Text version
SECTION 022250 -MINOR DEMOLITION FOR REMODELING
PART 1 GENERAL
1.1 SUMMARY
A. Section includes removal of designated building equipment and fixtures; removal of designated construction; dismantling, cutting and alterations for completion of the Work; disposal of materials; storage of removed materials; identification of utilities; salvaged items; and protection of items to remain as indicated on Drawings.
1.2 SUBMITTALS
A. Section 013300 - Submittal Procedures: Requirements for submittals.
B. Shop Drawings: Indicate demolition and removal sequence and location of salvageable items; location and construction of temporary work.
1.3 CLOSEOUT SUBMITTALS
A. Section 017000 - Execution Requirements: Requirements for submittals.
B. Project Record Documents: Accurately record actual locations of capped utilities, subsurface obstructions, and all items, which differ from the contract documents.
C. Operation and Maintenance Data: Submit description of system, inspection data, and parts lists.
1.4 SCHEDULING
A. Section 013000 - Administrative Requirements
B. Schedule Work to coincide with new construction.
C. Describe demolition removal procedures and schedule.
1.5 PROJECT CONDITIONS
A. Conduct demolition to minimize interference with adjacent and occupied building areas.
B. Cease operations immediately when structure appears to be in danger and notify Architect/Engineer. Do not resume operations until directed.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.1 PREPARATION
A. Erect, and maintain temporary safeguards, for protection of the public, Owner, Contractor’s employees, and existing improvements to remain..
B. Erect and maintain weatherproof closures for exterior openings.
C. Erect and maintain temporary partitions to prevent spread of dust, odors, and noise to permit continued Owner occupancy.
D. Protect existing materials and existing improvements not indicated to be demolished.
E. Prevent movement of structure; provide temporary bracing and shoring required to ensure safety of existing structure.
F. Notify affected utility companies before starting work and comply with their requirements.
G. Mark location and termination of utilities.
H. Provide appropriate temporary signage including signage for exit or building egress.
3.2 DEMOLITION
A. Disconnect and identify designated utilities within demolition areas.
B. Demolish in orderly and careful manner. Protect existing improvements and supporting structural members.
C. Remove demolished materials from site except where specifically noted otherwise. Do not burn or bury materials on site.
D. Remove materials as Work progresses. Upon completion of Work, leave areas in clean condition.
E. Remove temporary Work.
END OF SECTION