022250-Minor Demolition for Remodeling.doc

DOC document 28 KB Posted

Attached to
RECOVERY Replace Annex Building HVAC, Beneficial Insects Introduction Research Unit (BIIRU), Newark, DE
Solicitation number
AG-3615-S-10-0001
Issued by

About this file

J.1 -02 SPECIFICATIONS - FILE 8

View the file

Other files

File Type Posted
SF-30 Amendment 03.pdf PDF
BiddersSign-InSheet.pdf PDF
sf-30 amend 02.pdf PDF
of 17.pdf PDF
SF-30 AMEND NO 01.pdf PDF
SF 30 AMEND NO 02.pdf PDF
AG-3615-S-10-0001 newark replace annex hvac IFB amend 02 COVERLETTER.docx DOCX document
260502_Minor Electrical Demolition.DOC DOC document
013300 Submittal Procedures.doc DOC document
230593_Testing Adjusting and Balancing for HVAC Systems.doc DOC document
260526_Grounding Bonding for Electrical Systems.DOC DOC document
230553_Identification for HVAC Piping and Equipment.DOC DOC document
2003.162.031-USDA-TS-22x34-Model.PDF PDF
DE6.dvb DVB file
095100_Acoustical Ceilings.DOC DOC document
SF-LLL FORM.pdf PDF
238113_Packaged Terminal Air Conditioners.DOC DOC document
230513_Common Motor Requirements For HVAC Equipment.DOC DOC document
2003.162.031-M101-USDA 22x34.PDF PDF
260529_Hangers Supports for Electrical Systems.DOC DOC document
230500_Common Work Results For HVAC.doc DOC document
260519_Low-Voltage Electrical Power Conductors Cables.DOC DOC document
099000-Paints and Coatings.doc DOC document
2003.162.031-A101-USDA 22x34.PDF PDF
260553_Identification for Electrical Systems.DOC DOC document
NEWARK RECOVERY - UPGRADE ANNEX BUILDING HVAC FAC 2005-37.DOCX DOCX document
AG-3615-S-10-0001 newark replace annex hvac IFB COVERLETTER.docx DOCX document
013000 Administrative Requirements.doc DOC document
233300_Air Duct Accessories.DOC DOC document
283111 Digital Addressable Fire Alarm System.DOC DOC document
017000 Execution and Closeout Requirements.doc DOC document
014000 Quality Requirements.doc DOC document
233713_Diffusers Registers Grilles and Louvers.DOC DOC document
260533_Raceway Boxes for Electrical Systems.DOC DOC document
2003.162.031-Specification Cover.pdf PDF
230700_HVAC Insulation.doc DOC document
2003.162.031-M201-USDA 22x34.PDF PDF
233113_Metal Ducts.DOC DOC document
2003.162.031-E101-USDA 22x34.PDF PDF
016000 Product Requirements.doc DOC document
2003.162.031-M001-Layout.PDF PDF
2003.162.031-M102-USDA 22x34.PDF PDF
2003.162.031-M202-USDA 22x34.PDF PDF
000110ST - Table of Contents.doc DOC document
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 022250 -MINOR DEMOLITION FOR REMODELING

PART 1 GENERAL

1.1 SUMMARY

A. Section includes removal of designated building equipment and fixtures; removal of designated construction; dismantling, cutting and alterations for completion of the Work; disposal of materials; storage of removed materials; identification of utilities; salvaged items; and protection of items to remain as indicated on Drawings.

1.2 SUBMITTALS

A. Section 013300 - Submittal Procedures: Requirements for submittals.

B. Shop Drawings: Indicate demolition and removal sequence and location of salvageable items; location and construction of temporary work.

1.3 CLOSEOUT SUBMITTALS

A. Section 017000 - Execution Requirements: Requirements for submittals.

B. Project Record Documents: Accurately record actual locations of capped utilities, subsurface obstructions, and all items, which differ from the contract documents.

C. Operation and Maintenance Data: Submit description of system, inspection data, and parts lists.

1.4 SCHEDULING

A. Section 013000 - Administrative Requirements

B. Schedule Work to coincide with new construction.

C. Describe demolition removal procedures and schedule.

1.5 PROJECT CONDITIONS

A. Conduct demolition to minimize interference with adjacent and occupied building areas.

B. Cease operations immediately when structure appears to be in danger and notify Architect/Engineer. Do not resume operations until directed.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.1 PREPARATION

A. Erect, and maintain temporary safeguards, for protection of the public, Owner, Contractor’s employees, and existing improvements to remain..

B. Erect and maintain weatherproof closures for exterior openings.

C. Erect and maintain temporary partitions to prevent spread of dust, odors, and noise to permit continued Owner occupancy.

D. Protect existing materials and existing improvements not indicated to be demolished.

E. Prevent movement of structure; provide temporary bracing and shoring required to ensure safety of existing structure.

F. Notify affected utility companies before starting work and comply with their requirements.

G. Mark location and termination of utilities.

H. Provide appropriate temporary signage including signage for exit or building egress.

3.2 DEMOLITION

A. Disconnect and identify designated utilities within demolition areas.

B. Demolish in orderly and careful manner. Protect existing improvements and supporting structural members.

C. Remove demolished materials from site except where specifically noted otherwise. Do not burn or bury materials on site.

D. Remove materials as Work progresses. Upon completion of Work, leave areas in clean condition.

E. Remove temporary Work.

END OF SECTION