
Kathy Scheel
Mike Wang
Thong Tran
Adam Green
Bob Wallace
Tom Goldsmith
| ITEM |
| STATUS |
| ACTION BY |
| PN20.1 |
| Ronda Ford, the Contracting Officer (CO), introduced the attendees and described the purpose of the meeting to kickoff the Pre-Proposal Conference and conduct a job walk for contractors. Photos are acceptable for the job walk to be directed by Tom Moreno. [Note: All PowerPoint presentations from today’s conference will be posted on USDA’s Sharepoint website; and transferred to FedBizOps as appropriate.] |
| Info |
| PN20.2 |
| Ronda Ford stated that important research is conducted here for safe foods. Minimal disruptions to research are a priority. |
| Info |
| PN20.3 |
| Questions raised at this conference must be submitted in writing (utilizing the provided form) or via email to kathy.scheel@jacobs.com with a copy to ronda.ford@ars.usda.gov and the solicitation number referenced in the subject line. Questions are acceptable up to Feb 04, 5:00 pm, Pacific time; responses will be provided via an Amendment posted on FedBizOps at a later date. |
| Info |
| PN20.4 |
| A sign-in list for today’s conference was distributed for attendees, requesting name, company and email address. |
| Info |
| PN20.5 |
| Ronda Ford explained that project phasing is reduced from 6 phases to 4 “Sequences”. |
| Info |
| PN20.6 |
| Ronda Ford explained Request for Proposal (RFP) process and indicated that construction/performance time is 900 days. |
| Info |
| PN20.7 |
| Ronda Ford stated that 15% of work will be performed by the General Contractor. |
| Info |
| PN20.8 |
| Ronda Ford said selection will be based on best merit using a scoring system and provided an explanation of the evaluation method. |
| Info |
| PN20.9 |
| Ronda Ford will provide Homeland Security review forms for contractor personnel for Federal facilities. |
| Info |
| RF |
| PN20.10 |
| Ronda Ford indicated the technical proposal process requirement is posted on Fed BizOps. |
| Info |
| PN20.11 |
| Ronda Ford asked if any contractor had any electronic problems downloading drawings, specs and project requirements. No comments were voiced. |
| Info |
| PN20.12 |
| Dr. Zhang (USDA) explained the ongoing research and the importance of this research to nationwide agriculture production. Research must continue simultaneous with construction. Renovation must respect functioning systems. He thanked everyone and looks forward to working with the selected contractor in the future. |
| Info |
| PN20.13 |
| Greg Owen (Jacobs) gave a presentation on project sequencing and a high level overview of the project. Sequence and scheduling with be coordinate with the site personnel. The specs and drawings will be followed closely. |
| Info |
| PN20.14 |
| Greg Owen noted that bid preparation must consider sheets G004 and G005. |
| Info |
| PN20.15 |
| Base Bid and two Bid Options: |
Bid Option 1: PGEC balconies
Bid Option 2: Reroof all of FPL and IPL Info
| PN20.16 |
| Owen discussed swing spaces for maintaining equipment as operational during construction. New equipment will purchased before removal of existing equipment and commissioning of equipment will be required. |
| Info |
| PN20.17 |
| Owen noted the integration of construction activities with the Government’s website, SharePoint. |
| Info |
| PN20.18 |
| Owen indicated the Hazardous materials side of the work and plan for remediation. |
| Info |
| PN20.19 |
| Eloy Cisneros (ATC Associates) presented the hazardous materials overview: lead-based paint, asbestos, etc. Regulations were discussed and materials identified. Specification guidelines will be strictly enforced. Monitoring will be performed and stop work authority is authorized by USDA. |
| Info |
| PN20.20 |
| Job walk directed by Tom Moreno (USDA Facilities Engineer) and Greg Owen (Jacobs Project Manager) started at 11:00 am and ended at 1:15 pm. The group visited the Overpass Building, the new steam line path, the Food Processing Lab (FPL), the Industrial Process Lab (IPL), the roof, the Renovated Equipment Relocation Area (RERA), including the Autoclave suite. |
| Info |
The foregoing conveys our understanding of the conversations and decisions reached during this meeting. We shall assume the above to be a reasonably correct and accurate representation unless written notice to the contrary is received by this office within seven working days of receipt of these meeting minutes.
Attachment:
· List of Prospective Bidders in attendance
· PowerPoint presentations: Ronda Ford, Greg Owen, Eloy Cisneros
EMBED PowerPoint.Show.8
EMBED PowerPoint.Show.8
PROSPECTIVE BIDDERS ATTENDING PRE-BID CONFERENCE (1-27-10):
| Company (alpha order) |
| Name of Representative |
| Email Address |
| AFM Environmental, Inc. |
| Al Hardwick |
| afmenviro@aol.com |
| Alarcon Bohme/Bohme Environ. |
| Ron Rentrop |
| rrentrop@alarconbohme.com |
| Allied Environmental |
| Larry Price |
| lpallied@sbcglobal.net |
| Alten Construction Inc. |
| Cliff Poulton |
| bids@altenconstruction.com |
| Arntz Builders, Inc. |
| Tom Arntz |
| Tom@arntzbuilders.com |
| Asbestos Management Group |
| Chris Davini |
| cdavini@amgofca.com |
| Best Contracting Services |
| Chris Gonzalez |
| valeriel@bestcontracting.com |
| Big Sky Fire |
| Lloyd Kuehne |
| lkuehne@bigskyfireprotection.com |
| Biltwell |
| Mike Hendrickson |
| BDCEPP@aol.com |
| Biltwell |
| Paul Epp |
| BDCEPP@aol.com |
| Brayer Electric |
| Albert Martinez |
| albert@brayerelectric.com |
| Campanella Corp. |
| Mike Littlefield |
| mikeL@campanellacorporation.com |
| Cal West Concrete Cutting |
| Sean Birch |
| Sean.birch@calwestcci.com |
| Cal-West Concrete Cutting |
| Ron Hunt |
| RonH@calwestcci.com |
| C. Overaa & Co. |
| William Rogan |
| willr@overaa.com |
| C. Overaa & Co. |
| Jennifer Sebay |
| Jennifers@overaa.com |
| Cosco Fire Protection |
| Gary Mahal |
| gmahal@coscofire.com |
| C.R. Acoustics |
| Chip Redding |
| CRAcoustics@frontier.net |
| CST Environmental, LP |
| Frank Leyva |
| fleyva@cstenv.com |
| Daleys Drywall |
| David Emery |
| emery@daleysdrywall.com |
| Demo Masters |
| Dennis lee |
| dlee@demomaster.com |
| DDR Mechanical |
| Dave Abscher |
| daviddk@sbcglobal.net |
| Doherty Restoration |
| Natalie Guilbault |
| Natalie@dohertyrestoration.com |
| DWG & Associates |
| Steve Simoulis |
| steves@DWG1.com |
| Eco-Bay Services |
| Scott Laird |
| scott@ecobayservices.com |
| Ferma Corp. |
| Mike ruff |
| MRuff@formacorp.com |
| GCS |
| David Eary |
| gcsdke@comcast.net |
| Geneva Scientific |
| John Uriakis |
| john@geneva-scientific.com |
| Glazier Iron Works |
| Rod Mord |
| rmord@glazierironworks.com |
| Hazmat Solutions |
| Mike Volatile |
| mvolatile@hazmatsolutions.com |
| ISEC |
| Jason Pollard |
| jmpollard@isecinc.com |
| Janus Corporation |
| Paul Chelstowski |
| paul@januscorp.com |
| J.S. Company |
| Kurt Sears |
| ksears@eltopia.com |
| LVI Facilities |
| Rudy Iniguez |
| riniguez@lviservices.com |
| LVI Services |
| Jack Hesotian |
| jhesotian@lviservices.com |
| Marelich Mechanical |
| Andy Beering |
| A.Beering@marelich.com |
| NV Heathorn |
| Steve Larsen |
| slarsen@nvheathorn.com |
| Oltman’s |
| Mark McClelland |
| markm@oltmans.com |
| Oltman’s |
| Ed Gorton |
| edg@oltmans.com |
| Pacific Power & Systems |
| Mike Messer |
| mike@pacificpowersystem.com |
| PARC Services |
| John Dockin |
| jgparcba@pacbell.net |
| Performance Abatement (PAS) |
| William Elbert |
| Bill.elbert@PCG.com |
| Peterson Mechanical |
| Mike Payne |
| MikeP@petersonmechanical.com |
| RCM Fire |
| Ali Namdar |
| anamdar@rcmfire.com |
| Reinhardt Roofing |
| David Moreno |
| david@reinhardtroofing.net |
| Restec Contractors |
| Geoffrey Larson |
| glarson@ansonindustries.com |
| Restec Contractors |
| Jose Acosta |
| Jacosta@ansonindustries.com |
| RH Co (Russell Hinton) |
| Matt Mengarelli |
| mmengarelli@russellhinton.com |
| Rodan Builders |
| Paul Becker |
| rbucio@rodanbuilders.com |
| Roebbelen |
| Janette Yamamoto |
| jazmynd@roebellen.com |
| San Joaquin Steel |
| Fred Vaughn |
| www.sjs-steel.com |
| San Francisco Interiors (SFI) |
| Victor Silva |
| victor@sfinteriors.com |
| Sasco |
| Alex Turner |
| aturner@sasco.com |
| Simplex Grinnell |
| Reg Reed |
| RegReed@simplexgrinnel.com |
| Southwest Hazard Control |
| David Mouser |
| dmouser@swhaz.com |
| Sterling Environmental Corp. |
| Matt Jensen |
| mjensen@sterlingenv.com |
| Stonhard |
| Bill Carpenter |
| bcarpenter@stonhard.com |
| Swinerton Builders |
| David Green |
| dgreen@swinerton.com |
| Swinerton Builders |
| Gary Bernardini |
| gbernardini@swinerton.com |
| Swinerton Builders |
| Peter Schoen |
| pschoen@swinerton.com |
| Thomas D. Eychner Co. |
| Brian Eychner |
| Eychnerco@sbcglobal.net |
| TM Demolition |
| Tarcio Mascarenhas |
| tarcio@tmdemolition.com |
| Tremco/WTI |
| Richard N. Egan |
| R5Egan@aol.com |
| W. Bradley Electric |
| Blaine Clinton |
| bclinton@wbeinc.com |
| Webcor Builders |
| John Egelston |
| jegelston@webcor.com |
| Western Roofing Service |
| George T. O’Neill |
| george@westroof.com |
| Young Electric |
| Joseph Browne |
| josephfbrowne@comcast.net |
_1326187380.ppt
Albany, California Facility
Hazardous Materials Work
Presented by: Eloy F. Cisneros, CMC, CAC, CLIA Director of Industrial Hygiene
Notes:
Hazardous Materials:
Asbestos containing materials
Lead containing paints and coatings
Universal wastes
PCB ballasts
Mercury tubes
Albany, CA Facility
Hazardous Materials:
Pre-construction submittals
Work plan
Disposal plan
Certifications/licenses
Asbestos Regulations:
The handling, disturbance, removal and disposal of asbestos is regulated by the EPA and OSHA.
EPA:
BAAQMD – NESHAP Regulation
CAL-EPA DTSC – Hazardous Waste
OSHA
DOSH (Cal-OSHA) – Construction Standard
Asbestos On-Site:
Identified materials:
Textured Flooring
Pipe Insulation Materials 2” to 8” diameter
Wallboard and Joint Compound
TransiteTM Fume Hoods
Cold Room Insulation Coatings (Various)
Autoclave Insulation
Additional suspect materials in un-surveyed/ un-impacted areas
All construction-impacted materials will be removed.
Asbestos Controls:
Strict Specifications and Strict Enforcement
Restricted work areas
Signs
Barriers
Negative-Pressure Containments
Glove-bags
Decontamination units
Asbestos Work Practices:
Challenge tested H.E.P.A. Filtration
Certified Asbestos Workers
Competent Person
Wet Methods (Surfactants)
Prompt Cleanup
Continuous Project Oversight and Air Monitoring
Asbestos Monitoring:
Inspect/Smoke Test Containment
Verify Negative-Pressure Continually
Coordinate with W.R.R.C. Facilities’ Staff
Third-Party Oversight of Procedures
CAC/SST with “Stop-Work Authority”
Daily Perimeter PCM Air Monitoring
On-Site Reading of Perimeter Samples
Visual Inspection and PCM Clearances
Lead Regulations:
The handling, disturbance, removal and disposal of lead is regulated by the EPA and OSHA.
EPA:
DPH – Lead Hazards
CAL-EPA DTSC – Hazardous Waste
OSHA
DOSH (Cal-OSHA) – Construction Standard
Lead On-Site:
All Coatings Tested had Detectable Lead
LBP is > 5000 PPM or >1.0mg/cm2
Paint Chip Samples Ranged 114 ppm to 176,000 ppm
XRF Samples Ranged from below detectable limit to >9.9 mg/cm2
Additional suspect materials in un-surveyed/ un-impacted areas
All construction-impacted coatings will be removed.
Lead Controls/Work Practices:
Strict Specifications and Strict Enforcement
Restricted work areas
Signs
Barriers
Containments
Decontamination units
Challenge Tested HEPA Filtration
Continuous Project Oversight and Monitoring
Lead Monitoring:
Inspect Containment
Third-Party Oversight of Procedures
DPH I/A or PM with “Stop-Work Authority”
Daily Perimeter Monitoring
Quick Laboratory Turn-Arounds
Visual Inspection and Wipe-Sample Clearances
Thank You !
_1326187381.ppt
Western Regional Research Center
(WRRC)
Major Renovations – South Wing
Pre-Proposal Conference
27 January 2010
Admin Remarks
Silence all Cell phones and pagers
No recording devices allowed
Photographs may be taken during the site visit
Rest Room Facilities
Site Visit Etiquette
This presentation and an attendee list will be posted on the FedBizOps website
AGENDA
0900 Arrival/Sign-In
0915 Admin Remarks/Agenda/Introductions
0930 Project/RFP Overview (Sections A-K)
1000 Program & Technical Overview
1030 Site Visit
1230 Adjourn
Key Personnel
Ronda Ford – Contract Specialist (Beltsville, MD)
Ken Cook – Engineering Project Mgr (Beltsville)
Tom Moreno – Facility Engineer (WRRC – Albany)
Adam Salvadalena – PWA Engineer (Albany)
Dr. Howard Zhang – WRRC Director (Albany)
Greg Jacobs – Jacobs Engineering (A&E Firm)
WRRC Mission
To enhance healthfulness of foods by creating crop plants and food products that promote health, and by developing systems and methods that ensure the safety of the food supply.
To develop new food and industrial products using biotechnology to develop improved, tailored agricultural crops and bioengineering to create new products from agricultural crops and processing co-products.
To protect and enhance the quality of the environment by developing ecologically sound methods for pest control and environmentally sound systems for efficient food and industrial processes.
To ensure the effective transfer of new and innovative technologies by integrating technology transfer into program and project design and developing partnerships with private and public sector clients.
Improve the understanding of the Government’s requirement
Allow potential offerors to judge whether or how they can satisfy the Government’s requirements
Enhance the Government’s ability to obtain quality construction at reasonable prices
Increase efficiency in proposal preparation, proposal evaluation, negotiation and contract award
Purpose of Conference/Site Visit
Questions raised at this conference must be submitting in writing (utilizing the provided form) or via email to kathy.scheel@jacobs.com with a copy to ronda.ford@ars.usda.gov and the solicitation number referenced in the subject line
Deadline for submission of questions is NLT 4 February 2010
All questions will be answered via an amendment to the solicitation and posted on FedBizOps
In order to maintain procurement integrity please avoid one on one conversations with Government/A&E personnel
Questions
Disclaimer
In the event that there is a conflict between the RFP terms and conditions and the information that is disseminated during today’s conference, the RFP terms and conditions takes precedence.
The formal RFP is the only document that should be relied upon in determining the Government’s requirements.
Any changes to the RFP will be with a formal amendment.
Project Overview
Background
The original WRRC structure was constructed in the 1930’s and 1940’s.
The original project modernization design consisted of 6 phases of construction. Phase 1 and 2 construction was completed in May 2004. Phase 3A construction was completed in November 2008.
This project includes the renovation of four floors (45,000 GSF) of the existing south wing, renovations in the existing administrative wing basement, upgrades to an existing exterior steam line, and renovations in the existing overpass building.
Project Overview
The proposed renovations include lead and asbestos abatement, architectural, mechanical, plumbing, electrical, the provision and movement of large, fixed scientific equipment and life safety system for the remaining design phases, known as Phase 3B, 4A, 4B, 5, and 6, in addition to other miscellaneous renovations. In addition, the work includes the re-commissioning of Phases 1, 2, and 3A.
The work shall be conducted in four sequences, numbered 1 thru 4, as indicated in the contract drawings and specifications. Each sequence will be inspected, commissioned, and accepted separately.
The schedule of items will include a base item and 2 optional items. The base item will encompass work primarily associated with sequences 1-3, option item 1 work is primarily associated with sequence 4 and option item 2 includes work to complete a new roofing system for the south wing.
RFP Overview
RFP OVERVIEW
Section A - Proposal
Standard Form 1442 - Complete blocks 14, 15, 16, 17, 19, 20a, 20b, 20c (Note: Refer to block 13D before completing block 17)
Section B – Schedule of Items
B.2 Identifies the base item and 2 option line items. Prospective offerors must propose on all items (base and option)
B.3 Identifies performance time at 900 calendar days
Section C - Specifications
Attachment in Section J – Identifies work disciplines (mechanical, electrical, etc.) by divisions
Section F - Deliveries or Performance
F.2 Liquidated Damages is $1,250.00 for each calendar day of delay
F.4 Performance of Work by the contractor shall be at lease 15 percent
Section H – Special Contract Requirements
H.25 Key Personnel, insert names of proposed key personnel
Section I – Contract Clauses
I.1 FAR 52.203-15 Whistleblower Protections Under American Recovery and Reinvestment Act
I.1 FAR 52.204-11 American Recovery and Reinvestment Act – Reporting Requirements
I.1 FAR 52.215-2 Audit and Records – Negotiation, Alternate I
I.6 FAR 52.225-23 – Required use of American iron, steel, and other manufactured goods – Buy American Act – Construction
Section J (Attachments)
1 Wage Determination(s), CA 20070029, mod 40, Dated 11/13/2009
2 Bid Bond, SF-24
3 Performance & Payment Bonds, SF-25 & 25a
4 Disclosure of Lobbying Activities, SF-LLL & LLLa
5 Construction Progress and Payment Schedule, ARS-371
6 Contractor’s Request for Payment Transmittal, ARS-372
7 Past Performance Evaluation Form
8 Specifications
9 Drawings
Section K (Representations and Certifications)
Online Representations and Certifications Application (ORCA)
Section L – Instructions, Conditions and Notices to Offerors
L.2 Data Universal Numbering System (DUNS NUMBER) – Enter DUNS number in block 14 of SF 1442 (company name/address)
L.3 Instructions to Offerors – Competitive Acquisition – Provides instructions concerning the procedures relative to this type of procurement
L.10 Bid Guarantee (FAR 52.228-1) – Failure to furnish a bid guarantee in the proper form and amount , by the time set for submission of proposal may be cause for rejection of the proposal.
Section M – Evaluation Factors for Award
M.2 Criteria for Evaluation Proposals – Provides values assessed to specific evaluation factors and sub-factors. When all evaluation factors are combined they are approximately equal to cost or price
M.3 Award will be made to the responsible offeror whose proposal presents the “best value” to the Government, which may not necessarily be the proposal offering the lowest price nor the highest technical score
Overview of
Sections L & M, Evaluation Process
Sections L and M
Understanding and following Section L&M are the keys to developing a good proposal; a mutually beneficial goal for award
Proposal Instructions – Section L of the RFP:
Tells Offerors what to include in the proposal
Evaluation Factors – Section M of the RFP:
Identifies how Offerors will be evaluated
TECHNICAL PROPOSAL
Technical Proposal – evaluate and determine whether a proposal will meet Government requirements, includes;
(1) Relevant Project Experience and Past Performance
(2) Key Personnel
(3) Contract Administration
(4) Schedule and Resources
(5) Small Disadvantaged Participation Program
EXPERIENCE
Prime Contractor experience on 5 projects within the last 5 years of similar size, scope, function, and complexity
Experience with new construction and renovations, ability to manage multiple projects - emphasis on research laboratory type facilities
Government experience is desired but not required.
PAST PERFORMANCE (reference Form SF 1420)
Conformance to specifications and standard of workmanship
Adherence to contract schedules
History of reasonable, cooperative behavior and responsiveness to customer needs
Coordination and management of subcontractors
Note: Government Past Performance databases will also be utilized
KEY PERSONNEL (Staffing Plan)
Identify key construction and management personnel - their level authority - relationship to the company - their roles in recent relevant projects
Distinguish between in-house staff and subcontractors
Identify number of present employees and their roles
Identify number of new hires
KEY PERSONNEL (Personnel Qualifications)
Resumes for;
Project Manager
Site Superintendent
Quality Control Manager
Safety Officer
CONTRACT ADMINISTRATION – Administrative Approach
Administration of contract /subcontract
CPM scheduling
Maintaining records
Administration of quality control program and related inspection
Commissioning
Close out/turn over
Quality Control Plan/Commissioning
Description of the plan and process methodology
Personnel qualifications and reporting requirements
Approach to meeting commissioning requirements
Subcontractor –
Provide names of 1-3 potential contractors specifically for;
Mechanical Controls Test and Balance
Plumbing Electrical
Fire Alarm Hazardous Abatement
Stucco Window
Roofing Concrete
Structural Steel Scientific Equipment Vendors
Subcontractor (cont’d) –
- address subcontractor management with respect to work schedule, change order requests, quality of work, adherence of labor standards
- methods to select subcontractors/number of prior projects with each
Note: For any resultant contract, subcontractors utilized shall be those presented in the offer
Schedule –
Define project scheduling capabilities
Provide schedule for proposed project (50-100 activities)
Identify significant work segments and critical path items, including material & equipment
Work Plan Approach –
Narrative of approach, identifying assumptions made to develop schedule
- Describe understanding of construction sequencing
Describe alternate strategies to mitigate schedule problems
Resources -
Facility information
Technological information
Office automation capabilities
Software capabilities (must be compatible with gov’t)
Manufacturers -
Provide names of 1-3 potential manufactures for;
growth chambers growth rooms cold rooms proctor dryer chiller roofing system direct digital control system fire detection & alarm system
Note: For any resultant contract, equipment shall be provided from the manufacturers presented in the offer
Cost Proposal –
Shall be submitted separate from the Technical Proposal in order for the Technical Proposal to be evaluated solely upon the basis of technical merit, independent of dollars values
Each Offeror’s cost proposal shall be evaluated to determine if it is complete, consistent and reasonable with the Offeror’s technical approach, reflects a clear understanding of the solicitation requirements and contains no material imbalances.
Supporting Documentation – Cost Proposal shall list all required tasks, labor categories and fully burdened hourly rates; a breakdown of all direct costs, or any other indirect cost; travel and material costs; and contractor’s overhead and profit
COST /BUSINESS PROPOSAL
Section M - Evaluation Criteria Value
1. RELEVENT PROJECTEXPERIENCE AND PAST PERFORMANCE 40
a. Experience (20)
b. Past performance (20)
KEY PERSONNEL 20
a. Staffing Plan (10)
b. Personnel Qualifications (10)
3. CONTRACT ADMINISTRATION 15
a. Administrative Approach (5)
b. Quality Control/Commissioning Plan (5)
c. Subcontractor (5)
SCHEDULE AND RESOURCES 20
a. Schedule (5)
b. Work Plan Approach (5)
c. Resources (5)
d. Manufacturers (5)
5. SMALL DISADVANTAGED BUSINESS PARTICIPATION PROGRAM 5
TOTAL POSSIBLE TECHNICAL POINTS 100
UNKNOWN-0.bin
UNKNOWN-1.bin
_1326187296.ppt
Major Renovations – South Wing Pre-Proposal Conference
USDA WRRC, Albany, CA
January 27, 2010
Project Team
Greg Owen Project Manager
Anthony DeSimone Mechanical Engineer
John Westwood Electrical Engineer
Paul Verbout Architect
Tom Goldsmith Telecommunications
Mike Wang Structural Engineer
Thong Tran Life Safety
Adam Green I & C
Kathy Scheel Project Coordinator
Project Scope
Project Scope
Construction Sequence
High Level Definition of Scope and Construction Sequence Shown on:
G004
G005
Sequence broken into four definable parts
Base Bid + Two Bid Options
Contractor to provide there Construction Sequencing Approach for the Project
Sequence 1
Sequence 2
Sequence 3
Bid Option 2
Sequence 4
Bid Option 1
Design Hot Topics
Research Equipment
Growth Chambers and Rooms
Autoclaves
Cold Laboratories
Tray Dryer
Construction Sequence Dependent
Start-up and Commissioning of Research Equipment
Commissioning
As Defined in Specs and Drawings
Re-Commissioning of Phase 1, 2 and 3A Required as Defined in Sequence 1 (re G004)
Anthony DeSimone will Support Commissioning / Re-Commissioning at the Site
Project Coordination
Working Facility
Coordination with Center Personnel
After Hours Work
Section 01040
Project Schedule
CPM Baseline Schedule
Bi-Weekly Updates to Progress Schedule
Schedule indicated percentage complete
Section 01310
Submittals
Submittal Schedule
Timeliness
Section 01330
Web Based Construction Management
Sharepoint Web Site
Section 01322
Hazardous Materials
“H” Drawings in Base Bid and Optional Items
Section 13281 - Asbestos
Section 13283 - Lead Containing Paint
Section 13286 – PCB’s and Mercury
Hazardous Material Consultant
Eloy Cisneros ,ATC Associates, Inc
Keys for Success
Work Sequence and Scheduling
Coordination with Site
Follow Specs and Drawings
Questions
Other files
Show all 48
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .